STOCK TITAN

Osisko Development (NYSE: ODV) resumes work at Cariboo Gold Project

Filing Impact
(Neutral)
Filing Sentiment
(Neutral)
Form Type
6-K

Rhea-AI Filing Summary

Osisko Development Corp. has resumed planned site activities at its 100%-owned Cariboo Gold Project in British Columbia after a temporary suspension following an isolated tragic incident on January 22, 2026. Operations are restarting under a phased plan coordinated with regulatory authorities, with health and safety emphasized as the top priority.

The site now has over 250 personnel supporting pre-construction, early works and exploration drilling. About 2.1 km of underground development has been completed from the Cow Portal into the Lowhee Zone, though progress has been slower than planned in challenging ground around the Lowhee fault. An ongoing 13-km underground infill program continues, with 1.6 km remaining on the 1260 level and additional drilling on the 1290 level.

Six surface drill rigs are active, including deeper drilling below the current Cariboo Gold deposit and a new program at the nearby Proserpine target, with roughly 5,500 meters completed so far and assays pending. Key infrastructure is advancing, including the waste rock storage facility, sediment control pond, and mine site complex early works, while the camp expansion to 266 rooms is complete to align with expected peak construction manpower for this flagship project.

Positive

  • None.

Negative

  • None.

Insights

Cariboo activities restart with phased ramp-up and ongoing development work.

Osisko Development has moved from a temporary safety-related suspension back to normal activity levels at the Cariboo Gold Project. Over 250 personnel are engaged in underground development, surface infrastructure and multi-rig drilling, which supports continued advancement toward construction readiness.

Underground development totals 2.1 km, but progress has lagged plan in the Lowhee fault zone due to difficult ground and extra support requirements. A 13-km underground infill drilling program is nearing completion on one level, while deeper and regional surface drilling continues with assays pending, so geological understanding is still evolving.

The upgraded Bonanza Ledge water treatment plant is in final commissioning and site infrastructure such as the waste rock storage facility and sediment control pond is being built. A 266-room camp expansion is complete, aligning camp capacity with anticipated peak construction manpower. Overall impact on project timelines and costs is not quantified in this disclosure.

 

UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549

Form 6-K

REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO RULE 13a-16 OR 15d-16 UNDER THE SECURITIES EXCHANGE ACT OF 1934

For the month of March 2026

Commission File Number: 001-41369

Osisko Development Corp.
(Translation of registrant's name into English)

1100 Avenue des Canadiens-de-Montréal, Suite 300, Montréal, Quebec H3B 2S2
(Address of principal executive office)

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.
Form 20-F [   ]      Form 40-F [ X ]

 

 


EXHIBIT INDEX

 

Exhibit Number Description
  
99.1 Press Release dated March 2, 2026

SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

      Osisko Development Corp.    
  (Registrant)
   
  
Date: March 2, 2026     /s/ Alexander Dann    
  Alexander Dann
  Chief Financial Officer and VP Finance
  

EXHIBIT 99.1

Osisko Development Announces Resumption of Planned Site Activities at the Cariboo Gold Project

MONTREAL, March 02, 2026 (GLOBE NEWSWIRE) -- Osisko Development Corp. (NYSE: ODV, TSXV: ODV) ("Osisko Development" or the "Company") announces the resumption of planned site activities at its Cariboo Gold Project (the "Project") in British Columbia, following a temporary suspension related to an isolated tragic incident that occurred at surface on January 22, 2026. A phased gradual reopening plan of surface and underground activities was successfully implemented over the last several weeks, while ensuring the health and safety of all employees and contractors, in coordination with and approval from the relevant regulatory authorities.

"I want to thank the entire site team for their professionalism and unwavering commitment throughout this difficult period. As we move forward, the health, safety and wellbeing of everyone who works at Osisko Development remains our highest priority," said Sean Roosen, Chairman and CEO.

