Orla Mining (ORLA) posts strong South Railroad NPV and IRR in new study

Filing Impact
(Neutral)
Filing Sentiment
(Neutral)
Form Type
6-K

Rhea-AI Filing Summary

Orla Mining has released an updated feasibility study for its South Railroad gold project in Nevada, outlining a larger, more advanced, construction-ready operation. The mine plan envisions a 10‑year open-pit heap leach operation processing 66.6 million tonnes of ore, with total proven and probable mineral reserves of 1.52 million ounces of gold and 6.20 million ounces of silver.

At a base case gold price of $3,100 per ounce and silver at $36.50 per ounce, the study estimates average annual gold production of 103,756 ounces, an after-tax NPV at 5% of $783 million, an after-tax IRR of 48%, and a 2.0‑year after-tax payback. Initial capital is estimated at $395 million, with total life-of-mine capital (including sustaining and working capital) of about $604 million and an AISC of $1,505 per ounce of gold.

The project is advancing through U.S. federal and state permitting, with NEPA and USACE processes well underway and a Record of Decision targeted for mid‑2026. Detailed engineering, EPCM engagement with M3, and long-lead procurement have started, and construction is expected to begin in mid‑2026 and take approximately 18 months, subject to receipt of final permits and regulatory approvals.

Positive

  • Robust economics: Updated feasibility shows after-tax NPV 5% of $783 million, 48% after-tax IRR, and 2.0-year payback at $3,100/oz gold, indicating a high-margin project on disclosed assumptions.

Negative

  • None.

Insights

Updated study shows robust economics and permits nearing key decisions.

The South Railroad feasibility update presents a sizeable open-pit heap leach project with proven and probable reserves of 66.6 million tonnes grading 0.71 g/t gold for 1.52 million ounces of gold and 6.20 million ounces of silver. Using base case prices of $3,100/oz gold and $36.50/oz silver, it estimates average annual gold production of 103,756 ounces over a 10‑year life. Unit costs are framed by a total cash cost of $1,207 per ounce and AISC of $1,505 per ounce.

On these assumptions, the study indicates strong project economics: after-tax NPV at 5% of $783 million, after-tax IRR of 48%, and a 2.0‑year after-tax payback, against initial capital of $395 million and total life-of-mine capital of about $603.9 million. Sensitivity work shows after-tax NPV at 5% ranging from $82 million at $2,000/oz gold to $1,651 million at $4,500/oz, with IRRs from 10% to 95%.

Permitting and execution are progressing: NEPA and Section 404 public comment periods closed in September 2025 without significant issues identified, EPCM has been awarded to M3, and detailed engineering and long-lead procurement are underway. The company targets a BLM Record of Decision in mid‑2026 and construction start in mid‑2026, with an approximately 18‑month build, all explicitly flagged as forward-looking and subject to permitting, financing, and other risks described in its risk disclosures.

 

 

 

UNITED STATES 

SECURITIES AND EXCHANGE COMMISSION 

Washington, D.C. 20549

 

FORM 6-K

 

Report of Foreign Private Issuer 

Pursuant to Rule 13a-16 or 15d-16 

UNDER the Securities Exchange Act of 1934

 

For the month of January 2026

 

Commission File Number: 001-39766

 

 

ORLA MINING LTD.

(Translation of registrant's name into English)

 

Suite 2020, 666 Burrard Street
Vancouver, British Columbia, 

V6C 2X8, Canada 

(Address of principal executive offices)

 

Indicate by check mark whether the registrant files or will file annual reports under cover Form 20-F or Form 40-F.

 

Form 20-F          ¨            Form 40-F           x

 

Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(1):  ¨

 

Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(7): ¨

  

 

 

 

 

 

Signature

 

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

 

  ORLA MINING LTD.
    
Date:   January 21, 2026 /s/ Etienne Morin
  Name: Etienne Morin
  Title: Chief Financial Officer

 

 

 

 

EXHIBIT INDEX

 

Exhibit   Description of Exhibit
     
99.1   Material Change Report

 

 

 

 

Exhibit 99.1

 

FORM 51-102F3

MATERIAL CHANGE REPORT

 

1.Name and Address of Company

 

Orla Mining Ltd. (“Orla” or the “Company”)
Suite 2020, 666 Burrard Street
Vancouver, BC, V6C 2X8

 

2.Date of Material Change

 

January 15, 2026

 

3.News Release

 

A news release with respect to the material change referred to in this report was disseminated through various approved public media and filed on SEDAR+ on January 15, 2026.

 

4.Summary of Material Change

 

On January 15, 2026, the Company provided an update for its South Railroad Gold Project (“South Railroad” or the “Project”). This update presented the results of the optimized Feasibility Study (the “FS” or “Study”) and confirms the Board of Directors’ approval to begin spending for detailed engineering, procurement, and project execution.

 

5.Full Description of Material Change

 

5.1Full Description of Material Change

 

On January 15, 2026, the Company provided an update for South Railroad. This update presented the results of the optimized Study and confirmed the Board of Directors’ approval to begin spending for detailed engineering, procurement, and project execution. The Board also approved the start of project construction, subject to receipt of all required permits. South Railroad is located in Nevada, USA, and forms a part of the Company’s larger South Carlin Complex (“South Carlin”) land package on the prolific Carlin Trend.

 

All amounts expressed in U.S. dollars unless otherwise stated.

 

Table 1: South Railroad Feasibility Study Summary

 

Feasibility Study Summary (At $3100 Gold)   Units   Values  
Ore Mined   M tonnes     66.6  
Waste Mined   M tonnes     266.8  
Total Tonnes Mined   M tonnes     333.4  
Strip Ratio   w:o     4.0  
Mine Life   years     10  
             
LOM Run of Mine (ROM) - Processing   M tonnes     33.7  
LOM Two-Stage Crush - Processing   M tonnes     33.0  
Total Ore to Leach Pad   M tonnes     66.6  
Throughput - ROM Avg Per Day   tpd     10,100  
Throughput - Two- Stage Crush Avg Per Day   tpd     9,900  
Gold Grade (Average)   (g/t)     0.71  
Silver Grade (Average; Over Pinion Ore Tonnes Only)   (g/t)     5.1  

 

 

 

 

Feasibility Study Summary (At $3100 Gold)  Units  Values 
Contained Gold  ounces   1,516,332 
Contained Silver  ounces   6,194,776 
Average Gold Recovery  %   71%
Average Silver Recovery  %   12%
Recovered Gold  ounces   1,072,306 
Recovered Silver  ounces   760,005 
Average Annual Gold Production (first 10 years)  ounces   103,756 

