ABRIDGED, PRELIMINARY AND UNAUDITED QUARTERLY AND FULL YEAR RESULTS AND DETAILS OF MANAGEMENT CONFERENCE Call for the Fourth Quarter and Full Year Ended December 31, 2025 ("The Quarter" or "Q4 2025" and "FY 2025" Respectively)
Rhea-AI Summary
Caledonia Mining (LSE:CMCL) reported preliminary, unaudited FY 2025 results: revenue US$267.7M (+46%), EBITDA US$125.3M, profit after tax US$67.5M (+193%) and free cash flow US$62.1M. Blanket produced 76,213 oz gold; AISC averaged US$1,952/oz. Cash rose to US$35.7M resulting in net cash of US$23.8M. The Bilboes feasibility study was completed and a 14¢ quarterly dividend was declared payable 17 April 2026.
FY2026 capex guidance totals US$178.9M, including US$132.1M for Bilboes development.
Positive
- Revenue +46% to US$267.7M in FY2025
- EBITDA US$125.3M (up 109.9% YoY)
- Profit after tax US$67.5M (up 193% YoY)
- Free cash flow US$62.1M (up 483.6% YoY)
- Net cash position US$23.8M at year end
- Bilboes feasibility study completed (single‑phase development confirmed)
Negative
- AISC US$1,952/oz (up 29.6% YoY)
- On‑mine cash cost US$1,263/oz (up 17.7% YoY)
- Large FY2026 capex guidance US$178.9M, including US$132.1M for Bilboes (funding required)
- Fatal accident at Blanket in Sept 2025; company initiated comprehensive safety review
News Market Reaction – CMCL
On the day this news was published, CMCL gained 3.87%, reflecting a moderate positive market reaction. Argus tracked a peak move of +3.5% during that session. Our momentum scanner triggered 2 alerts that day, indicating moderate trading interest and price volatility. This price movement added approximately $17M to the company's valuation, bringing the market cap to $447.48M at that time.
Data tracked by StockTitan Argus on the day of publication.
RECORD FINANCIAL PERFORMANCE IN FY 2025, STRONG CASH GENERATION AND CLEAR GROWTH MOMENTUM INTO 2026
SAINT HELIER, JE / ACCESS Newswire / March 23, 2026 / Caledonia Mining Corporation Plc ("Caledonia" or "the Company" and together with its subsidiaries "the Group") is pleased to report preliminary unaudited financial and operating performance for the Quarter and FY 2025, reflecting a year of strong revenue, profit and cash generation, alongside continued progress on its growth strategy across Blanket Mine, Bilboes and Motapa.
The Group's performance during the year was underpinned by a higher gold price environment, providing a robust platform to execute the next phase of growth into 2026 and beyond.
Unaudited consolidated statements of profit or loss and other comprehensive income, consolidated statements of financial position and consolidated statements of cash flows are included in the appendices at the end of this announcement. The Company expects to file its Annual Report on Form 20-F for the year ended December 31, 2025, containing audited financial statements for FY 2025, ("Form 20-F") with the U.S. Securities and Exchange Commission in the next few weeks, and an announcement will be made to notify of its filing in due course.As a result, all financial results described herein should be considered preliminary (and are unaudited), and are subject to change to reflect any necessary adjustments or changes in accounting estimates that are identified prior to the time we file our Form 20-F.
Summary for Quarter and FY 2025
The Group delivered an exceptional financial performance in FY 2025, benefiting from a higher gold price environment.
Gold Production and Sales:
Blanket Mine ("Blanket") produced 76,213 ounces ("oz") of gold in FY 2025 and sold 77,392 oz, with 2,262 oz of gold bullion on hand at year end.
The Bilboes oxide operation produced and sold 1,683 oz of gold during FY 2025.
Total consolidated gold sales were 79,075 oz, compared to 77,917 oz in the previous year ("FY 2024").
Revenue increased by
46% to US$267.7 million , compared with US$183.0 million in FY 2024, driven primarily by a significantly higher realised gold price and strong sales volumes.Gross profit increased to US
$137.1 million , compared to US$77.0 million in FY 2024, reflecting improved margins due to the higher gold price.EBITDA increased to US
$125.3 million , compared with US$59.7million in FY 2024, representing a substantial improvement driven by higher gold prices.Profit after tax increased to US
$67.5 million , compared with US$23.1 million in FY 2024, an increase of193% .Net cash generated from operating activities increased by
82% to US$76.2 million (FY 2024: US$42.0 million ).Unit Costs:
Consolidated on-mine cash cost averaged US
$1,263 /oz sold.All in sustaining cost ("AISC") averaged US
$1,952 /oz sold, based on 79,075 oz sold.
