STOCK TITAN

Bitdeer Announces May 2026 Production and Operations Update

(Positive)
Tags

Bitdeer (NASDAQ:BTDR) reported its May 2026 production and operations update, highlighting growth in Bitcoin mining and AI infrastructure.

Bitcoin production reached 921 BTC, up 370% year-over-year, with self-mining hash rate at 70.2 EH/s. AI Cloud annual recurring revenue was approximately $69 million at 90% GPU utilization, and total global electrical capacity reached 3,003.5 MW, including online and pipeline projects.

Loading...
Loading translation...

AI-generated analysis. How Rhea-AI works. Not financial advice.

Positive

  • Bitcoin production of 921 BTC in May 2026, a 370% Y/Y increase
  • Self-mining hash rate 70.2 EH/s vs 13.6 EH/s in May 2025
  • Total hash rate under management 83.1 EH/s vs 27.4 EH/s a year earlier
  • AI Cloud ARR approximately $69M with 90% GPU utilization in May 2026
  • Deployment of 2 NVIDIA GB300 NVL72 clusters expanding AI GPU capacity
  • Total global electrical capacity 3,003.5 MW across online and pipeline sites

Negative

  • AI Cloud GPU utilization decreased to 90% from 92% month-over-month
  • BTC held 171 at May 2026 vs 1,351 at May 2025
  • Massillon, OH 21 MW energization shifted into phased Q3 2026 timing
  • Reconstruction of two fire-damaged Massillon buildings (26 MW) ongoing through end of Q3 2026
  • Clarington, OH 570 MW project timing may be affected by ongoing legal proceedings

News Market Reaction – BTDR

+1.17%
+1.17% News Effect

On the day this news was published, BTDR gained 1.17%, reflecting a mild positive market reaction.

Data tracked by StockTitan Argus on the day of publication.

What This Means

This announcement highlights sustained growth in BTC production to 921 BTC and stable AI Cloud ARR n...
Analysis

This announcement highlights sustained growth in BTC production to 921 BTC and stable AI Cloud ARR near $69M on a 3.0 GW portfolio. Prior updates have usually been well-received, though elevated short interest adds volatility risk to future news flow.

Key Figures

BTC mined: 921 BTC AI Cloud ARR: ~$69M Global energy capacity: 3.0 GW +5 more
8 metrics
BTC mined 921 BTC May 2026, up 370% year-over-year
AI Cloud ARR ~$69M May 2026, at 90% GPU utilization
Global energy capacity 3.0 GW Total global electrical capacity across portfolio
Self-mining hash rate 70.2 EH/s May 2026 self-mining operations
Co-mining hash rate 10.0 EH/s May 2026 co-mining in third-party datacenters
Self-mining rigs 231,000 rigs Self-mining rigs under management in May 2026
GPUs deployed 4,248 GPUs Bitdeer AI Cloud deployed GPUs in May 2026
GPU utilization rate 90% Bitdeer AI Cloud utilization in May 2026

Historical Context

5 past events · Latest: Jun 02 (Positive)
Pattern 5 events
Date Event Sentiment 24h Move Catalyst
Jun 02 Alberta facility build Positive +1.4% Groundbreaking for 101 MW Alberta energy and high-performance computing facility.
Jun 01 Miner launch Positive +5.8% Launch of SEALMINER DL1 Hydro with high Scrypt hash rate and efficiency.
May 14 Q1 2026 results Neutral +11.6% Strong revenue growth but swing to net loss with positive adjusted EBITDA.
May 12 April ops update Positive -2.6% Significant growth in BTC mined, hash rate, GPUs, and AI ARR to ~$69M.
May 01 Earnings call notice Neutral +4.9% Scheduling of Q1 2026 earnings release and conference call details.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

Pattern Detected

BTDR has generally reacted positively to growth and operations news, with one recent divergence on an April operations update.

Regulatory & Risk Context

Short Interest: 39.76%
Short Interest
39.76% of shares outstanding
as of 2026-05-29 Days to cover: 4.54

Short interest appears elevated, suggesting positioning that can increase volatility and leave room for sharp moves if sentiment or liquidity conditions change.

