Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.
Rhea-AI Summary
BQE Water (BTQNF) reported record quarterly GAAP revenue of $12.3 million for the third quarter of 2026. Revenue rose 32% from Q3 2025, and net income rose 33% to $3.7 million. Basic earnings per share rose to $2.84 from $2.15, and adjusted EBITDA rose 38% to $4.6 million. GAAP revenue and net income remained below the prior year for the first nine months. Excluding a $4.6 million equipment sale in 2025, nine-month GAAP revenue rose 13%.
Working capital rose to $25.1 million from $21.4 million at year-end 2025, while cash and cash equivalents fell $1.3 million to $17.6 million. BQE Water restarted seasonal treatment at Kemess Mine, resumed operations at Minto Mine under a new arrangement with Selkirk Copper, and began three years of operations support for an Alaska facility. Some operations will pause over the winter.
How this balance works
Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.
It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.
Rhea-AI Sentiment measures something else, the tone of the wording.
Hollow bars mark forward-looking points. How the balance works
Positive
- Moderate pointQ3 GAAP revenue rose 32% year over year to a quarterly record of $12.3 million.
- Moderate pointQ3 net income rose 33% year over year to $3.7 million.
- Moderate pointQ3 basic earnings per share rose 32% year over year to $2.84 from $2.15.
- Moderate pointQ3 adjusted EBITDA rose 38% year over year to $4.6 million.
- Moderate pointQ3 proportional revenue, which includes BQE Water's share of Chinese joint venture revenue, rose 36% year over year to $14.5 million.
- Moderate pointQ3 gross margin in dollars rose 25% year over year to $5.9 million from $4.7 million.
- Moderate pointOperational services revenue rose year over year to $4.963 million in Q3 and $10.007 million over nine months.
16 minor points
- Minor pointNew operations and support services contributed $4.6 million in additional revenue over the first nine months versus 2025.
- Minor pointWorking capital rose 17% to $25.1 million at September 30, 2026, from $21.4 million at year-end 2025.
- Minor pointBQE Water's share of Chinese joint venture revenue rose to $2.233 million in Q3 and 38% to $4.783 million over nine months, year over year.
- Minor pointShort-term operations revenue rose to $4.960 million from $3.917 million in Q3 but fell to $10.222 million from $11.031 million over nine months.
- Minor pointAlaska operations support began under a three-year assignment for cyanide destruction at a metallurgical facility.
- Minor pointKemess Mine treatment restarted and ran on a seasonal basis in 2026.
- Minor pointMinto Mine operations resumed after a one-year hiatus under a new arrangement with property owner Selkirk Copper.
- Minor pointResearch and development tax credits of $745,000 are non-refundable but can offset future corporate income taxes payable.
- Minor point. Forward-looking: it has not happened yet and may not happen.Future qualifying research claims for 2025 onward are expected to generate refundable tax credits.
- Minor point. Forward-looking: it has not happened yet and may not happen.Technical advisory and engineering services are expected to grow gradually in Q4 2026 and the first half of 2027.
- Minor point. Forward-looking: it has not happened yet and may not happen.Feasibility studies and an engineering design project are expected to start in the coming months and run five to ten months.
- Minor point. Forward-looking: it has not happened yet and may not happen.Winter operating opportunities are expected to let BQE Water redeploy seasonal crews and continue generating operations revenue.
- Minor pointCapital asset investment totaled $724,000 in 2026, including equipment at Britannia and laboratory upgrades.
- Minor pointJCC-BQE copper recovery rose 45% year over year to 572,000 pounds in Q3 and reached 1,207,000 pounds over nine months, up from 1,012,000.
- Minor pointJCC-BQE water treatment volume rose 59% year over year to 5.796 million cubic metres in Q3 and reached 13.134 million over nine months, up from 11.707 million.
- Minor pointAll three JCC-BQE plants met BQE Water's mechanical availability and process performance targets in Q3.
Negative
- Moderate pointNine-month net income fell 33% year over year to $4.270 million from $6.415 million.
- Moderate pointNine-month GAAP revenue fell to $26.315 million from $28.037 million, but rose 13% excluding a $4.6 million equipment sale in 2025. 7.6% of market cap
- Moderate pointNine-month adjusted EBITDA fell to $5.952 million from $7.679 million a year earlier.
