Blue Moon Metals (OTCQX: BMOOF) announced that construction of the exploration decline at the Blue Moon VMS project in Mariposa County, California, commenced on October 5, 2025.

The company states the decline contractor is Small Mine Development (SMD), the initial 2,500 feet of decline is expected to be completed in Q2 2026, and underground exploration drilling will begin concurrently to collect geological, geotechnical and metallurgical data to support future feasibility studies and commercialization decisions.

The PR also discloses an investor relations agreement with SRC Swiss Resource Capital effective October 6, 2025 at 5,000 CHF per month, and that technical information was reviewed by Mr. Dustin Small, P.Eng., a non-independent Qualified Person under NI 43-101.

Blue Moon Metals (OTCQX: BMOOF) ha annunciato che la costruzione della discesa di esplorazione presso il progetto Blue Moon VMS nella contea di Mariposa, California, è iniziata il 5 ottobre 2025.

La società riferisce che l'appaltatore della discesa è Small Mine Development (SMD), i primi 2.500 piedi di discesa dovrebbero essere completati nel Q2 2026, e l'esplorazione sotterranea con fori di sondaggio inizierà contestualmente per raccogliere dati geologici, geotecnici e metallurgici a supporto di futuri studi di fattibilità e decisioni di commercializzazione.

Il comunicato stampa rivela inoltre un accordo di relazioni con gli investitori con SRC Swiss Resource Capital valido dal 6 ottobre 2025 al 5.000 CHF al mese, e che l'informazione tecnica è stata esaminata dal signor Dustin Small, P.Eng., un Qualified Person non indipendente ai sensi del NI 43-101.

Blue Moon Metals (OTCQX: BMOOF) anunció que la construcción de la entrada de exploración en el proyecto Blue Moon VMS en el condado de Mariposa, California, comenzó el 5 de octubre de 2025.

La empresa indica que el contratista de la entrada es Small Mine Development (SMD), los primeros 2,500 pies de entrada se espera completar en el segundo trimestre de 2026, y la perforación de exploración subterránea empezará en paralelo para recopilar datos geológicos, geotécnicos y metalúrgicos para respaldar futuros estudios de viabilidad y decisiones de comercialización.

El comunicado también revela un acuerdo de relaciones con inversores con SRC Swiss Resource Capital vigente a partir del 6 de octubre de 2025 para 5,000 CHF por mes, y que la información técnica fue revisada por el señor Dustin Small, P.Eng., una Persona Calificada no independiente conforme NI 43-101.

Blue Moon Metals (OTCQX: BMOOF)는 캘리포니아 주 Mariposa 카운티의 Blue Moon VMS 프로젝트에서 탐사 내리막길 공사가 2025년 10월 5일에 착수했다고 발표했다.

내리막길 시공자는 Small Mine Development(SMD)이며, 초기 2,500피트의 내리막길은 2026년 2분기에 완공될 것으로 예상되며, 지질학적, 지반공학적 및 금속공학적 데이터를 수집하기 위해 지하 탐사 시추도 동시 시작되어 향후 타당성 연구 및 상용화 결정에 활용될 것이다.

PR은 또한 2025년 10월 6일에 유효한 SRC Swiss Resource Capital과의 투자자 관계 협정이 있으며 월 5,000 CHF를 지불하고, 기술 정보는 NI 43-101에 따라 독립적이지 않은 자격 있는 사람으로 간주되는 Dustin Small, P.Eng.에 의해 검토되었다고 공개한다.

Blue Moon Metals (OTCQX: BMOOF) a annoncé que la construction de la descente d'exploration sur le projet Blue Moon VMS dans le comté de Mariposa, Californie, a commencé le 5 octobre 2025.

La société indique que l'entrepreneur de la descente est Small Mine Development (SMD), les premiers 2 500 pieds de descente devraient être achevés au 2e trimestre 2026, et que le forage d'exploration souterrain commencera simultanément pour collecter des données géologiques, géotechniques et métallurgiques afin d'appuyer les futures études de faisabilité et les décisions de commercialisation.

Le communiqué divulge également un accord de relations investisseurs avec SRC Swiss Resource Capital efficace à partir du 6 octobre 2025 pour 5 000 CHF par mois, et que l'information technique a été examinée par M. Dustin Small, P.Eng., une Personne Qualifiée non indépendante selon NI 43-101.

Blue Moon Metals (OTCQX: BMOOF) gab bekannt, dass der Bau der Explorations-Tunnelabstieg am Blue Moon VMS-Projekt im Mariposa County, Kalifornien, am 5. Oktober 2025 begann.

