Bunker Hill Provides Project Update
Bunker Hill Mining (OTCQB: BHLL) has reported significant progress in H1 2025, highlighted by the completion of a transformational US$31M equity financing and debt restructuring package. The company's mining project is now 67% complete, up from 53% in November 2024, with 98% of procurement completed.
Key achievements include zero lost-time incidents, completion of a 2,000m underground ramp rehabilitation, and 83% completion of the 1,800 tons per day processing plant. The company has successfully reduced its debt by 40% and decreased gross revenue royalty costs by 58%. Strategic partnerships have been established with Teck Resources, including a $10M standby working capital facility.
Looking ahead, Bunker Hill plans to pursue US$150M in debt finance from US EXIM, advance to 90% project completion by year-end, and aims to list on the NYSE American. The company targets operational ramp-up during H1 2026.
Bunker Hill Mining (OTCQB: BHLL) ha riportato progressi significativi nella prima metà del 2025, evidenziati dal completamento di un pacchetto trasformativo di finanziamento azionario da 31 milioni di dollari e ristrutturazione del debito. Il progetto minerario dell'azienda è ora completato al 67%, rispetto al 53% di novembre 2024, con il 98% degli approvvigionamenti completati.
Tra i risultati chiave figurano zero incidenti con perdita di tempo, il completamento della riabilitazione di una rampa sotterranea di 2.000 metri e il completamento all'83% dell'impianto di lavorazione da 1.800 tonnellate al giorno. L'azienda ha ridotto con successo il proprio debito del 40% e diminuito i costi delle royalty sul fatturato lordo del 58%. Sono state inoltre stabilite partnership strategiche con Teck Resources, inclusa una linea di credito standby da 10 milioni di dollari.
Guardando al futuro, Bunker Hill intende ottenere un finanziamento del debito di 150 milioni di dollari da US EXIM, raggiungere il 90% di completamento del progetto entro fine anno e punta a quotarsi sul NYSE American. L'azienda mira ad avviare le operazioni nella prima metà del 2026.
Bunker Hill Mining (OTCQB: BHLL) ha reportado avances significativos en el primer semestre de 2025, destacados por la finalización de un paquete transformador de financiamiento de capital por 31 millones de dólares y reestructuración de deuda. El proyecto minero de la compañía está ahora completado en un 67%, frente al 53% en noviembre de 2024, con el 98% de las adquisiciones completadas.
Los logros clave incluyen cero incidentes con pérdida de tiempo, la finalización de la rehabilitación de una rampa subterránea de 2,000 metros y el 83% de avance en la planta de procesamiento de 1,800 toneladas por día. La empresa ha reducido exitosamente su deuda en un 40% y disminuido los costos de regalías sobre ingresos brutos en un 58%. Se han establecido alianzas estratégicas con Teck Resources, incluyendo una línea de capital de trabajo en espera de 10 millones de dólares.
De cara al futuro, Bunker Hill planea obtener un financiamiento de deuda de 150 millones de dólares de US EXIM, avanzar hasta un 90% de finalización del proyecto para fin de año y tiene como objetivo cotizar en la NYSE American. La empresa apunta a iniciar operaciones en el primer semestre de 2026.
Bunker Hill Mining (OTCQB: BHLL)은 2025년 상반기에 3100만 달러 규모의 자본 조달 및 부채 재구성 패키지를 완료하며 중요한 진전을 보고했습니다. 회사의 광산 프로젝트는 2024년 11월 53%에서 67% 완료되었고, 조달은 98% 완료되었습니다.
주요 성과로는 무재해 기록, 2,000미터 지하 경사로 복구 완료, 그리고 일일 1,800톤 처리 공장의 83% 완공이 포함됩니다. 회사는 부채를 40% 줄이고 총수익 로열티 비용을 58% 감소시켰습니다. 또한 Teck Resources와 전략적 파트너십을 맺어 1,000만 달러 대기 자본 시설을 확보했습니다.
앞으로 Bunker Hill은 US EXIM으로부터 1억 5천만 달러의 부채 자금 조달을 추진하고, 연말까지 프로젝트 90% 완료를 목표로 하며, NYSE American 상장을 계획하고 있습니다. 회사는 2026년 상반기 중 운영을 시작할 예정입니다.