Key Terms

asic, scrypt algorithm, self-mining, annualized recurring revenue, +1 more
5 terms
asic technical
"with Bitdeer’s proprietary ASIC technology with hydro-cooling thermal"
ASIC is Australia’s corporate, markets and financial services regulator that enforces rules for companies, financial advisers and market operators; think of it as the referee and rulebook keeper for financial activity. It matters to investors because ASIC’s oversight, investigations and enforcement actions affect company credibility, legal risk and market fairness—actions that can change stock prices, investor confidence and the safety of financial products.
scrypt algorithm technical
"SEALMINER DL1 Hydro, designed for Scrypt algorithm mining with"
scrypt algorithm is a computer method originally designed to turn passwords into secure codes and, in cryptocurrencies, to create the mining puzzle that secures a blockchain by requiring not just raw computing power but substantial memory use. It matters to investors because the algorithm determines which mining hardware and energy costs are effective, shaping mining profitability, network security and the rate new coins enter the market—similar to how a factory’s equipment and energy needs affect its production costs and supply.
self-mining technical
"Self-mining hash rate reached ~70.2 EH/s. Co-mining hashrate"
Self-mining is when a person or company uses its own equipment and resources to create new cryptocurrency coins rather than buying them or hiring someone else to mine. For investors, it matters because self-mining turns computing power into an ongoing source of revenue and digital assets, like owning a small factory instead of just selling its products; it affects costs, cash flow, asset holdings and exposure to energy and regulatory risks.
annualized recurring revenue financial
"ARR as of the last day of the respective month is calculated by multiplying the daily revenue"
Annualized recurring revenue is the predictable income a business expects to earn over a year from ongoing customer subscriptions or contracts. It’s similar to estimating how much money you would make in a year if your current monthly income stayed the same. Investors use this figure to assess the stability and growth potential of a company's revenue stream.
utilization rate technical
"Utilization Rate 8 | 90% | 92%"
Utilization rate measures the percentage of a company's available capacity that is actually being used over a given period — for example, how full a factory, hospital unit, or loan facility is compared with its maximum. It matters to investors because it signals efficiency and future revenue potential: higher utilization often means better use of fixed costs and stronger demand, while very low or extremely high rates can indicate underuse, lost sales, or strained resources. Think of it like the share of seats filled in a restaurant; it helps show whether the business is making the most of what it has.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Monthly Highlights

  • Bitcoin: Production increased 370% Y/Y to 921 Bitcoin
  • SEALMINERs: Recent launch of SEALMINER DL1 Hydro, designed for Scrypt algorithm mining with Bitdeer’s proprietary ASIC technology with hydro-cooling thermal management system
  • Colocation: Executing on colocation lease agreements is THE top priority for management, with Tydal, Norway site in advanced stages of negotiations
  • AI Cloud: Deployment and production launch of 2 units of NVIDIA GB300 NVL72 clusters, further expanding Bitdeer AI Cloud’s advanced GPU infrastructure
Key Metrics Summary
 
Global Energy CapacitySelf-Mining Hash Rate1Co-Mining Hash Rate2Self-Mining RigsBTC MinedAI Cloud ARRColocation AI Data Center
       
3.0 GW70.2 (EH/s)10.0 (EH/s)231K921~$69MTydal, Norway in advanced stages of negotiations
       

SINGAPORE, June 18, 2026 (GLOBE NEWSWIRE) -- Bitdeer Technologies Group (NASDAQ: BTDR) (“Bitdeer” or the “Company”), a world-leading technology company for AI and Bitcoin mining infrastructure, today announced its unaudited operations updates for May 2026.

Management Commentary

“May reflected continued execution across Bitdeer's AI infrastructure platform. AI Cloud ARR held at approximately $69 million at 90% GPU utilization, with GB300 NVL72 cluster deployment and Nemotron 3 availability reinforcing our enterprise-grade capabilities,” said Michael G. Potter, Chief Financial Officer of Bitdeer. “Tydal, Norway is in advanced stages of negotiations, representing the most visible proof point of our strategy to convert owned power into long-duration contracted revenue across our 3.0 GW global portfolio.” Mr. Potter continued, “Bitcoin production of 921 BTC, up 370% year-over-year, and self-mining hashrate of 70.2 EH/s underscore the complementary strength of our vertically integrated mining platform as we accelerate the AI transition across our sites.”

