Sunshine Silver plans late-2028 mine production return

Sunshine Silver Mining & Refining Co (SSMR) reported operational-readiness progress at the Sunshine Mine, supporting a feasibility study targeted for the second quarter of 2027 and a planned return to production in late 2028.

(Moderate)

Sentiment and the balance of points

Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

Form Type
8-K

Rhea-AI Filing Summary

Sunshine Silver Mining & Refining Co (SSMR) reported operational-readiness progress at the Sunshine Mine, supporting a feasibility study targeted for the second quarter of 2027 and a planned return to production in late 2028. Underground development totaled approximately 1,200 meters in the first half of 2026; the company expects approximately 1,300 additional meters in the second half, with approximately 700 meters completed as of September 30, 2026. The 50,000-meter infill drilling program had reached approximately 47,600 meters as of that date, and additional results are expected before year-end.

The company installed approximately 1,200 meters of new rail through September 30 and anticipates another 1,900 meters by year-end; fleet expansion includes acquisition of approximately 20 pieces of mobile equipment. A new production hoist servicing the Jewell Shaft was completed in May 2026; Silver Summit Shaft upgrades are underway, with broader improvements continuing through 2027 and into early 2028. An additional Sterling Ramp portal is expected in the first half of 2027. Legacy mill demolition, begun in 2025, is expected to finish by year-end. The plan assumes initial processing of up to approximately 1,000 tons per day, with the facility designed for potential future throughput up to approximately 2,000 tons per day.

Item 7.01 Regulation FD Disclosure Disclosure
Material non-public information disclosed under Regulation Fair Disclosure, often investor presentations or guidance.
Item 9.01 Financial Statements and Exhibits Exhibits
Financial statements, pro forma financial information, or exhibit attachments filed with this report.
Underground development completed Approximately 1,200 meters First half of 2026
Additional underground development expected Approximately 1,300 meters Second half of 2026
Second-half underground development completed Approximately 700 meters As of September 30, 2026
Infill drilling program 50,000 meters Underground program
Infill drilling completed Approximately 47,600 meters As of September 30, 2026
New underground rail installed Approximately 1,200 meters Through September 30, 2026
Additional underground rail anticipated 1,900 meters By year-end
Planned processing throughput Up to approximately 1,000 tons per day initially; designed for potential future throughput up to approximately 2,000 tons per day Current development plan
infill drilling program technical
"50,000-meter infill drilling program"
An infill drilling program is a planned set of additional drill holes placed between earlier holes to create a tighter grid of samples and more detailed information about a mineral deposit. For investors, it matters because the denser data lowers uncertainty about how much ore exists and its quality—think of adding pixels to a blurry picture—helping turn speculative estimates into more reliable categories used for valuation, financing and mine planning.
production hoist technical
"new production hoist servicing the Jewell Shaft"
hoist re-drive technical
"complete a hoist re-drive"
access portal technical
"developing an additional portal within the Sterling Ramp system"
throughput technical
"potential future throughput increases"
Throughput is the amount of stuff, like products or data, that a system can handle or move through in a certain period of time. For example, a factory’s throughput is how many items it produces each hour, and it matters because higher throughput usually means things are running efficiently and meeting demand quickly.

FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

How much underground drilling has SSMR completed at the Sunshine Mine?

Sunshine had completed approximately 47,600 meters of its 50,000-meter underground infill drilling program as of September 30, 2026. The second-half program, focused on downshaft drilling, was largely complete, and the company expected to report additional results before year-end.

What processing capacity is planned at the Sunshine Mine?

The current development plan assumes initial processing of up to approximately 1,000 tons per day. The facility and associated infrastructure are being designed to accommodate potential future throughput increases up to approximately 2,000 tons per day.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google
Available on EDGAR Accepted by SEC EDGAR Learn about SEC filing dates
FALSE000209101700020910172026-10-192026-10-19

UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
FORM 8-K
CURRENT REPORT
Pursuant to Section 13 or 15(d) of the Securities Exchange Act of 1934
Date of Report (Date of earliest event reported): October 19, 2026
SUNSHINE SILVER MINING & REFINING COMPANY
(Exact name of Registrant as Specified in Its Charter)
Delaware001-4332585-3794822
(State or Other Jurisdiction
of Incorporation)
(Commission File Number)
(IRS Employer
Identification No.)

