B2Gold Announces Positive Feasibility Study Results for the Gramalote Project
B2Gold (NYSE: BTG) has announced positive Feasibility Study results for its 100% owned Gramalote gold project in Colombia. The study reveals an after-tax NPV of $941 million (at $2,500/oz gold) and $1.716 billion (at $3,300/oz spot gold), with IRRs of 22.4% and 33.5% respectively.
The project features an 11-year open pit mine with 13 years of mill processing, expecting to produce 227,000 ounces of gold annually in the first five years and 177,000 ounces annually over the project life. The initial construction capital is estimated at $740 million, with all-in sustaining costs of $985 per gold ounce.
The Probable Mineral Reserves stand at 76.7 million tonnes grading 0.96 g/t gold for 2.36 million contained gold ounces. The project requires permit modifications, expected to take 12-18 months.
B2Gold (NYSE: BTG) ha annunciato risultati positivi dello Studio di Fattibilità per il suo progetto aurifero Gramalote interamente di proprietà in Colombia. Lo studio evidenzia un NPV post-tasse di 941 milioni di dollari (a 2.500 $/oz oro) e 1,716 miliardi di dollari (a 3.300 $/oz oro spot), con un IRR rispettivamente del 22,4% e del 33,5%.
Il progetto prevede una miniera a cielo aperto di 11 anni con 13 anni di lavorazione in impianto, con una produzione stimata di 227.000 once d'oro all'anno nei primi cinque anni e 177.000 once annue per tutta la durata del progetto. Il capitale iniziale per la costruzione è stimato in 740 milioni di dollari, con costi totali sostenuti di 985 dollari per oncia d'oro.
Le Riserve Minerarie Probabili ammontano a 76,7 milioni di tonnellate con una gradazione di 0,96 g/t oro per un totale di 2,36 milioni di once d'oro contenute. Il progetto necessita di modifiche ai permessi, che si prevede richiederanno dai 12 ai 18 mesi.
B2Gold (NYSE: BTG) ha anunciado resultados positivos del Estudio de Factibilidad para su proyecto aurífero Gramalote 100% propio en Colombia. El estudio muestra un VPN después de impuestos de 941 millones de dólares (a 2.500 $/oz de oro) y 1.716 millones de dólares (a 3.300 $/oz de oro al contado), con TIRs del 22,4% y 33,5% respectivamente.
El proyecto cuenta con una mina a cielo abierto de 11 años y 13 años de procesamiento en planta, con una producción estimada de 227.000 onzas de oro anuales durante los primeros cinco años y 177.000 onzas anuales durante toda la vida del proyecto. El capital inicial para la construcción se estima en 740 millones de dólares, con costos totales sostenidos de 985 dólares por onza de oro.
Las Reservas Minerales Probables son de 76,7 millones de toneladas con una ley de 0,96 g/t de oro para un total de 2,36 millones de onzas de oro contenidas. El proyecto requiere modificaciones en los permisos, que se espera tomen entre 12 y 18 meses.
B2Gold (NYSE: BTG)는 콜롬비아에 위치한 100% 소유한 그라마로테 금 프로젝트에 대한 긍정적인 타당성 조사 결과를 발표했습니다. 이 연구는 세후 순현재가치(NPV)가 9억 4,100만 달러 (금 가격 온스당 2,500달러 기준) 및 17억 1,600만 달러 (현물 금 가격 온스당 3,300달러 기준)을 나타내며, 내부수익률(IRR)은 각각 22.4%와 33.5%입니다.
이 프로젝트는 11년간 노천 광산과 13년간 제련 공정을 특징으로 하며, 초기 5년 동안 연간 227,000 온스의 금을 생산하고, 프로젝트 전체 기간 동안 연간 177,000 온스를 생산할 것으로 예상됩니다. 초기 건설 자본은 7억 4,000만 달러로 추산되며, 온스당 총 유지 비용은 985달러입니다.
추정 광물 매장량은 7,670만 톤이며, 금 함량은 그램당 0.96으로 236만 온스의 금 함유량을 보유하고 있습니다. 이 프로젝트는 허가 변경이 필요하며, 12~18개월이 소요될 것으로 예상됩니다.
