BUSCAR COMPANY ANNOUNCES MAJOR ADVANCEMENT IN THE PERMITTING PROCESS FOR THE TREASURE CANYON GOLD MINE PROJECT IN CALIFORNIA

(Positive)
Tags

Buscar Company (OTC:CGLD) reported significant progress in permitting for its Treasure Canyon Mine in Plumas County, California. Key milestones include a burn permit from the Northern Sierra Air Quality Management District and a Lake and Streambed Alteration Agreement from the California Department of Fish and Wildlife.

Multiple plans under SMARA, water quality certifications, and waste discharge requirements remain under regulatory review. The project benefits from prior wildfire impacts that reduced live tree cover, potentially lowering environmental disturbance. Buscar plans to file mine safety permits after final Plan of Operations approval.

Loading...
Loading translation...

Positive

  • Burn Permit No. 5186 approved, valid 7/15/2026–7/15/2027 for hazard-reduction burning
  • Lake and Streambed Alteration Agreement (EPIMS No. PLU-13720-R2) for temporary bridge issued by CDFW
  • SMARA Reclamation Plan, waste characterization, SWPPP, and Road Access Plan formally submitted
  • Plan of Operations submitted to USFS in February 2026 and actively reviewed
  • Prior wildfires reduced live tree removal needs, potentially lowering environmental disturbance

Negative

  • Permanent bridge crossing application within SMARA Road Access Plan still under review
  • 401 Water Quality Certification and Waste Discharge Requirements remain under regulatory review
  • Report of Waste Discharge still required for excess pond water discharge
  • Regulatory status of onsite spring for potable water remains under review
  • Magazine Storage and Explosives permits not filed until final Plan of Operations approval

News Market Reaction – CGLD

-4.26%
-4.26% Session close to close

In the May 14 session, CGLD declined 4.26%, reflecting a moderate negative market reaction.

Data tracked by StockTitan Argus on the day of publication.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

BEVERLY HILLS, Calif., May 14, 2026 /PRNewswire/ -- Buscar Company (OTC ID: CGLD) ("Buscar" or the "Company") today announced progress in the permitting process for its Treasure Canyon Mine Project located in Plumas County, California. The Company has received an update from its permitting consultant, Lumwana LLC, indicating that the project has advanced through several permitting stages, with ongoing coordination among multiple federal and state regulatory agencies.

The Treasure Canyon Mine project is located approximately 11 miles northeast of Taylorsville, California, within Township 27 North, Range 11 East (Mount Diablo Base and Meridian), in the Plumas National Forest.

According to an update from Martin L. Gallon, CPG of Lumwana LLC, the USFS received the draft Plan of Operations in February 2026 and distributed the documentation to federal and state regulatory agencies for review and comment. The Company's consultant reports that permitting activities have continued to progress, with ongoing communication among participating agencies.

Key Permitting Milestones Achieved

Buscar Company confirmed that certain approvals have been obtained, while multiple remaining applications continue advancing through the review process.

Northern Sierra Air Quality Management District

The following permits have been officially approved:

  • Dust Control Plan Application - Submitted; NSAQMD confirmed most requirements have been met
  • Burn Permit (NSAQMD Permit No. 5186, issued 4/29/2026) - Issued, valid from 7/15/2026 through 7/15/2027; valid only on designated Burn Days; a separate Project Burn Permit from CalFire/USFS must also be obtained prior to burning

The burn permit, subject to applicable conditions, including burn-day designations and a separate CalFire/USFS project burn permit, covers hazard-reduction pile burning that may assist in removing dead timber and wildfire debris from the property.

California Department of Fish and Wildlife (CDFW)

  • Lake and Streambed Alteration Agreement (EPIMS No. PLU-13720-R2) for a temporary bridge crossing of Lights Creek - Agreement issued by CDFW; subject to a 35-day CEQA statute-of-limitations period and additional conditions set forth in the Agreement
  • Permanent bridge crossing application — Included within the SMARA Road Access Plan and currently under agency review

Surface Mining and Reclamation Act (SMARA) – Division of Reclamation

The following documents and plans have been formally submitted and are currently under regulatory review:

  • SMARA Reclamation Plan

  • Mining Waste Characterization

  • Storm Water Pollution Prevention Plan

  • Road Access Plan

Central Valley Regional Water Quality Control Board

Current regulatory review items include:

  • State Water Board Division of Water Rights review

  • 401 Water Quality Certification and Waste Discharge Requirements review

The Company noted that clarification was requested regarding water discharge requirements. The Plan of Operations proposes to recycle mine water for operational reuse, with Lights Creek as the source of make-up water. The Plan also proposes discharge of any excess pond water, which is subject to pending regulatory review and approval, including a Report of Waste Discharge requirement identified by the Central Valley Regional Water Quality Control Board.

The Plan of Operations proposes the use of a spring located on site for potable water supply. The status of any regulatory requirements applicable to that water source is subject to ongoing review.

Mine Safety and Operational Readiness

Following final approval of the Plan of Operations, Buscar intends to immediately file the remaining mine safety-related permits, including:

  • Magazine Storage Permit

  • Explosives Permit

These permits will be processed through MSHA, Cal/OSHA, and local regulatory authorities.