 

Operating Costs (Average LOM)       
Mining  $/t mined  $2.45 
Processing & Support  $/t mined  $0.91 
General & Administrative  $/t mined  $0.24 
Refining  $/t mined  $0.01 
Total Operating Cost  $/t mined  $3.60 
         
Total Cash Costi (net of by-product credits)  $/ounce Au  $1,207 
AISC1  $/ounce Au  $1,505 

 

Capital Costs (Excluding value added tax)       
Initial Capital  $ million  $395 
Life of Mine Sustaining Capital  $ million  $202 
Working Capital  $ million  $7 
Closure Costs  $ million  $29 

 

Financial Evaluation (Base Case)       
Gold Price Assumption  $/ounce  $3,100 
Silver Price Assumption  $/ounce  $36.50 
Average Annual Cashflow (Pre-Tax)  $ million  $137 
Average Annual Cashflow (After-Tax)  $ million  $112 
IRR, Pre-Tax  %   55%
IRR, After-Tax  %   48%
NPV @ 5% (Pre-Tax)  $ million  $1,011 
NPV @ 5% (After-Tax)  $ million  $783 
Pay-Back Period (After-Tax)  years   2.0 

 

Table 2: Feasibility Study Sensitivity Analysis

 

Gold Price ($/oz)  $2,000   $2,500   $3,100   $3,500   $4,000   $4,500 
After-tax NPV 5% ($M)  $82   $406   $783   $1,031   $1,341   $1,651 
After-tax IRR (%)   10%   28%   48%   61%   78%   95%
Payback (years)   4.9    3.1    2.0    1.5    1.1    0.9 

 

Feasibility Study Overview

 

The updated Study was prepared by a team of independent industry experts who are qualified persons as defined under NI 43-101, led by M3 Engineering (“M3”) and supported by NewFields Mining Design and Technical Services (“NewFields”), Forte Dynamics (“Forte”), Stantec, Ray Walton Consulting Inc., RESPEC, APEX Geoscience Ltd., and Westland Resources. See Table 7 below for further details.

 

 

 

 

The updated Study was conducted using a base case gold and silver price of $3,100 per ounce and $36.50 per ounce, respectively.

 

The South Railroad Project includes Mineral Reserves for the Dark Star and Pinion deposits.

 

The Mineral Reserve estimate at South Railroad includes Proven and Probable Mineral Reserves of 66.6 million tonnes (73.4 million tons) at a gold grade of 0.71 grams per tonne (“g/t”), for total Mineral Reserves of 1.52 million ounces of gold. In addition, the Pinion deposit contains 6.2 million ounces of silver from 37.9 million Mineral Reserve tonnes (41.8 million tons) at 5.1 g/t silver.

 

The total Measured and Indicated Mineral Resource is 105.9 million tonnes at 0.72 g/t gold, resulting in an estimated 2.46 million ounces of gold. In addition, the Pinion deposit contains 7.4 million ounces of silver from 50.7 million Measured and Indicated tonnes at 4.6 g/t silver. The Inferred Mineral Resource totals 55.7 million tonnes at 0.56 g/t gold, resulting in an estimated 1.01 million ounces of gold. In addition, the Pinion deposit contains 0.1 million ounces of silver from 1.3 million Inferred tonnes at 2.65 g/t silver. Mineral Resources are inclusive of Mineral Reserves.

 

Further details on the Mineral Resource and Mineral Reserve estimates are provided below under “South Railroad Technical Report Summary Information”.

 

Operating costs are based on Orla-performed mining, with all mine components being financed or owned by the Company. Capital cost estimates are based on a combination of material takeoffs (MTOs), vendor quotations, database pricing, Engineering, Procurement, Construction Management (“EPCM”)-awarded contract values, and allowances. The scope and costs related to mechanical and electrical equipment is well-defined with 67% of those costs supported by firm vendor quotes.

 

South Railroad is situated on federal land and is currently advancing under the guidance of the BLM in accordance with the National Environmental Policy Act (“NEPA”) for permitting. The BLM NEPA public comment period closed on September 18, 2025 with the largest category of submissions being letters of support, reflecting strong community and stakeholder backing for the project and the U.S. Army Corps of Engineers Section 404 public comment period ended on September 25, 2025 with no significant comments received. Orla has all the mineral rights, surface use and right of way agreements in place to commence construction upon receipt of all required permits.

 

Key Optimizations

 

The updated FS reflects an optimized and more advanced, construction-ready project than the previous Feasibility Study published in 2022 (the “2022 FS”). Advanced engineering, vendor pricing, and execution plans inform the FS and enhance the overall confidence in delivery. Key optimizations are highlighted below, and the associated cost movements are outlined in the Capital Cost section.

 

·Revised Processing Flowsheet – Two-stage Crushing Added:

 

The optimized FS replaces the run-of-mine (“ROM”)-only approach in the 2022 FS with a two-stage crushing circuit for a significant portion of the ore, improving recovery confidence and reducing metallurgical risk identified in the earlier study.

 

·Updated Metallurgical Recoveries Based on Expanded Test Work:

 

The recovery model reflects 187 column tests completed since 2022, simplifying ore types and incorporating new data for Pinion East and Dark Star North. The updated model provides higher confidence in both crushed and ROM performance.

 

·Enhanced Water Management and Site Infrastructure Design:

 

The updated scope includes redesigned water supply systems, updated hydrogeological information, and refined site infrastructure layouts to support operational reliability and reduce environmental risk. See Figure 1 in the Appendix for Site Plan Layout.

 

 

 

 

·Transition to an Execution-Ready Project:

 

The FS incorporates detailed engineering, a defined project delivery model, EPCM engagement, long-lead procurement planning, and construction sequencing to support the transition into execution. This level of planning and detail was not included in the 2022 FS.

 

Capital Costs

 

The updated capital cost estimate reflects a significantly more advanced and construction-ready project compared to the 2022 FS, which estimated initial capital of $190 million. The updated study and cost estimate are supported by comprehensive engineering, vendor pricing, and execution plans that enhance overall confidence in project delivery.

 

Key variances in initial capital costs from the FS in comparison to the 2022 FS include:

 

·$46 million related to inflationary cost escalation;

·$101 million in direct cost additions, primarily reflecting the inclusion of a two-stage crushing system (previously ROM only) and updated water management systems;

·$33 million in indirect costs associated with the crushing system and water circuit; and

·$25 million in additional contingency more reflective of a project of this study level.