B2Gold (NYSE : BTG) a annoncé des résultats positifs de l'Étude de Faisabilité pour son projet aurifère Gramalote détenu à 100% en Colombie. L'étude révèle une VAN après impôts de 941 millions de dollars (à 2 500 $/oz d'or) et 1,716 milliard de dollars (au prix spot de 3 300 $/oz d'or), avec des TRI de 22,4% et 33,5% respectivement.
Le projet comprend une mine à ciel ouvert de 11 ans avec 13 ans de traitement en usine, prévoyant une production annuelle de 227 000 onces d'or durant les cinq premières années et 177 000 onces par an sur la durée totale du projet. Le capital initial de construction est estimé à 740 millions de dollars, avec des coûts totaux de maintien à 985 dollars par once d'or.
Les réserves minérales probables s'élèvent à 76,7 millions de tonnes avec une teneur en or de 0,96 g/t pour un total de 2,36 millions d'onces d'or contenues. Le projet nécessite des modifications de permis, dont la durée est estimée entre 12 et 18 mois.
B2Gold (NYSE: BTG) hat positive Ergebnisse der Machbarkeitsstudie für sein zu 100 % im Besitz befindliches Gramalote-Goldprojekt in Kolumbien bekannt gegeben. Die Studie zeigt einen Nachsteuer-NPV von 941 Millionen US-Dollar (bei 2.500 $/oz Gold) und 1,716 Milliarden US-Dollar (bei 3.300 $/oz Spot-Gold) mit IRRs von 22,4% bzw. 33,5%.
Das Projekt umfasst eine 11-jährige Tagebaumine mit 13 Jahren Verarbeitung in der Mühle und erwartet eine jährliche Goldproduktion von 227.000 Unzen in den ersten fünf Jahren und 177.000 Unzen über die gesamte Projektdauer. Die anfänglichen Baukosten werden auf 740 Millionen US-Dollar geschätzt, bei Gesamtkosten von 985 US-Dollar pro Goldunze.
Die wahrscheinlichen Mineralreserven betragen 76,7 Millionen Tonnen mit einem Gehalt von 0,96 g/t Gold für 2,36 Millionen enthaltene Goldunzen. Das Projekt erfordert Genehmigungsänderungen, die voraussichtlich 12 bis 18 Monate dauern werden.
- After-tax NPV of $941M with 22.4% IRR at $2,500/oz gold price
- Strong gold recovery rate of 95.7% from conventional processing
- Robust first 5-year production averaging 227,000 oz gold annually
- Competitive AISC of $985/oz over project life
- Significant mineral reserves of 2.36M contained gold ounces
- Strong local community and government support
- Existing mining permits in place, though modifications needed
- High initial capital cost of $740M required
- 12-18 month timeline for permit modifications needed
- Production decline after first 5 years from 227,000 to 177,000 oz annually
- Additional post-construction capital of $444M needed over project life
Insights
B2Gold's Gramalote feasibility study shows robust economics with 22.4% IRR at $2,500/oz gold, supporting a viable 177,000 oz/year operation with manageable capital requirements.
The feasibility study for B2Gold's Gramalote project in Colombia reveals an economically viable gold mine with compelling metrics. The $941 million after-tax NPV (at 5% discount rate) and 22.4% IRR at $2,500/oz gold price indicate a project that significantly exceeds typical mining investment thresholds of 15% IRR. The economics become even more attractive at the current spot price of $3,300/oz, with NPV jumping to $1.72 billion and IRR to 33.5%.
The capital intensity is relatively efficient with $740 million construction capital yielding a 177,000 oz annual production over the 13-year life of project. This translates to approximately $4,180 per annual ounce of production capacity, which is competitive for new gold projects. The 3.4-year payback period (at $2,500/oz) is favorable by industry standards.
The all-in sustaining costs (AISC) of $985/oz positions Gramalote in the lower half of the global cost curve, providing significant operating margin at current gold prices. The project benefits from high metallurgical recoveries of 95.7%, which is exceptional for a gold operation and enhances economic viability.
The initial five years show particularly strong economics with higher grade (1.23 g/t gold vs. life-of-mine 0.96 g/t) and lower AISC ($851/oz). This front-loading of value reduces financial risk and improves financing prospects. The project has been de-risked through 270,000 meters of drilling and extensive technical studies.
