Denison Reports Financial and Operational Results for Q1 2025, Highlighted by Continued Advancement of the Phoenix Project, and the Results of its Shareholder Meeting
- Engineering for Phoenix ISR project is 75% complete, supporting timeline for first production by mid-2028
- Strong financial position with 2.2M pounds U3O8 holdings, healthy cash balance, and zero debt
- CNSC hearing dates set for late 2025, supporting construction start in early 2026
- Strategic exploration joint ventures formed with Cosa Resources, including 19.95% ownership stake
- McClean North mining operations expected to commence in mid-2025 using SABRE method
- None.
Insights
Denison's regulatory progress, 75% engineering completion, and strong financial position keeps Phoenix uranium project on track for 2028 production.
Denison Mines has reached several critical milestones that significantly strengthen its position in the uranium development landscape. The CNSC's announcement of public hearing dates (October and December 2025) for the Phoenix ISR project represents a crucial final step in the regulatory approval process. With construction potentially starting in early 2026, Denison remains on schedule for first production by mid-2028, which would make Phoenix the first new large-scale uranium mine in northern Saskatchewan since Cigar Lake began operations in 2014.
The 75% completion of total engineering for Phoenix demonstrates substantial execution progress. The company has already funded
Denison's financial position is particularly noteworthy in the capital-intensive uranium development space. With 2.2 million pounds of physical uranium holdings, a strong cash balance, and zero debt, the company has effectively de-risked its funding position. This uranium inventory represents a significant asset that provides optionality – it can be monetized if needed for project funding or held as a potential hedge against future uranium price movements.
The advancement of the SABRE mining method at the McClean Lake Joint Venture offers Denison potential near-term production upside while the Phoenix project advances. SABRE represents an innovative mining approach that could potentially offer lower capital costs and greater operational flexibility compared to conventional mining methods.
The company's strategic partnerships with junior explorers Cosa Resources and Foremost Clean Energy provide low-cost optionality on exploration upside while allowing management to maintain focus on advancing Phoenix. Early positive results from these partnerships, including Cosa's two-kilometer extension of the Hurricane Trend and Foremost's new discovery at Hatchet Lake, validate this approach.
The board appointments of Ken Hartwick (former OPG CEO) and Jinsu Baik (KHNP Canada's nominee) strengthen Denison's nuclear industry connections, which could prove valuable for future uranium marketing efforts. The addition of Wes Carson from Wheaton Precious Metals brings mining operations expertise as the company transitions toward construction and operations.
Denison's Phoenix project demonstrates exceptional execution with 75% engineering completion and strategic procurement positioning it well for 2028 production.
Denison's Phoenix ISR uranium project is demonstrating exemplary project execution fundamentals that distinguish it from many mining development peers. The 75% completion of total engineering this early in the development cycle represents a sophisticated approach to de-risking the project before construction. By finalizing process design, P&IDs, HAZOPs, major equipment selection, and electrical infrastructure ahead of regulatory approvals, Denison is positioning itself to minimize the execution risks that typically plague mining projects.
The company's proactive approach to procurement is particularly noteworthy in today's challenging supply chain environment. Having already funded
The engagement of Wood Canada Limited for detailed engineering reflects a thoughtful approach to execution planning. Wood brings substantial experience in uranium processing facilities, which should translate to improved design quality and reduced construction rework. The scheduled completion of detailed engineering in Q3 2025 aligns perfectly with the anticipated regulatory approvals in late 2025, eliminating potential gaps between approval and execution readiness.
The planned deployment of the proprietary SABRE mining method at McClean North represents an important operational test case for this innovative extraction technology. If successful, this mining approach could potentially reshape economics for smaller uranium deposits throughout the Athabasca Basin. The site preparation activities indicate this initiative remains on schedule for mid-2025 operation.
From a project development perspective, Denison's transparent communication of its regulatory milestones, engineering progress, and capital commitments provides stakeholders with clear visibility into project status. The consistent messaging around first production in mid-2028 suggests the company has built appropriate contingency into its schedule, which is essential for complex nuclear projects subject to rigorous regulatory oversight.
