Applied Digital Brings an Additional 75 MW of AI Infrastructure Online at Polaris Forge 1

The completed phase brings Building 2 to its full capacity within a campus contracted for further buildout.

(Moderate)

Sentiment and the balance of points

Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

Tags
AI

Applied Digital (NASDAQ: APLD) brought an additional 75 MW of AI infrastructure online at its Polaris Forge 1 campus. The second phase of Building 2 reached Ready for Service across three 25 MW data halls, completing the building’s full 150 MW of critical IT load, or power capacity for computing equipment.

Fully operational capacity at the Ellendale, North Dakota campus now totals 250 MW, following delivery of the first 100 MW building and Building 2’s initial 75 MW phase. The campus is fully leased and contracted to deliver 400 MW of critical IT load at full buildout.

Loading...
Loading translation...
2 points · 0 major

How this balance works

Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.

It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.

Rhea-AI Sentiment measures something else, the tone of the wording.

0 major · 0 points

Hollow bars mark forward-looking points. How the balance works

Positive

  • Moderate pointAn additional 75 MW is operational, completing Building 2’s 150 MW and bringing campus capacity to 250 MW.
  • Moderate point. Forward-looking: it has not happened yet and may not happen.Polaris Forge 1 is fully leased and contracted to deliver 400 MW at full buildout.

Negative

  • None.
Argus 15 min delay 1 alert
+3.35% vs previous close $24.97 last price 2.3x rel. volume Open Argus
Details

Market move: APLD +3.35% vs previous close. AI infrastructure delivery

$24.13 – $25.09 Day Range
$7.47B Market Cap

On Oct 2, the day this news came out, the latest delayed price for APLD is 3.35% above the previous close. The latest delayed price is $24.97. Relative volume is elevated at 2.3x the average.

Data tracked by StockTitan Argus (15 min delayed). Upgrade to Gold for real-time data.

Key Figures

Additional operational capacity: 75 MW Operational critical IT load: 250 MW Contracted critical IT load: 400 MW
Additional operational capacity
75 MW
Second phase of Building 2 at Polaris Forge 1
Operational critical IT load
250 MW
Polaris Forge 1 campus
Contracted critical IT load
400 MW
Polaris Forge 1 at full buildout

Key Terms

high-performance computing
1 terms
high-performance computing technical
"high-performance computing (“HPC”) workloads"
A cluster of very powerful computers, special chips and fast networks designed to tackle huge, complex calculations far faster than a normal PC — like replacing a single delivery van with a synchronized fleet to move a city’s worth of packages. For investors, high-performance computing matters because it enables faster product development, more accurate simulations and data analysis, and new revenue streams for hardware, software and services, making firms that supply or use it potentially more competitive and scalable.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Completion of three additional 25 MW data halls brings fully operational capacity at Polaris Forge 1 to 250 MW

DALLAS, Oct. 02, 2026 (GLOBE NEWSWIRE) -- Applied Digital (NASDAQ: APLD), a U.S. based designer, developer, owner and operator of large-scale, purpose-built data centers engineered to support high-performance computing (“HPC”) workloads, including artificial intelligence (“AI”), machine learning, and other accelerated-compute applications, today announced it has achieved Ready for Service for the second phase of Building 2 at its Polaris Forge 1 campus, delivering an additional 75 MW of critical IT load across three 25 MW data halls.

The milestone completes Building 2’s full 150 MW of critical IT load and brings fully operational critical IT load at Polaris Forge 1 to 250 MW. The fully leased AI Factory Campus is contracted to deliver 400 MW of critical IT load at full buildout.

“Bringing another 75 MW of AI infrastructure online at Polaris Forge 1 further demonstrates our ability to turn large-scale power into operational AI infrastructure,” said Wes Cummins, Chairman and Chief Executive Officer of Applied Digital. “Securing power is only the starting point. The real work is designing, building, commissioning, and operating the infrastructure that transforms those megawatts into usable capacity for customers. That is the capability we continue to scale across our platform.”

The latest delivery follows the first 100 MW building at Polaris Forge 1 and the initial 75 MW phase of Building 2. With 250 MW now operational, Polaris Forge 1 reflects Applied Digital’s repeatable approach to developing and operating large-scale infrastructure purpose-built for advanced AI and high-performance computing workloads.