- Moderate pointAdvisory and design revenue fell year over year to $2.347 million from $3.068 million in Q3 and to $6.086 million from $11.567 million over nine months.
- Minor pointNine-month proportional revenue fell to $31.098 million from $31.511 million a year earlier.
9 minor points
- Minor pointNine-month gross margin in dollars fell to approximately $11.3 million from $11.6 million, while the margin rate rose to 43.0% from 41.4%.
- Minor pointCash and cash equivalents fell $1.3 million from year-end 2025 to $17.6 million, largely because accounts receivable increased.
- Minor point. Forward-looking: it has not happened yet and may not happen.Project execution will increasingly depend on expanding the technical team and successfully bringing new staff on board.
- Minor point. Forward-looking: it has not happened yet and may not happen.Internal systems investment will add near-term expenses for accounting, safety management and resource management.
- Minor point. Forward-looking: it has not happened yet and may not happen.Seasonal operations at some sites will pause over the winter.
- Minor pointQ3 general and administrative expenses included a one-time professional fee for preparing and submitting 2024 research tax claims.
- Minor pointShandong Gold's treatment plant was shut down in Q3, leaving BQE Water supervising two of its three plants in the region.
- Minor pointJCC-BQE zinc recovery fell to 392,000 pounds from 994,000 over nine months; the venture made no Q3 zinc shipments.
- Minor pointMWT-BQE water treatment volume fell year over year to 42,000 from 57,000 cubic metres in Q3 and to 156,000 from 163,000 over nine months.
AI-generated analysis. How Rhea-AI works. Not financial advice.
Vancouver, British Columbia--(Newsfile Corp. - November 26, 2026) - BQE Water Inc. (TSXV: BQE), a leader in the treatment and management of mine impacted waters, is pleased to release its interim consolidated financial results for the three and nine months ended September 30, 2026.
"With GAAP revenue up
FINANCIAL HIGHLIGHTS
Revenues under GAAP of
$12.3 million in Q3 2026, a record high for a 3-month period, compared to$9.3 million in Q3 2025, a32% increase.Proportional Revenues of
$14.5 million in Q3 2026 compared to$10.7 million in Q3 2025, a36% increase.Gross margin of
$5.9 million in Q3 2026 compared to$4.7 million in Q3 2025, a25% increase.Net income of
$3.7 million in Q3 2026 compared to net income of$2.8 million in Q3 2025, a33% increase.Earnings per share (basic) of
$2.84 in Q3 2026 compared to$2.15 in Q3 2025, a32% increase.Adjusted EBITDA of
$4.6 million in Q3 2026 compared to$3.3 million in Q3 2025, a38% increase.Working capital of
$25.1 million at September 30, 2026, compared to$21.4 million at December 31, 2025, a17% increase.
Selected financial results for the three and nine months ended September 30, 2026 are as follows:
| (in '000s) | 3 months ended Sept. 30 | 9 months ended Sept. 30 | ||||||||||
| Revenue | 2026 | 2025 | 2026 | 2025 | ||||||||
| Operational services | 4,963 | 2,330 | 10,007 | 5,439 | ||||||||
| Technical services - short-term operations | 4,960 | 3,917 | 10,222 | 11,031 | ||||||||
| Technical services - advisory and design | 2,347 | 3,068 | 6,086 | 11,567 | ||||||||
| Total revenues under GAAP | 12,270 | 9,315 | 26,315 | 28,037 | ||||||||
| Share of revenue from joint ventures in China | 2,233 | 1,340 | 4,783 | 3,474 | ||||||||
| Proportional Revenues (Non-GAAP measures) | 14,503 | 10,655 | 31,098 | 31,511 | ||||||||
| Net income | 3,694 | 2,783 | 4,270 | 6,415 | ||||||||
| Adjusted EBITDA (Non-GAAP measures) | 4,587 | 3,324 | 5,952 | 7,679 | ||||||||
COMMENTARY AND OUTLOOK
We are pleased to have delivered strong third quarter results, with GAAP revenue up
Matching last year's Proportional Revenue on a year-to-date basis masks the strong underlying growth in our business. Recall that 2025 included a one-time revenue contract for the equipment sale, construction, design and commissioning of the Valley Tailings Facility, which was all recorded under technical services (advisory and design) revenue. Excluding the equipment sale component of
The primary driver of our growth in Q3 2026 and year-to-date has been recurring operations and short-term operations, which accounted for
Excluding the above-noted equipment sale, our technical advisory and engineering services revenue has also grown but not to the same degree as our operations. We expect these services to increase gradually in Q4 2026 and into the first half of 2027 as our engineers currently undergoing site-based training to join our technical teams. All engineers hired in 2026 have been assigned to our operating sites for hands-on training before transitioning into technical teams in process design, field commissioning, or technology development. This approach is integral to the Company's vision of ensuring our technical staff develops practical field experience as a foundation for their professional growth.