 

Table 3: Capital Cost Summary (excl. value added tax)

 

Description  Cost (US$m) 
Process Facilities (Adsorption, Desorption, and Recovery (“ADR”)/Refinery)   48.2 
Crushing & Stacking   47.1 
Heap Leach Facility   20.7 
Mining & Waste Rock Disposal Facilities   60.7 
Power Systems   16.4 
Site Water Management Infrastructure & Treatment   62.4 
Ancillaries  24.3 
Indirects   57.1 
Owner’s Costs   10.8 
Contingency   47.0 
Total Initial Capital   394.7 
Working Capital & Initial Fills   6.9 
Sustaining Capital – Mine & Process   202.3 
Total LOM Capital (incl. working capital)   603.9 
Closure Costs   29.2 

 

The initial capital cost of $395 million excludes regulatory costs, expenses related to permit conditions, off-site infrastructure support, financial assurance instruments, and other expenses not directly related to the construction of the mine, totaling $45 million, which are tracked as permitting obligations or management reserve and disclosed separately.

 

Operating Costs

 

Operating costs for the feasibility study were estimated by RESPEC (mine development) and M3 (process plant, site development, power generation, and ancillaries), Stantec (site-wide water management systems), NewFields (heap leach and waste rock disposal facilities) and Linkan Engineering (water treatment plant and potable water systems).

 

Mine operating costs were estimated using first principles. This was done using estimated hourly costs of equipment and personnel against the anticipated hours of work for each. The equipment hourly costs were estimated for fuel, oil, and lubrication, tires, undercarriage, repair and maintenance costs, and special wear items.

 

 

 

 

Process operating costs have been estimated by M3 from first principles. Labour costs were estimated using project specific staffing, salary and wage, and benefit requirements. Unit consumptions of materials, supplies, power, and delivered supply costs were also estimated.

 

Operating costs were estimated based on third quarter 2025 US dollars and are presented with no added contingency based upon the design and operating criteria. Operating costs are considered to have an accuracy of +/- 15%.

 

Operating costs estimates have been based upon information obtained from the following sources:

 

·Project metallurgical test work and process engineering;

 

·Development of a detailed equipment list and demand calculations;

 

·M3 in-house data for reagent pricing; and

 

·Experience with other similar operations.

 

Table 4: Operating Cost Summary

 

Description  LOM Costs   LOM Costs 
   $/t (Ore)   $/oz 
Mining   12.25    761 
Process   4.54    282 
G&A   1.21    75 
Total Operating Costs   18.00    1,118 
Refining & Transport   0.03    2 
Royalties   1.46    91 
By-product Credits   (0.06)   (4)
Total Cash Costs (net of by products)1   19.43    1,207 
Sustaining Capital   2.79    173 
Reclamation   0.44    27 
Net Proceeds and Excise Tax   1.56    97 
AISC1   24.22    1,505 

 

Mineral Resource & Reserves Summary

 

Mineral Resources were estimated for Dark Star, Pinion, Jasperoid Wash, North Bullion and Pony Creek deposits at a gold price $2,800 per ounce, while the Mineral Reserves were estimated for Dark Star and Pinion deposits at a gold price of $2,300 per ounce. The Mineral Reserves and Mineral Resources estimate included in the Feasibility Study have an effective date of September 30, 2025. The Mineral Resources are reported inclusive of Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

 

Since the 2022 FS, which was completed by Gold Standard Ventures Corp., the Mineral Resource has been updated to incorporate new drilling data, revised geological interpretations, and the addition of the Pony Creek deposits acquired in 2024. Additionally, new drilling at Dark Star and Pinion has increased the confidence level of the Mineral Reserves and helped further derisk the project. Updates to the Mineral Reserve modifying factors include revised cost assumptions and parameter changes associated with the incorporation of crushed-ore stacking alongside ROM ore stacking on the heap-leach facility.

 

 

 

 

Table 5: South Railroad Mineral Reserves (Dark Star and Pinion Deposits)

 

   Tonnage   Grades   Contained Metal 
   (kt)   Au (g/t)   Ag (g/t)   Gold (koz)   Silver (koz) 
Proven   10,585    1.04    6.56    354    445 
Probable   56,033    0.65    5.00    1,162    5,749 
Proven and Probable   66,618    0.71    5.08    1,516    6,195 

 

Notes:

 

1.The estimate of Mineral Reserves was done by Thomas L. Dyer, PE of RESPEC.

2.Mineral Reserves are classified in accordance with Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Standards and are recognized at the point process feed.

3.Mineral Reserves are reported based on gross metal value (GMV) cutoff grades based on gold prices of $2,300 per ounce Au and silver prices of $25.00 per ounce Ag. The Mineral Reserve effective date is September 30, 2025.

4.Economic parameters and recoveries will be described in the South Railroad Technical Report.

5.As Mineral Reserves were defined using lower metal prices compared to the economic analysis that supports them, resulting Proven and Probable Mineral Reserves are justified.

6.Rounding may result in apparent discrepancies between tons, grade, and contained metal content.

7.Cutoff grades are applied by material type as will be described in the South Railroad Technical Report.

8.Proven and Probable Mineral Reserves for Pinion include silver as reported above;

9.Silver Mineral Reserves apply to Pinion only, and silver grade is based on Pinion tonnes

 

Table 6: South Carlin Mineral Resources

 

Category  Tonnage   Grades   Contained Metal 
   (kt)   Au (g/t)   Ag (g/t)   Gold (koz)   Silver (koz) 
Mineral Resources - Dark Star, Pinion, Jasperoid Wash and North Bullion Deposits  
Measured   13,609    0.92    6.05    401    509 
Indicated   92,296    0.69    4.48    2,058    6,915 
Measured + Indicated   105,905    0.72    4.56    2,459    7,424 
Inferred   20,298    0.8    2.65    519    111 
Mineral Resources - Pony Creek                         
Inferred   35,417    0.43         493      
Total South Carlin Resources                         
Measured   13,609    0.92    6.05    401    509 
Indicated   92,296    0.69    4.48    2,058    6,915 
Measured + Indicated   105,905    0.72    4.56    2,459    7,424 
Inferred   55,716    0.56    2.65    1,012    111 

 

Notes - Dark Star, Pinion, Jasperoid Wash and North Bullion Deposits.

 

1.The estimate of Mineral Resources was done by Michael S. Lindholm, CPG of RESPEC in Imperial tons.

2.In-situ Mineral Resources are classified in accordance with CIM Standards.

3.The base cases for all mineral resources are reported at a gold price of $2,800 oz Au and have an effective date of September 30, 2025.

