Calpine and CyrusOne Announce Phase 2 of Powered Land Agreement to Support Hyperscale Data Center at Thad Hill Energy Center in Texas
Rhea-AI Summary
Calpine (NYSE:CEG) and CyrusOne expanded their Powered Land Agreement to a total of 400 MW at the Thad Hill Energy Center in Bosque County, Texas, adding 210 MW to the original 190 MW.
The supply secures power, grid connection, and land for a hyperscale CyrusOne data center currently under construction and expected to be operational by Q4 2026. Calpine highlighted coordinated operations to curtail generation during supply scarcity to support grid reliability. The companies said the deal supports fast deployment for large-load customers and positions Calpine as a provider of scalable power solutions for hyperscale data centers.
Positive
- 400 MW total power secured for CyrusOne data center
- Added 210 MW to the prior 190 MW agreement
- Targeted commercial operation by Q4 2026
- Planned operational coordination to enhance grid reliability
- Secures power, grid connection, and land for hyperscale build
Negative
- None.
News Market Reaction – CEG
In the Nov 3 session, CEG gained 0.19%, reflecting a mild positive market reaction.
Data tracked by StockTitan Argus on the day of publication.
AI-generated analysis. How Rhea-AI works. Not financial advice.
"Our partnership with Calpine exemplifies the innovation required to meet the growth in data center demand," said Eric Schwartz, CEO of CyrusOne. "By expanding our agreement to 400MW with their Powered Land Capabilities, we've enabled a comprehensive solution for power, grid connectivity and site infrastructure, while maintaining our commitment to responsible energy use. The Thad Hill facility will set a benchmark for future hyperscale developments across
"One of the agreement attributes that we are most proud of is the ability for Calpine and CyrusOne to coordinate our operations to ensure grid reliability in times of supply scarcity," said Andrew Novotny, Calpine President and CEO. "By continuing to actively manage our generation output, these partnerships actually enhance grid reliability by curtailing in times of need. These agreements also deliver significant financial benefits for the community and the state of
Calpine's world-class fleet in
"Our best-in-class Powered Land Capabilities ("PLC") reflect Calpine's unmatched expertise in serving large loads, such as data centers. This innovative suite of products and services will continue to ensure grid reliability while preserving
Calpine's PLC suite of products and services is tailored to provide the needed speed-to-market and reliability that hyperscale customers demand while ensuring reliability and predictability for all Texans.
About Calpine:
Calpine Corporation is America's largest generator of electricity from natural gas and geothermal resources with operations in competitive power markets. Our fleet of 79 energy facilities in operation represents over 27,000 megawatts of generation capacity. Through wholesale power operations and our retail businesses, we serve customers in 22 states and
View original content to download multimedia:https://www.prnewswire.com/news-releases/calpine-and-cyrusone-announce-phase-2-of-powered-land-agreement-to-support-hyperscale-data-center-at-thad-hill-energy-center-in-texas-302602881.html
SOURCE Calpine Corporation