Aston Bay and American West Metals Announce Extensive Strike of Copper Gossans Discovered in Regional Exploration at the Storm Project, Nunavut, Canada
Aston Bay Holdings (OTCQB:ATBHF) has announced significant copper discoveries at its Storm Project in Nunavut, Canada. The company, in a 20/80 joint venture with American West Metals, reported extensive copper gossans along 8km of strike and successful drilling results.
Key developments include 8 diamond drill holes totaling 1,786m with significant visual copper sulfides, including PFS-001 with 43m of chalcocite mineralization and PFS-002 with 49.5m of copper mineralization. Additionally, 21 RC drill holes have been completed for resource expansion.
Notably, Ocean Partners Holdings has agreed to provide up to 80% of initial capital for development through a senior secured loan facility, securing 100% offtake rights for copper, silver, and gold products from the Project.
Aston Bay Holdings (OTCQB:ATBHF) ha annunciato importanti scoperte di rame nel suo progetto Storm in Nunavut, Canada. La società, in joint venture 20/80 con American West Metals, ha riportato estesi gossani di rame lungo 8 km di estensione e risultati positivi nelle perforazioni.
Gli sviluppi principali includono 8 perforazioni diamantate per un totale di 1.786 m con evidenti solfuri di rame, tra cui il foro PFS-001 con 43 m di mineralizzazione di calcocite e PFS-002 con 49,5 m di mineralizzazione di rame. Inoltre, sono stati completati 21 fori RC per l'espansione delle risorse.
Da segnalare che Ocean Partners Holdings ha accettato di fornire fino al 80% del capitale iniziale per lo sviluppo tramite un prestito senior garantito, assicurandosi il diritto di acquisto esclusivo al 100% per rame, argento e oro prodotti dal progetto.
Aston Bay Holdings (OTCQB:ATBHF) ha anunciado importantes descubrimientos de cobre en su Proyecto Storm en Nunavut, Canadá. La compañía, en una empresa conjunta 20/80 con American West Metals, reportó extensos gossanes de cobre a lo largo de 8 km de traza y resultados exitosos en perforaciones.
Los avances clave incluyen 8 perforaciones diamantinas que suman 1,786 m con sulfuro de cobre visible significativo, incluyendo el PFS-001 con 43 m de mineralización de calcocita y el PFS-002 con 49,5 m de mineralización de cobre. Además, se han completado 21 perforaciones RC para la expansión de recursos.
Destaca que Ocean Partners Holdings acordó proporcionar hasta el 80% del capital inicial para el desarrollo mediante un préstamo senior garantizado, asegurándose el derecho exclusivo del 100% de la compra para cobre, plata y oro producidos en el proyecto.
Aston Bay Holdings (OTCQB:ATBHF)는 캐나다 누나부트의 Storm 프로젝트에서 중요한 구리 발견을 발표했습니다. 이 회사는 American West Metals와 20/80 합작 투자로 8km 구간에 걸친 광범위한 구리 고산과 성공적인 시추 결과를 보고했습니다.
주요 진전 사항으로는 총 1,786m의 8개 다이아몬드 시추공에서 상당한 구리 황화물이 시각적으로 확인되었으며, PFS-001은 43m의 칼코사이트 광화대, PFS-002는 49.5m의 구리 광화대를 포함합니다. 또한, 자원 확장을 위해 21개의 RC 시추공이 완료되었습니다.
특히, Ocean Partners Holdings는 개발 자금의 최대 80%를 선순위 담보 대출 형태로 제공하기로 합의했으며, 프로젝트에서 생산되는 구리, 은, 금 제품에 대해 100% 구매 권리를 확보했습니다.
Aston Bay Holdings (OTCQB:ATBHF) a annoncé d'importantes découvertes de cuivre sur son projet Storm au Nunavut, Canada. La société, en coentreprise 20/80 avec American West Metals, a rapporté de vastes gisements de cuivre sur 8 km de tracé ainsi que des résultats de forage réussis.
Les développements clés comprennent 8 forages diamantés totalisant 1 786 m avec des sulfures de cuivre visibles significatifs, notamment PFS-001 avec 43 m de minéralisation en chalcocite et PFS-002 avec 49,5 m de minéralisation en cuivre. De plus, 21 forages RC ont été réalisés pour l'expansion des ressources.
