Electra Reactivates Construction at Cobalt Sulfate Refinery
Electra (NASDAQ: ELBM) has resumed construction at its brownfield cobalt sulfate refinery after securing approximately US$82 million in project financing, including about US$48 million in non-dilutive government support from U.S., Canadian and Ontario sources. The refinery is designed to produce 6,500 tonnes of battery-grade cobalt sulfate annually and targets commissioning in 2027. Key near-term work includes detailed engineering, HAZOP reviews, reactivation of mechanical/electrical/instrumentation systems, major tenders, site preparation, and construction mobilization in early 2026. Electra cites offtake with LG Energy Solution and feedstock agreements with Glencore and ERG, and says final capital estimates will be updated with a market update planned for January.
Electra (NASDAQ: ELBM) ha riavviato la costruzione del suo raffinatorio di solfato di cobalto di tipo brownfield dopo aver ottenuto circa US$82 milioni di finanziamento per il progetto, inclusi circa US$48 milioni di supporto governativo non diluitivo proveniente da fonti statunitensi, canadesi e dell'Ontario. La raffinineria è progettata per produrre 6.500 tonnellate di solfato di cobalto di grado batteria all'anno e punta al collaudo/avvio nel 2027. Le principali attività a breve termine includono ingegneria dettagliata, revisioni HAZOP, riattivazione dei sistemi meccanici/elettrici/di strumentazione, grandi appalti, preparazione del sito e mobilitazione della costruzione all'inizio del 2026. Electra cita contratti di vendita con LG Energy Solution e accordi di fornitura con Glencore e ERG, e afferma che le stime finali del capitale saranno aggiornate con un aggiornamento di mercato previsto per gennaio.
Electra (NASDAQ: ELBM) ha reanudado la construcción en su refinería de sulfato de cobalto existente brownfield tras asegurar aproximadamente US$82 millones en financiamiento del proyecto, incluyendo unos US$48 millones en apoyo gubernamental no dilutivo de EE. UU., Canadá y Ontario. La refinería está diseñada para producir 6,500 toneladas de sulfato de cobalto de grado batería al año y apunta a la puesta en servicio en 2027. Las tareas cercanas a corto plazo incluyen ingeniería detallada, revisiones HAZOP, reactivación de sistemas mecánicos/eléctricos/instrumentación, grandes licitaciones, preparación del sitio y movilización de la construcción a principios de 2026. Electra cita contratos de compra con LG Energy Solution y acuerdos de suministro con Glencore y ERG, y afirma que las estimaciones finales de capital se actualizarán con una actualización de mercado prevista para enero.
Electra (NASDAQ: ELBM)는 약 미화 8,200만 달러의 프로젝트 자금을 확보한 후 기존형 브라운필드 코발트 설페이트 정제소에서 건설 재개했고, 여기에는 미국, 캐나다 및 온타리오 출처의 비희석(non-dilutive) 정부지원 약 미화 4,800만 달러도 포함됩니다. 이 정제소는 매년 6,500톤의 배터리급 코발트 설페이트를 생산하도록 설계되었으며 2027년 가동 개시를 목표로 합니다. 단기간의 핵심 작업으로는 상세 설계, HAZOP 검토, 기계/전기/계측 시스템의 재가동, 주요 입찰, 현장 준비, 2026년 초의 건설 동원 등이 있습니다. Electra는 LG Energy Solution과의 수요처 계약 및 Glencore와 ERG와의 원료 공급 계약을 언급하며, 연간 자본 추정치는 1월에 예정된 시장 업데이트와 함께 업데이트될 예정이라고 말합니다.
Electra (NASDAQ: ELBM) a repris les travaux de construction sur son raffinerie de sulfate de cobalt brownfield après avoir sécurisé environ US$82 millions de financement de projet, dont environ US$48 millions en soutien gouvernemental non dilutif provenant des États‑Unis, du Canada et d’Ontario. La raffinerie est conçue pour produire 6 500 tonnes de sulfate de cobalt de qualité batterie par an et vise une mise en service en 2027. Les travaux clés à court terme incluent l’ingénierie détaillée, les revues HAZOP, la réactivation des systèmes mécaniques/électriques/instrumentation, de gros appels d’offres, la préparation du site et la mobilisation de la construction début 2026. Electra cite des accords d’achats avec LG Energy Solution et des accords d’approvisionnement avec Glencore et ERG, et indique que les estimations finales du capital seront mises à jour avec une mise à jour du marché prévue en janvier.