4.Tabulations comprise all model blocks at variable cutoff grades for oxide/transitional and sulphide materials within the $2,800 optimized pits or within a 2.57 Au g/t grade shell for underground. Pit optimizations vary by deposit and throughput rates of 11 kt/day and 18 kt/day; waste mining costs of US$2.34/t mined to US$2.43/t mined; crushing, stacking and heap leaching costs of US$4.01/t to US$4.94/t; and general and administrative costs of $1.26/t. At North Bullion, transportation costs of $44.09/t are applied for shipping refractory material off-site.

5.Recoveries are calculated within each block model, and vary by deposit, ore-type, redox state, sulphide-sulfur and inorganic-carbon content, and gold and silver grade. At Dark Star, assumed minimum metallurgical recoveries of 65% and 70% for gold for ROM and crushed ore, respectively, are applied; At Pinion, assumed variable metallurgical recoveries with base cases at 53% and 70% for gold for ROM and crushed ore, respectively, and base cases at 5% and 15% for silver for ROM and crushed ore, respectively.

6.The average grades of the tabulations are comprised of the weighted average of block-diluted grades within the optimized pits.

7.Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

8.Rounding may result in apparent discrepancies between tons, grade, and contained metal content.

9.Silver Mineral Resources from Pinion only, silver grade is based on Pinion tonnes.

 

Notes - Pony Creek Resources:

 

1.The estimate of Mineral Resources was completed by Warren Black, M.Sc., P.Geo., APEX.

2.Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

3.There are no known legal, political, environmental or other risks that could materially affect the potential development.

4.The Inferred Mineral Resource in this estimate has a lower level of confidence and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of the Inferred Mineral Resource could potentially be upgraded to an Indicated Mineral Resource with continued exploration.

5.The Mineral Resources were estimated in accordance with the CIM Standards on Mineral Resources and Reserves, Definitions (2014) and Best Practices Guidelines (2019) prepared by the CIM Standing Committee on Reserve Definitions and adopted by the CIM Council.

6.The reported open-pit Mineral Resources utilize a cutoff of 0.103 Au g/t Au for heap leach and 0.17 Au g/t for vat leach material.

7.Economic assumptions used include US$2,800/oz Au, process recoveries of 75% for Au in heap leach material and 85% for Au in vat leach material, a processing cost of US$1.90/t for heap leach and US$6.70/t for vat leach material, and a G&A cost of US$0.56/t.

8.The base cases for all Mineral Resources have an effective date of September 30, 2025.

9.The constraining pit optimization parameters included a mining cost of US$2.49/t for both mineralized and waste material and assumed pit slope angles of 45°.

 

 

 

 

Mining & Processing Summary

 

Mining at South Railroad is planned over an initial 10-year period across the Dark Star and Pinion deposits using conventional open-pit truck and shovel methods. Ore from both deposits will be processed through a single, shared heap leach facility utilizing a combination of ROM and two-stage crushed material.

 

All leach material will be placed on the heap leach pad, with crushed ore temporarily stockpiled to decouple crushing and stacking activities and provide operational flexibility. The processing schedule incorporates both ROM and crushed heap leach material, with a maximum combined processing rate of approximately 29,940 tonnes per day, or 10.9 million tonnes per year, allowing the operation to balance throughput, recovery, and operating efficiency.

 

The FS assumes Orla-operated mining, supported by a fleet of primary mining equipment including drills, loaders, hydraulic shovels, and 200-ton (181 tonne) capacity haul trucks. This approach provides Orla with direct control over mining performance, cost management, and scheduling. Capital costs reflect a financing option of the major mining equipment purchases.

 

Life-of-mine (“LOM”) average gold recovery across the Dark Star and Pinion deposits is estimated at 70.2%, reflecting the application of both ROM and crushed heap leach processing. At Dark Star, the LOM average gold recoveries are estimated at 75.6% for ROM material and 82.6% for crushed material. At Pinion, the LOM average gold recoveries are estimated at 52.3% for ROM material and 61.5% for crushed material.

 

Overall, the mining plan reflects an executable, low-risk approach that supports strong economics and operational flexibility.

 

Site Infrastructure Summary

 

Project infrastructure for South Railroad has been designed to support the planned mining and heap leach operations and includes site roads, power supply and distribution, communications, heap leach pad, process plant and ancillary buildings.

 

South Railroad will be powered by an on-site power plant comprising seven natural-gas reciprocating generators, with liquefied natural gas (“LNG”) delivered by truck. This configuration was selected based on prior power studies and provides a scalable solution with staged capital requirements, favourable operating costs, and reduced emissions relative to alternative on-site generation options. Associated capital and operating costs have been incorporated into the FS cost estimates.

 

Mine water requirements will be met primarily through groundwater dewatering associated with the Dark Star pit. Dewatering at Dark Star will be supported by a network of wells producing a peak combined flow of approximately 2,300 gallons per minute (gpm), with additional wells developed at Pinion during later mining phases. Pumping rates decline over time as the system transitions from pit dewatering to process and heap leach supply, with long-term average pumping of approximately 310 gpm. Groundwater modeling confirms sufficient water availability to meet operational requirements throughout the life of the mine. Recovered water is managed through a series of large-capacity raw water tanks, which distribute water to the mine water treatment plant, consumptive uses, and fire-water storage, with excess water treated and discharged via an on-site outfall structure.

 

 

 

 

The primary access to the South Railroad Project begins in Elko, Nevada and follows a 67 kilometres route that transitions from state highways to county roads and finally to BLM roads. Approximately 35 kilometres of the route will be upgraded to a two-way road with wide lanes and shoulders to accommodate safety and drainage. The final 10 kilometres, which involve steeper grades and winding terrain, will be improved to reduce slopes and straighten curves.

 

Key facilities have been strategically located on the site layout to optimize material handling, access, and operational safety. The heap leach facility is situated northeast of the Pinion pit, with gravity flow of pregnant leach solution to the adjacent process ponds, and controlled access for both ROM placement and initial ore stacking.

 

Centralized mine infrastructure includes a truck shop and maintenance complex, fuel and warehousing facilities, administration and security buildings along the main access road, and an on-site ADR plant and refinery for gold and silver recovery. Supporting facilities include a laboratory, training areas, potable water treatment plant, and site services facilities.

