Ecopetrol and AES Colombia sign an agreement to build the Jemeiwaa Ka'I wind cluster in La Guajira
Ecopetrol has signed an Investment Framework Agreement with AES Colombia to acquire a 49% stake in the Jemeiwaa Ka'I wind cluster in La Guajira, Colombia. The project features:
- Total capacity of approximately 1,087 MW
- Location: Upper and middle Guajira, Uribia municipality
- 35 km transmission line included
Ecopetrol, Colombia's largest energy company, brings significant expertise to the project. The company:
- Employs over 19,000 people
- Controls 60% of Colombia's hydrocarbon production
- Leads in petrochemicals and gas distribution
- Owns 51.4% of ISA, expanding into power transmission
The deal remains subject to conditions and legal requirements. Upon completion, Ecopetrol will release additional information through appropriate channels.
Ecopetrol ha firmato un Accordo Quadro di Investimento con AES Colombia per acquisire una quota del 49% nel cluster eolico Jemeiwaa Ka'I situato a La Guajira, Colombia. Il progetto presenta:
- Una capacità totale di circa 1.087 MW
- Posizione: Alta e media Guajira, comune di Uribia
- Inclusa una linea di trasmissione di 35 km
Ecopetrol, la più grande compagnia energetica della Colombia, apporta al progetto una significativa esperienza. L'azienda:
- Impiegando oltre 19.000 persone
- Controlla il 60% della produzione di idrocarburi colombiana
- È leader nel settore della petrochimica e della distribuzione di gas
- Possiede il 51,4% di ISA, espandendosi nella trasmissione di energia
L'accordo è soggetto a condizioni e requisiti legali. Al completamento, Ecopetrol fornirà ulteriori informazioni attraverso i canali appropriati.
Ecopetrol ha firmado un Acuerdo Marco de Inversión con AES Colombia para adquirir una participación del 49% en el cluster eólico Jemeiwaa Ka'I en La Guajira, Colombia. El proyecto cuenta con:
- Una capacidad total aproximada de 1.087 MW
- Ubicación: Guajira alta y media, municipio de Uribia
- Línea de transmisión de 35 km incluida
Ecopetrol, la mayor empresa energética de Colombia, aporta una amplia experiencia al proyecto. La compañía:
- Emplea a más de 19.000 personas
- Controla el 60% de la producción de hidrocarburos en Colombia
- Es líder en petroquímica y distribución de gas
- Posee el 51,4% de ISA, expandiéndose en transmisión eléctrica
El acuerdo está sujeto a condiciones y requisitos legales. Al completarse, Ecopetrol divulgará información adicional a través de los canales correspondientes.
Ecopetrol은 콜롬비아 라 과히라에 위치한 제메이와 카이 풍력 클러스터의 49% 지분을 인수하기 위해 AES Colombia와 투자 기본 계약을 체결했습니다. 프로젝트 특징은 다음과 같습니다:
- 총 용량 약 1,087MW
- 위치: 과히라 상부 및 중부, 우리비아 시
- 35km 송전선 포함
콜롬비아 최대 에너지 기업인 Ecopetrol은 이 프로젝트에 풍부한 전문 지식을 제공합니다. 회사는:
- 19,000명 이상의 직원을 고용
- 콜롬비아 탄화수소 생산의 60%를 통제
- 석유화학 및 가스 배급 분야 선도
- ISA 지분 51.4% 보유, 전력 송전 분야로 확장 중
이 거래는 조건 및 법적 요구 사항에 따라 진행됩니다. 완료 시, Ecopetrol은 적절한 채널을 통해 추가 정보를 공개할 예정입니다.
Ecopetrol a signé un accord-cadre d'investissement avec AES Colombia pour acquérir une participation de 49 % dans le cluster éolien Jemeiwaa Ka'I à La Guajira, en Colombie. Le projet comprend :
- Une capacité totale d'environ 1 087 MW
- Emplacement : Haut et Moyen Guajira, municipalité d'Uribia
- Ligne de transmission de 35 km incluse
Ecopetrol, la plus grande entreprise énergétique de Colombie, apporte une expertise significative au projet. La société :
- Emploie plus de 19 000 personnes
- Contrôle 60 % de la production colombienne d'hydrocarbures
- Est leader dans la pétrochimie et la distribution de gaz
- Détient 51,4 % d'ISA, s'étendant à la transmission d'électricité
L'accord reste soumis à des conditions et exigences légales. Une fois finalisé, Ecopetrol communiquera des informations supplémentaires par les canaux appropriés.