Il est à noter que Ocean Partners Holdings a accepté de fournir jusqu'à 80 % du capital initial pour le développement via une facilité de prêt senior garantie, assurant ainsi 100 % des droits d'achat pour les produits en cuivre, argent et or issus du projet.
Aston Bay Holdings (OTCQB:ATBHF) hat bedeutende Kupferfunde bei seinem Storm-Projekt in Nunavut, Kanada, bekannt gegeben. Das Unternehmen meldete in einem 20/80 Joint Venture mit American West Metals umfangreiche Kupfergossane entlang von 8 km Streichen und erfolgreiche Bohrergebnisse.
Zu den wichtigsten Entwicklungen gehören 8 Diamantbohrlöcher mit insgesamt 1.786 m mit signifikanten sichtbaren Kupfersulfiden, darunter PFS-001 mit 43 m Chalcocit-Mineralisierung und PFS-002 mit 49,5 m Kupfermineralisierung. Zusätzlich wurden 21 RC-Bohrlöcher zur Ressourcenerweiterung abgeschlossen.
Bemerkenswert ist, dass Ocean Partners Holdings zugestimmt hat, bis zu 80 % des Anfangskapitals für die Entwicklung über eine vorrangige besicherte Kreditfazilität bereitzustellen und sich 100 % der Abnahmerechte für Kupfer-, Silber- und Goldprodukte aus dem Projekt sichert.
- Ocean Partners to provide up to 80% of initial capital funding for development
- Discovery of extensive copper gossans and outcrop along 8km of strike
- Thick intersections of visual copper sulfides in drilling (43m and 49.5m)
- 21 RC drill holes completed for resource expansion
- 100% offtake agreement secured with Ocean Partners
- Project still requires completion of bankable feasibility study
- Drill results pending laboratory assays for confirmation
- Development funding conditional on feasibility study completion
High-priority regional targets identified as ongoing drilling continues to intersect copper sulfides at Storm
Highlights:
Extensive copper gossans and outcrop discovered along 8km of strike. A large mapping and sampling program aimed to follow up the preliminary MMT survey results in the Tornado area has discovered extensive visual copper in outcrop, including:
Extensive chalcocite and malachite in outcrop have been mapped along the interpreted major fault network, with chalcocite (copper sulfide) confirmed by portable XRF
RC drilling planned to test a number of the fault-related copper occurrences and stratigraphic targets at Tornado in the coming days
Diamond drilling has intersected thick intervals of visual copper sulfides. 8 diamond drill holes (for a total of 1,786m) are now complete with thick intervals of visual copper sulfides intersected, including;
PFS-001 was drilled into the southern margin of the Cyclone Deposit and intersected a combined total of 43 metres ("m") of chalcocite and chalcopyrite mineralization, including visual semi-massive sulfides
PFS-002 was drilled into the northern margin of the Cyclone Deposit and intersected approximately 49.5m combined total of chalcocite and chalcopyrite mineralization, including visual semi-massive sulfides
Reverse-Circulation (RC) drilling continuing: 21 RC drill holes completed to date (for a total of 3,194m), including;
12 holes completed at the Thunder, Lightning Ridge, Cirrus, Cyclone and Corona Deposits for resource category upgrade and expansion purposes
2 holes testing resource extensions to the south of the Cyclone Deposit
7 exploration holes completed in The Gap, Cyclone West, Squall and Hailstorm areas
Project financing agreement finalized: Ocean Partners Holdings Ltd. to provide debt finance for up to
80% of initial capital for the development of Storm
TORONTO, ON / ACCESS Newswire / July 24, 2025 / Aston Bay Holdings Ltd. (TSXV:BAY)(OTCQB:ATBHF) ("Aston Bay" or the "Company") is pleased to provide an update on exploration activities at the Storm Copper Project ("Storm" or the "Project") on Somerset Island, Nunavut. American West Metals Limited ("American West"), the Project operator, is conducting the exploration program. Aston Bay and American West have formed a 20/80 unincorporated joint venture with respect to the Storm Project property, with Aston Bay maintaining a free carried interest until a decision to mine is made upon completion of a bankable feasibility study.
Thomas Ullrich, Chief Executive Officer of Aston Bay, commented:
"We are excited to continue exploration during 2025 with additional copper discoveries at Storm. The long intercepts of visual chalcocite and other copper minerals in the geotechnical drilling bode well for resource expansion.