David Cates, President and CEO of Denison commented, "With the Canadian Nuclear Safety Commission ('CNSC') announcing in Q1'2025 the scheduling of a public hearing ('Hearing') for our flagship Phoenix In-Situ Recovery ('ISR') project in late 2025, our focus for the remainder of the year has shifted to completion of the detailed design engineering phase and advancement of construction planning and procurement efforts. Our plans are designed to put us in a position to start construction in early 2026, following anticipated regulatory approvals. Based on this timeline, we expect to be able to maintain our previous guidance of first production from
By the end of Q1'2025, we have achieved approximately
At our McClean Lake Joint Venture ('MLJV') with Orano Canada, we are expecting 2025 to be a notable year with the commencement of mining at the McClean North deposit using the MLJV's patented Surface Access Borehole Resource Extraction ('SABRE') mining method. Thus far this year, site preparation activities have recommenced and we are expecting mining to commence in the coming months.
In addition to our planned investments in the Company's project development portfolio, we are working to amplify our exposure to exploration discovery. With that objective we entered into agreements with Cosa Resources Corp. ('Cosa') (TSX-V: COSA) in Q1'2025 and Foremost Clean Energy ('Foremost') (NASDAQ:FMST) (CSE:FAT) in Q4'2024, both of which involve collaborating on the exploration of several of Denison's non-core properties. Initial exploration results from this strategy are encouraging – as Cosa has already identified a two-kilometre strike extension of the Hurricane Trend through its initial drilling program at the Murphy Lake North uranium property, and Foremost has reported a new discovery of uranium mineralization at the
At the corporate level, during the quarter, we welcomed Ken Hartwick, who previously served as the CEO of Ontario Power Generation, and Jinsu Baik, KHNP Canada Energy Ltd.'s nominee, to the Denison board of directors. We believe Ken and Jinsu will bolster the breadth of nuclear industry and commercial knowledge on our Board and enhance its oversight during the critical process of
We are also pleased to welcome Wes Carson, Vice President, Mining Operations at Wheaton Precious Metals Corp., to the Denison board today, after his election at Denison's annual and special shareholders meeting. Wes enhances the depth of technical expertise on our Board, as he brings a wealth of mining industry experience and best practices, having held a variety of leadership roles in operations, project development, and engineering."
Highlights
- Regulatory Approval Hearing Dates set for the Phoenix ISR Project Supporting Guidance for First Production by First Half of 2028
The Canadian Nuclear Safety Commission ('CNSC') Registrar announced the schedule for the CNSC public hearing (the 'Hearing') for the Wheeler River Uranium Project ('Wheeler River'). The Hearing is scheduled to be held in two parts (October 8, 2025, and December 8 to 12, 2025) and represents the final step in the federal approval process for the Wheeler River Project's ('Project') Environmental Assessment ('EA') and the Licence to Prepare and Construct a Uranium Mine and Mill ('Licence'). The Hearing dates are expected to support commencement of construction in early 2026 and first production in the first half of 2028, consistent with past guidance.
The announcement of the Hearing schedule follows the successful completion of multiple key regulatory milestones in late 2024, including (i) completion of the technical review phase of the federal EA approval process in November, (ii) acceptance by the CNSC of the Company's final Environmental Impact Statement ('EIS') for the Project in December, and (iii) the CNSC's determination of the sufficiency of Denison's Licence application, also in November. These accomplishments indicate that the CSNC staff support the advancement of the Project and are transitioning their efforts to prepare an evidence-based summary report for the Commission members that will govern the Hearing and render their decision on the EA and Licence once the Hearing is complete.
- Achieved
75% Completion of Total Engineering forPhoenix
In January 2024, Denison awarded a contract to Wood Canada Limited ('Wood'), for the completion of a significant portion of the detailed design engineering for the Phoenix ISR project. The work commenced in the first quarter of 2024 and is expected to be substantially completed in the third quarter of 2025.
Total engineering completion at end of the first quarter of 2025 was approximately
- McClean Lake Joint Venture Advances Site Preparation Activities for Planned 2025 SABRE Mining Program
Site preparation activities have recommenced at McClean North in preparation for the 2025 SABRE mining program. Site development is on track to support the commencement of mining activities in mid-2025.