Bunker Hill Mining (OTCQB: BHLL) a annoncé des progrès significatifs au premier semestre 2025, marqués par la finalisation d’un financement en actions de 31 millions de dollars et d’un plan de restructuration de la dette. Le projet minier de la société est désormais achevé à 67 %, contre 53 % en novembre 2024, avec 98 % des approvisionnements réalisés.
Les réalisations clés comprennent zéro accident avec arrêt de travail, l’achèvement de la réhabilitation d’une rampe souterraine de 2 000 m et 83 % d’avancement de l’usine de traitement de 1 800 tonnes par jour. La société a réussi à réduire sa dette de 40 % et à diminuer les coûts des redevances sur le chiffre d’affaires brut de 58 %. Des partenariats stratégiques ont été établis avec Teck Resources, incluant une facilité de crédit standby de 10 millions de dollars.
Pour l’avenir, Bunker Hill prévoit de rechercher un financement par dette de 150 millions de dollars auprès de US EXIM, d’atteindre 90 % d’achèvement du projet d’ici la fin de l’année et vise une cotation à la NYSE American. La société prévoit de lancer ses opérations au premier semestre 2026.
Bunker Hill Mining (OTCQB: BHLL) hat im ersten Halbjahr 2025 bedeutende Fortschritte gemeldet, darunter den Abschluss eines transformativen Eigenkapitalfinanzierungs- und Schuldenrestrukturierungspakets in Höhe von 31 Mio. USD. Das Bergbauprojekt des Unternehmens ist nun zu 67 % abgeschlossen, gegenüber 53 % im November 2024, mit 98 % der Beschaffungen abgeschlossen.
Zu den wichtigsten Erfolgen zählen keine Arbeitsausfallunfälle, die Fertigstellung der Sanierung einer 2.000 m langen unterirdischen Rampe und die 83 % Fertigstellung der Aufbereitungsanlage mit einer Kapazität von 1.800 Tonnen pro Tag. Das Unternehmen hat seine Schulden um 40 % reduziert und die Bruttoerlös-Royaltykosten um 58 % gesenkt. Strategische Partnerschaften wurden mit Teck Resources geschlossen, einschließlich einer 10-Millionen-Dollar-Standby-Kapitalfazilität.
Für die Zukunft plant Bunker Hill, 150 Mio. USD an Fremdfinanzierung von US EXIM zu beschaffen, den Projektabschluss bis Jahresende auf 90 % zu steigern und strebt eine Notierung an der NYSE American an. Das Unternehmen plant, im ersten Halbjahr 2026 den Betrieb hochzufahren.
- Project construction advanced to 67% completion with 98% procurement done
- Perfect safety record with zero lost-time incidents and environmental issues
- 40% reduction in total debt through equity conversions
- 58% decrease in gross revenue royalty costs via amended agreements
- Secured US$31M equity financing package with Teck Resources as anchor investor
- $10M standby working capital facility secured from Teck
- Processing plant reached 83% completion
- Payable ore already being stockpiled for commissioning
- Construction pace slowed in Q4 2024 to conserve cash
- Tailings Filtration Plant remains on critical path at only 40% completion
- Additional US$150M debt financing still needed from US EXIM
- Legacy environmental agreements still need restructuring
Recent Equity Raise and Debt Restructure Closing paves the way to Major Milestones
KELLOGG, Idaho and VANCOUVER, British Columbia, July 14, 2025 (GLOBE NEWSWIRE) -- Bunker Hill Mining Corp. (“Bunker Hill” or the “Company”) (TSX-V: BNKR |OTCQB: BHLL) is pleased to provide an update of the significant progress made during H1 2025. Over the past six months, as previously announced, the corporate team has worked closely with its strategic partners to close the transformational equity and debt restructuring deal. Meanwhile, the scaled-back Idaho-based team took measured action to advance construction of the project, moving us closer to the sustainable restart of the Bunker Hill Mine.