"As well, the large areas of copper and iron gossans at the surface above conductivity anomalies from the newly-acquired MobileMT geophysical survey increase our confidence in the prospectivity of these areas and open up new areas for future potential drilling.
With

Figure 1: Diamond drill core from drill hole PFS-002. The core is from approximately 74m downhole and contains semi-massive visual chalcocite (dark grey mineral) within dolomite host rock (light grey). This interval has not yet been assayed.
DIAMOND DRILLING
The diamond drilling program at Storm is progressing rapidly with eight drill holes now completed for a total of 1,786m.
After completion of the first deep diamond drill hole, ST25-02, the diamond drill rig moved onto geotechnical (and potential resource) drilling to allow time for the final processing and interpretation of the MMT data to help refine the deep drill targeting. The geotechnical drilling was required for the ongoing pre-feasibility study (PFS) work for the Storm Project, and is designed to gather structural and rock strength information in the conceptual open-pit walls.
Two geotechnical drill holes have intersected wide intervals of visual copper sulfide mineralization on the margins of the current Mineral Resource Estimate (MRE). Mineralization in these areas was unexpected and has extremely positive implications for potential resource growth and upgrade.
Drilling is now underway on the Cirrus Deeps target (see June 12, 2025, Aston Bay news release).
Drill hole PFS-001 details
PFS-001 was drilled to a depth of 152m on the southern margin of the Cyclone Deposit (Figures 2, 3 and 9). The drill hole was designed to test the conceptual open-pit walls for geotechnical study purposes, and was therefore completed on the very edge of the current resource envelope.
The drill hole has intersected five broad zones of visual sulfide mineralization (see Table 1) between 29-47m, 51-53m, 57-61m, 65-76m, and 83-91m downhole for a total of 43m of visual sulfide mineralization.
The visual sulfide mineralization is hosted within a thick sequence of fractured and brecciated dolomudstones of the Allen Bay Formation. Two broad styles of mineralization are present within PFS-001: stratabound style to a depth of approximately 53m, and intermittent fault-hosted to a downhole depth of 91m. The mineralization consists of chalcocite, chalcopyrite and pyrite, and is zoned with chalcocite commonly located within the core of the mineralization, and chalcopyrite/pyrite on the margins or within faults. Portable XRF is used to aid in the determination of mineral type.

Figure 2: Dense breccia and semi-massive visual chalcocite in drill hole PFS-001 (33.94-41.4m downhole).

Figure 3: Schematic NE-SW geological section (+/-25m) through PFS-001. Visual copper mineralization has been logged outside of the conceptual open-pit design.
Drill hole PFS-002 details
PFS-002 was drilled to a depth of 176m on the northern margin of the Cyclone Deposit (Figures 4, 5 and 9), and was designed to test the conceptual open-pit walls for geotechnical studies.
The drill hole has intersected three broad zones of visual copper mineralization (see Table 2), including chalcocite, between 51-67m, 70.5-83m, and 98-119m downhole for a total of 47m of visual sulfide mineralization.
The sulfide mineralization is hosted within a thick sequence of fractured dolomudstones of the Allen Bay Formation. The visual mineralization within PFS-002 is interpreted to be entirely stratabound in nature as with the rest of the Cyclone Deposit. The visual mineralization consists of semi-massive sulfides, veinlets and matrix breccias in the host rock. The mineralization is zoned, with a core of chalcocite surrounded by lesser pyrite, and coated with a weathering rind of malachite.

Figure 4: Semi-massive and breccia hosted visual chalcocite from PFS-002 (72.7-78.6m downhole).

Figure 5: Schematic NE-SW geological section (+/-25m) through PFS-002. Visual copper mineralization has been logged outside of the conceptual open-pit design.
REGIONAL SAMPLING IDENTIFIES EXTENSIVE COPPER IN OUTCROP
An extensive mapping, soil sampling and rock sampling program has been completed throughout the project, with Initial work from the Storm-Tornado Corridor providing exceptional results.
Phase 1 of the regional scale MMT survey was completed along the Midway-Storm-Tornado corridor and identified six strong and large conductive features within the higher frequency dataset and several broad anomalous features in the lower frequencies (Figure 7; see July 12, 2025, Aston Bay news release). Given the proximity and potential relationship of the anomalies to the large graben faults in the Tornado area, a mapping and sampling program was planned to support follow-up drill targeting.