There are currently over 250 personnel onsite, reflecting normal operating levels for the current phase of work, supporting the advancement of pre-construction, early works and exploration drilling activities, including:

  • Water treatment plant: Upgrades to the Bonanza Ledge water treatment plant are in the final stages of commissioning and the facility is anticipated to be fully operational in the coming weeks.
  • Underground development: To date, approximately 2.1 kilometres ("km") of underground development has been completed from the existing Cow Portal into the Lowhee Zone, and along the main access ramp, through the Lowhee fault, towards the Cow Mountain Zone. Development progress has been below plan while encountering challenging ground conditions in and around the Lowhee fault, requiring enhanced ground support. Development rates are expected to improve as the ramp advances beyond this zone.
  • Lowhee infill program: Infill drilling has resumed and is underway, with approximately 1.6 km remaining in the final drill fan under the ongoing 13-km underground program on the 1260 level. Additional exploration and infill drilling is also ongoing on the 1290 level. A total of three drill rigs are currently operating underground.
  • Surface exploration: A total of six drill rigs are currently operating on two exploration programs. Three drill rigs are targeting exploration below the current extent of the Cariboo Gold deposit down to a depth of 1,000 meters. Approximately 5,000 meters of drilling have been completed to date, with assays pending. A second surface exploration program on the adjacent Proserpine regional target has also commenced with three drill rigs, and approximately 500 meters completed to date.
  • Surface infrastructure: Construction of the waste rock storage facility, the sediment control pond, early works in the mine site complex area and other critical infrastructure continues.
  • Camp upgrade: The upgrade and expansion of the site camp to 266 rooms is complete and is expected to provide accommodation capacity aligned with peak construction manpower requirements for the Project.

Qualified Persons

The scientific and technical information contained in this news release has been reviewed, verified and approved by Scott Smith, P. Geo., Vice President, Exploration of Osisko Development, a "qualified person" within the meaning of National Instrument 43-101 – Standards of Disclosure for Mineral Projects.

Figure 1: Waste rock storage facility excavation continues.


Figure 2: Sediment control pond spillway concrete work & dam raise.


Figure 3: Water treatment plant commissioning underway.


Figure 4: Project site camp expansion complete.


ABOUT OSISKO DEVELOPMENT CORP.

Osisko Development Corp. is a continental North American gold development company focused on past producing mining camps with district scale potential. The Company's objective is to become an intermediate gold producer through the development of its flagship, fully permitted, 100%-owned Cariboo Gold Project, located in central British Columbia, Canada. Its project pipeline is complemented by the Tintic Project located in the historic East Tintic mining district in Utah, U.S.A., a brownfield property with significant exploration potential, extensive historical mining data, and access to established infrastructure. Osisko Development is focused on developing long-life mining assets in mining-friendly jurisdictions while maintaining a disciplined approach to capital allocation, development risk management, and mineral inventory growth.

For further information, contact:

Sean RoosenPhilip Rabenok
Chairman and CEOVice President, Investor Relations
Email: sroosen@osiskodev.comEmail: prabenok@osiskodev.com
Tel: +1 (514) 940-0685Tel: +1 (437) 423-3644
  