 

Permitting

 

The South Railroad Project is situated on federal land and is currently advancing under the guidance of the BLM as a FAST-41 Covered Project in accordance with the National Environmental Policy Act (“NEPA”) for permitting. The BLM published the Notice of Intent (“NOI”) in the Federal Register on August 13, 2025, thereby initiating the formal Environmental Impact Statement (“EIS”) process under NEPA. The BLM is also consulting with the U.S. Fish and Wildlife Service (USFWS) under Section 7 of the Endangered Species Act. A Biological Assessment has been prepared and shared with the USFWS for pre-consultation technical assistance and completeness review in advance of the formal consultation process. In parallel, the U.S. Army Corps of Engineers (USACE) Section 404 permit application, addressing wetland and surface-disturbance impacts, was submitted in August 2025 and deemed administratively complete. The public-comment period closed on September 25, 2025, without significant issues. The USACE’s review of the compensatory-mitigation plan is underway.

 

At the state level, the Company has secured Class I and II Air Operating Permits, while water-related applications continue to progress with the Nevada Division of Water Resources (NDWR). The Water Pollution Control Permit and the National Pollutant Discharge Elimination System (NPDES) discharge permit applications were submitted for review in the third quarter 2025.

 

The BLM’s Record of Decision (the final permitting decision) is targeted for mid-2026.

 

Project Execution

 

Orla has defined a clear and actionable execution path to advance South Railroad through construction and into production. With the Study complete, the Project has entered the Execution Phase, supported by a robust project delivery framework. M3 has been contracted to provide integrated EPCM services for the development and construction of the Project following a competitive tender process conducted earlier this year. This leverages their technical leadership during the Study and their prior involvement with South Railroad.

 

Detailed engineering is well underway and M3 has ramped up its team alongside Orla’s Owner’s Team to finalize construction planning and readiness activities. Long-lead procurement activities are also advancing with key awards beginning in early 2026.

 

Construction activities are expected to commence in mid-2026, subject to the receipt of final permits and regulatory authorization and is expected to be completed in approximately 18 months.

 

Orla, M3 and the supporting consultants will work in an integrated manner to ensure seamless alignment between design, construction and the future operations. Operational readiness is being embedded across all workstreams with progressive onboarding of Orla’s operations personnel to enable an efficient transition through commissioning and into steady-state operations.

 

Orla will continue to apply its ESG framework throughout the design and execution of the Project with a focus on environmental management, workforce safety, and constructive engagement with local and regional stakeholders. These priorities are being incorporated into all aspects of the designs and plans to ensure the Project is developed responsibly and in alignment with Orla’s long-term sustainability objectives.

 

 

 

 

Data Verification & QA/QC

 

Michael S. Lindholm, CPG, Principal Resource Geologist at RESPEC Company LLC and the Qualified Person for the South Railroad Mineral Resource estimate (except Pony Creek), last visited the site August 21, 2025. During this and prior visits, collar locations were verified, and core storage, security, and sampling procedures were observed. Core from both mineralized and unmineralized zones was examined. The database was reviewed and considered suitable for Mineral Resource estimation.

 

Michael Dufresne, P.Geo Principal at APEX Consulting Ltd. (“APEX”) and the Qualified Person for the Pony Creek Geology and Exploration visited the site from January 26 to 27, 2022. During the visit, collar locations were verified, along with core storage, security and sampling procedures. Core from mineralized and unmineralized zones were examined. Warren Black, P.Geo, Senior Consultant – Mineral Resources & Geostatistics and the Qualified Person for the Pony Creek Mineral Resource estimate reviewed the database and considered it suitable for Mineral Resource estimation.

 

Sampling and assay data from the drill core are monitored through a quality assurance–quality control (“QA/QC”) program designed to follow industry best practices.

 

The independent Qualified Persons for the Mineral Resource estimate, Michael S. Lindholm and Warren Black are of the opinion that the drilling and sampling procedures for South Railroad and Pony Creek drill samples by Orla (and prior to acquisition by Gold Standard Ventures and Contract Gold) were reasonable and adequate for the purposes of the Mineral Resource estimate, and that the QA/QC program meets industry standards.

 

Technical Report

 

Additional supporting details regarding the information in this material change report will be provided in the new independent technical report for South Railroad (the “South Railroad Technical Report”), which will be prepared in accordance with National Instrument (“NI”) 43-101 and filed on SEDAR+ and EDGAR under the Company’s profile at www.sedarplus.ca and www.sec.gov, respectively, within 45 days of the news release issued on January 15, 2026. The South Railroad Technical Report is intended to be read as a whole, and sections should not be read or relied upon out of context. It will include further details on qualifications, assumptions, exclusions and risks that relate to the details of the news release issued on January 15, 2026, including the Study and Mineral Resource and Reserve estimate.

 

Qualified Persons Statement

 

The scientific and technical information in this material change report related to the Study were provided, reviewed and approved by the authors listed in Table 7, who are Qualified Persons as defined under NI 43-101.

 

All other scientific and technical information in this material change report was also reviewed and approved by Mr. J. Andrew Cormier, P. Eng., Chief Operating Officer of the Company, and Mr. Sylvain Guerard, P. Geo., Senior Vice President, Exploration of the Company, who are Qualified Persons as defined under NI 43-101.

 

 

 

 

Table 7: 2026 Feasibility Study Qualified Person

 

QP Name Company Qualification Main Area of Responsibility
Matthew Sletten M3 Engineering & Technology Corporation, Chandler, AZ P.E. Lead author, infrastructure, costing (except mining) and economic analysis
Benjamin Bermudez M3 Engineering & Technology Corporation, Chandler, AZ P.E. Recovery methods – Process plant
Michael S. Lindholm RESPEC Company LLC, Reno, NV CPG Mineral Resources, geology and exploration (except Pony Creek)
Thomas Dyer RESPEC Company LLC, Reno, NV P.E. Mineral Reserves
Gary (Joe) Petersen RESPEC Company LLC, Reno, NV SME-RM, QP Mining methods and mining costs
Ray Walton Ray Walton Consulting P.E. Metallurgical testing
Richard DeLong EM Strategies, Inc., Reno, NV QP-MMSA, RG, PG Environment, permitting, and social
Warren Black APEX Geoscience Ltd. MSc, P.Geo. Mineral Resources (Pony Creek)
Michael Dufresne APEX Geoscience Ltd. M.Sc., P.Geol., P.Geo. Geology and exploration (Pony Creek)

 

South Railroad Technical Report Summary Information:

 

The mineral reserves and mineral resources estimate shown here has an effective date of September 30, 2025. The mineral resources are inclusive of mineral reserves. Mineral resources that are not mineral reserves do not have demonstrated economic viability. There are no known legal, political, environmental, or other risks that could materially affect the potential development of the mineral reserves or mineral resources.