2209 Big Creek Rd

Kellogg, Idaho
83837
 (Address of Principal Executive Offices)(Zip Code)
Registrant’s Telephone Number, Including Area Code: (208) 783-1700
Not Applicable
(Former Name or Former Address, if Changed Since Last Report)
Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions:

☐Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)
☐Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)
☐Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))
☐Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))

Securities registered pursuant to Section 12(b) of the Act:
Title of each classTrading Symbol(s)Name of each exchange on which registered
common stock, par value $0.001 per shareSSMRNew York Stock Exchange
Indicate by check mark whether the registrant is an emerging growth company as defined in Rule 405 of the Securities Act of 1933 (§ 230.405 of this chapter) or Rule 12b-2 of the Securities Exchange Act of 1934 (§ 240.12b-2 of this chapter).
Emerging growth company ☑
If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act. ☐







    
Item 7.01     Regulation FD Disclosure.

On October 19, 2026, Sunshine Silver Mining & Refining Company issued a press release announcing progress on operational readiness, including underground development, major infrastructure upgrades, and site-preparation. A copy of the press release is furnished as Exhibit 99.1 to this Current Report on Form 8-K.

The information included herein and in Exhibit 99.1 shall not be deemed “filed” for purposes of Section 18 of the Securities Exchange Act of 1934, as amended (the “Exchange Act”), or otherwise subject to the liabilities of that section, nor shall it be deemed incorporated by reference in any filing under the Securities Act of 1933, as amended, or the Exchange Act.
Item 9.01     Financial Statements and Exhibits.
(d) Exhibits

Exhibit No.Description
99.1
Press Release dated October 19, 2026
104Cover Page Interactive Data File (embedded within the Inline XBRL document)




SIGNATURE
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned hereunto duly authorized.

SUNSHINE SILVER MINING & REFINING COMPANY
By:/s/ Michelle Shepston
Michelle Shepston
Date: October 19, 2026General Counsel


image_0a.jpg
Sunshine Silver Mining & Refining Advances Operational Readiness at the Sunshine Mine
Underground development, major infrastructure upgrades and site-preparation continue at the Sunshine Mine in support of its planned return to production in late 2028
KELLOGG, Idaho, October 19, 2026 -- Sunshine Silver Mining & Refining Company (NYSE: SSMR) (“Sunshine” or the “Company”), a mining company advancing the next chapter of American silver, today provided an update on operational readiness activities at the Sunshine Mine in Idaho’s Silver Valley — the most prolific silver district in the United States. The Company’s ongoing operational readiness program is focused on advancing underground development, modernizing critical infrastructure and preparing surface facilities in support of a feasibility study targeted for completion in the second quarter of 2027 and the Sunshine Mine’s planned return to production in late 2028.
Recent notable progress includes:
•Advancement of underground development, rehabilitation and drilling activities, supported by continued investment in new underground mining equipment;
•Initiation of the multiphase Silver Summit Hoist and Shaft upgrade project and completion of the new production hoist servicing the Jewell Shaft; and
•Development of an additional access portal within the Sterling Ramp system, which services the Upper Country of the mine.
In parallel with underground readiness activities, Sunshine continues to advance site preparation work through demolition of the legacy mill and related infrastructure. The work, which began in 2025, is expected to be completed by year-end and is intended to prepare the site for construction of a new processing facility contemplated in the Company’s current development plan. The plan presently assumes initial processing of up to approximately 1,000 tons per day, however, along with associated infrastructure, it is being designed to accommodate potential future throughput increases up to approximately 2,000 tons per day — providing flexibility as the Sunshine Mine advances through feasibility and toward a construction decision.
“Our team is safely advancing the work needed to prepare the Sunshine Mine for both a future construction decision and planned return to production in late 2028,” said Heather White, Chief Executive Officer of Sunshine. “The progress underway above and below ground is optimizing mine access, strengthening critical infrastructure, and preparing the site for future construction, long-term production requirements as well as growth opportunities. Our efforts are supporting the feasibility study and laying the foundation for the mine’s next phase of development.”
Dr. Thomas S. Kaplan, Chairman of Sunshine, shared: “The Sunshine Mine is an exceptional North American silver asset, distinguished by its combination of world-beating silver grade, large scale, excellent growth potential in terms of both resources and production, and remarkable history of proven production. Most encouragingly, the considerable progress reported today reflects sustained disciplined investment in