Key challenges include permit modifications required for the medium-scale project design, with an estimated 12-18 month timeline. The technical transition from oxide to sulfide processing is well addressed in the processing design with conventional crushing, grinding, flotation, and carbon-in-pulp recovery.
The $444 million post-construction capital requirement is substantial but staged over the project life. Overall, Gramalote represents a technically sound, economically attractive development opportunity that could meaningfully increase B2Gold's production profile and cash flow generation.
After-Tax NPV (
After-Tax NPV (
VANCOUVER, British Columbia, July 14, 2025 (GLOBE NEWSWIRE) -- B2Gold Corp. (TSX: BTO, NYSE AMERICAN: BTG, NSX: B2G) (“B2Gold” or the “Company”) is pleased to announce the positive results of a Feasibility Study (“FS”) on its
Feasibility Study Highlights
- Meaningful gold production profile with favorable metallurgical characteristics
- Open pit gold mine with an initial life of mine of 11 years, with mill processing over 13 years (“Life of Project”)
- Average grade processed of 1.23 grams per tonne (“g/t”) gold over the first five years, benefitting from the processing of the higher-grade core at the Gramalote Project; Life of Project average grade processed of 0.96 g/t gold
- Life of Project gold production of approximately 2.3 million ounces with an average gold recovery of
95.7% from conventional milling, flotation and cyanide leach of the flotation concentrate - Average annual gold production of approximately 227,000 ounces per year for the first five years of production
- Average annual gold production of approximately 177,000 ounces per year over the Life of Project
- All-in sustaining costs (“AISC”) of
$985 per gold ounce over the Life of Project - Annual processing rate of 6.0 million tonnes per annum (“Mtpa”)
- Strong project economics
- Life of Project after-tax free cash flow of
$1.67 billion at a$2,500 per ounce gold price (“$2,500 Gold Price”)- Life of Project after-tax free cash flow of
$2.81 billion at the spot gold price of approximately$3,300 per ounce (“Spot Gold Price”)
- Life of Project after-tax free cash flow of
- Assuming a discount rate of
5.0% and$2,500 Gold Price, net present value (“NPV”) after-tax of$941 million , generating an after-tax internal rate of return (“IRR”) of22.4% , with a project payback on pre-production capital of 3.4 years- Assuming a discount rate of
5.0% and Spot Gold Price, NPV after-tax of$1,716 million , generating an IRR of33.5% , with a project payback on pre-production capital of 2.4 years
- Assuming a discount rate of
- Estimated construction capital cost of
$740 million (includes approximately$73 million for mining equipment and$81 million for contingency)
- Life of Project after-tax free cash flow of
- Robust amount of drilling and engineering studies have been completed on Gramalote, which significantly de-risks future project development
- Over 270,000 meters of drilling completed, providing B2Gold with a robust mineral resource model
- Gramalote has a long history of studies and technical reports which supported the existing mining permit that is currently in place
- Specific mining, processing, infrastructure, environmental, and social studies have been completed. Extensive metallurgical test work has demonstrated high gold recoveries (approximately
96% ) at a coarse grind size for the selected processing flow sheet.
- Gramalote benefits from strong local community and government support
- Mine plan and environmental permits are currently in place for a larger-scale project; these permits will require modification to reflect the new medium-scale project contemplated in the FS
- B2Gold anticipates the permit modification time frame should be approximately 12 to 18 months
Feasibility Study Overview
The Gramalote Project is located in central Colombia, approximately 230 kilometers (“km”) northwest of Bogota and 100 km northeast of Medellin, in the Province of Antioquia, which has expressed a positive attitude towards the development of responsible mining projects in the region. Following B2Gold’s consolidation of the Gramalote Project in October 2023, B2Gold completed a detailed review including the higher-grade core of the mineral resource, facility size and location, power supply, mining and processing options, tailings design, resettlement, potential construction sequencing and camp design to identify potential cost savings to develop a medium-scale project. The results of the review allowed the Company to determine the optimal parameters and assumptions for this FS.