 

Mineral Reserves

 

Dark Star  Kt   g Au/t   Koz Au 
Proven   8,472    1.12    304 
Probable   20,253    0.70    456 
Total Reserves   28,726    0.82    761 

 

Pinion  Kt   g Au/t   Koz Au   g Ag/t   Koz Ag 
Proven   2,113    0.73    50    6.56    445 
Probable   35,779    0.61    706    5.00    5,749 
Total Reserves   37,892    0.62    756    5.08    6,195 

 

Dark Star & Pinion - Consolidated  Kt   g Au/t   Koz Au 
Proven   10,585    1.04    354 
Probable   56,033    0.65    1,162 
Total Reserves   66,618    0.71    1,516 

 

Notes:

 

1.The estimate of Mineral Reserves was done by Thomas L. Dyer, PE of RESPEC.

2.Mineral Reserves are classified in accordance with CIM Standards and are recognized at the point process feed.

3.Mineral reserves are reported based on gross metal value (GMV) cutoff grades based on gold prices of $2,300/oz Au and silver prices of $25.00/oz Ag. The Mineral Reserve effective date is September 30, 2025.

4.Economic parameters and recoveries will be described in the South Railroad Technical Report.

5.As Mineral Reserves were defined using lower metal prices compared to the economic analysis that supports them, resulting Proven and Probable Mineral Reserves are justified.

6.Rounding may result in apparent discrepancies between tons, grade, and contained metal content.

7.Cutoff grades are applied by material type as will be described in the South Railroad Technical Report.

8.Proven and Probable Mineral Reserves for Pinion include silver as reported above;

9.Silver Mineral Reserves apply to Pinion only, and silver grade is based on Pinion tonnes.

 

 

 

 

Mineral Resources

 

Dark Star, Pinion, Jasperoid Wash, and North Bullion Deposits

 

Oxide

 

Dark Star Mineral Resources  Kt   g/t Au   K oz Au   g/t Ag   Koz Ag 
Measured – Open Pit   10,992    0.96    340         
Indicated – Open Pit   29,177    0.61    573           
Measured + Indicated – Open Pit   40,169    0.71    913           
Inferred – Open Pit   1,287    0.41    17           

 

Pinion Mineral Resources  Kt   g/t Au   Koz Au   g/t Ag   Koz Ag 
Measured – Open Pit   2,616    0.73    61    6.05    509 
Indicated – Open Pit    48,062    0.56    871    4.48    6,915 
Measured + Indicated – Open Pit   50,678    0.57    932    4.56    7,424 
Inferred – Open Pit   1,302    0.41    17    2.65    111 

 

Jasperoid Wash Mineral Resources  Kt   g/t Au   K oz Au   g/t Ag   Koz Ag 
Indicated – Open Pit   5,635    0.31    57         
Inferred – Open Pit   10,057    0.25    82           

 

North Bullion Deposits Mineral Resources  Kt   g/t Au   Koz Au   g/t Ag   Koz Ag 
North Bullion Indicated - Open Pit   149    0.27    1         
North Bullion Inferred - Open Pit   218    0.36    3           
POD/SH/SL Indicated – Open Pit   2,512    0.69    56           
POD/SH/SL Inferred – Open Pit   2,920    0.56    53           

 

ALL OXIDE  Kt   g/t Au   K oz Au   g/t Ag   K oz Ag 
Measured   13,609    0.92    401    6.05    509 
Indicated   85,534    0.57    1,558    4.48    6,915 
Measured + Indicated   99,143    0.61    1,959    4.56    7,424 
Inferred   15,784    0.34    172    2.65    111 

 

Sulphide

 

Dark Star Mineral Resources  Kt   g/t Au   Koz Au   g/t Ag   Koz Ag 
Measured – Open Pit                         
Indicated -Open Pit   1,373    2.09    92         
Measured + Indicated – Open Pit   1,373    2.09    92           
Inferred - Open Pit                         
Inferred - Underground   345    3.72    41           

 

North Bullion Deposits Mineral Resources  Kt   g/t Au   Koz Au   g/t Ag   Koz Ag 
North Bullion Indicated - Open Pit   4,983    2.31    370         
North Bullion Inferred - Open Pit   3,592    2.17    251           
North Bullion Inferred - Underground   381    3.17    39           
POD/SH/SL Indicated – Open Pit   406    2.91    38           
POD/SH/SL Inferred – Open Pit   169    2.76    15           

 

 

 

 

ALL SULPHIDE  Kt   g/t Au   Koz Au   g/t Ag   Koz Ag 
Measured                    
Indicated   6,672    2.30    500         
Measured + Indicated   6,672    2.30    500           
Inferred   4,514    2.39    347           

 

Notes - Dark Star, Pinion, Jasperoid Wash and North Bullion Deposits.

 

1.The estimate of Mineral Resources was done by Michael S. Lindholm, CPG of RESPEC in Imperial tons.

2.In-situ Mineral Resources are classified in accordance with CIM Standards.

3.The base cases for all Mineral Resources are reported at a gold price of $2,800 oz Au and have an effective date of September 30, 2025.

4.Tabulations comprise all model blocks at variable cutoff grades for oxide/transitional and sulphide materials within the $2,800 optimized pits or within a 2.57 Au g/t grade shell for underground. Pit optimizations vary by deposit and throughput rates of 11 kt/day and 18 kt/day; waste mining costs of US$2.34/t mined to US$2.43/t mined; crushing, stacking and heap leaching costs of US$4.01/t to US$4.94/t; and general and administrative costs of $1.26/t. At North Bullion, transportation costs of $44.09/t are applied for shipping refractory material off-site.

5.Recoveries are calculated within each block model, and vary by deposit, ore-type, redox state, sulphide-sulfur and inorganic-carbon content, and gold and silver grade. At Dark Star, assumed minimum metallurgical recoveries of 65% and 70% for gold for ROM and crushed ore, respectively, are applied; At Pinion, assumed variable metallurgical recoveries with base cases at 53% and 70% for gold for ROM and crushed ore, respectively, and base cases at 5% and 15% for silver for ROM and crushed ore, respectively.

6.The average grades of the tabulations are comprised of the weighted average of block-diluted grades within the optimized pits.

7.Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

8.Rounding may result in apparent discrepancies between tons, grade, and contained metal content.

9.Silver resources from Pinion only, silver grade is based on Pinion tonnes.

 

Pony Creek Estimated Mineral Resources

 

Pony Creek Mineral Resources  Material Type  Kt   Au   Au 
      (kmt)   (g/t)   (koz) 
Bowl Inferred – Open Pit  Heap Leach   3,298    0.50    53 
   VAT Leach   19,763    0.50    317 
Appaloosa Inferred – Open Pit  Heap Leach   9    0.28    0 
   VAT Leach   3,541    0.51    59 
Stallion Inferred – Open Pit  Heap Leach   7,755    0.21    53 
   VAT Leach   1,052    0.35    12 
All Inferred – Open Pit  Heap Leach   11,061    0.30    105 
   VAT Leach   24,356    0.49    387 

  

Notes - Pony Creek Resources:

 

1.The estimate of Mineral Resources was completed by Warren Black, M.Sc., P.Geo., APEX.