Polaris Forge 1 is located in Ellendale, North Dakota, where Applied Digital has operated since 2021 and built long-standing relationships with local leaders, partners, and community stakeholders. As the campus continues to expand, the Company remains focused on responsible development, local partnership, and creating long-term value in the communities where it builds.

About Applied Digital

Applied Digital (Nasdaq: APLD) — named Best Data Center in the Americas 2025 by Datacloud — designs, builds, and operates high-performance, sustainably engineered data centers and colocation services for artificial intelligence, cloud, networking, and blockchain workloads. Headquartered in Dallas, TX, and founded in 2021, the company combines hyperscale expertise, closed-loop cooling, and rapid deployment capabilities to deliver secure, scalable compute at industry-leading speed and efficiency, while creating economic opportunities in underserved communities through its AI Factory franchise model.

Learn more at applieddigital.com or follow @APLDdigital on X and LinkedIn.

Forward-Looking Statements
This press release contains “forward-looking statements” as defined in the Private Securities Litigation Reform Act of 1995 regarding, among other things, future operating and financial performance, product development, market position, business strategy and objectives, and future financing plans. These statements use words, and variations of words, such as “will,” “continue,” “build,” “future,” “increase,” “drive,” “believe,” “look,” “ahead,” “confident,” “proven,” “deliver,” “outlook,” “expect,” “project” and “predict.” Other examples of forward-looking statements may include, but are not limited to, (i) statements that reflect perspectives and expectations regarding lease agreements and any current or prospective data center campus development; (ii) statements about the high-performance computing (HPC) industry; (iii) statements of company plans and objectives, including the company’s evolving business model, or estimates or predictions of actions by suppliers; (iv) statements of future economic performance; and (v) statements of assumptions underlying other statements and statements about the company or its business. You are cautioned not to rely on these forward-looking statements. These statements are based on current expectations of future events and thus are inherently subject to uncertainty. If underlying assumptions prove inaccurate or known or unknown risks or uncertainties materialize, actual results could vary materially from the company’s expectations and projections. These risks, uncertainties, and other factors include, among others: whether or not our customers exercise the renewal options under their leases with us (if not, we will not recognize further revenue from such customer under its respective lease); our ability to complete construction of our data center campuses as planned; the lead time of customer acquisition and leasing decisions and related internal approval processes; changes to artificial intelligence and HPC infrastructure needs and their impact on future plans; costs related to the HPC operations and strategy; our ability to timely deliver any services required in connection with completion of installation under lease agreements; our ability to raise additional capital to fund the ongoing datacenter construction and operations; our ability to obtain financing of datacenter leases and more broadly for our development and general corporate activities; our dependence on principal customers, including our ability to execute and perform our obligations under our leases with key customers; our ability to timely and successfully build new hosting facilities with the appropriate contractual margins and efficiencies; power or other supply disruptions and equipment failures; the inability to comply with regulations, developments and changes in regulations; cash flow and access to capital; availability of financing to continue to grow our business; decline in demand for our products and services; maintenance of third party relationships; and conditions in the debt and equity capital markets. A further list and description of these risks, uncertainties, and other factors can be found in the company’s most recently filed Annual Report on Form 10-K and Quarterly Reports on Form 10-Q, including in the sections captioned “Forward-Looking Statements” and “Risk Factors,” and in the company’s subsequent filings with the Securities and Exchange Commission. Copies of these filings are available online at www.sec.gov, on the company’s website (www.applieddigital.com) under “Investors,” or on request from the company. Information in this press release is as of the dates and time periods indicated herein, and the company does not undertake to update any of the information contained in these materials, except as required by law.

Media Contact
JSA (Jaymie Scotto & Associates)
(856) 264-7827
jsa_applied@jsa.net

Investor Relations Contacts
Matt Glover or Ralf Esper
Gateway Group, Inc.
(949) 574-3860
APLD@gateway-grp.com


FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

How much capacity did Applied Digital bring online at Polaris Forge 1?

Applied Digital brought an additional 75 MW of critical IT load online across three 25 MW data halls. This completed Building 2’s full 150 MW and brought fully operational campus capacity to 250 MW.

Is Applied Digital’s Polaris Forge 1 campus fully leased?

Polaris Forge 1 is fully leased and contracted to deliver 400 MW of critical IT load at full buildout. Its fully operational capacity currently totals 250 MW.