- Appointment of New Board Members
In March 2025, Denison announced the appointment of Ken Hartwick, who previously served as the CEO of Ontario Power Generation ('OPG'). Mr. Hartwick's appointment comes following the retirement from the Board of Brian Edgar, after having served as a Director of Denison and its predecessors for over 20 years. Denison also reported the appointment of Mr. Jinsu Baik to the Board, replacing Mr. Jong Ho Hong as KHNP Canada Energy Ltd.'s ('KHNP Canada') nominated director to the Board. Additionally, Mr. Wes Carson, Vice President, Mining Operations at Wheaton Precious Metals Corp., was appointed to the Board at the Corporation's annual and special shareholder meeting held on May 12, 2025.
- Formation of Exploration Joint Ventures with Cosa Resources Corp.
In January 2025, Denison completed an acquisition agreement with Cosa Resources Corp. ('Cosa') for Cosa to acquire a
2025 Annual & Special Shareholders Meeting
Denison is also pleased to report the passing of all items of business presented to shareholders at the Company's annual and special shareholders meeting held in
Nominee | Votes For | % For | Votes Withheld | % Withheld |
Jennifer Traub | 367,438,770 | 94.99 % | 19,399,921 | 5.01 % |
David Cates | 366,920,809 | 94.85 % | 19,917,881 | 5.15 % |
Jinsu Baik | 384,502,960 | 99.40 % | 2,335,731 | 0.60 % |
Wes Carson | 366,457,344 | 94.73 % | 20,381,346 | 5.27 % |
Ken Hartwick | 384,596,396 | 99.42 % | 2,242,294 | 0.58 % |
David Neuburger | 379,319,168 | 98.06 % | 7,519,522 | 1.94 % |
Laurie Sterritt | 378,238,679 | 97.78 % | 8,600,011 | 2.22 % |
Patricia Volker | 379,592,941 | 98.13 % | 7,245,749 | 1.87 % |
The Company has provided more details on the results of all matters considered at the Meeting in its Report of Voting Results which has been filed under its profile on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.gov/edgar.
About Denison
Denison Mines Corp. was formed under the laws of
Denison is a leading uranium mining, development, and exploration company with interests focused in the
Denison's interests in
Additionally, through its
In 2024, Denison celebrated its 70th year in uranium mining, exploration, and development, which began in 1954 with Denison's first acquisition of mining claims in the
Technical Disclosure and Qualified Person
The technical information contained in this press release has been reviewed and approved by Chad Sorba, P.Geo., Denison's Vice President Technical Services & Project Evaluation, who is a Qualified Persons in accordance with the requirements of NI 43-101.
CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING STATEMENTS
Certain information contained in this press release constitutes 'forward-looking information', within the meaning of the applicable
In particular, this press release contains forward-looking information pertaining to the following: projections with respect to exploration, development and expansion plans and objectives, including the scope, objectives and interpretations of the FS, PFS and the Wheeler River technical de-risking process for the proposed ISR operation for the
Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made, and they are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Denison to be materially different from those expressed or implied by such forward-looking statements. For example, the results and underlying assumptions and interpretations of the FS and PFS may not be maintained after further testing or be representative of actual conditions within the applicable deposits. In addition, Denison may decide or otherwise be required to discontinue testing, evaluation, engineering, and development work if it is unable to maintain or otherwise secure the necessary approvals or resources (such as testing facilities, capital funding, etc.). Denison believes that the expectations reflected in this forward-looking information are reasonable, but no assurance can be given that these expectations will prove to be accurate and results may differ materially from those anticipated in this forward-looking information. For a discussion in respect of risks and other factors that could influence forward-looking events, please refer to the Annual Information Form dated March 25, 2025 under the heading 'Risk Factors'. These factors are not, and should not be, construed as being exhaustive.
Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking information contained in this press release is expressly qualified by this cautionary statement. Any forward-looking information and the assumptions made with respect thereto speaks only as of the date of this press release. Denison does not undertake any obligation to publicly update or revise any forward-looking information after the date of this press release to conform such information to actual results or to changes in Denison's expectations except as otherwise required by applicable legislation.
View original content to download multimedia:https://www.prnewswire.com/news-releases/denison-reports-financial-and-operational-results-for-q1-2025-highlighted-by-continued-advancement-of-the-phoenix-project-and-the-results-of-its-shareholder-meeting-302453111.html
SOURCE Denison Mines Corp.