Our year-to-date gross margin in dollar terms remained largely consistent at approximately
Our balance sheet remains strong, with working capital of
We continue to have long pipeline of projects and operations to build on the quarters ahead. While certain operations are seasonal and will pause over the winter, we have good visibility into new near-term operating opportunities that are expected to enable us to redeploy operation teams and continue generating operations revenue through the winter months. We also expect to commence several feasibility studies and a significant engineering design-for-construction project in the coming months, with anticipated project durations ranging from five to ten months.
Our growing pipeline provides strong visibility over the next 18 months. Our ability to execute on these opportunities will increasingly depend on expanding and successfully onboarding our technical team members. We will also continue to invest in and implement internal systems for accounting, safety management, and resource management to support a growing organization, resulting in additional near-term expenses. With mining industry activity remaining strong, we see a healthy environment for continued growth. We nevertheless remain mindful of geopolitical and market uncertainties and will maintain a disciplined approach to hiring, investment, and resource allocation to support profitable growth.
OPERATIONAL SERVICES HIGHLIGHTS
Our operational services consist of the operation or technical supervision of water treatment plants, which generate recurring revenues from three main sources: sales of recovered metals, water treatment fees and operations support fees. The Company's operations by source of revenue are as follows:
| Operations | Location | Revenue Source |
| JCC-BQE Joint Venture | Jiangxi province, China | Sales of recovered metals |
| MWT-BQE Joint Venture | Shandong province, China | Water treatment fees |
| Raglan Mine for Glencore | Northern Québec, Canada | Water treatment fees |
| Nunavik Nickel Project for Canadian Royalties | Northern Québec, Canada | Water treatment fees |
| Britannia Mine water treatment plant | British Columbia, Canada | Water treatment fees |
| Water treatment plant for lead smelter | Quebec, Canada | Operations support fees |
| Metallurgical Facilities for MWT | Shandong province, China | Operations support fees |
| Power utility ash pond for WesTech | Eastern USA | Water treatment fees |
| Wharf Mine water treatment plant | South Dakota, USA | Operations support fees |
| Base metal project for a metal producer | Southwestern USA | Operations support fees |
| Cyanide destruction for a metallurgical facility | Alaska, USA | Operations support fees |
JCC-BQE Joint Venture Operations
Our 50/50 joint venture with partner Jiangxi Copper Company ("JCC") operates three water treatment plants at Dexing Mine and at Yinshan Mine in Jiangxi province of China. The volume of water treated, and metals recovered by the plants fluctuate seasonally depending on precipitation levels in the region. The operating results for Q3 2026 are as follows:
| (in '000s) | 3 months ended Sept. 30 | 9 months ended Sept. 30 | ||||||||||
| 2026 | 2025 | 2026 | 2025 | |||||||||
| Water treated (cubic metres) | 5,796 | 3,641 | 13,134 | 11,707 | ||||||||
| Copper recovered (pounds) | 572 | 394 | 1,207 | 1,012 | ||||||||
| Zinc recovered (pounds) | - | 305 | 392 | 994 | ||||||||
In Q3 2026, all three plants met mechanical availability and process performance set by the Company. When compared to Q3 2025, the volume of water treated increased by
MWT-BQE Joint Venture Operations
Our
| (in '000s) | 3 months ended Sept. 30 | 9 months ended Sept. 30 | ||||||||||
| 2026 | 2025 | 2026 | 2025 | |||||||||
| Water treated (cubic metres) | 42 | 57 | 156 | 163 | ||||||||
BQE Water Operation
The number of operating days contributing to water treatment or support fees by operation sites for the three and nine months ended September 30, 2026, is as follows:
| (in days) | 3 months ended Sept. 30 | 9 months ended Sept. 30 | ||||||||||
