STOCK TITAN

Santacruz Silver buys 500 tpd Bolivia mill

Santacruz Silver is investing about US$14 million in a new 500 tpd Bolivian milling facility to expand third-party processing and unlock additional capacity at its existing mines.

(Neutral)
(Neutral)
Form Type
6-K

Rhea-AI Filing Summary

Santacruz Silver Mining Ltd. (SCZM) has completed the acquisition of a 500-tonne-per-day milling facility in Bolivia, consisting of two 250 tpd circuits with selective flotation for lead and zinc with high-grade silver. The facility will be dedicated to ore from its wholly owned Bolivian subsidiary, San Lucas, supporting expansion of its third-party ore-sourcing business.

By shifting San Lucas material to this new plant, Santacruz expects to free capacity at its three existing mine processing facilities, enabling further mine development and production growth from its Bolivian operations. The mill is about 5 kilometres from the Reserva mine, providing logistical advantages within the Caballo Blanco group.

The facility is expected to be commissioned in the fourth quarter of 2026 and reach commercial production by year-end 2026. Total investment is anticipated at about US$14 million, including a US$9.2 million purchase price—of which US$4.6 million has been paid and US$4.6 million is due on November 8, 2026—and US$4.8 million for upgrades and working capital.

Positive

  • Acquisition of a 500 tpd milling facility in Bolivia increases dedicated processing capacity for the San Lucas business.
  • Planned total investment of about US$14 million is expected to free capacity at existing mine plants, supporting production growth from Santacruz’s own Bolivian operations.
  • The facility’s location about 5 km from the Reserva mine provides logistical benefits within a key operating district.

Negative

  • Santacruz is committing approximately US$14 million of capital, including US$4.6 million still payable on November 8, 2026 and US$4.8 million for upgrades and working capital, creating execution and cost risks highlighted in its forward-looking statements.
Milling facility capacity 500 tonnes per day Total capacity of newly acquired Bolivian milling facility
Total anticipated investment US$14 million Acquisition, commissioning and costs to reach commercial production
Purchase price US$9.2 million Total consideration for the milling facility
Initial payment US$4.6 million Already paid toward the US$9.2 million purchase price
Deferred payment US$4.6 million Remaining purchase price payable November 8, 2026
Upgrades and working capital US$4.8 million Allocated to milling upgrades and working capital through commissioning
Distance from Reserva mine 5 kilometres Approximate location of the new facility relative to Reserva mine
Commissioning start Fourth quarter 2026 Expected start of commissioning for the new mill
selective flotation technical
"each equipped with selective flotation systems for the recovery of lead"
vertically integrated financial
"strengthens Santacruz’s vertically integrated operating model in Bolivia"
Vertically integrated describes a company that owns and controls multiple steps in making and selling its products or services — for example sourcing raw materials, manufacturing, and distribution. Like a bakery that grows its own wheat, mills the flour, bakes the bread and runs the shops, this setup can lower costs, improve quality and speed to market and protect profit margins, but it also requires more capital and can reduce flexibility.
commercial production financial
"expected to be commissioned during the fourth quarter of 2026 and to reach commercial production"
Commercial production is the full-scale manufacturing and release of a product for sale to customers after development and any required approvals. It matters to investors because it signals a shift from testing and one-off batches to steady revenue, larger costs for facilities and supplies, and risks around meeting demand and quality standards — like turning a home-cooked recipe into a restaurant menu that must be produced consistently and profitably.
third-party ore-sourcing business financial
"capacity to support continued expansion of its third-party ore-sourcing business"
commissioning technical
"Commissioning activities will include the testing and optimization of the milling"
Commissioning is the process of officially starting or activating a new project, system, or facility after it has been built or prepared. It involves testing and checking that everything functions correctly and safely before it begins full operation. For investors, commissioning signals that a project or asset is moving closer to generating value or revenue, which can impact its potential profitability and timing of returns.

FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

What did Santacruz Silver Mining Ltd. (SCZM) acquire in Bolivia?

Santacruz Silver acquired a 500-tonne-per-day milling facility in Bolivia, with two 250 tpd selective flotation circuits for lead and zinc with high-grade silver. The plant will process ore from its wholly owned Bolivian subsidiary, San Lucas, supporting expansion of third-party ore sourcing.

How much will Santacruz Silver (SCZM) invest in the new milling facility?

Santacruz expects a total investment of about US$14 million, including a US$9.2 million purchase price and US$4.8 million for milling upgrades and working capital through commissioning and commercial production.