Crypto Mining Update:

CRYPTO Mining, R&D, Manufacturing:

  • Mined 921 Bitcoins3, an increase of 370% Y/Y; we continue to expect momentum in our mining results over the coming months.
  • Self-mining hash rate reached ~70.2 EH/s. Co-mining hashrate of 10.0 EH/s driven by Co-Mining collaboration, using Bitdeer’s mining rigs operated in 3rd party datacenters
  • Recent launch of SEALMINER DL1 Hydro, designed for Scrypt algorithm mining with Bitdeer’s proprietary ASIC technology with hydro-cooling thermal management system

Key Crypto Metrics:

MetricMay 2026April 2026May 2025
Hash Rate Metrics:
Self-Mining (Operated in self-owned datacenters)70.265.513.6
Other Proprietary Hash Rate44.75.30.1
Hosting58.28.213.7
Total Hash Rate under Mgmt.6 (EH/s)83.179.027.4
    
Co-Mining (Operated in 3rd party datacenters)10.08.4-
    
Mining Rig Metrics:
Self-Mining231,000218,000103,000
Hosted46,00046,00086,000
Total Mining Rigs under Mgmt.277,000264,000 189,000
    
Co-Mining39,00033,000-
 
BTC Mined3921783196
BTC Held7171731,351
    

Bitdeer AI Update:

Colocation AI Data Center:

  • Bitdeer is in advanced stages of negotiations with a potential colocation tenant for Tydal, Norway and remains in active dialogue in Ohio, Texas and various other sites.

AI Cloud Key Metrics:

MetricMay 2026April 2026
GPU Amount Deployed4,248
4,184
GPU TypesH100, H200, B200, GB200, GB300H100, H200, B200, GB200
Utilization Rate890%
92%
GPUs Under External Subscription3,305
3,323
ARR9~$69M~$69M
   
  • GB300 Deployment and Launch: Successfully completed the deployment and production launch of 2 units of NVIDIA GB300 NVL72 clusters, further expanding Bitdeer AI Cloud’s advanced GPU infrastructure and enabling support for next-generation AI training and inference workloads at scale.
  • Deployed NVIDIA Nemotron 3 Nano Omni on Day 0 of its launch onto the Bitdeer AI Model Studio via a streamlined, serverless inference API. This significantly expands enterprise model optionality, accelerating the transition from experimentation to production-ready workflows.
  • Participated in the Oslo Tech Show 2026 in Norway, strategically expanding our European footprint. Delivered a keynote address highlighting next-generation data centers and resilient networks designed to support large-scale AI infrastructure.

Infrastructure Summary:

Site(MW) CapacityEnergization Timing10Planned UsageConstruction Update
     
Online Electrical Capacity:
 
1)Rockdale, TX563OnlineCrypto to Colocation / AI CloudIn active evaluation of AI transition
      
2)Knoxville, TN – phase 137Q4 ‘26Crypto to AI Cloud

Phase 1 AI data center conversion design work initiated, targeting to complete by Q4 ’26.

    
3)Knoxville, TN – phase 249Q1 ‘27
      
4)Wenatchee, WA13Q4 ‘26Crypto to AI CloudAI data center design documents and building permit application submitted for approval. Core equipment is being delivered in succession; we plan to begin with a GB300 cluster. Dismantling of the crypto mining datacenter started in March 2026. Completion targeted Q4 ’26.
      
5)Molde, Norway84OnlineCrypto and in early assessment of converting to AI Cloud 
      
6)Tydal, Norway – phase 150Q4 ‘26Crypto to Colocation

Planning and design continue to advance. Orders for critical long-lead equipment have been placed on an ongoing basis. Engaged Data Center Installations AS as Bitdeer’s design and construction partner for Tydal AI datacenter conversion.

    
7)Tydal, Norway – phase 2175Q4 ‘26
      
8)Gedu, Bhutan100OnlineCrypto 
      
9)Jigmeling, Bhutan500OnlineCrypto 
      
10)Oromia Region, Ethiopia50OnlineCryptoConstruction of the 50 MW site has been completed and energized, with ongoing energization in phases driven by SEALMINER deliveries.
      