2.Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

3.There are no known legal, political, environmental or other risks that could materially affect the potential development.

4.The Inferred Mineral Resource in this estimate has a lower level of confidence and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of the Inferred Mineral Resource could potentially be upgraded to an Indicated Mineral Resource with continued exploration.

5.The Mineral Resources were estimated in accordance with the CIM Standards on Mineral Resources and Reserves, Definitions (2014) and Best Practices Guidelines (2019) prepared by the CIM Standing Committee on Reserve Definitions and adopted by the CIM Council.

6.The reported open-pit resources utilize a cutoff of 0.103 Au g/t Au for heap leach and 0.17 Au g/t for vat leach material.

7.Economic assumptions used include US$2,800/oz Au, process recoveries of 75% for Au in heap leach material and 85% for Au in vat leach material, a processing cost of US$1.90/t for heap leach and US$6.70/t for vat leach material, and a G&A cost of US$0.56/t.

8.The base cases for all Mineral Resources have an effective date of September 30, 2025.

9.The constraining pit optimization parameters included a mining cost of US$2.49/t for both mineralized and waste material and assumed pit slope angles of 45°.

 

 

 

 

Figure 1: South Railroad Site Plan Layout

 

 

5.2            Disclosure for Restructuring Transactions

 

Not applicable.

 

6.            Reliance on Subsection 7.1(2) of National Instrument 51-102

 

Not applicable.

 

7.            Omitted Information

 

Not applicable.

 

8.            Executive Officer

 

The name of the executive officer of the Company who is knowledgeable about the material change and this report is:

 

Jason Simpson

 

President and Chief Executive Officer

 

Tel: 604-564-1852

 

9.            Date of Report

 

January 21, 2026

 

 

 

 

Forward-looking Statements

 

This material change report contains certain “forward-looking information” and “forward-looking statements” within the meaning of Canadian securities legislation and within the meaning of Section 27A of the United States Securities Act of 1933, as amended, Section 21E of the United States Exchange Act of 1934, as amended, the United States Private Securities Litigation Reform Act of 1995, or in releases made by the United States Securities and Exchange Commission, all as may be amended from time to time, including, without limitation, statements regarding: the timing of permitting, construction and production at South Railroad; the Company’s ability to reach 500 koz of annual gold production; the results of the FS, including projected NPV, IRR, production, grades, recovery, revenue, costs, taxes, sensitivities, cash flows, mine life, payback periods and other similar information; the Company’s pre-construction capital commitments; the Company’s ability to finance development of South Railroad through operating cash flow and existing liquidity; mineral resource and reserve estimates; the Company’s anticipated exploration programs for the South Carlin Complex; further upside, growth potential, mineral resource and reserve expansion and mine life extension as a result of the Company’s exploration programs; and the Company’s goals and strategies. Forward-looking statements are statements that are not historical facts which address events, results, outcomes or developments that the Company expects to occur. Forward-looking statements are based on the beliefs, estimates and opinions of the Company’s management on the date the statements are made and they involve a number of risks and uncertainties. Certain material assumptions regarding such forward-looking statements were made, including without limitation, assumptions regarding: the future price of gold and silver; anticipated costs and the Company’s ability to fund the development of the South Railroad Project and its other programs; the Company’s ability to carry on exploration, development, and mining activities; the Company’s ability to successfully integrate the Musselwhite Mine; tonnage of ore to be mined and processed; ore grades and recoveries; decommissioning and reclamation estimates; currency exchange rates remaining as estimated; prices for energy inputs, labour, materials, supplies and services remaining as estimated; the Company’s ability to secure and to meet obligations under property agreements, including the layback agreement with Fresnillo plc; that all conditions of the Company’s credit facility will be met; the timing and results of drilling programs; mineral reserve and mineral resource estimates and the assumptions on which they are based; the discovery of mineral resources and mineral reserves on the Company’s mineral properties; that political and legal developments will be consistent with current expectations; the timely receipt of required approvals and permits, including those approvals and permits required for successful project permitting, construction, and operation of South Railroad; the timing of cash flows; the costs of operating and exploration expenditures; the Company’s ability to operate in a safe, efficient, and effective manner; the Company’s ability to obtain financing as and when required and on reasonable terms; that the Company’s activities will be in accordance with the Company’s public statements and stated goals; and that there will be no material adverse change or disruptions affecting the Company or its properties. Consequently, there can be no assurances that such statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements. Forward-looking statements involve significant known and unknown risks and uncertainties, which could cause actual results to differ materially from those anticipated. These risks include, but are not limited to: uncertainty and variations in the estimation of mineral resources and mineral reserves; risks related to the Company’s indebtedness and gold prepayment; risks related to exploration, development, and operation activities; foreign country and political risks, including risks relating to foreign operations; tailings risks; reclamation costs; delays in obtaining or failure to obtain governmental permits, or non-compliance with permits; environmental and other regulatory requirements; loss of, delays in, or failure to get access from surface rights owners; uncertainties related to title to mineral properties; water rights; risks related to natural disasters, terrorist acts, health crises, and other disruptions and dislocations; financing risks and access to additional capital; risks related to guidance estimates and uncertainties inherent in the preparation of feasibility studies; uncertainty in estimates of production, capital, and operating costs and potential production and cost overruns; the fluctuating price of gold and silver; risks related to the Cerro Quema Project; unknown labilities in connection with acquisitions; global financial conditions; uninsured risks; climate change risks; competition from other companies and individuals; conflicts of interest; risks related to compliance with anti-corruption laws; volatility in the market price of the Company's securities; assessments by taxation authorities in multiple jurisdictions; foreign currency fluctuations; the Company’s limited operating history; litigation risks; the Company’s ability to identify, complete, and successfully integrate acquisitions; intervention by non-governmental organizations; outside contractor risks; risks related to historical data; risks related to the Company’s foreign subsidiaries; risks related to the Company’s accounting policies and internal controls; the Company’s ability to satisfy the requirements of Sarbanes–Oxley Act of 2002; enforcement of civil liabilities; the Company’s status as a passive foreign investment company (PFIC) for U.S. federal income tax purposes; information and cyber security; gold industry concentration; shareholder activism; other risks associated with executing the Company’s objectives and strategies; as well as those risk factors discussed in the Company's most recently filed management's discussion and analysis, as well as its annual information form dated March 18, 2025, which are available on www.sedarplus.ca and www.sec.gov. Except as required by the securities disclosure laws and regulations applicable to the Company, the Company undertakes no obligation to update these forward-looking statements if management’s beliefs, estimates or opinions, or other factors, should change.