Free cash flow increased to US
$62.1 million , compared with US$10.6 million in FY 2024.Basic earnings per share ("EPS") increased by
211% to US$2.83 (FY 2024: US$0.91) , driven by higher profitability.Bilboes Gold Project ("Bilboes" or "the Project"):
The Bilboes sulphide feasibility study was completed and published in November 2025, confirming a single-phase development, robust economics and a clear pathway to development.See "Bilboes Gold Project Technical Report Summary" with effective date October 31, 2025 prepared by DRA Projects (Pty) Ltd and filed by the Company on EDGAR as an exhibit to a Form 6-K Report of Foreign Private Issuer on November 24, 2025 (the "Feasibility Study").
On 5 November 2025, Caledonia announced the appointment of Mr. July Ndlovu as an independent non‑executive director to the Board.
Quarterly dividend: Caledonia announces today that the board of directors of the Company (the "Board") has approved a dividend of 14 cents per share which will be paid on April 17, 2026.
The Group's balance sheet strengthened materially during the year. Cash and cash equivalents increased to US
OPERATING RESULTS SUMMARY
Q4 2025 | Q4 2024 | % ∆ | 12-Months 2025 | 12-Months 2024 | % ∆ | |||||||||||||||||||
SAFETY | ||||||||||||||||||||||||
Group LTIFR (per 1m hours)1,5 | 0.0 | 1.11 | -100 | % | 0.8 | 0.71 | 12.7 | % | ||||||||||||||||
Group TIFR (per 1m hours)1,6 | 2.8 | 2.21 | 26.7 | % | 3.5 | 4.41 | -20.5 | % | ||||||||||||||||
UNDERGROUND MINING2 | ||||||||||||||||||||||||
Ore broken in tonnes (t) ('000's) | 221.6 | 229.0 | -3.2 | % | 916.2 | 851.4 | 7.6 | % | ||||||||||||||||
Ore hoisted in tonnes (t) ('000's) | 197.4 | 213.5 | -7.5 | % | 840.2 | 772.2 | 8.8 | % | ||||||||||||||||
PROCESSING2 | ||||||||||||||||||||||||
Ore processed/milled (t) ('000's) | 207.7 | 207.7 | 0.0 | % | 826.8 | 797.5 | 3.7 | % | ||||||||||||||||
Head/feed grade (grams/tonne) | 2.8 | 3.2 | -12.5 | % | 3.07 | 3.2 | -4.1 | % | ||||||||||||||||
Gold recovery (%) | 92.8 | 93.6 | -0.9 | % | 93.4 | 93.6 | -0.2 | % | ||||||||||||||||
Gold production (oz) | 17,367 | 19,841 | -12.5 | % | 76,213 | 76,656 | -0.6 | % | ||||||||||||||||
COSTS AND SALES | ||||||||||||||||||||||||
Gold sold (oz) | 18,408 | 18,141 | 1.5 | % | 79,075 | 77,917 | 1.5 | % | ||||||||||||||||
On-mine costs (US | 28,037 | 21,361 | 31.3 | % | 99,873 | 83,619 | 19.4 | % | ||||||||||||||||
On-mine (US$/oz sold) | 1,523 | 1,177 | 29.4 | % | 1,263 | 1,073 | 17.7 | % | ||||||||||||||||
AISC (US | 42,249 | 34,055 | 24.1 | % | 154,335 | 117,321 | 31.6 | % | ||||||||||||||||
AISC (US$/oz sold) | 2,295 | 1,877 | 22.3 | % | 1,952 | 1,506 | 29.6 | % | ||||||||||||||||
Realised gold price (US$/oz) | 4,057 | 2,618 | 55.0 | % | 3,383 | 2,347 | 44.1 | % | ||||||||||||||||
FINANCIALS3 | ||||||||||||||||||||||||
Revenue (US | 74,736 | 47,515 | 57.3 | % | 267,663 | 183,018 | 46.2 | % | ||||||||||||||||
EBITDA (US | 29,817 | 17,426 | 71.1 | % | 125,319 | 59,695 | 109.9 | % | ||||||||||||||||
Profit after tax (US | 14,099 | 7,516 | 87.5 | % | 67,511 | 23,054 | 192.8 | % | ||||||||||||||||
Capital expenditure (US | 6,604 | 10,437 | -36.7 | % | 30,772 | 27,915 | 10.2 | % | ||||||||||||||||
Free cash-flow (US | 13,788 | 876 | 1,473.9 | % | 62,116 | 10,643 | 483.6 | % | ||||||||||||||||
Basic earnings per share ($) | 0.56 | 0.30 | 86.7 | % | 2.83 | 0.91 | 211.0 | % | ||||||||||||||||
Diluted earnings per share ($) | 0.56 | 0.30 | 86.7 | % | 2.83 | 0.91 | 211.0 | % | ||||||||||||||||
Previously reported in 200,000 man hours.