What is the payment structure for Santacruz Silver’s (SCZM) milling facility purchase?

The total purchase price is US$9.2 million. Santacruz has already paid US$4.6 million, with the remaining US$4.6 million payable on November 8, 2026, one month after receipt of the milling facility expected on October 8, 2026.

When will the new Santacruz Silver (SCZM) mill start operating?

The milling facility is expected to be commissioned in the fourth quarter of 2026 and to reach commercial production by year-end 2026, following testing, optimization, and ramp-up of the milling and selective flotation circuits.

How will the new mill affect Santacruz Silver’s (SCZM) existing mines?

By moving San Lucas ore to the new mill, Santacruz expects to free capacity at its three existing mine processing facilities in Bolivia, allowing mine development plans and production from its own operations to advance without competing for processing capacity.

Where is Santacruz Silver’s new milling facility located relative to its mines?

The acquired facility is located approximately 5 kilometres from the Reserva mine, which is part of the Caballo Blanco group of mines in Bolivia, providing logistical and operational advantages within one of Santacruz’s key operating districts.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google
Learn about SEC filing dates

 

 

 

UNITED STATES

SECURITIES AND EXCHANGE COMMISSION

Washington, D.C. 20549

 

FORM 6-K

 

Report of Foreign Private Issuer

Pursuant to Rule 13a-16 or 15d-16

UNDER the Securities Exchange Act of 1934

 

For the month of September 2026

 

Commission File No.: 001-43051

 

Santacruz Silver Mining Ltd.

(Translation of registrant’s name into English)

 

480 - 1140 West Pender Street

Vancouver, British Columbia

Canada V6E 4G1

(Address of principal executive office)

 

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F: Form 20-F ☐ Form 40-F ☒

 

 

 

 

 

 

EXHIBIT INDEX

 

Exhibit   Description
99.1   News release dated September 18, 2026

 

 

 

 

SIGNATURE

 

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

 

  Santacruz Silver Mining Ltd.
   
Date: September 18, 2026 By: /s/ Andres Bedregal
  Name: Andres Bedregal
  Title: Chief Financial Officer

 

 

 

 

 

Exhibit 99.1

 

News Release

 

September 18, 2026

 

Santacruz Silver Acquires New 500-Tonne-Per-Day Milling Facility to Unlock Further Production Growth in Bolivia

 

Acquisition Provides Dedicated Processing Capacity for San Lucas While Releasing Additional Capacity Across Existing Mines

 

Vancouver, B.C. – Santacruz Silver Mining Ltd. (NASDAQ: SCZM) (TSX.V:SCZ) (“Santacruz” or the “Company”) is pleased to announce that it has completed the acquisition of a 500-tonne-per-day (“tpd”) milling facility located in Bolivia, comprising two 250-tonne-per-day processing circuits, each equipped with selective flotation systems for the recovery of lead and zinc with high-grade silver contents. The newly acquired facility will be solely dedicated to processing ore sourced through the Company’s wholly-owned Bolivian subsidiary, San Lucas, providing additional milling capacity to support continued expansion of its third-party ore-sourcing business.

 

By transitioning materials from San Lucas to the acquired facility, Santacruz will free up capacity at its existing three mine processing facilities, allowing the Company to advance its mine development plans and increase production from its own operations in Bolivia without internally competing for available processing capacity.

 

Strategically located approximately 5 kilometres from Santacruz’s Reserva mine, part of the Company’s Caballo Blanco group of mines, the acquired facility provides logistical and operational advantages as Santacruz continues to develop and expand its Bolivian asset base. The acquisition also strengthens Santacruz’s vertically integrated operating model in Bolivia by providing greater flexibility and control over the processing of third-party sourced ore. Together with the Company’s existing facilities, it establishes an expanded processing platform in one of Santacruz’s key operating districts, supporting longer-term production and development plans.

 

The facility is expected to be commissioned during the fourth quarter of 2026 and to reach commercial production by year-end 2026. Commissioning activities will include the testing and optimization of the milling and selective flotation circuits, followed by the ramp-up of operations toward commercial production. The total investment in the milling facility is expected to be approximately US$14 million, inclusive of acquisition, commissioning and all costs required to bring the facility to commercial production.

 

Arturo Préstamo, Executive Chairman and CEO of Santacruz, commented: “This acquisition is a win-win for Santacruz’s operating platform. The addition of 500 tpd of milling capacity gives San Lucas a clear path to continue increasing its volumes, while freeing up capacity at our existing milling facilities for ore from our own mines. This will allow our mining operations to advance their development and production growth plans without being constrained by milling capacity. This is exactly the type of operating leverage we look for at Santacruz—one investment that allows two parts of our business to grow at the same time.”