| 2026 | 2025 | 2026 | 2025 | |||||||||
| Raglan Mine water treatment plants | 90 | 91 | 145 | 149 | ||||||||
| Nunavik Nickel Project water treatment plants | 92 | - | 103 | - | ||||||||
| Britannia Mine water treatment plant | 65 | - | 235 | - | ||||||||
| Lead smelter treatment plant in Eastern Canada | 92 | - | 269 | - | ||||||||
| Zhongkuang SART plant | 92 | 92 | 216 | 267 | ||||||||
| Zhaojin SART plant | 92 | 91 | 273 | 267 | ||||||||
| Shandong Gold SART plant | - | - | 93 | - | ||||||||
| Water treatment plant in Eastern USA | 71 | 73 | 200 | 201 | ||||||||
| Wharf Mine water treatment plant | 78 | - | 161 | - | ||||||||
| Water treatment plants in Southwest USA | 92 | 92 | 273 | 273 | ||||||||
| Cyanide destruction at a metallurgical facility | 44 | - | 44 | - | ||||||||
The volume of water treated by geographic location for the three and nine months ended September 30, 2026, is as follows:
| (in '000s cubic metres) | 3 months ended Sept. 30 | 9 months ended Sept. 30 | ||||||||||
| 2026 | 2025 | 2026 | 2025 | |||||||||
| Raglan Mine water treatment plants | 1,345 | 1,588 | 1,573 | 1,861 | ||||||||
| Nunavik Nickel Project water treatment plants | 2,101 | - | 2,234 | - | ||||||||
| Britannia Mine water treatment plant | 380 | - | 2,654 | - | ||||||||
| Lead smelter treatment plant in Eastern Canada | 53 | - | 170 | - | ||||||||
| SART plants in China | 117 | 153 | 411 | 434 | ||||||||
| Water treatment plants in USA | 862 | 666 | 1,602 | 1,993 | ||||||||
The Company, with our Inuit partner Nuvumiut Development, operates four water treatment plants at Raglan Mine for Glencore Canada Corporation ("Glencore"). The plants at Raglan Mine are usually shut down in the first quarter as water stored in the outdoor reservoirs is frozen. During Q3 2026, we continued treating water across all four plants for our 23rd operating season at the mine.
In 2021, we began providing operation support to two SART (sulphidization-acidification-recycling-thickening) plants at metallurgical facilities in Shandong province, China. In 2025, we commissioned the third SART plant in the same region. All three SART plants have been under our technical supervision since the start of production. During Q3 2026, our team provided ongoing technical supervision at two of the three plants as the Shandong Gold plant was shut down.
In 2022, we began operations of a treatment plant utilizing our Selen-IX™ process to remove selenium from ash pond water for WesTech Engineering ("WesTech"). In Q3 2026, our team continued on site, providing water treatment services with the Selen-IX™ circuit to manage the presence of selenium in the feed.
In 2022, we began operations of a treatment plant utilizing a combination of nanofiltration and our proprietary selenium electroreduction process for the simultaneous removal of selenium and sulphate from mine water for a base metal project in the American Southwest. In 2023, our team began operations for a second newly constructed selenium removal water treatment plant at the same site. In Q3 2026, our team continued to provide onsite operations support and technical supervision at both treatment plants.
In October 2025, we completed the commissioning of a Selen-IX™ treatment plant located at the Coeur Wharf Mine in South Dakota and began providing routine operation support. In Q3 2026, our team continued to provide onsite and offsite support to the selenium removal circuit to manage the presence of selenium in the feed.
In January 2026, we assumed operational responsibility for the provision of operations and maintenance services for the Britannia Mine water treatment plant for the BC government under a 20-year arrangement. This High-Density Sludge lime treatment plant neutralizes acidity and removes heavy metals, primarily copper and zinc, from the mine water collected in the legacy underground workings prior to its discharge into Howe Sound. In Q3 2026, our team continued to operate and treat water daily without interruption until August 2026 and carried out the annual shut-down maintenance in September 2026.