Das Unternehmen gibt an, dass der Abstieg- Auftragnehmer Small Mine Development (SMD) sei, die ersten 2.500 Fuß des Abstiegs voraussichtlich im 2. Quartal 2026 abgeschlossen werden, und unterirdische Explorationsbohrungen zeitgleich beginnen werden, um geologische, geotechnische und metallurgische Daten zur Unterstützung zukünftiger Machbarkeitsstudien und Vermarktungsentscheidungen zu sammeln.

Der PR zufolge besteht auch eine Investor Relations Vereinbarung mit SRC Swiss Resource Capital, gültig ab dem 6. Oktober 2025 zu 5.000 CHF pro Monat, und dass technische Informationen von Herrn Dustin Small, P.Eng., einer nicht-unabhängigen Qualified Person gemäß NI 43-101 geprüft wurden.

Blue Moon Metals (OTCQX: BMOOF) أعلنت أن بناء المنحدر الاستكشافي في مشروع Blue Moon VMS في مقاطعة مارِيْبُوسا، كاليفورنيا، بدأ في 5 أكتوبر 2025.

تذكر الشركة أن مقاول المنحدر هو Small Mine Development (SMD)، ومن المتوقع استكمال أول 2,500 قدم من المنحدر في الربع الثاني من 2026، وسيبدأ الحفر الاستكشافي تحت الأرض بشكل متزامن لجمع البيانات الجيولوجية والجيوميكانيكية والميتالوغرافية لدعم دراسات الجدوى والت decisions تجارية مستقبلية.

كما يكشف البيان الصحفي عن اتفاق علاقات مع المستثمرين مع SRC Swiss Resource Capital ساري المفعول اعتباراً من 6 أكتوبر 2025 بـ 5,000 CHF شهرياً، وأن المعلومات الفنية راجعها السيد Dustin Small، P.Eng., وهو شخص مؤهل غير مستقل وفق NI 43-101.

Blue Moon Metals (OTCQX: BMOOF)宣布在加利福尼亚州马里波萨县的 Blue Moon VMS 项目探索下坡道的建设已于 2025年10月5日开始。

公司表示下坡道承包商为 Small Mine Development (SMD),初始的 2,500 英尺 下坡道预计在 2026年第二季度完工,地下勘探钻探将同步开始,以收集地质、岩土和冶金数据,为未来的可行性研究和商业化决策提供支持。

新闻稿还披露与 SRC Swiss Resource Capital 的投资者关系协议自 2025年10月6日 起生效,月费为 5,000 CHF,技术信息由 Dustin Small, P.Eng. 先生审核,他是在 NI 43-101 下的非独立合格人员。

Positive
  • Decline construction commenced on October 5, 2025
  • Initial 2,500 ft decline expected complete by Q2 2026
  • Underground drilling to start concurrently with decline advance
  • IR agreement with SRC effective October 6, 2025 at 5,000 CHF/month
Negative
  • Qualified Person review performed by a non-independent QP (Dustin Small, P.Eng.)
  • Ongoing IR cost of 5,000 CHF/month under SRC agreement

TORONTO, Oct. 6, 2025 /PRNewswire/ - Blue Moon Metals Inc. ("Blue Moon" or the "Company") (TSXV: MOON) (OTCQX: BMOOF), is pleased to announce that construction of the exploration decline at its Blue Moon volcanogenic massive sulphide ("VMS") project (the "Project"), located in Mariposa County, California, officially commenced on October 5, 2025.

This marks a major milestone in advancing the Project, following the award of the contract to Small Mine Development, L.L.C. ("SMD") earlier this year (see June 26, 2025 news release). The decline will provide underground access for infill and exploration drilling, geotechnical and metallurgical test work, and studies of underground mining conditions. These activities are critical to supporting future feasibility studies and a potential mine commercialization decision.

The CEO of Blue Moon, Christian Kargl-Simard stated:

"The commencement of decline construction is a transformative moment for Blue Moon. Moving underground allows us to accelerate exploration drilling and technical studies, while maintaining a very small surface footprint. We are excited to advance toward unlocking the full potential of the Blue Moon deposit and to continue working closely with SMD, our local partners, and the Mariposa County community."

Portal construction activities began on October 5 and the initial 2,500 feet of the exploration decline is expected to be completed in Q2-2026. Exploration drilling activities will commence from underground concurrently with the advance of the decline, enabling the Company to accelerate the collection of geological, geotechnical and metallurgical data in parallel with ongoing development. The Company is committed to supporting the economic and social development of the local and regional communities.

European Outreach

In addition, the Company announces that it has entered into an agreement (the "Agreement") with SRC Swiss Resource Capital AG ("SRC") for investor relations and communications services Europe. The Agreement is effective as of October 6, 2025, for a period of one year, after which time the SRC Agreement is automatically renewable on a quarterly basis. The Agreement can be terminated by either party by providing seven (7) days written notice. The services to be provided by SRC to the Company under the terms of the Agreement include communications services, generally viewed as investor relations, including dissemination of information to existing and potential shareholders, creating media through interview and videos as well as supporting or representing the Company at trade and investment shows. Pursuant to the terms of the Agreement, SRC is to be paid 5,000 CHF per month with additional fees for special services such as trade and investment shows. 