The production summaries above only show Blanket results. Bilboes contributes marginally to the overall results; however, due to materiality, its numbers have not been included above.
Please refer to the financial statement appendices at the end of the report.
The capex relates to Blanket only.
LTIFR - lost time injury frequency rate.
TIFR - total incident frequency rate.
Chief Executive Officer's Comment
Mark Learmonth, Caledonia's Chief Executive Officer, commented:
"2025 has been a strong year for the Group, marked by record financial performance, excellent cash generation and continued strategic progress across the business. Revenue increased by
At Blanket, we produced 76,213 ounces of gold, meeting our revised increased guidance, while continuing to invest in exploration. The results from our drilling programmes are highly encouraging and reinforce our confidence in the long-term future of the operation.
Beyond Blanket, we advanced our organic growth strategy and made decisive progress with Bilboes, our next mine. The publication of the Feasibility Study confirmed our expectations that Bilboes is an attractive and robust project that has the potential to materially change our production and profit profile and at the same time provide meaningful contributions to Zimbabwe.
Our investment in Motapa, which sits contiguous to Bilboes, forms an important part of our strategy to build a broader production and growth platform in Zimbabwe. Our post-period funding initiatives, together with the proceeds from the sale of the solar plant at Blanket, have significantly strengthened our balance sheet and leave us well positioned to fund growth while importantly maintaining financial flexibility.
We continue to receive strong and constructive support from the Government of Zimbabwe in implementing our strategy. Looking ahead to 2026, our focus is on execution and the strategic objective of becoming a multi-mine producer. Our commitment is unwavering to safety and our people while maintaining consistent operations at Blanket, advancing Bilboes in line with the financing and development timetable, continuing targeted exploration at Motapa, and delivering sustainable value for shareholders, employees and the communities in which we operate. We intend to use the current strong gold price to invest in projects at Blanket to improve operating resilience and contain further upward pressure on input prices."
WEBCAST
The Company will host a remote presentation for analysts and investors on its preliminary and unaudited operating and financial results for the Quarter and FY 2025 on Monday March 23, 2026 at 2:00pm London time, followed by an opportunity to ask questions.
Webcast link: https://stream.brrmedia.co.uk/broadcast/69ae9fc354af4a0013267828
Safety
Safety remains a core priority for the Group. During FY 2025, the Company reported a fatal accident involving a Blanket employee in September 2025, following an incident related to secondary blasting. The Group remains deeply saddened by the loss and extends its condolences to the family and those affected. In response, management initiated a comprehensive review of safety procedures, controls and training programmes across the operation, with a continued focus on reinforcing safety standards, improving risk management practices and strengthening the safety culture throughout the business.
At Blanket, work is underway to further strengthen the fatal risk management framework, including the enhancement of risk registers, risk standards, and verification and assurance processes. In parallel, the Group has implemented the IsoMetrix electronic SHEC management system to support consistent incident reporting, hazard identification and risk management across its operations. The system went live in December 2025, with training continuing into 2026.
No lost time injuries or fatalities occurred during the Quarter, and the LTIFR for FY2025 was 0.84 per million work hours.
Production
Blanket delivered a strong and resilient operational performance in FY 2025, meeting increased production guidance despite operational challenges experienced during the year. FY 2025 gold production of 76,213 oz was within the revised guidance range of 75,500 to 79,500 oz and broadly consistent with production achieved over the prior two years, reflecting the underlying stability of the operation.
Production in the second half of the year was affected by lower tonnages from higher grade areas, which are being addressed through ongoing mine development, and by an increased incidence of prolonged electricity supply interruptions towards the end of the year. These impacts were partially offset by robust milling throughput and the draw-down of material from the ore stockpile, which helped to maintain overall production levels.
For 2026, Caledonia expects Blanket gold production to be in the range of 72,000 to 76,500 oz[1], with the quarterly production profile anticipated to be stronger in the second half of the year as higher-grade areas increasingly come on stream.
1 Refer to "S-K 1300 Technical Report Summary on the Blanket Gold Mine, Zimbabwe" with effective date December 31, 2023 prepared by Caledonia and filed by the Company on EDGAR as an exhibit to its annual report on Form 20-F on May 15, 2024; and "NI 43-101 Technical Report on the Blanket Gold Mine, Zimbabwe" with effective date December 31, 2023 prepared by Caledonia and filed by the Company on SEDAR+ on May 15, 2024
Capital Expenditure and Investment for Growth
The main capital projects at Blanket in 2025 were the ongoing mine development to provide access to new mining areas and the completion of the new Tailings Storage Facility ("TSF").
On-mine capital development has established critical infrastructure across the 26, 30, and 34 Levels, thereby supporting sustained operations at greater depth. Currently, significant progress is being made on the development of a twin decline system designed to provide enhanced access to the 38 Level. The decline system has successfully advanced to the 36 Level, where the establishment of a mid-level is underway to facilitate production activities below the 34 Level. 5,532 and 22,284 meters of development were achieved for the Quarter and FY 2025 respectively.