The mapping and sampling between Storm and Tornado have defined copper gossans, ferruginous (iron-bearing) and copper carbonate outcrops over approximately 8km of strike and along several targeted faults in the area (Figure 6). The large extent of copper and ferruginous minerals outcropping within the faults indicates that a significant volume of mineralizing fluids has migrated through these structures. These results support the broad copper anomalies in the area defined by historical soil sampling programs, and highlight the exceptional prospectivity of this relatively untested area.

Figure 6: Examples of the copper gossans and outcrop from the Storm-Tornado area. For detailed descriptions of samples A-F above, see Table 1 in this report. Portable XRF was used to aid visual identification.

Figure 7: Plan view of the Midway-Storm-Tornado Corridor showing MMT imagery (4274Hz, interpreted <350m depth of investigation), known copper deposit outlines (black), major faults (dotted dark grey, copper soil geochemistry anomalies (dotted white outlines) and rock and gossan sampling area. See Table 1 for sample details.
Soil sampling programs are also underway at Storm (Figure 8). These are testing regional targets produced from a recent project-wide technical review. The soil grids consist of varying sample spacings and are primarily targeting structures within the project that are interpreted to be analogous to the Storm graben faults and thus prospective for copper. 1,217 samples have been collected to date over 8 new prospect areas (see Figure 8).

Figure 8: Regional soil sampling program sample locations overlaying regional topographic map.

Figure 9: Drill hole locations from the 2025 drilling program, overlaying deposit MRE blocks, existing drilling, and regional geology overlaying aerial photography.
COPPER-SILVER OFFTAKE DEAL FINALIZED
American West has finalized an offtake agreement with Ocean Partners Holdings Ltd. ("OP"), a global metal trading, technical advisory, and financing company (see April 9, 2024, Aston Bay news release). OP has secured rights to
In exchange, OP will provide up to
OP will provide ongoing technical and copper market advisory services to American West and the Project.
PLANNED PROGRAM
RC drilling continues with a pipeline of high-priority geophysical and exploration targets.
Diamond drilling is currently drilling the Cirrus Deeps target.
Environmental monitoring and survey activities are continuing.
PFS activities continue, including permitting, processing, and mining studies.
Annual site visit by council members from the Hamlet of Resolute Bay scheduled for this week.
Sample-ID | East | North | Unit | Description |
ST-00008 | 476105 | 8152618 | Osa | Breccia calcite, iron oxide staining. |
ST-00087 | 472529 | 8168391 | Osa | Malachite with iron oxide fill |
ST-00089 | 472492 | 8168399 | Scs | Malachite with possible chalcocite |
ST-00100 | 472842 | 8168519 | Osa | Contact; Iron oxide scree |
ST-00103 | 472480 | 8168523 | Osa | Malachite scree at geology contact |
ST-00106 | 472349 | 8168571 | Osa | Malachite |
ST-00116 | 472940 | 8168617 | .goss | Iron oxide, vuggy. Prominent scree. Figure 6 - D |
ST-00121 | 472331 | 8168627 | Osa | Contact? Iron oxide, nodular with malachite. |
ST-00129 | 472791 | 8168721 | Osa | Iron altered. Figure 6 - A |
ST-00135 | 472291 | 8168880 | Osa | Iron alteration along contact |
ST-00137 | 472279 | 8168893 | Osa | Iron staining |
ST-00169 | 472186 | 8169253 | Osa | Iron staining |
ST-00172 | 472697 | 8169270 | Scs | Contact. Iron stain/fracture fill. Osa to west |
ST-00180 | 472212 | 8169347 | Osa | Iron staining |
ST-00181 | 472075 | 8169350 | Sdo | Malachite/Azurite scree at contact. Chalcocite |
ST-00183 | 472115 | 8169354 | Osa | Malachite |
ST-00186 | 472102 | 8169360 | Osa | Malachite |
