Black Hills Corp. Provides an Update on 1.8-Gigawatt Project in Cheyenne

(Moderate)
(Positive)
Tags

Black Hills (NYSE:BKH) updated progress on its proposed 1.8‑gigawatt data center project in Cheyenne, Wyoming. The project is still moving forward and targets service beginning in early 2028.

The prior developer Crusoe has exited, but Black Hills continues directly with the large-load data center customer, supported by over $200 million in refundable construction contributions and agreements for generation equipment and a substation.

Loading...
Loading translation...

AI-generated analysis. How Rhea-AI works. Not financial advice.

Positive

  • 1.8‑GW Cheyenne data center project still targeting early 2028 service
  • Over $200 million refundable construction contributions received from prospective customer
  • Agreement signed to procure long lead-time generation equipment with customer
  • Substation agreement executed and CPCN filed in January 2026

Negative

  • Original development partner Crusoe is no longer involved in the project

News Market Reaction – BKH

+6.14%
23 alerts
+6.14% News Effect
+$319M Valuation Impact
$5.52B Market Cap
1.2x Rel. Volume

On the day this news was published, BKH gained 6.14%, reflecting a notable positive market reaction. Our momentum scanner triggered 23 alerts that day, indicating elevated trading interest and price volatility. This price movement added approximately $319M to the company's valuation, bringing the market cap to $5.52B at that time.

Data tracked by StockTitan Argus on the day of publication.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Continues to advance the project and is working directly with the hyperscaler customer

RAPID CITY, S.D., June 10, 2026 (GLOBE NEWSWIRE) -- Black Hills Corp. (NYSE: BKH) today provided an update on development activity associated with a proposed 1.8-gigawatt data center project in Cheyenne, Wyoming.

The company is continuing to advance the project and is working directly with the potential large-load customer. While Crusoe is no longer the development partner for this project, the project continues to progress as planned and is tracking for service to begin in early 2028.

“We remain committed to supporting the project’s data center customer and delivering the infrastructure necessary to meet their long-term energy needs,” said Linn Evans, president and CEO of Black Hills Corp. “The 1.8-gigawatt project has not been paused and continues to represent a significant opportunity for the company. Our efforts remain fully directed toward successfully delivering the project.”

In April 2026, the company’s electric utility subsidiary in Wyoming entered into an agreement to procure long lead-time generation equipment with the prospective customer to support the project, which is expected to be served under the Wyoming utility’s Large Power Contract Service Tariff. The customer has provided over $200 million in refundable contributions in aid of construction to date in support of milestone payments to secure generation equipment. Additionally, the company executed a substation agreement with the large-load customer and filed a CPCN for a substation to support the project in January 2026. 

About Black Hills Corporation
Black Hills Corp. (NYSE: BKH) is a customer-focused, growth-oriented utility company with a tradition of improving life with energy and a vision to be the energy partner of choice. Based in Rapid City, South Dakota, the company serves 1.37 million natural gas and electric utility customers in eight states: Arkansas, Colorado, Iowa, Kansas, Montana, Nebraska, South Dakota and Wyoming. More information is available at www.blackhillscorp.com.

CAUTION REGARDING FORWARD-LOOKING STATEMENTS

This press release includes “forward-looking statements” as defined by the Securities and Exchange Commission. We make these forward-looking statements in reliance on the safe harbor protections provided under the Private Securities Litigation Reform Act of 1995. All statements, other than statements of historical facts, included in this press release that address activities, events or developments that we expect, believe or anticipate will or may occur in the future are forward-looking statements. This includes, without limitations, the expected timing, scope and benefits of the Cheyenne data center project, the timing and availability of equipment and milestone payments related thereto and the timing of regulatory or licensing approvals. These forward-looking statements are based on assumptions which we believe are reasonable based on current expectations and projections about future events and industry conditions and trends affecting our business. However, whether actual results and developments will conform to our expectations and predictions is subject to a number of risks and uncertainties that, among other things, could cause actual results to differ materially from those contained in the forward-looking statements, including without limitation, the risk factors described in Item 1A of Part I of our 2025 Annual Report on Form 10-K and other reports that we file with the SEC from time to time.

New factors that could cause actual results to differ materially from those described in forward-looking statements emerge from time-to-time, and it is not possible for us to predict all such factors, or the extent to which any such factor or combination of factors may cause actual results to differ from those contained in any forward-looking statement. We assume no obligation to update publicly any such forward-looking statements, whether as a result of new information, future events or otherwise.

Investor Relations
Sal Diaz
investorrelations@blackhillscorp.com

24-Hour Media Relations Line
888-242-3969


FAQ

What update did Black Hills (NYSE:BKH) give on the 1.8‑GW Cheyenne data center project?

Black Hills reported that its proposed 1.8‑gigawatt Cheyenne data center project remains on track, with service expected to begin in early 2028. According to Black Hills, development continues with the large-load customer and key infrastructure agreements are already in place.

When is the Black Hills 1.8‑GW Cheyenne data center project expected to start service?

Black Hills expects the 1.8‑gigawatt Cheyenne data center project to begin service in early 2028. According to Black Hills, current work includes securing long lead-time generation equipment and pursuing required substation approvals to meet the customer’s long-term power needs.

How much has the customer contributed so far to Black Hills’ Cheyenne data center project (BKH)?

The prospective large-load customer has provided over $200 million in refundable construction contributions for the Cheyenne project. According to Black Hills, these funds support milestone payments to secure long lead-time generation equipment tied to the 1.8‑gigawatt data center load.

What agreements has Black Hills signed to support the 1.8‑GW Cheyenne project for BKH shareholders?

Black Hills has signed an agreement to procure long lead-time generation equipment and a separate substation agreement with the large-load customer. According to Black Hills, the project is expected to be served under its Wyoming Large Power Contract Service Tariff.

Is Crusoe still involved in Black Hills’ 1.8‑GW Cheyenne data center project (NYSE:BKH)?

Crusoe is no longer the development partner for the 1.8‑gigawatt Cheyenne data center project. According to Black Hills, the project continues to progress, with the company now working directly with the hyperscale large-load customer.

What does the Cheyenne data center project mean for Black Hills (BKH) utility operations in Wyoming?

The Cheyenne data center project would be served by Black Hills’ Wyoming electric utility under its Large Power Contract Service Tariff. According to Black Hills, the utility has already filed for a CPCN for a supporting substation and secured key equipment commitments.