“Concurrent with the complex financing process, in the first half of 2025, we continued to advance the new Bunker Hill Mine towards a safe, sustainable and profitable restart in H1 2026,” stated Sam Ash, the Company’s President and CEO. Mr. Ash added, “Our project construction is now
As the world navigates ongoing geostrategic and economic challenges, we believe that establishing a new, profitable, and long-life source of critical metals in the United States offers a meaningful contribution to national strategic resilience and presents a compelling, low-risk, and high-value opportunity for investors and strategic partners alike. Along with our community partners, we are very excited by our potential to generate new, long-life mining employment within the world-famous Silver Valley, Idaho.”
SAFE AND SUSTAINED MOMENTUM IN CONSTRUCTION
Although the Company slowed the pace of development from Q4 2024 to conserve cash resources during the financing process, the smaller site team made significant progress in constructing the processing plant, as well as in procurement and underground development. As a result, the project is now
- Safety Excellence and “Safety First:” Zero lost-time incidents year-to-date.
- Environmental Management Excellence: The Company maintained a perfect safety record, with zero incidents to date, while effectively managing mine water discharge from the Kellogg Tunnel to the IDEQ-operated Central Treatment Plant.
- Steady, Safe, Development Progress Underground:
- The underground mining team completed the rehabilitation of the 2,000m long 15’ x 15’ ramp that connects the upper mining areas on Level 5, adjacent to the Russell Portal, with the first mining areas on Level 8. This provided mechanized mining equipment and haulage vehicles with easy access to the ore zones to be mined for the first three years of the current mine plan. Low-cost grid power is connected and efficient, and the underground ventilation system is fully operational and working as planned.
- The construction of an underground powder magazine between the 7 and 6 Levels has been completed.
- Ongoing development work within the Newgard Ore body has already released payable ore, which is being stockpiled underground for use during plant commissioning.
- The UTZ mining zone, adjacent to the Russell Portal, has been prepared for immediate mining. This is not included within the current mine plan but is being kept available to support commissioning and the ramp-up phases.
- The underground mining team completed the rehabilitation of the 2,000m long 15’ x 15’ ramp that connects the upper mining areas on Level 5, adjacent to the Russell Portal, with the first mining areas on Level 8. This provided mechanized mining equipment and haulage vehicles with easy access to the ore zones to be mined for the first three years of the current mine plan. Low-cost grid power is connected and efficient, and the underground ventilation system is fully operational and working as planned.
- Optimized Engineering along with Steady, Safe Construction Progress on Surface in the Kellogg Yard
- The 1,800 tons per day processing plant is now
83% complete, with all mechanical installations completed and the piping systems optimized significantly compared to the original plan. - The installation of piping and electrical cables is now accelerating and is on track to enable the plant’s power system to be energized in phases. Phased plant commissioning is scheduled to commence later this year.
- The construction of the crusher tower and associated systems was completed in the Kellogg yard, incorporating the refurbished cone crushers from the Pend Oreille facility.
- The construction of the redesigned Tailings Filter Press is currently
40% complete. This is a key item for targeted progress. With engineering and procurement activities now finalized, progress in this area is expected to accelerate significantly with concrete work commencing this week. - To review this progress, please see the link to the June Update Video.
- The 1,800 tons per day processing plant is now
Figure 1 – Overview of Kellogg Processing Plant,
Figure 2 – Inside the Processing Plant,
Figure 3 – Tailings Filter Press (
Figure 4 - Rehabilitation work on 8 Level, with ore collected during development work being stockpiled
With the financing completed, the Company is advancing the construction of the Tailings Filtration Plant, which remains on the critical path.
EXPLORATION FOCUSED ON IMPROVING THE OPERATING MARGIN AT THE RESTART
- Near-Mine Opportunities: The primary focus for the geological team is to support the mine restart by improving the quality and size of existing reserves and resources in the upper part of the mine. These efforts are progressing, with significant upside potential identified, including the identification of high-grade silver zones near the planned mining areas.
- Incorporation of Incremental High-Grade Silver into Year 1 Mine Plan: Mining crews have begun drifting towards the previously identified high-grade silver zone, located 180 feet away from the development on the 8 Level, and anticipate confirmatory sampling results in August. Historical drill results have indicated silver grades in excess of 20OPT as previously reported on September 9, 2020. The silver potential, if incorporated within the initial mine plan over the next nine months, could materially improve net operating margins and early cash flow.