The FS, with an effective date of April 1, 2025, was prepared by B2Gold and evaluates recovery of gold from an open pit mining operation that will move up to approximately 97,000 tonnes per day (“tpd”) (35.5 Mtpa), with an approximately 16,500 tpd (6.0 Mtpa) processing plant that includes crushing, grinding, flotation, with fine grinding of the flotation concentrate and agitated leaching of the flotation concentrate followed by a carbon-in-pulp recovery process to process doré bullion. The Mineral Reserve estimate for the Gramalote Project that forms the basis for the FS includes Probable Mineral Reserves of 76.7 million tonnes grading 0.96 g/t gold for a total of 2,360,000 ounces of contained gold.
The FS assumptions include revenues using a gold price of
Table 1 - Key Results of the FS
First Five Years | Life of Project | |
Production Profile | ||
Years | 5 | 13 |
Ore tonnes processed (Mt) | 30.0 | 76.7 |
Average gold grade processed (g/t) | 1.23 | 0.96 |
Gold recovery (%) | 96.1 | 95.7 |
Gold ounces produced (oz) | 1,137,000 | 2,260,000 |
Average annual gold production (oz) | 227,000 | 177,000 |
Operating Costs | ||
Cash operating costs1 ($/oz gold) | 512 | 700 |
All-In Sustaining Costs2 ($/oz gold) | 851 | 985 |
Mining cost ($/t mined) | 2.61 | 2.71 |
Processing cost ($/t processed) | 8.13 | 8.16 |
General & administration ($/t processed) | 4.11 | 3.64 |
Capital Costs | ||
Construction capital3 ($M) | 740 | 740 |
Post Construction capital4 ($M) | 305 | 444 |
Notes:
1. Cash operating costs consist of mining costs, processing costs and site G&A.
2. AISC consist of cash operating costs, royalties, corporate G&A, selling costs and silver credits and excluding pre-production capital costs.
3. Construction capital calculated as of the start of construction expenditure.
4. Post Construction capital occurs after the start of commercial production, and includes capital defined both as sustaining and non-sustaining.
Table 2 – Construction Capital Estimate
($M) | |
Mining equipment | 73 |
Pre-stripping | 21 |
Other Mining | 12 |
Processing | 313 |
Site general & Infrastructure | 186 |
Resettlement | 29 |
Other | 26 |
Subtotal | 660 |
Contingency | 81 |
Total | 740 |
Table 3 – Project Economics Summary
After-Tax Project Economics | ||
Spot Gold Price | ||
NPV | 941 | 1,716 |
IRR | ||
Payback (years) | 3.4 | 2.4 |
Free cash flow ($M) | 1,669 | 2,805 |
Note: NPV
The FS is subject to a number of assumptions and risks, including among others that a Modified Work Plan and Modified Environmental Impact Study will be approved, all required permits, permit amendments and other rights will be obtained in a timely manner, the Gramalote Project will have the support of the local government and community, the regulatory environment will remain consistent, and no material increase will have occurred to the estimated costs.
Economic Sensitivities
Gramalote is a medium-scale, low operating cost project and sensitive to the gold price, as demonstrated in the following table:
Table 4 – Economic Sensitivity to Long-Term Gold Price
Gold Price ($/oz) | After-Tax NPV ($M) | After-Tax IRR (%) | |
457 | 14.3 | ||
941 | 22.4 | ||
1,425 | 29.5 | ||
Spot Gold Price | 1,716 | 33.5 |
Note: NPV
Gramalote Project Mineral Reserve Estimate
The Mineral Reserve estimate for the Gramalote Project has an effective date of April 1, 2025, and is reported using a gold price of
Category | Tonnes (kt) | Gold Grade (g/t) | Contained Gold Ounces |
Probable Mineral Reserves | 76,700 | 0.96 | 2,360,000 |
Notes:
1. Mineral Reserves have been classified using the CIM Standards.
2. All tonnage, grade and contained metal content estimates have been rounded; rounding may result in apparent summation differences between tonnes, grade, and contained metal content.
3. The Mineral Reserves have been prepared by Peter Montano, P.E., our Vice President, Projects, and a Qualified Person under NI 43-101.
4. Mineral Reserves are reported on a
5. Mineral Reserves are based on a conventional open pit mining method, gold price of
6. Mineral Reserves are reported above a cut-off grade of 0.40 g/t of sulphide ore. Oxide material is not processed.
Gramalote Project Next Steps
The Gramalote Project will continue to advance resettlement programs, establish coexistence programs for small miners, work on health, safety and environmental projects and continue to work with the government and local communities on social programs.