In February 2026, we initiated an annual operation support arrangement with an integrated lead smelter-recycling facility in Eastern Canada. Prior to this arrangement, we completed an upgrade to the existing treatment system, implemented a new sulphate removal stage to a discharge limit of less than 1,500 mg/L and provided short-term operations support for the newly upgraded facility. In Q3 2026, our team continued to provide ongoing site support and technical supervision.
In May 2026, we initiated a 3-year water treatment operations contract, with our Inuit partner Nuvumiut Development, to operate five treatment systems at the Nunavik Nickel Project owned by Canadian Royalties Inc. Treatment operations typically run from May to October depending on the volume of water requiring treatment. In Q3 2026, the operations team continued to operate across all five treatment systems.
In August 2026, we initiated a 3-year operations support contract to optimize a cyanide destruction circuit for a metallurgical facility in Alaska, USA. The support is intended to achieve consistent cyanide destruction performance, reducing reagent consumption, minimizing dilution water requirements, improving operational consistency between shifts, and ensuring effective implementation of the operating strategies and control philosophy. In Q3 2026, we mobilized our support team to support the facility.
SHORT-TERM OPERATIONS SERVICES HIGHLIGHTS
In addition to long-term operations, BQE Water provides operations and technical support services on a temporary basis at several sites. Short-term operations are non-recurring in nature with contracts typically lasting less than a year. Short-term operations during Q3 2026 are summarized below.
Continued providing water treatment operations services for the temporary emergency treatment system at the Eagle Gold Mine in the Yukon.
Continued operations at the ERDC Valley Tailings facility in the Yukon, which was constructed and commissioned last year.
Continued providing operations services at Minto Mine in the Yukon.
Initiated operations at the Kemess Mine water treatment plant in BC, which was the first selenium removal plant commissioned in 2020.
Demobilized our team from site services at Bell Mine in BC.
TECHNICAL SERVICES HIGHLIGHTS
BQE Water's technical expertise and IP are applicable globally across broad areas of water management. Highlights of some of our technical services and technical innovation projects during Q3 2026 are summarized below.
Trusted Advisory Services (Water Management and Water Studies)
Continued providing water management and treatment design advisory services to an operating mine in Ontario.
Completed lab testing and issued a report for ammonia management to a mining operation in Saskatchewan.
Continued to provide water management and treatment design advisory services to the KSM project in BC.
Continued providing water management and treatment design advisory services to a new mine undergoing permitting in the Yukon.
Initiated laboratory testing and advisory services to a new project in prefeasibility stage in Argentina.
Continued with detailed engineering for a water treatment system using ion exchange to expand rhenium production at an existing facility in Eastern Canada.
Continued to provide engineering design services for a water treatment system integrated into a rare earth extraction project in Brazil.
Performed a study to identify options for implementing selenium removal at an operating site in Quebec.
Completed engineering advisory services and restarted the selenium removal plant for short-term operations for the Kemess project in BC.
Completed a review of water treatment proposed for a new mine undergoing permitting in Yukon on behalf of the Yukon Government.
Initiated a pre-feasibility study engineering design for a plant to selectively recovery cobalt and scandium from copper heap leach solution in Chile.
Performed a review and assessment of opportunities to improve mine water treatment systems operations at legacy mines in Greece.
Performed a field assessment of selenium mitigation at a mine in Europe including a plan for implementing active treatment in the next 18 months.
Cyanide Management (Destruction and Recycle)
Completed engineering advisory services for cyanide destruction for a project in Australia.
Completed SART design for a new heap leach project in Mexico.
Continued providing engineering advisory services for estimating cyanide emissions, designing an emissions control system for cyanide, and revising engineering design of cyanide destruction for a project in the US.
Continued to provide plant engineering design services requiring an end-of-pipe cyanide level below 8 ppb to a project in the US.
Initiated field engineering advisory services for improving cyanide destruction performance at a mine in Alaska.
Continued detailed engineering for SART integration into the New Britannia mill in Manitoba, Canada.
Aquatic Toxicology Services
Continued assessment of chronic effects on aquatic environment caused by mine effluent at a mine in Western Canada.