- Untapped Potential: The Company will allocate capital, as appropriate, to several previously identified, highly prospective targets, including those near-surface anomalies identified by the 2022 geophysical survey, as well as several high-grade silver targets.
STRATEGIC FINANCING AND RESTRUCTURING CREATING IMPROVED RESILIENCE
On June 5, 2025, we completed a US
$31M of Equity Finance: A combined brokered and non-brokered equity raise, anchored by Teck Resources Limited (“Teck”) – Canada’s leading base metals company, which contributed$2 for every$1 raised in the brokered offering.- Debt Restructuring: A
40% reduction in total debt through conversions to equity, improving our debt-to-capitalization ratio by22% . - Short-Term Payables reduction:
$10.2M of short-term payables settled - Royalty Cost Reductions: A
58% decrease in gross revenue royalty costs via amended agreements, enhancing project economics. - Offtake Agreements:
100% of all zinc and silver-lead concentrate will be delivered to Teck’s Trail Smelter in British Columbia. - Standby Facility: The provision of a
$10M standby working capital facility from Teck to de-risk the project ramp-up. - Strategic and Commercial Partnerships: Strengthened alliances with Teck, Sprott Streaming and Royalty Corp., and Monetary Metals, supported by leading brokers including BMO Capital Markets and CIBC Capital Markets.
LOOKING AHEAD
H2 2025 will focus on:
- Raising the remaining project finance, including marketing optimization of existing offtake agreements and pursuing US
$150M of debt finance from US EXIM, as announced on October 28, 2024. - Advancing the project safely to
90% completion by year-end and preparing the business for operational ramp-up during H1 2026. - Completing a resource update in H2 2025, incorporating results from silver-focused exploration in the upper mine.
- Advancing a listing application to apply to list its common shares on the NYSE American in the coming months. There is no assurance that the Company will receive listing approval to complete such a listing. Bunker Hill believes this listing will provide access to a broader investor audience and improve trading liquidity.
- Initiating discussions regarding the restructuring of existing legacy environmental agreements with local and federal agencies.
- Optimizing the silver-rich production targets to improve near-term cash flow.
Clarification to the Completion of the
- Additional Debt Settlements: As further described in the Company’s news releases dated May 16, 2025 and June 5, 2025, the Company issued (i) 761,904 units of the Company (“Units”) to MineWater LLC (together with its affiliates, “MineWater”) in full settlement of an outstanding cooperation fee in the aggregate amount of US
$80,000 for the period beginning on January 1, 2025 and ending on April 30, 2025, (ii) an aggregate of 257,379 common stock in the capital of the Company (“Common Shares”) to certain directors of the Company (the “Participating Directors”) in settlement of a total of US$27,025 owing for services rendered by the Participating Directors between March 1 - April 30, 2025 (collectively, the “Director Services”); and (iii) 30,302,180 Units to certain other arm’s length creditors or contractors of the Company to settle certain other outstanding receivables and other amounts owing in the aggregate amount of US$3,045,229 and C$195,000. In aggregate, 40,468,846 Units and 257,379 Common Shares were issued in settlement of the additional debt settlements described above, which included the equity payment of 4,761,905 Units issued to C & E Tree Farm, L.L.C. to satisfy US$500,000 of the purchase price payable under an existing option agreement between Silver Valley and C&E, dated March 3, 2023 and 4,642,857 Units to Sprott Streaming and Royalty Corp. (together with its affiliates, “Sprott Streaming”) to settle US$487,500 of unpaid interest for the period beginning on January 1, 2025 and ending on March 31, 2025 under certain secured convertible debentures held by Sprott Streaming. - Equity Offerings: The Company previously completed the Equity Offerings, as further described in the Company’s news release dated May 16, 2025, and June 5, 2025. The Company wishes to clarify the aggregate gross proceeds raised under the Brokered Private Placement and Non-Brokered Private Placement, being US
$5,976,715.08 (C$8,588,539.57) 1 and US$20,505,938.80 (C$29,467,034.06) 2, respectively. In connection with the Brokered Private Placement, the agents received an aggregate cash commission of C$461,061 , of which BMO Capital Markets received C$184,424.40 , CIBC Capital Markets received C$115,265.25 , Red Cloud Securities Inc. received C$115,265.25 , and National Bank Financial Inc. received C$46,106.10 .