The TSF was built on a modular basis to spread the cost over a longer period, and to ensure that the first phase could receive material before the old TSF reached its full capacity. Work on the TSF was completed on July 31, 2025. A second return water dam to support the TSF was commissioned in November 2025.
The Company published guidance on January 14, 2026 for capital expenditure for 2026, in which it stated that guidance may be increased to cater for the construction of a 34km electricity line to connect Blanket to Zimbabwe's 132Kv backbone. This investment is expected to reduce the price of power received from the grid and reduce the incidence of power outages experienced by Blanket, thereby reducing the use of expensive diesel generators and allowing an increase in expected production of about 1,000 oz per annum due to improved operating reliability. The study for this project has been completed, and the Board has approved an amount of
(US | Q4 2025 | 2025 | ||||||
SUSTAINING CAPEX | ||||||||
Underground mine development | 1,215 | 6,659 | ||||||
Engineering equipment | 1,329 | 9,612 | ||||||
Other sustaining capex | 3,205 | 8,444 | ||||||
Total sustaining capex | 5,749 | 24,715 | ||||||
NON-SUSTAINING CAPEX | ||||||||
TSF | 855 | 6,057 | ||||||
Total non-sustaining capex | 855 | 6,057 | ||||||
TOTAL CAPEX * | 6,604 | 30,772 | ||||||
* The capex relates to Blanket only.
Total Group capital expenditure for FY 2026 is projected to be US
This comprises:
Sustaining capital of US
$43.0 million , largely focused on Blanket.Growth capital of US
$135.9 million , including:US
$132.1 million allocated to the Bilboes development project, subject to Board approval and funding; andUS
$3.8 million for exploration at Motapa, reflecting the Group's focus on longer term value creation and synergies with Bilboes.
Costs
During FY2025, total production costs for the Group increased to US
On a unit basis, the Group reported a consolidated on-mine cash cost of US
Administrative expenses increased to US
Sales
Gold sales during FY 2025 reflected both stable production levels and a significantly higher gold price environment, resulting in strong revenue growth and margin expansion. The Group sold a total of 79,075 ounces of gold during the year (FY 2024: 77,917 ounces), primarily from Blanket, with additional contribution from the Bilboes oxide operation. Gold sales volumes were broadly consistent year-on-year, demonstrating the underlying reliability of the Group's operations.
Average realised gold prices increased materially to US
Underground Mining and Processing
During FY 2025, underground milling and processing activities continued to support production delivery at Blanket, as reflected in total gold production of 76,213 oz for the year. Q4 2025 was impacted by crew moves to new areas as production areas in the upper levels reached the end of their life span. Some delays in bringing the crews into production in the new areas resulted in lower than planned tonnages from these areas, adversely affecting the overall grade for the Quarter. Production from the new areas remained under pressure in January and February 2026 but has improved in March 2026.
Processing related costs, including consumables, electricity and maintenance associated expenditure, increased year on year, consistent with higher inflationary pressures and increased underground development activity. Expenditure on processing and plant related infrastructure formed part of the Group's ongoing capital investment programme aimed at sustaining operational capacity and supporting future production requirements.
Exploration and Resource Development - Blanket
During 2025, the Group continued its underground resource expansion drilling programme at Blanket, completing 6,976 metres of drilling. Results returned grades and widths that were generally better than expected relative to the current mineral resource model.
The programme confirmed the continuation of the Blanket and Eroica orebodies at depth to beyond 36 Level (1,230 meters below surface) and demonstrated the extension of the Lima orebody to 30 Level (990 meters below surface) from 22 Level (750 meters below surface), which is the lowest level of mining on the Lima orebody. The deep drilling program continues to reinforce confidence in the long-term production profile and life of mine extension potential at Blanket.
Surface exploration activities at Blanket have identified an anomalous area of gold mineralisation located approximately 200 meters to the east of the Sheet surface shaft. The area was trenched to obtain sample material for assay and follow up reverse circulation drilling commenced down to a depth of 40 meters below surface. Currently, assay results are pending from external laboratories although indications from selective assaying at the Blanket laboratory appear positive. Future updates will follow once assay results are received and processed during the first half of 2026.
Motapa Exploration - Investing for Future Growth
During 2025, the Group continued to invest in exploration activities at the Motapa property, recognising its potential to deliver long term, value enhancing synergies alongside the development of Bilboes. Motapa is a brownfield exploration asset located adjacent to Bilboes and is considered strategically important as part of the Group's broader ambition to establish a multi asset gold production hub in Zimbabwe. Exploration expenditure during the year was directed towards advancing geological understanding and supporting longer term growth optionality.