infrastructure and access that should strengthen an already extraordinary asset. As we advance toward completion of the feasibility study, we continue to believe that Sunshine represents a truly unique opportunity to gain singular exposure to silver as well as critical minerals production and processing in the United States.”
The Sunshine Mine benefits from an extensive network of existing and upgraded underground workings and multiple access points, including the Jewell Shaft, the Sterling Ramp and the Silver Summit Shaft. This infrastructure provides access to active development areas and supports the Company’s ongoing drilling, feasibility and mine preparation activities (see Figure 1).
Figure 1: Sunshine Mine Footprint as of October 2026
image_1a.jpg
Underground Development, Drilling and Rehabilitation
Sunshine continues to advance underground development and rehabilitation activities that support drilling, engineering studies and future mining access. During the first half of 2026, the Company completed approximately 1,200 meters of underground development and expects to complete approximately 1,300 additional meters during the second half of the year, of which approximately 700 meters had been completed as of September 30, 2026 (see Figure 1). The remaining development planned for 2026 is expected to be completed by year-end.
To support the growing scope of underground activities, Sunshine is expanding its underground mining fleet through the acquisition of approximately 20 pieces of mobile equipment for underground development and exploration use. These additions provide increased capacity for development, rehabilitation, and drilling activities and are an important component of the Company’s operational-readiness program.






Figure 2: Underground Development Work Underway on the 3100 Level
image_2a.jpg
Underground drilling continues as part of the Company’s 50,000-meter infill drilling program. As of September 30, 2026, Sunshine had completed approximately 47,600 meters of underground infill drilling (see Figure 3). The program is intended to increase confidence in the mineral resource and provide key technical inputs for the Sunshine Mine feasibility study, which remains on track for completion in the second quarter of 2027.
In July 2026, the Company reported results from the first half of its 50,000-meter infill drilling program, which focused on the Upper Country of the Sunshine Mine and returned multiple assays exceeding 1,000 grams per tonne silver (see Sunshine Silver Mining & Refining Press Release, July 23, 2026). The second half of the program, focused on downshaft drilling, is now largely complete, and Sunshine expects to report the additional drill results before year-end.






Figure 3: One of Three Active Underground Drill Rigs Supporting the 50,000-meter Infill Drilling Program
image_3a.jpg
As part of its underground rehabilitation program, Sunshine installed approximately 1,200 meters of new rail on the 3100 Level and in the ConSil-Silver Summit area through September 30, 2026, and anticipates installing an additional 1,900 meters by year-end. The new rail will improve underground logistics and support the safe and efficient movement of personnel, equipment and materials as development and drilling activities continue to advance (see Figure 4).






Figure 4: New Rail Infrastructure on the 3100 Level
image_4a.jpg
The Company is also developing an additional portal within the Sterling Ramp system. Expected to be completed during the first half of 2027, the portal will increase ventilation capacity and improve airflow as underground activities expand. The project is designed to support a safe underground working environment while enhancing the infrastructure needed for ongoing development, engineering and mine-planning programs.
Mine Shaft Access Upgrades
Sunshine recently initiated the Silver Summit Shaft Project, a multiphase upgrade of the Silver Summit Hoist, Shaft and related infrastructure. Through the remainder of 2026, the Company plans to continue upgrading the hoistroom and complete a hoist re-drive (see Figure 5), with broader shaft and infrastructure improvements continuing through 2027 and into early 2028.