Continued investigation into the effects of ammonia on acute toxicity under site-specific conditions at a mine in Eastern Canada.
Continued routine effluent toxicity quality monitoring for Eagle Mine water treatment operations and investigated the root cause of algae bloom.
Initiated laboratory tests required to establish a site-specific performance objective limit for sulphate and total dissolved solids at a mine in BC.
SELECTED FINANCIAL INFORMATION
For a complete set of Financial Statements and MD&A, please go to www.bqewater.com.
| (in $'000 except for per share amounts) | 3 months ended Sept. 30 | 9 months ended Sept. 30 | ||||||||||
| 2026 | 2025 | 2026 | 2025 | |||||||||
| $ | $ | $ | $ | |||||||||
| Revenues | 12,270 | 9,315 | 26,315 | 28,037 | ||||||||
| Operating expenses (excluding depreciation) | (6,402 | ) | (4,610 | ) | (15,010 | ) | (16,425 | ) | ||||
| Gross margin | 5,868 | 4,705 | 11,305 | 11,612 | ||||||||
| Share of income from joint ventures | 834 | 275 | 1,717 | 762 | ||||||||
| General and administration | (1,151 | ) | (868 | ) | (3,522 | ) | (2,664 | ) | ||||
| Sales and development | (1,330 | ) | (957 | ) | (4,246 | ) | (2,437 | ) | ||||
| Share-based payments | (267 | ) | (199 | ) | (896 | ) | (473 | ) | ||||
| Depreciation and amortization | (163 | ) | (126 | ) | (479 | ) | (387 | ) | ||||
| Income from operations and joint ventures | 3,791 | 2,830 | 3,879 | 6,413 | ||||||||
| Other income (expenses) | (14 | ) | 126 | 479 | 179 | |||||||
| Income tax expenses | (83 | ) | (173 | ) | (88 | ) | (177 | ) | ||||
| Net income for the period | 3,694 | 2,783 | 4,270 | 6,415 | ||||||||
| Net earnings per share (basic) | 2.84 | 2.15 | 3.28 | 4.96 | ||||||||
| Net earnings per share (diluted) | 2.81 | 2.12 | 3.25 | 4.90 | ||||||||
| Proportional Revenues (Non-GAAP measures) | 14,503 | 10,655 | 31,098 | 31,511 | ||||||||
| Adjusted EBITDA (Non-GAAP measures) | 4,587 | 3,324 | 5,952 | 7,679 | ||||||||
| Comprehensive income | 3,791 | 2,957 | 4,740 | 6,336 | ||||||||
| at Sept. 30, | at Dec. 31, | |||||||||||
| 2026 | 2025 | |||||||||||
| $ | $ | |||||||||||
| Cash and cash equivalents | 17,647 | 18,982 | ||||||||||
| Working capital | 25,074 | 21,410 | ||||||||||
| Total assets | 41,491 | 35,710 | ||||||||||
| Total non-current liabilities | 3,355 | 2,549 | ||||||||||
| Shareholders' equity | 33,618 | 28,795 | ||||||||||
NON-GAAP MEASURES
The Company uses non-GAAP financial measures to supplement our consolidated financial statements presented in accordance with generally accepted accounting principles (IFRS), or GAAP, to enhance overall understanding of the Company's current financial performance with investors and observers. Non-GAAP financial measures have limitations in that they do not reflect all amounts associated with our operational results as determined in accordance with GAAP. In addition, non-GAAP financial measures do not have any standardized meaning prescribed by GAAP and are unlikely to be comparable to similar non-GAAP financial measures presented by other companies. Non-GAAP financial measures should only be used to evaluate our operational results in conjunction with the corresponding GAAP measures.