 

Non-GAAP Measures

 

The Company has included herein certain performance measures (“non-GAAP measures”) which are not specified, defined, or determined under generally accepted accounting principles (“GAAP”). These non-GAAP measures are common performance measures in the gold mining industry, but because they do not have any mandated standardized definitions, they may not be comparable to similar measures presented by other issuers. Accordingly, we use such measures to provide additional information, and readers should not consider these non-GAAP measures in isolation or as a substitute for measures of performance prepared in accordance with GAAP. As South Railroad is not in production, it does not have historical non-GAAP financial measures nor historical comparable measures under IFRS, and therefore the foregoing prospective non-GAAP financial measures or ratios may not be reconciled to the nearest comparable measures under IFRS.

 

All-In Sustaining Cost

 

The Company has provided AISC performance measures that reflect all the expenditures that are required to produce an ounce of gold from operations. While there is no standardized meaning of the measure across the industry, the Company’s definition conforms to the AISC definition as set out by the World Gold Council in its guidance dated November 14, 2018. Orla believes that this measure is useful to market participants in assessing operating performance and the Company’s ability to generate cash flow from operating activities.

 

Cash Costs

 

The Company calculated total cash costs as the sum of operating costs, royalty costs, production taxes, refining and shipping costs, net of by-product silver credits. Cash costs per ounce is calculated by taking total cash costs and dividing such amount by payable gold ounces. While there is no standardized meaning of the measure across the industry, the Company believes that this measure is useful to external users in assessing operating performance.

 

Cautionary Note to U.S. Readers

 

This material change report has been prepared in accordance with Canadian standards for the reporting of mineral resource and mineral reserve estimates, which differ from the previous and current standards of the United States securities laws. In particular, and without limiting the generality of the foregoing, the terms “mineral reserve”, “proven mineral reserve”, “probable mineral reserve”, “inferred mineral resources”, “indicated mineral resources”, “measured mineral resources” and “mineral resources” used or referenced in this material change report are Canadian mineral disclosure terms as defined in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum (the “CIM”) – CIM Definition Standards on Mineral Resources and Mineral Reserves, adopted by the CIM Council, as amended (the “CIM Definition Standards”).

 

 

 

 

For United States reporting purposes, the United States Securities and Exchange Commission (“SEC”) has adopted amendments to its disclosure rules (the “SEC Modernization Rules”) to modernize the mining property disclosure requirements for issuers whose securities are registered with the SEC under the Securities Exchange Act of 1934, as amended. The SEC Modernization Rules more closely align the SEC’s disclosure requirements and policies for mining properties with current industry and global regulatory practices and standards, including NI 43-101, and replace the historical property disclosure requirements for mining registrants that were included in Industry Guide 7 under the U.S. Securities Act. As a foreign private issuer that is eligible to file reports with the SEC pursuant to the multijurisdictional disclosure system (MJDS), the Company is not required to provide disclosure on its mineral properties under the SEC Modernization Rules and provides disclosure under NI 43-101 and the CIM Definition Standards. Accordingly, mineral reserve and mineral resource information contained in this material change report may not be comparable to similar information disclosed by United States companies.

 

As a result of the adoption of the SEC Modernization Rules, the SEC now recognizes estimates of “measured mineral resources”, “indicated mineral resources” and “inferred mineral resources.” In addition, the SEC has amended its definitions of “proven mineral reserves” and “probable mineral reserves” to be “substantially similar” to the corresponding CIM Definition Standards that are required under NI 43-101. While the above terms are “substantially similar” to CIM Definition Standards, there are differences in the definitions under the SEC Modernization Rules and the CIM Definition Standards. There is no assurance any mineral reserves or mineral resources that the Company may report as “proven mineral reserves”, “probable mineral reserves”, “measured mineral resources”, “indicated mineral resources” and “inferred mineral resources” under NI 43-101 would be the same had the Company prepared the reserve or resource estimates under the standards adopted under the SEC Modernization Rules. Accordingly, information contained in this material change report may not be comparable to similar information made public by U.S. companies subject to the reporting and disclosure requirements under the United States federal securities laws and the rules and regulations thereunder.

 

 

i Non-GAAP measure. Refer to the “Non-GAAP Measures” section of this press release.

 

 

 

FAQ

What is the main update Orla Mining (ORLA) provided in this Form 6-K?

The company filed a material change report summarizing an updated feasibility study for its South Railroad gold project in Nevada, detailing reserves, costs, economics, permitting status, and execution plans.

What are the projected economics for Orla Mining's South Railroad project?

At $3,100/oz gold and $36.50/oz silver, the study estimates average annual gold production of 103,756 ounces, an after-tax NPV 5% of $783 million, an after-tax IRR of 48%, and a 2.0-year after-tax payback.

What mineral reserves and resources does Orla Mining report for South Railroad?

Proven and probable mineral reserves total 66.6 million tonnes at 0.71 g/t gold and 5.08 g/t silver for 1.52 million ounces of gold and 6.20 million ounces of silver. Measured and indicated mineral resources total 105.9 million tonnes at 0.72 g/t gold for 2.46 million ounces of gold, inclusive of reserves.

What are the estimated capital and operating costs for South Railroad?

Initial capital is estimated at $395 million, with life-of-mine sustaining capital of $202 million and closure costs of $29 million. Average life-of-mine operating costs are $18.00/t ore, with total cash costs of $1,207/oz and AISC of $1,505/oz of gold.

Where does permitting stand for Orla Mining's South Railroad project?

The project is advancing under NEPA as a FAST-41 Covered Project. Federal NEPA and USACE Section 404 public comment periods closed in September 2025 without significant issues, and the BLM Record of Decision is targeted for mid-2026, alongside ongoing state-level water and discharge permitting.

When does Orla Mining expect to start and complete construction at South Railroad?

Construction is expected to begin in mid-2026, subject to final permits and regulatory authorization, and is expected to take approximately 18 months to complete, based on the disclosed execution schedule.

What non-GAAP measures does Orla Mining use in this South Railroad study?

The company uses non-GAAP measures including total cash costs and all-in sustaining costs (AISC) per ounce of gold, calculated from operating, royalty, tax, refining, and sustaining capital components, following World Gold Council guidance.