Due to the desired modifications to the processing plant and infrastructure locations, a Modified Work Plan and Modified Environment Impact Study are required. B2Gold has commenced work on the modifications and expects them to be completed and submitted in late 2025 and early 2026, respectively. If B2Gold makes the decision to develop the Gramalote Project as an open pit gold mine, B2Gold would utilize its proven internal mine construction team to build the mine and mill facilities.
About B2Gold
B2Gold is a responsible international senior gold producer headquartered in Vancouver, Canada. Founded in 2007, today, B2Gold has operating gold mines in Canada, Mali, Namibia and the Philippines, and numerous development and exploration projects in various countries. B2Gold forecasts gold production of between 970,000 and 1,075,000 ounces in 2025.
Qualified Person
Peter Montano, P.E., Vice President, Projects, a qualified person under NI 43-101, has approved the scientific and technical information related to operations matters contained in this news release.
ON BEHALF OF B2GOLD CORP.
“Clive T. Johnson”
President and Chief Executive Officer
The Toronto Stock Exchange and NYSE American LLC neither approve nor disapprove the information contained in this news release.
Production guidance presented in this news release reflect total production at the mines B2Gold operates on a
This news release includes certain "forward-looking information" and "forward-looking statements" ("collectively forward-looking statements") within the meaning of applicable Canadian and United States securities legislation, including: projections; outlook; guidance; forecasts; estimates; and other statements regarding future or estimated financial and operational performance, gold production and sales, revenues and cash flows, and capital costs (sustaining and non-sustaining) and operating costs, including projected cash operating costs and AISC, and budgets on a consolidated and mine by mine basis; future or estimated mine life, metal price assumptions, ore grades or sources, gold recovery rates, stripping ratios, throughput, ore processing; statements regarding anticipated exploration, drilling, development, construction, permitting and other activities or achievements of B2Gold; and including, without limitation: consolidated gold production of between 970,000 and 1,075,000 ounces in 2025; the results and estimates in the Gramalote FS, including the project life, average annual gold production, total gold production, processing rate, capital cost, net present value, after-tax net cash flow and payback; the timing of the permit modification on the Gramalote Project; the completion and submittal of the Modified Environmental Impact Study and Modified Work Plan; and the potential to develop the Gramalote Project as an open pit gold mine. All statements in this news release that address events or developments that we expect to occur in the future are forward-looking statements. Forward-looking statements are statements that are not historical facts and are generally, although not always, identified by words such as "expect", "plan", "anticipate", "project", "target", "potential", "schedule", "forecast", "budget", "estimate", "intend" or "believe" and similar expressions or their negative connotations, or that events or conditions "will", "would", "may", "could", "should" or "might" occur. All such forward-looking statements are based on the opinions and estimates of management as of the date such statements are made.
Forward-looking statements necessarily involve assumptions, risks and uncertainties, certain of which are beyond B2Gold's control, including risks associated with or related to: the volatility of metal prices and B2Gold's common shares; changes in tax laws; the dangers inherent in exploration, development and mining activities; the uncertainty of reserve and resource estimates; not achieving production, cost or other estimates; actual production, development plans and costs differing materially from the estimates in B2Gold's feasibility and other studies; the ability to obtain and maintain any necessary permits, consents or authorizations required for mining activities; environmental regulations or hazards and compliance with complex regulations associated with mining activities; climate change and climate change regulations; the ability to replace mineral reserves and identify acquisition opportunities; the unknown liabilities of companies acquired by B2Gold; the ability to successfully integrate new acquisitions; fluctuations in exchange rates; the availability of financing; financing and debt activities, including potential restrictions imposed on B2Gold's operations as a result thereof and the ability to generate sufficient cash flows; operations in foreign and developing countries and the compliance with foreign laws, including those associated with operations in Mali, Namibia, the Philippines, Canada, and Colombia and including risks related to changes in foreign laws and changing policies related to mining and local ownership requirements or resource nationalization generally; remote operations and the availability of adequate infrastructure; fluctuations in price and availability of energy and other inputs necessary for mining operations; shortages or cost increases in necessary equipment, supplies and labour; regulatory, political and country risks, including