Proportional Revenues
This non-GAAP financial measure of Proportional Revenue adds BQE Water's share of revenues from its China joint ventures to the Company's revenues reported under GAAP. Proportional Revenues for the three and nine-month periods ended September 30, 2026 and 2025, are as follows:
| (in $'000s) | 3 months ended Sept. 30 | 9 months ended Sept. 30 | ||||||||||
| 2026 | 2025 | 2026 | 2025 | |||||||||
| $ | $ | $ | $ | |||||||||
| Reported revenues under GAAP | 12,270 | 9,315 | 26,315 | 28,037 | ||||||||
| Share of revenues from joint ventures in China | 2,233 | 1,340 | 4,783 | 3,474 | ||||||||
| Proportional Revenue for the period | 14,503 | 10,655 | 31,098 | 31,511 | ||||||||
Adjusted EBITDA
Adjusted EBITDA ("earnings before interest, taxes, depreciation and amortization") is intended to provide additional information only and does not have any standardized meaning under IFRS and may not be comparable to similar measures presented by other companies. It should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. Consequently, the presentation of Adjusted EBITDA enables shareholders to better understand the underlying financial performance of our business through the eyes of management. Adjusted EBITDA includes adjustments of the Company's Proportional share of joint venture results. The following table reconciles this non-GAAP measure to the most directly comparable IFRS measure of net income:
| (in $'000s) | 3 months ended Sept. 30 | 9 months ended Sept. 30 | ||||||||||
| 2026 | 2025 | 2026 | 2025 | |||||||||
| $ | $ | $ | $ | |||||||||
| GAAP: Net income | 3,694 | 2,783 | 4,270 | 6,415 | ||||||||
| deduct: interest income | (17 | ) | (21 | ) | (76 | ) | (49 | ) | ||||
| add: income tax expenses | 327 | 267 | 425 | 276 | ||||||||
| add: depreciation and amortization | 290 | 214 | 850 | 715 | ||||||||
| EBITDA | 4,294 | 3,243 | 5,469 | 7,357 | ||||||||
| add: share-based payment expenses | 267 | 199 | 896 | 473 | ||||||||
| deduct: other income | - | (9 | ) | (204 | ) | (244 | ) | |||||
| add/deduct: net foreign exchange | 26 | (109 | ) | (209 | ) | 93 | ||||||
| Adjusted EBITDA | 4,587 | 3,324 | 5,952 | 7,679 | ||||||||
About BQE Water
BQE Water is a service provider specializing in water treatment and management for metals mining, smelting and refining. We are helping to transform the way the industry thinks about water in the context of natural resource projects by offering services and expertise which enables more sustainable water management practices and improved overall project performance at reduced risks. BQE Water invests in innovation and has developed unique intellectual property through the commercialization of several new technologies at mine sites around the world for organizations including Glencore, Jiangxi Copper, Freeport-McMoRan and the US EPA. BQE Water is headquartered in Vancouver, Canada and trades on the TSX Venture Exchange under the symbol BQE. Visit www.bqewater.com for more information.
****
The Toronto Venture Exchange has not reviewed and does not accept responsibility for the adequacy or the accuracy of this release.
CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION
Certain information contained herein may not be based on historical fact and therefore constitutes "forward-looking information" under applicable Canadian securities legislation. This includes without limitation statements containing the words "plan", "expect", "project", "estimate", "intend", "believe", "anticipate", "may", "will" and other similar words or expressions. Forward-looking statements are based on the opinions and estimates of management at the date the statements are made, and are subject to a variety of risks, uncertainties and other factors that may cause actual events or results to differ materially from those expressed or implied by such forward-looking statements. Factors that could cause or contribute to such differences include, but are not limited to, the Company's dependence on key personnel and contracts, uncertainty with respect to the profitability of the Company's technologies, competition, technology risk, the Company's ability to protect its intellectual property and proprietary information, fluctuations in commodity prices, currency risk, environmental regulation and the Company's ability to manage growth and other factors described in the Company's filings with the Canadian securities regulators at www.sedarplus.ca (including without limitation the factors described in the section entitled "Risks and Uncertainties" in the Company's MD&A for the year ended December 31, 2025). Given these risks and uncertainties, the reader is cautioned not to place undue reliance on forward-looking statements. All forward-looking information contained herein is based on management's current expectations and the Company undertakes no obligation to revise or update such forward-looking information to reflect subsequent events or circumstances, except as required by law.
For further information please contact:
BQE Water Inc.
Suite 200 - 30 East 6th Avenue, Vancouver, BC Canada V5T 1J4
604-685-1243 or 1-800-537-3073
David Kratochvil, President & CEO
dkratochvil@bqewater.com
Heman Wong, CFO