Boliden: Lower production rate in Aitik
Rhea-AI Summary
Boliden (BDNNY) announces production challenges at its Aitik copper mine due to high deposits of hard diorite rock encountered during a new pushback operation. The company expects:
- First quarter 2025 production of just over 9 Mtonnes
- Full-year 2025 production estimate of nearly 40 Mtonnes
- Copper grade maintaining at 0.16%
The challenges stem from oxidized ore and diorite deposits in an area representing half of Aitik's production. The oxidization negatively impacts recoveries, while the hard rock significantly limits grinding capacity. These conditions are expected to persist throughout 2025.
Positive
- Copper grade maintaining stable at 0.16%
Negative
- Production rate reduced to 9 Mtonnes in Q1 2025 due to hard rock deposits
- Full-year 2025 production lowered to 40 Mtonnes
- Oxidized ore causing negative effect on recoveries
- Grinding capacity significantly by hard diorite rock
News Market Reaction
On the day this news was published, BDNNY gained 3.76%, reflecting a moderate positive market reaction.
Data tracked by StockTitan Argus on the day of publication.
In 2024, the Aitik copper mine began a new pushback, which means that mining will take place from ground level and that the open pit will thus be expanded. In this area, where half of Aitik's production is now taking place, parts of the ore are oxidized and contain deposits of the very hard rock type diorite. The oxidization means a slight negative effect on recoveries and the hard rock means that the capacity for grinding is clearly limited. This means that the production rate for the first quarter is estimated at just over 9 Mtonnes.
Drilling has established that the diorite deposits will continue to affect the production process in Aitik for the remainder of 2025. Aitik's total production in 2025 is therefore estimated at close to 40 Mtonnes. The copper grade is estimated at
For further information, please contact:
Klas Nilsson
Director Group Communications
+46 70 453 65 88
Klas.nilsson@boliden.com
This information is information that Boliden AB is obliged to make public pursuant to the EU Market Abuse Regulation. The information was submitted for publication, through the agency of Director Group Communications, at 08.00 CET on March 5, 2025.
This information was brought to you by Cision http://news.cision.com
https://news.cision.com/boliden/r/lower-production-rate-in-aitik,c4114481