local instability or acts of terrorism and the effects thereof; the reliance upon contractors, third parties and joint venture partners; the lack of sole decision-making authority related to Filminera Resources Corporation, which owns the Masbate Project; challenges to title or surface rights; the dependence on key personnel and the ability to attract and retain skilled personnel; the risk of an uninsurable or uninsured loss; adverse climate and weather conditions; litigation risk; competition with other mining companies; community support for B2Gold's operations, including risks related to strikes and the halting of such operations from time to time; conflicts with small scale miners; failures of information systems or information security threats; the ability to maintain adequate internal controls over financial reporting as required by law, including Section 404 of the Sarbanes-Oxley Act; compliance with anti-corruption laws, and sanctions or other similar measures; social media and B2Gold's reputation; as well as other factors identified and as described in more detail under the heading "Risk Factors" in B2Gold's most recent Annual Information Form, B2Gold's current Form 40-F Annual Report and B2Gold's other filings with Canadian securities regulators and the U.S. Securities and Exchange Commission (the "SEC"), which may be viewed at www.sedar.com and www.sec.gov, respectively (the "Websites"). The list is not exhaustive of the factors that may affect B2Gold's forward-looking statements.
B2Gold's forward-looking statements are based on the applicable assumptions and factors management considers reasonable as of the date hereof, based on the information available to management at such time. These assumptions and factors include, but are not limited to, assumptions and factors related to B2Gold's ability to carry on current and future operations, including: development and exploration activities; the timing, extent, duration and economic viability of such operations, including any mineral resources or reserves identified thereby; the accuracy and reliability of estimates, projections, forecasts, studies and assessments; B2Gold's ability to meet or achieve estimates, projections and forecasts; the availability and cost of inputs; the price and market for outputs, including gold; foreign exchange rates; taxation levels; the timely receipt of necessary approvals or permits; the ability to meet current and future obligations; the ability to obtain timely financing on reasonable terms when required; the current and future social, economic and political conditions; and other assumptions and factors generally associated with the mining industry.
B2Gold's forward-looking statements are based on the opinions and estimates of management and reflect their current expectations regarding future events and operating performance and speak only as of the date hereof. B2Gold does not assume any obligation to update forward-looking statements if circumstances or management's beliefs, expectations or opinions should change other than as required by applicable law. There can be no assurance that forward-looking statements will prove to be accurate, and actual results, performance or achievements could differ materially from those expressed in, or implied by, these forward-looking statements. Accordingly, no assurance can be given that any events anticipated by the forward-looking statements will transpire or occur, or if any of them do, what benefits or liabilities B2Gold will derive therefrom. For the reasons set forth above, undue reliance should not be placed on forward-looking statements.
Non-IFRS Measures
This news release includes certain terms or performance measures commonly used in the mining industry that are not defined under International Financial Reporting Standards ("IFRS"), including "cash operating costs" and "all-in sustaining costs" (or "AISC"). Non-IFRS measures do not have any standardized meaning prescribed under IFRS, and therefore they may not be comparable to similar measures employed by other companies. The data presented is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS and should be read in conjunction with B2Gold's consolidated financial statements. Readers should refer to B2Gold's Management Discussion and Analysis, available on the Websites, under the heading "Non-IFRS Measures" for a more detailed discussion of how B2Gold calculates certain of such measures and a reconciliation of certain measures to IFRS terms.
Cautionary Statement Regarding Mineral Reserve and Resource Estimates
The disclosure in this news release was prepared in accordance with Canadian National Instrument 43-101, which differs significantly from the requirements of the United States Securities and Exchange Commission ("SEC"), and resource and reserve information contained or referenced in this news release may not be comparable to similar information disclosed by public companies subject to the technical disclosure requirements of the SEC. Historical results or feasibility models presented herein are not guarantees or expectations of future performance.
Source: B2Gold Corp.

For more information on B2Gold please visit the Company website at www.b2gold.com or contact: Michael McDonald VP, IR, Corporate Development & Treasury +1 604-681-8371 investor@b2gold.com Cherry DeGeer Director, Corporate Communications +1 604-681-8371 investor@b2gold.com