11)Massillon, OH174OnlineCrypto 
      
12)Cyberjaya, Malaysia112OnlineAI Cloud 
      
Online Electrical Subtotal:1,797   
     
Pipeline Electrical Capacity:
 
1)Massilon, OH21 / 26Q3 ’26CryptoDue to delivery delays for key electrical components, 21 MW is expected to be energized in phases during Q3 ’26. Reconstruction of the two fire-damaged buildings (26MW) is currently underway and expected to be rebuilt and energized by the end of Q3’ 26. A significant portion of the reconstruction cost has now been successfully recovered through the supplier’s insurance coverage.
      
2)Clarington, OH570To be updatedColocation / Crypto570 MW of power under contract with a local utility. Timing of power availability and construction may be affected by ongoing legal proceedings filed by a neighboring company, American Heavy Plate Solutions, LLC., which is under extensive influence from MHR, a New York based PE firm founded by Mark H. Rachesky. Design and other preparation work continues.
      
3)Niles, OH300Q4 ‘28Colocation / AI Cloud300 MW grid-interconnected development site, with target energization in Q4 ‘28. The project includes 41.8 acres of owned land and a transmission line extension agreement with a local utility company.
      
4)Rockdale, TX1792026Colocation / AI CloudIn Planning
      
5)Fox Creek, Alberta, Canada101Q2 ‘27Crypto101 MW site acquired, fully licensed and permitted for the construction of an on-site natural gas power plant. Assessing current design potential to accommodate future AIDC requirements. We were pleased to host a successful groundbreaking ceremony on June 1st, 2026, joined by Minister Dale Nally, Minister Todd Loewen, the Reeve of the MD of Greenview, and the Mayor of Fox Creek.
      
6)Cyberjaya, Malaysia119.5Q4 ‘26AI CloudIn Progress
      
Pipeline Electrical Subtotal:1,206.5   
     
Total Global Electrical Capacity:3,003.5   
     

Upcoming Conferences and Events

  • June 18, 2026: Roth London Conference
  • June 23, 2026: Northland Capital Markets Growth Conference - Virtual

Footnotes

1 Self-Mining (Operated in self-owned datacenters) refers to cryptocurrency mining for Bitdeer’s own account, whereby its mining rigs are operated in self-owned datacenters

2 Co-mining (Operated in 3rd party datacenters) refers to cryptocurrency mining for Bitdeer’s own account, whereby its mining rigs are operated in third-party datacenters

3 Includes BTC from self-mining operations and BTC from co-mining operations.

4 Other Proprietary Hash Rate includes the hashrate from Bitdeer’s cloud hashrate business, mining rigs delivered in the crypto mining datacenters but not deployed and the mining rigs temporarily offline due to limited economic benefit.

5 Hosting encompasses a one-stop mining machine hosting solution including deployment, maintenance, and management services for efficient cryptocurrency mining.

6 Total hash rate under management as of May 30, 2026, across Bitdeer’s primary business lines: Self-mining, Cloud Hash Rate, and Hosting.

7 Bitcoins held does not include Bitcoins from customer deposits but does include Bitcoins that are pledged as collateral by us.

8 Utilization Rate as of the last day of the respective month is calculated as the total number of GPUs under internal and external orders divided by the total number of deployed GPUs.

9 ARR as of the last day of the respective month is calculated by multiplying the daily revenue generated from all contractually obligated GPU orders on that specific day by 365. This metric provides an annualized view of the revenue run-rate based on active contracts at the end of the reporting period.

10 Indicative timing for completion of power. All timing references are to calendar quarters and years.

11 Capacity under lease arrangement.

About Bitdeer Technologies Group

Bitdeer is a world-leading technology company for AI and Bitcoin mining infrastructure. Bitdeer is committed to providing comprehensive Bitcoin mining solutions for its customers and building AI computational infrastructure to support the AI revolution. Bitdeer handles complex processes involved in computing such as equipment procurement, transport logistics, data center design and construction, equipment management, and daily operations. Bitdeer also offers advanced cloud capabilities to customers with high demand for artificial intelligence. Headquartered in Singapore, Bitdeer has deployed data centers across multiple countries, including the United States, Norway, Bhutan, and Ethiopia. To learn more, visit https://ir.bitdeer.com/ or follow Bitdeer on X@Bitdeer and LinkedIn @Bitdeer.