ST-00198 | 471997 | 8169469 | Osa | Transported. Malachite present |
ST-00199 | 471998 | 8169487 | Osa | Malachite fragments |
ST-00202 | 472010 | 8169528 | Osa | Malachite fragments |
ST-00217 | 471839 | 8169716 | Osa | Iron staining |
ST-00230 | 471321 | 8169814 | Scs | Hematite alteration |
ST-00238 | 471307 | 8169849 | Osa | Disseminated pyrite, vugs |
ST-00239 | 471285 | 8169849 | Osa | Malachite/chalcocite |
ST-00241 | 471260 | 8169855 | Osa | Malachite |
ST-00242 | 471250 | 8169859 | Osa | Iron staining |
ST-00243 | 471271 | 8169859 | Osa | Malachite |
ST-00245 | 471278 | 8169874 | Osa | Chalcocite/malachite |
ST-00296 | 469945 | 8170995 | Osa | Malachite staining |
ST-00299 | 469515 | 8171012 | Sdo | Outcrop-with hematite alteration. Fault? |
ST-00321 | 468893 | 8171411 | Osa | Malachite |
ST-00323 | 468871 | 8171425 | Osa | Malachite at contact. Osa to north |
ST-00332 | 467657 | 8171519 | .goss | Iron-altered blk-wh calcite. Figure 6 - C |
ST-00341 | 467572 | 8171593 | Osa | Malachite in fractures. |
ST-00382 | 473685 | 8169315 | Osa | Banded iron staining |
ST-00383 | 473786 | 8169324 | Osa | Iron staining, malachite staining. Figure 6 - F |
ST-00384 | 473830 | 8169333 | .goss | Gossan with malachite staining. Figure 6 - E |
ST-00385 | 473877 | 8169337 | .goss | Eastern limit of gossan |
ST-00389 | 472697 | 8169270 | Scs | Iron fracture fill |
ST-00395 | 472523 | 8168387 | Osa | Malachite |
ST-00396 | 472489 | 8168398 | Osa | Malachite/chalcocite Figure 6 - B |
ST-00399 | 472063 | 8169352 | Osa | Malachite/azurite/chalcocite |
Table 1: 2025 Rock and gossan sampling details Osa = Allen bay Fm, Scs = Cape Storm Fm, Sdo = Douro Fm, .goss = gossan
Hole ID | Prospect | Easting | Northing | RL | Depth (m) | Azimuth | Dip | Comments |
SR25-01 | Thunder | 465245 | 8172771 | 242 | 164.59 | 182 | -88 | Resource upgrade |
SR25-02 | Thunder | 464970 | 8172881 | 250 | 124.97 | 181 | -63 | Resource upgrade |
SR25-03 | Cyclone | 464800 | 8173996 | 291 | 149.35 | 360 | -75 | Exploration |
SR25-04 | Cyclone | 464900 | 8173977 | 290 | 149.35 | 360 | -75 | Exploration |
SR25-05 | Corona | 466390 | 8172256 | 235 | 89.92 | 178 | -56 | Resource upgrade |
SR25-06 | Corona | 466430 | 8172256 | 232 | 89.92 | 184 | -65 | Resource upgrade |
SR25-07 | Corona | 466370 | 8172241 | 235 | 82.3 | 175 | -67 | Resource upgrade |
SR25-08 | Corona | 466093 | 8172243 | 225 | 45.72 | 360 | -65 | Resource upgrade |
SR25-09 | Lightning | 466171 | 8172515 | 242 | 164.59 | 360 | -60 | Resource upgrade |
SR25-10 | Gap | 464066 | 8173192 | 238 | 149.35 | 191 | -50 | Exploration |
SR25-11 | Gap | 463938 | 8173162 | 237 | 149.35 | 170 | -50 | Exploration |
SR25-12 | Squall | 464827 | 8172501 | 240 | 199.64 | 0 | -65 | Exploration |
SR25-13 | Cycl W | 463934 | 8174739 | RC | 201 | 0 | -76 | Exploration |
SR25-14 | Cycl W | 464205 | 8174385 | RC | 201 | 180 | -70 | Exploration |
SR25-15 | Cyclone | 464553 | 8174330 | RC | 201 | 180 | -70 | Resource upgrade |
SR25-16 | Cyclone | 464750 | 8174407 | RC | 192 | 179 | -70 | Resource upgrade |
SR25-17 | Cyclone | 464981 | 8174407 | RC | 201 | 180 | -70 | Resource upgrade |
SR25-18 | Hailstorm | 465288 | 8172259 | RC | 168 | 135 | -55 | Exploration |
SR25-19 | Cirrus | 462432 | 8173883 | RC | 79 | 180 | -70 | Resource upgrade |
SR25-20 | Thunder | 465335 | 8172920 | RC | 122 | 179 | -73 | Resource upgrade |
SR25-21 | Chinook | 466430 | 8172736 | RC | 194 | 0 | -60 | Resource upgrade |
ST25-01 | Cirrus | 465051 | 8174321 | 212 | 191 | 035 | -70 | To be redrilled |
ST25-02 | Cyclone S | 464948 | 8174227 | 286 | 440 | 360 | -75 | Exploration |
PFS-001 | cyclone | 464629 | 8174119 | DDH | 152 | 227.18 | -65.7 | Geotech/Resource |
PFS-002 | cyclone | 464898 | 8174357 | DDH | 176 | 50 | -60 | Geotech/Resource |