 

Mr. Préstamo continued: “The new facility also creates a significant opportunity to accelerate growth across our Bolivian operations. We expect the additional processing capacity, together with ongoing mine development, operational optimization initiatives and increased ore availability, to support continued production growth across Santacruz’s platform. As a result, we anticipate increased consolidated production in 2027, while San Lucas is expected to further expand its standalone production, demonstrating the scalability and operating leverage of the Company’s vertically integrated Bolivian platform. Importantly, this acquisition is consistent with Santacruz’s strategy of leveraging our existing infrastructure, expanding processing capacity and maximizing production growth while maintaining a disciplined approach to capital allocation.”

 

 1

 

 

Transaction Details

 

The Company has paid US$4.6 million toward the US$9.2 million total purchase price, with the remaining US$4.6 million payable on November 8, 2026, one month following receipt of the milling facility, expected on October 8, 2026. A further US$4.8 million will be allocated to milling upgrades and working capital through commissioning and the achievement of commercial production.

 

About Santacruz Silver Mining Ltd.

 

Santacruz Silver is engaged in the operation, acquisition, exploration, and development of mineral properties across Latin America. In Bolivia, the Company operates the Bolivar, Porco, and Caballo Blanco mining complexes, with Caballo Blanco comprising the Tres Amigos and Colquechaquita mines. The Reserva mine, whose production is provided to the San Lucas ore sourcing and trading business, is also located in Bolivia. Additionally, the Company oversees the Soracaya exploration project. In Mexico, Santacruz operates the Zimapan mine.

 

‘signed’

 

Arturo Préstamo Elizondo,

Executive Chairman and CEO

 

For further information, please contact:

 

Arturo Préstamo

Santacruz Silver Mining Ltd.

Email: info@santacruzsilver.com

Telephone: +52 81 83 785707

 

Andrés Bedregal

Santacruz Silver Mining Ltd.

Email: info@santacruzsilver.com

Telephone: +591 22444849

 

Eduardo Torrecillas

Santacruz Silver Mining Ltd.

Email: info@santacruzsilver.com

Telephone: +591 22444849

 

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) nor the Nasdaq Capital Market LLC accepts responsibility for the adequacy or accuracy of this news release. No stock exchange, securities commission or other regulatory authority has approved or disapproved the information contained herein.

 

Cautionary and Forward-Looking Statements

 

This release includes certain statements and information that may constitute forward-looking information within the meaning of applicable Canadian securities laws. Forward-looking statements relate to future events or future performance and reflect the expectations or beliefs of management of the Company regarding future events. Generally, forward-looking statements and information can be identified by the use of forward-looking terminology such as “intends” or “anticipates”, or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “should”, “would” or “occur”. This information and these statements, referred to herein as “forward-looking statements”, are not historical facts, are made as of the date of this news release and include without limitation, statements regarding the expected commissioning and commercial production timeline for the newly acquired milling facility, the anticipated total investment of approximately US$14 million, the expected increase in processing capacity and its impact on production growth, the freeing up of capacity at existing mine processing facilities, anticipated increased consolidated production in 2027, and the expected expansion of San Lucas’s standalone production.

 

Such forward-looking information and statements are based on numerous assumptions, including among others, that the acquired milling facility will be commissioned on schedule and achieve commercial production by year-end 2026, that the total investment will not materially exceed the anticipated US$14 million, that the transition of San Lucas ore to the new facility will proceed as planned, and that market conditions will support continued production growth. Although the assumptions made by the Company in providing forward-looking information or making forward-looking statements are considered reasonable by management at the time, there can be no assurance that such assumptions will prove to be accurate.

 

These forward-looking statements involve numerous risks and uncertainties and actual results might differ materially from results suggested in any forward-looking statements. These risks and uncertainties include, among other things, the risk that the commissioning of the milling facility may not be completed on the anticipated timeline or at all, that costs may exceed expectations, that the facility may not achieve the expected processing capacity, and that market, operational or regulatory conditions may adversely affect production growth plans.

 

Although management of the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements or forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements and forward-looking information. Readers are cautioned that reliance on such information may not be appropriate for other purposes. The Company does not undertake to update any forward-looking statement, forward-looking information or financial outlook that are incorporated by reference herein, except in accordance with applicable securities laws. We seek safe harbour.

 

 2

 

 

Filing Exhibits & Attachments

3 documents

Keep reading