Figure 5: Silver Summit Hoistroom Upgrade Before and After; Upgrades are Ongoing
image_5a.jpg
Upon completion, the approximately 5,400-foot-deep Silver Summit Shaft is expected to provide a second shaft-based access and egress route. Together with the Jewell Shaft and Sterling Ramp, it will establish multiple points of underground access, increasing redundancy and operational flexibility in support of the mine’s future development.
In May 2026, Sunshine completed a comprehensive installation and commissioning of a new primary production hoist servicing the Jewell Shaft. The approximately 4,000-foot-deep Jewell Shaft is the mine’s primary access point and is currently active down to the 3100 Level. The new hoist modernizes a critical component of the mine’s existing infrastructure and improves the reliability of personnel, equipment and material transport, as well as the hoisting of ore and waste (see Figure 6). The Jewell Shaft also supports ongoing underground development, rehabilitation, and drilling activities.
Figure 6: Video of New Production Hoist for the Jewell Shaft in Operation
image_6a.jpg
Legacy Mill Demolition and Site Preparation






Sunshine continues to advance surface site-preparation activities through demolition of the legacy mill and related infrastructure (see Figure 7). The work, which began in 2025, includes the removal of legacy equipment, structures and materials and is expected to be completed by year-end.
Figure 7: Legacy Mill Demolition Advances from April to October 2026
image_7a.jpg
Completion of these activities represents an important operational-readiness milestone and will prepare the site for the next phase of project development.
Operational-readiness activities are expected to continue through 2027 in parallel with the completion of the Sunshine Mine feasibility study, which remains targeted for the second quarter of 2027. Ongoing work will focus on underground development, drilling, infrastructure modernization and surface site preparation activities designed to support a future construction decision and the Company’s planned return to production in late 2028.
About Sunshine Silver Mining & Refining Company
Sunshine Silver Mining & Refining Company is advancing toward silver production from the Sunshine Mine in Idaho’s Silver Valley, the most prolific silver district in U.S. history. The Sunshine Mine is North America’s highest-grade primary silver resource. It is characterized by exceptional size, extraordinary growth potential, existing infrastructure, and a history of proven production. Sunshine, the largest holder of mineral rights in the Silver Valley, also controls a consolidated land position with significant exploration potential and is evaluating additional value opportunities through silver/copper refining and antimony production. For more information, visit www.sunshinesilvermining.com.
Contact Information
Mike Patterson
Vice President of Investors Relations and Corporate Development
mpatterson@silveropp.com






General Inquiries
ir@silveropp.com
Media Relations
ssmr@fleishman.com
Cautionary Statements
This press release contains forward-looking statements, including statements regarding the Company’s planned return to production in late 2028, the timing of completion of feasibility studies, the Sunshine Mine’s growth potential, plans to design the mill and associated infrastructure to accommodate potential future throughput of up to approximately 2,000 tons per day, the anticipated progress of underground development and infill drilling in 2026 and 2027 and the timing and benefits of ongoing and future site preparation and operational readiness activities. In some cases, forward-looking statements can be identified by words such as “anticipate,” “believe,” “continue,” “estimate,” “expect,” “intend,” “may,” “will,” “could,” “predict” and similar expressions or terminology. These statements are not historical facts but rather are based on the Company's current expectations and projections regarding its business, operations and other factors relating thereto and are subject to a number of known and unknown risks, uncertainties and other factors, including the risk factors set forth in our registration statement on Form S-1 filed with the Securities and Exchange Commission (“SEC”) and other filings that we make from time to time with the SEC, that may cause the actual results, levels of activity, performance or achievements of the Company to be materially different from those expressed or implied by any forward-looking statements. Except to the extent required by law, the Company assumes no obligation to update any of these forward-looking statements or to conform these statements to actual results or revised expectations. We caution you not to place undue reliance on these forward-looking statements.