Ecopetrol hat einen Investitionsrahmenvertrag mit AES Colombia unterzeichnet, um einen 49%igen Anteil am Jemeiwaa Ka'I Windcluster in La Guajira, Kolumbien, zu erwerben. Das Projekt umfasst:
- Eine Gesamtkapazität von etwa 1.087 MW
- Standort: Ober- und Mittelguajira, Gemeinde Uribia
- Eine 35 km lange Stromleitung ist enthalten
Ecopetrol, das größte Energieunternehmen Kolumbiens, bringt umfangreiche Expertise in das Projekt ein. Das Unternehmen:
- Beschäftigt über 19.000 Mitarbeiter
- Kontrolliert 60 % der kolumbianischen Kohlenwasserstoffproduktion
- Führt in der Petrochemie und Gasverteilung
- Besitzt 51,4 % von ISA und expandiert in die Stromübertragung
Der Vertrag unterliegt noch Bedingungen und rechtlichen Anforderungen. Nach Abschluss wird Ecopetrol weitere Informationen über die entsprechenden Kanäle bekannt geben.
- Strategic investment in renewable energy with 49% stake in 1,087 MW wind cluster project
- Geographic expansion in high-potential La Guajira region
- Diversification of energy portfolio beyond traditional oil & gas operations
- Partnership with established player AES Colombia strengthens project execution capability
- Vertical integration through 35 km transmission line ownership
- Significant capital expenditure required for wind project development
- Project completion subject to multiple conditions and legal requirements
- Execution risks in new renewable energy sector outside core business
- Potential regulatory hurdles in La Guajira region
Insights
Ecopetrol's agreement with AES Colombia to build 49% of the Jemeiwaa Ka'I wind cluster represents a significant diversification move for Colombia's largest hydrocarbon producer. With an approximate capacity of 1,087 MW and accompanying 35 km transmission line, this is a substantial renewable energy project in La Guajira.
The investment aligns with Ecopetrol's broader portfolio evolution beyond its traditional operations, where it currently controls over 60% of Colombia's hydrocarbon production. Following its acquisition of 51.4% of ISA's shares, Ecopetrol has already established positions in energy transmission across several South American countries.
While financial terms remain undisclosed and the deal is subject to conditions precedent, the scale suggests material capital commitment. The conditional nature of the agreement indicates several regulatory and financial hurdles must still be cleared before implementation.
The location in La Guajira is noteworthy as this region offers among Colombia's strongest wind resources. For Ecopetrol, which has built its business primarily on fossil fuels, this wind project represents a complementary asset that potentially reduces portfolio volatility through revenue diversification while positioning the company in the growing renewable sector.
The Jemeiwaa Ka'I wind cluster represents a substantial infrastructure commitment with its 1,087 MW capacity and 35 km transmission line. For context, a project of this scale would typically require investment in the hundreds of millions to low billions of dollars, though specific figures aren't disclosed in the announcement.
Ecopetrol's 49% ownership structure is strategically significant - it allows them meaningful participation without assuming full development and operational responsibilities, suggesting a balanced risk approach. The municipality of Uribia in La Guajira provides geographical advantages for wind generation, though infrastructure projects in this region have historically faced implementation challenges.
The conditional nature of this agreement - subject to "precedent conditions and legal requirements" - signals that regulatory approvals, financing arrangements, and possibly community agreements remain outstanding. These conditions create execution uncertainty despite the formal agreement.
For Ecopetrol, this investment extends their energy value chain beyond their traditional hydrocarbon focus and complements their existing energy transmission assets acquired through ISA. The development timeline and eventual operational date remain undisclosed, which limits assessment of near-term financial impact on Ecopetrol's performance. However, once operational, such assets typically provide stable, long-term cash flows with different risk profiles than extraction-based businesses.
Jemeiwaa Ka'I comprises a portfolio of wind projects located in the upper and middle Guajira, in the municipality of Uribia, with an approximate capacity of 1,087 MW, along with a 35 km transmission line.
Once the precedent conditions and legal requirements are met, Ecopetrol S.A. will publish the pertinent information in accordance with its respective legal regime, through this same medium and/or any other applicable channels
Ecopetrol is the largest company in
This release contains statements that may be considered forward-looking statements within the meaning of Section 27A of the
For more information, please contact:
Head of Capital Markets
Carolina Tovar Aragón
Email: investors@ecopetrol.com.co
Head of Corporate Communications (
Marcela Ulloa
Email: marcela.ulloa@ecopetrol.com.co
View original content to download multimedia:https://www.prnewswire.com/news-releases/ecopetrol-and-aes-colombia-sign-an-agreement-to-build-the-jemeiwaa-kai-wind-cluster-in-la-guajira-302427665.html