CAUTION REGARDING FORWARD-LOOKING STATEMENTS

This news release contains "forward-looking information" (within the meaning of applicable Canadian securities laws) and "forward-looking statements" (within the meaning of the U.S. Private Securities Litigation Reform Act of 1995, as amended) (collectively, "forward-looking statements"). Such forward-looking statements are identified with words such as "may", "will", "would", "could", "anticipate", "believe", "expect", "plan", "intend", "potential", "estimate", "propose", "project", "outlook", "foresee", "objective", "strategy", variants of these words or the negative or comparable terminology, as well as terms usually used in the future and the conditional. Information contained in forward-looking statements is based upon certain material assumptions that were applied in drawing a conclusion or making a forecast or projection, including the assumptions, qualifications, limitations or statements pertaining to: the full resumption and continuation of planned site activities at the Cariboo Gold Project; the anticipated timing for the Bonanza Ledge water treatment plant to become fully operational; expectations regarding the improvement of underground development rates as the ramp advances beyond the Lowhee fault zone; the completion of the remaining infill drilling program on the 1260 level and ongoing exploration and infill drilling activities; the continuation of surface exploration drilling activities and receipt of assay results; the continuation of surface infrastructure construction, including the waste rock storage facility, sediment control pond, mine site complex early works and other critical infrastructure; expectations that the expanded camp will provide accommodation capacity aligned with peak construction manpower requirements; the ability to develop the Cariboo Gold Project; and the timing and ability to complete contemplated work. Such forward-looking statements are based on a number of risks, uncertainties and assumptions which may cause actual results or other expectations to differ materially from those anticipated and which may prove to be incorrect. These assumptions include, but are not limited to: the absence of further work stoppages or suspensions at the Project; favourable regulatory conditions and approvals; the ability to maintain adequate personnel and contractor levels; the absence of unforeseen ground conditions or other geological challenges; the availability of necessary equipment, supplies and infrastructure; and general economic and market conditions. Actual results could differ materially due to a number of factors, including, without limitation: risks related to the exploration, development and operation of the Cariboo Gold Project; health, safety and security incidents; unforeseen ground conditions, including in and around the Lowhee fault zone; delays in commissioning infrastructure, including the water treatment plant; regulatory delays or changes in regulatory framework and applicable laws; labour shortages or disputes; general economic and market conditions and business conditions in the mining industry; fluctuations in commodity and currency exchange rates; changes in regulatory framework and applicable laws, as well as those risks and factors disclosed in the Company's most recent annual information form, financial statements and management's discussion and analysis as well as other public filings on SEDAR+ (www.sedarplus.ca) and on EDGAR (www.sec.gov). Although the Company believes the expectations conveyed by the forward-looking statements are reasonable based on information available as of the date hereof, no assurances can be given as to future results, levels of activity and achievements. The Company disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results or otherwise, except as required by law. Forward-looking statements are not guarantees of performance and there can be no assurance that these forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release. No stock exchange, securities commission or other regulatory authority has approved or disapproved the information contained herein.

Photos accompanying this announcement are available at:

https://www.globenewswire.com/NewsRoom/AttachmentNg/8eff1504-09b1-40bc-8f72-9e0e78c13ea9

https://www.globenewswire.com/NewsRoom/AttachmentNg/4b9f965a-fcd2-4313-8564-a6e6bdb9a295

https://www.globenewswire.com/NewsRoom/AttachmentNg/299b8b71-1b27-4984-aac1-094605e4dd4b

https://www.globenewswire.com/NewsRoom/AttachmentNg/e6ce32c4-5082-448e-b930-100b25f7c2a7

FAQ

What did Osisko Development (ODV) announce about the Cariboo Gold Project?

Osisko Development announced that planned site activities at the Cariboo Gold Project have fully resumed after a temporary suspension. Operations restarted under a phased plan, coordinated with regulatory authorities, emphasizing the health, safety and wellbeing of all employees and contractors on site.

How many workers are currently at Osisko Development’s Cariboo site?

The Cariboo Gold Project currently has over 250 personnel onsite, which the company describes as normal operating levels for this phase. These workers support pre-construction activities, underground development, surface infrastructure construction, and both underground and surface exploration and infill drilling programs.

What underground development progress has Osisko Development reported at Cariboo?

Osisko Development reports approximately 2.1 km of underground development from the Cow Portal into the Lowhee Zone and along the main access ramp. Progress has been below plan in challenging ground around the Lowhee fault, requiring enhanced ground support before development is expected to improve beyond that zone.

What drilling programs are underway at Osisko Development’s Cariboo Gold Project?

The company is advancing a 13-km underground infill program on the 1260 level, with about 1.6 km remaining in the final drill fan, plus additional drilling on the 1290 level. Six surface rigs are testing deeper Cariboo extensions and the nearby Proserpine target, with 5,500 meters drilled and assays pending.

What infrastructure work is Osisko Development completing at Cariboo?

Infrastructure work includes construction of a waste rock storage facility, a sediment control pond, and early works in the mine site complex area. The Bonanza Ledge water treatment plant is in final commissioning, and the site camp has been upgraded and expanded to 266 rooms to match future construction manpower.

Who qualified the technical information in Osisko Development’s Cariboo update?

The technical information was reviewed, verified and approved by Scott Smith, P. Geo., Vice President, Exploration of Osisko Development. He is identified as a qualified person under National Instrument 43-101, which governs disclosure standards for mineral projects in Canadian securities regulation.

Filing Exhibits & Attachments

1 document
Osisko Development Corp

NYSE:ODV

ODV Rankings

ODV Latest News

ODV Latest SEC Filings

ODV Stock Data

1.37B
173.64M
Gold
Basic Materials
Link
Canada
Montreal