Exploration during 2025 was focussed on the sulphide mineralisation below the historical oxide open pits at Motapa North and for near surface oxide mineralisation at the eastern portion of the Motapa central trend known as Mpudzi.
For 2025, the following was achieved:
Surface Diamond Drilling
1,564 meters drilled from 18 drillholes (2024: 4,255 meters from 27 drillholes).
1,317 samples for fire assay submitted and received.
Surface Reverse Circulation Drilling.
18,325 meters drilled from 196 drillholes (2024: 5,461 meters from 61 drillholes).
12,460 samples for fire assay submitted and received.
The results from the exploration activities are expected to produce a maiden mineral resource estimate for the sulphide mineralisation of the Motapa north trend during the second quarter 2026.
Looking ahead, US
Bilboes Gold Project - Our Next Mine
In November 2025, Caledonia published the Feasibility Study and approved the Project for development. The Feasibility Study informs a single‑phase development, proven and probable mineral reserves of 1.75 million oz of gold contained in 24.1 million tonnes of ore at an average grade of 2.26 grams per tonne, and a life of mine of 10.8 years.
The Project is expected to produce approximately 200,000 oz of gold in its first full year of production, with first production anticipated in late 2028. The Feasibility Study demonstrates robust economics, including a post-tax NPV (
Funding, Liquidity and Capital Allocation
The Group's total liquidity is shown below.
Liquidity
Dec 31, 2025 | |||
(US | |||
Cash on hand | 35,738 | ||
Bullion on hand | 10,293 | ||
Gold sales receivables | 7,718 | ||
Fixed-term deposits | 5,000 | ||
TOTAL BEFORE UTILISATION OF FACILITIES | 58,749 | ||
Drawn down bank facilities | (11,898) | ||
NET CASH AND LIQUID ASSETS | 46,851 | ||
Undrawn bank facilities | 8,101 | ||
TOTAL LIQUIDITY | 54,952 |
During early 2026, Caledonia successfully completed a US
The Company also implemented a gold price hedging programme, securing a minimum price of US
Caledonia continues to progress discussions regarding an interim funding facility of up to US
Diesel and Operational Continuity
The recent geopolitical developments in the Middle East have had no impact on Caledonia's operations to date. Diesel, of which the Group consumes approximately two million litres per annum, represents less than
At present Caledonia is selling its exported portion of gold through South Africa (rather than the Middle East), ensuring uninterrupted revenue flows for that portion.
These factors collectively underpin strong operational resilience despite external geopolitical developments.
Dividend
Caledonia has approved a quarterly dividend of 14 United States cents (US
The relevant dates relating to the dividend are as follows:
Ex-dividend date VFEX: March 31, 2026
Ex-dividend date AIM and NYSE American: April 2, 2026
Record date: April 2, 2026
Payment date: April 17, 2026
Shareholders with a registered address in the UK will be paid in Sterling.
END NOTES
Financial information
As previously advised, Caledonia no longer publishes financial statements and management's discussion and analysis reports on a quarterly basis in accordance with Canadian securities regulations. This decision aligns with applicable exemptions under Canadian securities regulations, including National Instrument 71-102 - Continuous Disclosure and Other Exemptions Relating to Foreign Issuers, and reflects our status as an SEC foreign issuer with equivalent disclosure obligations outside Canada. Therefore there will no longer be annual financial statements issued with a Canadian audit report.
The audited financial statements for FY 2025 will be incorporated in the Form 20‑F.
The financial information presented herein and in the accompanying appendices has been extracted from the Company's preliminary and unaudited financial statements for the period ended December 31, 2025. The information has been prepared using accounting policies consistent with those applied in the preparation of the preliminary and unaudited annual financial statements for the year ended December 31, 2025. The extracted information does not include all the disclosures required by International Financial Reporting Standards (IFRS). The information has been provided to update shareholders on the performance of the Group and should be read together with the Form 20-F which is expected to be filed with the U.S. Securities and Exchange Commission in the next few weeks, and an announcement will be made to notify of its filing in due course. As a result, all financial results described herein should be considered preliminary (and are unaudited), and are subject to change to reflect any necessary adjustments or changes in accounting estimates that are identified prior to the time we file our Form 20-F.
Non-GAAP measures
This announcement includes certain financial performance measures which are non-GAAP measures. These include cash costs of production, AISC, cash and liquid assets, and free cash flow. Management believes these measures provide valuable additional information for users of the information to understand the underlying trading performance. Definitions and explanation of the measures used along with reconciliation to the nearest IFRS measures are detailed in the Form 20-F which will in due course be filed on the SEC's Electronic Data Gathering, Analysis, and Retrieval (EDGAR) system as well as being available at www.caledoniamining.com/investors/reports-presentations/.
Cash and liquid assets
Cash and liquid assets include cash, fixed-term deposits, bullion on hand, gold sales receivables and drawn down bank facilities.
