BUSCAR COMPANY ANNOUNCES MAJOR ADVANCEMENT IN THE PERMITTING PROCESS FOR THE TREASURE CANYON GOLD MINE PROJECT IN CALIFORNIA
Rhea-AI Summary
Buscar Company (OTC:CGLD) reported significant progress in permitting for its Treasure Canyon Mine in Plumas County, California. Key milestones include a burn permit from the Northern Sierra Air Quality Management District and a Lake and Streambed Alteration Agreement from the California Department of Fish and Wildlife.
Multiple plans under SMARA, water quality certifications, and waste discharge requirements remain under regulatory review. The project benefits from prior wildfire impacts that reduced live tree cover, potentially lowering environmental disturbance. Buscar plans to file mine safety permits after final Plan of Operations approval.
Positive
- Burn Permit No. 5186 approved, valid 7/15/2026–7/15/2027 for hazard-reduction burning
- Lake and Streambed Alteration Agreement (EPIMS No. PLU-13720-R2) for temporary bridge issued by CDFW
- SMARA Reclamation Plan, waste characterization, SWPPP, and Road Access Plan formally submitted
- Plan of Operations submitted to USFS in February 2026 and actively reviewed
- Prior wildfires reduced live tree removal needs, potentially lowering environmental disturbance
Negative
- Permanent bridge crossing application within SMARA Road Access Plan still under review
- 401 Water Quality Certification and Waste Discharge Requirements remain under regulatory review
- Report of Waste Discharge still required for excess pond water discharge
- Regulatory status of onsite spring for potable water remains under review
- Magazine Storage and Explosives permits not filed until final Plan of Operations approval
News Market Reaction – CGLD
In the May 14 session, CGLD declined 4.26%, reflecting a moderate negative market reaction.
Data tracked by StockTitan Argus on the day of publication.
AI-generated analysis. How Rhea-AI works. Not financial advice.
The Treasure Canyon Mine project is located approximately 11 miles northeast of
According to an update from Martin L. Gallon, CPG of Lumwana LLC, the USFS received the draft Plan of Operations in February 2026 and distributed the documentation to federal and state regulatory agencies for review and comment. The Company's consultant reports that permitting activities have continued to progress, with ongoing communication among participating agencies.
Key Permitting Milestones Achieved
Buscar Company confirmed that certain approvals have been obtained, while multiple remaining applications continue advancing through the review process.
Northern Sierra Air Quality Management District
The following permits have been officially approved:
- Dust Control Plan Application - Submitted; NSAQMD confirmed most requirements have been met
- Burn Permit (NSAQMD Permit No. 5186, issued 4/29/2026) - Issued, valid from 7/15/2026 through 7/15/2027; valid only on designated Burn Days; a separate Project Burn Permit from CalFire/USFS must also be obtained prior to burning
The burn permit, subject to applicable conditions, including burn-day designations and a separate CalFire/USFS project burn permit, covers hazard-reduction pile burning that may assist in removing dead timber and wildfire debris from the property.
California Department of Fish and Wildlife (CDFW)
- Lake and Streambed Alteration Agreement (EPIMS No. PLU-13720-R2) for a temporary bridge crossing of Lights Creek - Agreement issued by CDFW; subject to a 35-day CEQA statute-of-limitations period and additional conditions set forth in the Agreement
- Permanent bridge crossing application — Included within the SMARA Road Access Plan and currently under agency review
Surface Mining and Reclamation Act (SMARA) – Division of Reclamation
The following documents and plans have been formally submitted and are currently under regulatory review:
- SMARA Reclamation Plan
- Mining Waste Characterization
- Storm Water Pollution Prevention Plan
- Road Access Plan
Central Valley Regional Water Quality Control Board
Current regulatory review items include:
- State Water Board Division of Water Rights review
- 401 Water Quality Certification and Waste Discharge Requirements review
The Company noted that clarification was requested regarding water discharge requirements. The Plan of Operations proposes to recycle mine water for operational reuse, with Lights Creek as the source of make-up water. The Plan also proposes discharge of any excess pond water, which is subject to pending regulatory review and approval, including a Report of Waste Discharge requirement identified by the Central Valley Regional Water Quality Control Board.
The Plan of Operations proposes the use of a spring located on site for potable water supply. The status of any regulatory requirements applicable to that water source is subject to ongoing review.
Mine Safety and Operational Readiness
Following final approval of the Plan of Operations, Buscar intends to immediately file the remaining mine safety-related permits, including:
- Magazine Storage Permit
- Explosives Permit
These permits will be processed through MSHA, Cal/OSHA, and local regulatory authorities.
Environmental and Infrastructure Advantages
The Treasure Canyon Mine site possesses several unique environmental and logistical advantages that may substantially reduce development complexity and environmental impact.
According to the consultant's report, the project area has previously experienced repeated wildfires that removed a significant portion of the forest cover. As a result, the construction of mine infrastructure and access roads is not expected to require the removal of living trees, reducing environmental disturbance and potentially streamlining portions of the permitting and construction process.
The Company also emphasized that the approved burn permit authorizes the removal of remaining dead trees and wildfire debris, improving site safety and operational preparation.
Strong Relationship with
Lumwana LLC reported that the
The consultant further stated that edits to sections of the Plan of Operations have been provided and incorporated into updated submissions.
Management Commentary
"The progress we are seeing in the permitting process is extremely encouraging and reflects the professionalism and cooperation of everyone involved," said Aleksandr Dekhtyar, CEO of Buscar Company.
"We are particularly pleased with the continued engagement from the
About Treasure Canyon Mine
The Treasure Canyon Mine project is in
About Buscar Company
Buscar Company (OTC ID: CGLD) is a diversified holding company focused on natural resources, mining development, and environmentally sustainable technologies. The Company is actively advancing precious metals projects in
Forward-Looking Statements
This press release contains forward-looking statements within the meaning of federal securities laws. These statements include, but are not limited to, statements regarding permitting timelines, mine development plans, operational expectations, regulatory approvals, environmental assumptions, future production potential, and business strategy. Forward-looking statements involve risks and uncertainties that could cause actual results to differ materially from those projected. Investors are cautioned not to place undue reliance on forward-looking statements. Buscar Company undertakes no obligation to publicly update or revise forward-looking statements except as required by applicable law.
Contact:
Aleksandr Dekhtyar, CEO
Buscar Company
www.buscarco.com
Phone: +1 (833) 539-4777
Email: office@cgld.email
View original content to download multimedia:https://www.prnewswire.com/news-releases/buscar-company-announces-major-advancement-in-the-permitting-process-for-the-treasure-canyon-gold-mine-project-in-california-302772744.html
SOURCE Buscar Company (CGLD)