ABOUT BUNKER HILL MINING CORP.
Bunker Hill is an American mineral exploration and development company focused on revitalizing our historic mining asset: the renowned zinc, lead, and silver deposit in northern Idaho’s prolific Coeur d’Alene mining district. This strategic initiative aims to breathe new life into a once-productive mine, leveraging modern exploration techniques and sustainable development practices to unlock the potential of this mineral-rich region. Bunker Hill Mining Corp. aims to maximize shareholder value while responsibly harnessing the mineral wealth in the Silver Valley mining district by concentrating our efforts on this single, high-potential asset. Information about the Company is available on its website, www.bunkerhillmining.com, or within the SEDAR+ and EDGAR databases.
On behalf of Bunker Hill Mining Corp.
Sam Ash
President and Chief Executive Officer
For additional information, please contact:
Brenda Dayton
Vice President, Investor Relations
T: 604.417.7952
E: brenda.dayton@bunkerhillmining.com
Cautionary Statements
Neither the TSX Venture Exchange (the “TSX-V”) nor its Regulation Services Provider (as that term is defined in the policies of the TSX-V) accepts responsibility for the adequacy or accuracy of this news release.
Certain statements in this news release are forward-looking and involve a number of risks and uncertainties. Such forward-looking statements are within the meaning of that term in Section 27A of the Securities Act and Section 21E of the U.S. Securities Exchange Act of 1934, as amended, as well as within the meaning of the phrase ‘forward-looking information’ in the Canadian Securities Administrators’ National Instrument 51-102 – Continuous Disclosure Obligations (collectively, “forward-looking statements”). Forward-looking statements are not comprised of historical facts. Forward-looking statements include estimates and statements that describe the Company’s future plans, objectives or goals, including words to the effect that the Company or management expects a stated condition or result to occur. Forward-looking statements may be identified by such terms as “believes”, “anticipates”, “expects”, “estimates”, “may”, “could”, “would”, “will”, “plan” or variations of such words and phrases. Forward-looking statements in this news release include, but are not limited to, statements regarding: the Company’s objectives, goals or future plans, including the restart and development of the Bunker Hill Mine and the achievement of future short-term and long-term operational strategies, the safety, sustainability, profitability and risk-level of the restart, current and future progress of the project, future cash flow and net operating margins, generation of long-life mining employment, accessibility of ore zones within initial years of planned operations, stockpiles of payable ore and their intended future use, expected capacity of the processing plant, finalization of engineering and procurement activities, the expected timing of developments at the project, upside potential associated with identification of high-grade silver zones, including potentially material improvements to net operating margins and early cash flow, the Company’s allocation of capital, future financing plans, advancements in project safety, completion of a resource update, NYSE American listing matters, restructuring of legacy environmental agreements and optimizations to silver-rich production targets. Factors that could cause actual results to differ materially from such forward-looking statements include, but are not limited to, those risks and uncertainties identified in public filings made by Bunker Hill with the U.S. Securities and Exchange Commission (the “SEC”) and with applicable Canadian securities regulatory authorities. The Company disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, other than as required by law. No stock exchange, securities commission or other regulatory authority has approved or disapproved the information contained herein.
Readers are cautioned that the foregoing risks and uncertainties are not exhaustive. Additional information on these and other risk factors that could affect the Company’s operations or financial results are included in the Company’s annual report and may be accessed through the SEDAR+ website (www.sedarplus.ca) or through EDGAR on the SEC website (www.sec.gov).
______________________________________
1 Based on a USD/CAD exchange rate of 1.4370 as published by the Bank of Canada on March 5, 2025
2 Based on a USD/CAD exchange rate of 1.4370 as published by the Bank of Canada on March 5, 2025
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/114799f2-a31c-471d-8a78-20858f370c28
https://www.globenewswire.com/NewsRoom/AttachmentNg/f855662c-91fd-4669-ace7-21fdd0640c3b
https://www.globenewswire.com/NewsRoom/AttachmentNg/b68a56b5-2530-4976-a312-31563be1bf06
https://www.globenewswire.com/NewsRoom/AttachmentNg/ee249903-271e-4ab3-9a3d-3c574b3093f1