SRC is a private company based in Herisau, Switzerland. SRC is led by Jochen Staiger, Chief Executive Officer. SRC has experience in providing services to companies listed on various stock exchanges that are seeking to raise their profile in public markets. SRC does not own, directly or indirectly, any securities of the Company.

Qualified Persons

The technical and scientific information of this news release has been reviewed and approved by Mr. Dustin Small, P.Eng., a non-Independent Qualified Person, as defined by NI 43-101.

About Blue Moon

Blue Moon is advancing 3 brownfield polymetallic projects, including the Nussir copper-gold-silver project in Norway, the NSG copper-zinc-gold-silver project in Norway and the Blue Moon zinc-gold-silver-copper project in the United States. All 3 projects are well located with existing local infrastructure including roads, power and historical infrastructure. Zinc and copper are currently on the USGS and EU list of metals critical to the global economy and national security. More information is available on the Company's website (www.bluemoonmetals.com).

About Small Mine Development LLC (SMD)

Small Mine Development builds and operates America's underground mines. SMD's mission is to be the leader in safe, productive and innovative mining solutions. They specialize in underground, hardrock mining and advance projects from exploration, through engineering, development, production mining, and, ultimately, closure.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

CAUTIONARY DISCLAIMER - FORWARD LOOKING STATEMENTS

This news release includes "forward-looking statements" and "forward-looking information" within the meaning of applicable Canadian and U.S. securities laws. All statements included herein that address events or developments that we expect to occur in the future are forward-looking statements. Forward-looking information may in some cases be identified by words such as "will", "anticipates", "expects", "intends" and similar expressions suggesting future events or future performance.

We caution that all forward-looking information is inherently subject to change and uncertainty and that actual results may differ materially from those expressed or implied by the forward-looking information. A number of risks, uncertainties and other factors could cause actual results and events to differ materially from those expressed or implied in the forward-looking information or could cause our current objectives, strategies and intentions to change. Accordingly, we warn investors to exercise caution when considering statements containing forward-looking information and that it would be unreasonable to rely on such statements as creating legal rights regarding our future results or plans. We cannot guarantee that any forward-looking information will materialize and you are cautioned not to place undue reliance on this forward-looking information. Any forward-looking information contained in this news release represents management's current expectations and are based on information currently available to management, and are subject to change after the date of this news release. We are under no obligation (and we expressly disclaim any such obligation) to update or alter any statements containing forward-looking information, the factors or assumptions underlying them, whether as a result of new information, future events or otherwise, except as required by law. All of the forward-looking information in this news release is qualified by the cautionary statements herein.

Forward-looking information is provided herein for the purpose of giving information about the Project and its expected impact. Readers are cautioned that such information may not be appropriate for other purposes.

A comprehensive discussion of other risks that impact Blue Moon can also be found in its public reports and filings which are available at www.sedarplus.ca

Cision View original content:https://www.prnewswire.com/news-releases/blue-moon-commences-construction-of-exploration-decline-at-its-blue-moon-mine-in-mariposa-county-california-302575268.html

SOURCE Blue Moon Metals

FAQ

What did Blue Moon (BMOOF) announce on October 6, 2025 about the Mariposa County project?

The PR states decline construction at the Blue Moon VMS project commenced on October 5, 2025 to enable underground drilling and technical studies.

When will the initial portion of the Blue Moon exploration decline (BMOOF) be finished?

According to the company, the initial 2,500 feet of decline is expected to be completed in Q2 2026.

Who was awarded the Blue Moon decline contract and what will the decline be used for?

The PR says Small Mine Development (SMD) was awarded the contract; the decline will provide access for infill/exploration drilling, geotechnical and metallurgical work.

How will underground drilling be scheduled at Blue Moon (BMOOF)?

The company states underground exploration drilling will commence from the decline concurrently with its advance to accelerate data collection.

What are the terms of Blue Moon's investor relations agreement announced October 6, 2025?

The PR discloses an agreement with SRC effective October 6, 2025 for one year, renewing quarterly thereafter, at 5,000 CHF per month with additional fees for special services.

Who reviewed the technical information in the Blue Moon (BMOOF) news release?

The PR states Mr. Dustin Small, P.Eng., a non-independent Qualified Person as defined by NI 43-101, reviewed and approved the technical information.
Blue Moon Metals Inc

OTC:BMOOF

BMOOF Rankings

BMOOF Latest News

BMOOF Stock Data

124.09M
35.09M
30.9%
1.8%
Other Industrial Metals & Mining
Basic Materials
Link
Canada
Toronto