PFS-003 | cyclone | 465422 | 8174036 | DDH | 155 | 143.11 | -61.5 | Geotech/Resource |
PFS-004 | cyclone | 465619 | 8174327 | DDH | 212 | 319.8 | -59.8 | Geotech/Resource |
PFS-005 | chinook | 466339 | 8172795 | DDH | 179 | 140 | -65 | Geotech/Resource |
PFS-006 | chinook | 466138 | 8172835 | DDH | 125 | 260 | -70 | Geotech/Resource |
PFS-007 | chinook | 466216 | 8172875 | DDH | 161 | 20 | -60 | Geotech/Resource |
Table 2: 2025 drill program details.
Qualified Person
Michael Dufresne, M.Sc., P.Geol., P.Geo., is a Non-Independent Qualified Person as defined by the NI 43-101 Standards of Disclosure for Mineral Projects and has reviewed and approved the scientific and technical information in this press release.
About Aston Bay Holdings
Aston Bay is a publicly traded mineral exploration company exploring for high-grade critical and precious metal deposits in North America. The Company is exploring the Storm Copper Property and Cu-Ag-Zn-Co Epworth Property in Nunavut.
The Company and its joint venture partners, American West Metals Limited and its wholly-owned subsidiary, Tornado Metals Ltd. (collectively, "American West"), have formed a 20/80 unincorporated joint venture in respect of the Storm Project property, which hosts the Storm Copper Project and the Seal Zinc Deposit. Under the unincorporated joint venture, Aston Bay shall have a free carried interest until American West has made a decision to mine upon completion of a bankable feasibility study, meaning American West will be solely responsible for funding the joint venture until such a decision is made. After such a decision, Aston Bay will be diluted in the event it does not elect to contribute its proportionate share, and its interest in the Storm Project property will be converted into a
FORWARD-LOOKING STATEMENTS
Statements made in this news release, including those regarding entering into the joint venture and each party's interest in the Project pursuant to the agreement in respect of the joint venture, management objectives, forecasts, estimates, expectations, or predictions of the future may constitute "forward-looking statement", which can be identified by the use of conditional or future tenses or by the use of such verbs as "believe", "expect", "may", "will", "should", "estimate", "anticipate", "project", "plan", and words of similar import, including variations thereof and negative forms. This press release contains forward-looking statements that reflect, as of the date of this press release, Aston Bay's expectations, estimates and projections about its operations, the mining industry and the economic environment in which it operates. Statements in this press release that are not supported by historical fact are forward-looking statements, meaning they involve risk, uncertainty and other factors that could cause actual results to differ materially from those expressed or implied by such forward-looking statements. Although Aston Bay believes that the assumptions inherent in the forward-looking statements are reasonable, undue reliance should not be placed on these statements, which apply only at the time of writing of this press release. Aston Bay disclaims any intention or obligation to update or revise any forward-looking statement, whether as a result of new information, future events or otherwise, except to the extent required by securities legislation.
Neither TSX Venture Exchange nor its regulation services provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.
For more information contact:
Thomas Ullrich, Chief Executive Officer
thomas.ullrich@astonbayholdings.com
(416) 456-3516
Sofia Harquail, IR and Corporate Development
sofia.harquail@astonbayholdings.com
(647) 821-1337
SOURCE: Aston Bay Holdings Ltd.
View the original press release on ACCESS Newswire