LTIFR
Lost Time Injury Frequency Rate ("LTIFR") measures how often workplace injuries occur that result in employees missing work, normalized to hours worked to allow comparison over time or between organisations.
TIFR
The Total Injury Frequency Rate ("TIFR") is a key safety performance indicator that measures the frequency of all workplace injuries (including fatalities, lost time injuries, medical treatment cases, and restricted work injuries) relative to the total hours worked.
Reporting Changes
Notwithstanding that Caledonia no longer publishes financial statements and management's discussion and analysis reports on a quarterly basis in accordance with Canadian securities regulations, Caledonia remains fully committed to transparent and timely disclosure of material information through the publication of our annual and half-yearly financial statements and via recognised regulatory channels, and, going forwards, we anticipate continuing to publish revenue, costs and production results for the quarters for which we do not release detailed financial results (namely, the first and third quarters). This change does not affect our obligation to disclose any significant developments or risks that may materially impact the Group's financial position or performance.
FOR MORE INFORMATION, please visit the website www.caledoniamining.com or contact:
Enquiries
Caledonia Mining Corporation Plc Mark Learmonth | Tel: +44 1534 679 800 |
Cavendish Capital Markets Limited (Nomad and Broker) Adrian Hadden | Tel: +44 207 397 1965 |
Camarco, Financial PR (UK) Gordon Poole | Tel: +44 20 3757 4980 |
Curate Public Relations (Zimbabwe) Debra Tatenda | Tel: +263 77802131 |
IH Securities (Private) Limited (VFEX Sponsor - Zimbabwe) Lloyd Mlotshwa | Tel: +263 (242) 745 119/33/39 |
Craig James Harvey, MGSSA, MAIG, Caledonia Vice President, Technical Services, has reviewed and approved the scientific and technical information contained in this news release. Craig James Harvey is a "Qualified Person" as defined by each of (i) the Canadian Securities Administrators' National Instrument 43-101 - Standards of Disclosure for Mineral Projects and (ii) sub-part 1300 of Regulation S-K of the U.S. Securities Act.
Cautionary Note Concerning Forward-Looking Information
Information and statements contained in this news release that are not historical facts are "forward-looking information" within the meaning of applicable securities legislation that involve risks and uncertainties relating, but not limited, to Caledonia's current expectations, intentions, plans, and beliefs. Forward-looking information can often be identified by forward-looking words such as "anticipate", "believe", "expect", "goal", "plan", "target", "intend", "estimate", "could", "should", "may" and "will" or the negative of these terms or similar words suggesting future outcomes, or other expectations, beliefs, plans, objectives, assumptions, intentions or statements about future events or performance. Examples of forward-looking information in this news release include (but is not limited to): Caledonia's expectations with regard to entering into the Interim Funding Facility, raising the project finance necessary to construct the Project and ensuring the Group has the necessary financial capacity to complete the Project, expectations with respect to costs, the situation in the Middle East, improving the electricity situation at Blanket, as well as successful exploration at Motapa and Blanket. The forward-looking information contained in this news release is based, in part, on assumptions and factors that may change or prove to be incorrect, thus causing actual results, performance or achievements to be materially different from those expressed or implied by forward-looking information. Such factors and assumptions include, but are not limited to: the successful implementation of mine plans, the establishment of estimated resources and reserves, the grade and recovery of minerals which are mined varying from estimates, success of future exploration and drilling programs, reliability of drilling, sampling and assay data, the representativeness of mineralization being accurate, success of planned metallurgical test-work, capital availability and accuracy of estimated operating costs, obtaining required governmental, environmental or other project approvals, inflation, changes in exchange rates, fluctuations in commodity prices, delays in the development of projects and Caledonia's experience of project development in Zimbabwe and other factors.