Investors and others should note that Bitdeer may announce material information using its website and/or on its accounts on social media platforms, including X, formerly known as Twitter, Facebook, and LinkedIn. Therefore, Bitdeer encourages investors and others to review the information it posts on the social media and other communication channels listed on its website.

Forward-Looking Statements

Statements in this press release about future expectations, plans, and prospects, as well as any other statements regarding matters that are not historical facts, may constitute “forward-looking statements” within the meaning of The Private Securities Litigation Reform Act of 1995. The words “anticipate,” “look forward to,” “believe,” “continue,” “could,” “estimate,” “expect,” “intend,” “may,” “plan,” “potential,” “predict,” “project,” “should,” “target,” “will,” “would” and similar expressions are intended to identify forward-looking statements, although not all forward-looking statements contain these identifying words. Actual results may differ materially from those indicated by such forward-looking statements as a result of various important factors, including factors discussed in the section entitled “Risk Factors” in Bitdeer’s annual report on Form 20-F, as well as discussions of potential risks, uncertainties, and other important factors in Bitdeer’s subsequent filings with the U.S. Securities and Exchange Commission. Any forward-looking statements contained in this press release speak only as of the date hereof. Bitdeer specifically disclaims any obligation to update any forward-looking statement, whether due to new information, future events, or otherwise. Readers should not rely upon the information on this page as current or accurate after its publication date.

For investor and media inquiries, please contact:

Investor Relations
Tesh Dahya, Head of Investor Relations
tesh.dahya@bitdeer.com

Media
Elev8 New Media
Jessica Starman, MBA
bitdeer@elev8newmedia.com


FAQ

How many Bitcoin did Bitdeer (NASDAQ:BTDR) mine in May 2026 and how does it compare year-over-year?

Bitdeer mined 921 Bitcoin in May 2026, a 370% increase year-over-year. According to Bitdeer, BTC mined rose from 196 in May 2025 to 921 in May 2026, supported by higher self-mining hash rate and more rigs under management.

What was Bitdeer (BTDR) self-mining hash rate and total hash rate under management in May 2026?

Bitdeer reported self-mining hash rate of 70.2 EH/s and total hash rate under management of 83.1 EH/s in May 2026. According to Bitdeer, both metrics increased significantly from May 2025 levels of 13.6 EH/s and 27.4 EH/s respectively.

What is Bitdeer AI Cloud ARR and GPU utilization as of May 2026?

Bitdeer AI Cloud annual recurring revenue was approximately $69 million with 90% GPU utilization in May 2026. According to Bitdeer, 4,248 GPUs were deployed, with 3,305 under external subscription, spanning H100, H200, B200, GB200, and GB300 models.

What progress did Bitdeer (BTDR) report on its Tydal, Norway colocation AI data center in May 2026?

Bitdeer is in advanced stages of negotiations with a potential colocation tenant for Tydal, Norway. According to Bitdeer, phase 1 (50 MW) targets Q4 2026 for crypto-to-colocation conversion, with planning, design and long-lead equipment orders continuing alongside an engaged local design and construction partner.

How large is Bitdeer global electrical capacity for crypto and AI operations as of May 2026?

Bitdeer reported total global electrical capacity of 3,003.5 MW across online and pipeline sites. According to Bitdeer, 1,797 MW is online and 1,206.5 MW is in the pipeline, supporting crypto mining, colocation, and AI Cloud data center developments in multiple regions.

What new AI infrastructure did Bitdeer (BTDR) deploy in May 2026 for its AI Cloud business?

Bitdeer completed deployment and production launch of two NVIDIA GB300 NVL72 clusters in May 2026. According to Bitdeer, this expands advanced GPU infrastructure for next-generation AI training and inference, and includes Day 0 deployment of NVIDIA Nemotron 3 Nano Omni in its AI Model Studio.