Environmental and Infrastructure Advantages

The Treasure Canyon Mine site possesses several unique environmental and logistical advantages that may substantially reduce development complexity and environmental impact.

According to the consultant's report, the project area has previously experienced repeated wildfires that removed a significant portion of the forest cover. As a result, the construction of mine infrastructure and access roads is not expected to require the removal of living trees, reducing environmental disturbance and potentially streamlining portions of the permitting and construction process.

The Company also emphasized that the approved burn permit authorizes the removal of remaining dead trees and wildfire debris, improving site safety and operational preparation.

Strong Relationship with U.S. Forest Service

Lumwana LLC reported that the U.S. Forest Service has been engaged throughout the permitting process. The agency has communicated with the Company and its consultants regarding the Plan of Operations, including providing comments on submitted materials.

The consultant further stated that edits to sections of the Plan of Operations have been provided and incorporated into updated submissions.

Management Commentary

"The progress we are seeing in the permitting process is extremely encouraging and reflects the professionalism and cooperation of everyone involved," said Aleksandr Dekhtyar, CEO of Buscar Company.

"We are particularly pleased with the continued engagement from the U.S. Forest Service and the steady advancement of approvals across multiple agencies. The Treasure Canyon project continues to move forward in a responsible and efficient manner. This marks another important milestone as we position Buscar Company for long-term growth in the precious metals sector."

About Treasure Canyon Mine

The Treasure Canyon Mine project is in Plumas County, California, within a historically mineral-rich region known for significant placer and hard-rock gold production. Buscar Company, through its mining subsidiaries and operating partners, is advancing the project with a focus on regulatory compliance, environmental stewardship, operational efficiency, and long-term resource development.

About Buscar Company

Buscar Company (OTC ID: CGLD) is a diversified holding company focused on natural resources, mining development, and environmentally sustainable technologies. The Company is actively advancing precious metals projects in the United States while exploring strategic opportunities in clean technologies and industrial innovation.

Forward-Looking Statements

This press release contains forward-looking statements within the meaning of federal securities laws. These statements include, but are not limited to, statements regarding permitting timelines, mine development plans, operational expectations, regulatory approvals, environmental assumptions, future production potential, and business strategy. Forward-looking statements involve risks and uncertainties that could cause actual results to differ materially from those projected. Investors are cautioned not to place undue reliance on forward-looking statements. Buscar Company undertakes no obligation to publicly update or revise forward-looking statements except as required by applicable law.

Contact:
Aleksandr Dekhtyar, CEO
Buscar Company
www.buscarco.com
Phone: +1 (833) 539-4777
Email: office@cgld.email

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/buscar-company-announces-major-advancement-in-the-permitting-process-for-the-treasure-canyon-gold-mine-project-in-california-302772744.html

SOURCE Buscar Company (CGLD)

FAQ

What permitting progress did Buscar Company (OTC:CGLD) announce for the Treasure Canyon Mine on May 14, 2026?

Buscar Company reported advancing through several permitting stages for the Treasure Canyon Mine. According to Buscar Company, the Plan of Operations is under active USFS review and multiple federal and state agencies are coordinating on approvals, with several key permits already issued and others still in process.

Which air quality and burn permits for Treasure Canyon Mine have been approved for Buscar Company (CGLD)?

The Northern Sierra Air Quality Management District approved a Dust Control Plan and Burn Permit No. 5186. According to Buscar Company, the burn permit covers hazard-reduction pile burning from 7/15/2026 to 7/15/2027, subject to burn-day designations and a separate CalFire/USFS project burn permit.

What bridge and access permits are involved in Buscar Company’s (CGLD) Treasure Canyon Mine project?

A Lake and Streambed Alteration Agreement for a temporary Lights Creek bridge has been issued. According to Buscar Company, the permanent bridge crossing is included in the SMARA Road Access Plan, which, along with broader access and reclamation plans, remains under review by relevant regulators.

How will water use and discharge be managed at Buscar Company’s (CGLD) Treasure Canyon Mine?

The project plans to recycle mine water and use Lights Creek as make-up water, with excess pond water potentially discharged. According to Buscar Company, these discharges require 401 Water Quality Certification, Waste Discharge Requirements, and a Report of Waste Discharge, all currently under regulatory review.

What environmental factors could affect permitting at Buscar Company’s (CGLD) Treasure Canyon Mine?

Prior wildfires have removed much of the site’s forest cover, reducing live tree clearing for infrastructure. According to Buscar Company, this may lessen environmental disturbance and help permitting, while an approved burn permit supports removal of dead trees and wildfire debris to improve safety and site preparation.

What are the next steps for mine safety permits at Buscar Company’s (CGLD) Treasure Canyon Mine?

Buscar plans to file Magazine Storage and Explosives permits after final Plan of Operations approval. According to Buscar Company, these mine safety-related permits will be processed through MSHA, Cal/OSHA, and local authorities, forming part of the project’s operational readiness planning.

Where is Buscar Company’s Treasure Canyon Mine located and which agencies oversee permitting?

Treasure Canyon Mine lies about 11 miles northeast of Taylorsville, in Plumas National Forest, California. According to Buscar Company, the US Forest Service coordinates Plan of Operations review, while state agencies handle air quality, water, fish and wildlife, and SMARA-related mining and reclamation permits.