To the extent any forward-looking information herein constitutes a financial outlook or future oriented financial information, any such statement is made as of the date hereof and included herein to provide prospective investors with an understanding of the Company's plans and assumptions. Security holders, potential security holders and other prospective investors should be aware that these statements are subject to known and unknown risks, uncertainties and other factors that could cause actual results to differ materially from those suggested by the forward-looking statements. Such factors include, but are not limited to: risks relating to estimates of mineral reserves and mineral resources proving to be inaccurate, fluctuations in gold price, risks and hazards associated with the business of mineral exploration, development and mining, risks relating to the credit worthiness or financial condition of suppliers, refiners and other parties with whom the Company does business; inadequate insurance, or inability to obtain insurance, to cover these risks and hazards, employee relations; relationships with and claims by local communities and indigenous populations; political risk; risks related to natural disasters, terrorism, civil unrest, public health concerns (including health epidemics or outbreaks of communicable diseases such as the coronavirus (COVID-19)); availability and increasing costs associated with mining inputs and labour; the speculative nature of mineral exploration and development, including the risks of obtaining or maintaining necessary licenses and permits, diminishing quantities or grades of mineral reserves as mining occurs; global financial condition, the actual results of current exploration activities, changes to conclusions of economic evaluations, and changes in project parameters to deal with unanticipated economic or other factors, risks of increased capital and operating costs, environmental, safety or regulatory risks, expropriation, the Company's title to properties including ownership thereof, increased competition in the mining industry for properties, equipment, qualified personnel and their costs, risks relating to the uncertainty of timing of events including targeted production rate increase and currency fluctuations. These risks are not exhaustive. Further information on these and other risks that could affect Caledonia's results is included in its filings with the Securities and Exchange Commission ("SEC"), including its Annual Report on Form 20-F for the last completed financial year, reports on Form 6-K for the most recently completed three and six month periods and the future reports that it may file from time to time with the SEC.Security holders, potential security holders and other prospective investors are cautioned not to place undue reliance on forward-looking information. By its nature, forward-looking information involves numerous assumptions, inherent risks and uncertainties, both general and specific, that contribute to the possibility that the predictions, forecasts, projections and various future events will not occur. Caledonia undertakes no obligation to update publicly or otherwise revise any forward-looking information whether as a result of new information, future events or other such factors which affect this information, except as required by law.
This news release is not an offer of the shares of Caledonia for sale in the United States or elsewhere. This news release shall not constitute an offer to sell or the solicitation of an offer to buy, nor shall there be any sale of the shares of Caledonia, in any province, state or jurisdiction in which such offer, solicitation or sale would be unlawful prior to registration or qualification under the securities laws of such province, state or jurisdiction.
Appendix A
Consolidated statements of profit or loss and other comprehensive income
(in thousands of United States Dollars, unless indicated otherwise)
For the years ended December 31 | 2025 | 2024 | ||||||
Revenue | 267,663 | 183,018 | ||||||
Royalty | (13,521 | ) | (9,263 | ) | ||||
Production costs | (101,321 | ) | (80,744 | ) | ||||
Depreciation | (15,697 | ) | (16,021 | ) | ||||
Gross profit | 137,124 | 76,990 | ||||||
Net foreign exchange loss | (3,311 | ) | (9,722 | ) | ||||
Administrative expenses | (20,480 | ) | (15,658 | ) | ||||
Fair value loss on derivative financial instrument | (6,379 | ) | (831 | ) | ||||
Equity-settled share-based expense | (203 | ) | (1,054 | ) | ||||
Cash-settled share-based expense | (839 | ) | (201 | ) | ||||
Other expenses | (5,078 | ) | (6,940 | ) | ||||
Other income | 248 | 1,090 | ||||||
Profit on the sale of non-current assets held for sale | 8,540 | - | ||||||
Operating profit | 109,622 | 43,674 | ||||||
Finance income | 461 | 26 | ||||||
Finance cost | (3,514 | ) | (3,157 | ) | ||||
Profit before tax | 106,569 | 40,543 | ||||||
Tax expense | (39,058 | ) | (17,489 | ) | ||||
Profit for the year | 67,511 | 23,054 | ||||||
Other comprehensive income | ||||||||
Items that are or may be reclassified to profit or loss | ||||||||
Exchange differences on translation of foreign operations | 1,109 | (116 | ) | |||||
Total comprehensive income for the year | 68,620 | 22,938 | ||||||
Profit attributable to: | ||||||||
Owners of the Company | 55,219 | 17,899 | ||||||
Non-controlling interests | 12,292 | 5,155 | ||||||
Profit for the year | 67,511 | 23,054 | ||||||
Total comprehensive income attributable to: | ||||||||
Owners of the Company | 56,328 | 17,783 | ||||||
Non-controlling interests | 12,292 | 5,155 | ||||||
Total comprehensive income for the year | 68,620 | 22,938 | ||||||
Earnings per share | ||||||||
Basic earnings per share ($) | 2.83 | 0.91 | ||||||
Diluted earnings per share ($) | 2.83 | 0.91 | ||||||
Appendix B
Consolidated statements of financial position
(in thousands of United States Dollars, unless indicated otherwise)
December 31, | December 31, | |||||||
As at | 2025 | 2024 | ||||||
Assets | ||||||||
Exploration and evaluation assets | 103,829 | 97,326 | ||||||
Property, plant and equipment | 204,538 | 189,456 | ||||||
Right of use assets | 1,089 | - | ||||||
Deferred tax asset | 230 | 264 | ||||||
Total non-current assets | 309,686 | 287,046 | ||||||
Income tax receivable | 8 | 355 | ||||||
Inventories | 26,828 | 23,768 | ||||||
Derivative financial assets | 8,227 | - | ||||||
Trade and other receivables | 11,871 | 12,675 | ||||||
Prepayments | 14,537 | 6,748 | ||||||
Fixed term deposit | 5,000 | - | ||||||
Cash and cash equivalents | 35,738 | 4,260 | ||||||
Assets held for sale | - | 13,512 | ||||||
Total current assets | 102,209 | 61,318 | ||||||
Total assets | 411,895 | 348,364 | ||||||
Equity and liabilities | ||||||||
Share capital | 166,329 | 165,408 | ||||||
Reserves | 138,254 | 138,465 | ||||||
Retained loss | (45,586 | ) | (89,996 | ) | ||||
Equity attributable to shareholders of the parent | 258,997 | 213,877 | ||||||
Non-controlling interests | 24,549 | 20,587 | ||||||
Total equity | 283,546 | 234,464 | ||||||
Liabilities | ||||||||
Deferred tax liabilities | 51,015 | 48,418 | ||||||
Provisions | 9,722 | 9,664 | ||||||
Loans and borrowings | 1,074 | 1,500 | ||||||
Loan note instruments | 3,981 | 8,313 | ||||||
Cash-settled share-based payment | 1,294 | 411 | ||||||
Lease liabilities | 911 | 199 | ||||||
Total non-current liabilities | 67,997 | 68,505 | ||||||
Cash-settled share-based payment | 1,116 | 634 | ||||||
Income tax payable | 351 | 2,958 | ||||||
Lease liabilities | 268 | 95 | ||||||
Loans and borrowings | 6,706 | 1,174 | ||||||
Loan note instruments | 7,760 | 855 | ||||||
Trade and other payables | 32,253 | 26,647 | ||||||
Overdrafts | 11,898 | 12,928 | ||||||
Liabilities associated with assets held for sale | - | 104 | ||||||
Total current liabilities | 60,352 | 45,395 | ||||||
Total liabilities | 128,349 | 113,900 | ||||||
Total equity and liabilities | 411,895 | 348,364 | ||||||
Appendix C
Consolidated statements of cash flows
(in thousands of United States Dollars, unless indicated otherwise)
2025 | 2024 | |||||||
Cash inflow from operations | 105,419 | 55,438 | ||||||
Interest received | 461 | 26 | ||||||
Finance costs paid | (3,073 | ) | (2,864 | ) | ||||
Tax paid | (26,574 | ) | (10,645 | ) | ||||
Net cash inflow from operating activities | 76,233 | 41,955 | ||||||
Cash flows used in investing activities | ||||||||
Acquisition of property, plant and equipment | (32,450 | ) | (27,477 | ) | ||||
Acquisition of exploration and evaluation assets | (3,633 | ) | (3,835 | ) | ||||
Proceeds from sale of property, plant and equipment | 17 | - | ||||||
Gross proceeds from sale of non-current assets held for sale | 22,350 | - | ||||||
Selling cost on sale of non-current assets held for sale | (384 | ) | - | |||||
Acquisition of put options | (5,430 | ) | (743 | ) | ||||
Investment in fixed term deposits | (28,500 | ) | - | |||||
Matured fixed term deposits | 23,500 | - | ||||||
Net cash used in investing activities | (24,530 | ) | (32,055 | ) | ||||
Cash flows from financing activities | ||||||||
Dividends paid | (19,916 | ) | (12,302 | ) | ||||
Payment of lease liabilities | (244 | ) | (182 | ) | ||||
Proceeds from loans and borrowings | - | 3,000 | ||||||
Repayments of loans and borrowings | (1,473 | ) | (326 | ) | ||||
Loan notes - solar bond issue gross receipts | 2,500 | 2,000 | ||||||
Loan notes - solar bond issue transaction cost | (113 | ) | (30 | ) | ||||
Proceeds from share options exercised | 95 | 37 | ||||||
Net cash used in financing activities | (19,151 | ) | (7,803 | ) | ||||
Net increase in cash and cash equivalents | 32,552 | 2,097 | ||||||
Effect of exchange rate fluctuations on cash and cash equivalents | (44 | ) | 267 | |||||
Net cash and cash equivalents at the beginning of the year | (8,668 | ) | (11,032 | ) | ||||
Net cash and cash equivalents at the end of the year | 23,840 | (8,668 | ) | |||||
SOURCE: Caledonia Mining Corporation Plc
View the original press release on ACCESS Newswire
FAQ
What were Caledonia (CMCL) preliminary FY 2025 revenue and profit figures reported on March 23, 2026?
How much gold did Blanket produce in FY 2025 and what is Caledonia's 2026 guidance (CMCL)?
What is Caledonia's declared dividend and payment date announced March 23, 2026 (CMCL)?
What does Caledonia report about Bilboes project progress and capital allocation for 2026 (CMCL)?
How did cash flow and the balance sheet change for Caledonia in FY 2025 (CMCL)?
What cost pressures did Caledonia (CMCL) report in FY 2025 and how did unit costs move?