Electra (NASDAQ: ELBM) hat die Bauarbeiten an ihrem Brownfield-Standort für eine Kobalt-Sulfat-Raffinerie nach der Sicherung von ca. US$82 Millionen an Projektfinanzierung wieder aufgenommen, darunter ca. US$48 Millionen an nicht verwässerndem Regierungssupport aus den USA, Kanada und Ontario. Die Raffinerie ist ausgelegt, jährlich 6.500 Tonnen kobaltrotglSulfat herzustellen und strebt die Inbetriebnahme im Jahr 2027 an. Zu den kurzfristigen Kernarbeiten gehören detaillierte Planung, HAZOP-Prüfungen, Reaktivierung mechanischer/elektrischer/Instrumentation-Systeme, Großvergaben, Geländevorbereitung und der Baubeginn Anfang 2026. Electra nennt Abnahmen mit LG Energy Solution sowie Lieferverträge mit Glencore und ERG, und sagt, dass die endgültigen Kapitalabschätzungen mit einem im Januar geplanten Markupdate aktualisiert werden.
Electra (NASDAQ: ELBM) أَعادت تشغيل البناء في مصفاة كبريتات الكوبالت brownfield بعد تأمين نحو 82 مليون دولار أمريكي من تمويل المشروع، بما في ذلك نحو 48 مليون دولار من دعم حكومي غير مخفَّض من مصادر في الولايات المتحدة وكندا وأونتاريو. المصفاة مصممة لإنتاج 6,500 طن من كبريتات الكوبالت ذات الدرجة البطارية سنويًا وتستهدف التشغيل في عام 2027. الأعمال الأساسية القريبة تتضمن الهندسة التفصيلية ومراجعات HAZOP وإعادة تفعيل الأنظمة الميكانيكية/الكهروميكانيكية/القياس، ومناقصات كبيرة، وتحضير الموقع، وتعبئة البناء في أوائل 2026. تشير Electra إلى اتفاقيات شراء مع LG Energy Solution واتفاقيات توريد مع Glencore وERG، وتذكر أن التقديرات النهائية لرأس المال ستُحدَّث مع تحديث السوق المخطط في يناير.
- US$82 million of project financing secured
- US$48 million in non-dilutive government support
- 6,500 tonnes annual battery-grade cobalt sulfate capacity
- Offtake agreement with LG Energy Solution
- Feedstock agreements with Glencore and ERG
- Prior US$60 million re-baseline estimate being updated for inflation
- Targeted commissioning in 2027 leaves multi-year schedule risk
Insights
Electra resumed construction after securing ~
Electra restarts a brownfield cobalt sulfate refinery with permits, major equipment onsite, and a funded capital program including ~
Key dependencies and risks include finalizing updated capital estimates (the prior re-baseline was
TORONTO, Nov. 05, 2025 (GLOBE NEWSWIRE) -- Electra Battery Materials Corporation (NASDAQ: ELBM; TSX-V: ELBM) (“Electra” or the “Company”), a leader in advancing North America’s critical minerals processing, has resumed construction at its cobalt sulfate refinery following the arrangement of approximately US
This brownfield expansion positions Electra to complete North America’s first cobalt sulfate refinery, with permits and infrastructure in place, major equipment already on site, and supported by a fully funded capital program.
Highlights:
- Construction resumes at North America’s first cobalt sulfate refinery, a brownfield expansion fully funded for completion and commissioning.
- US
$82 million of financing secured, including US$48 million in support from the U.S., Canadian and Ontario governments. - The refinery is designed to produce 6,500 tonnes of battery-grade cobalt annually, supplying a critical input for North American defense and industrial applications.
“We have been building toward this moment for several years,” said Trent Mell, CEO. “Today, government support, private investment, and industrial policy are aligned to make completion of this refinery possible and to deliver a critical asset for North America. With the right team in place and a clear mandate, we are committed to driving this project through to completion. Once operational, this refinery will prove that midstream processing can be successfully onshored, creating a foundation for future growth.”
“This builds on the significant progress already achieved,” said Paolo Toscano, Vice President, Projects & Engineering. “Our focus is on disciplined execution, including completing detailed engineering, issuing key tenders, and ramping up site activity ahead of broader construction mobilization early next year. With infrastructure and equipment already in place, the restart of construction represents a major milestone for Electra. Our priorities remain safety, quality, and delivering the project on schedule as we target commissioning in 2027.”
Electra has engaged EXP to provide construction management support for the Construction Reactivation execution. Work is now underway to advance site preparations, reinstate mechanical, electrical, and instrumentation systems, and maintain project momentum through the winter.
Key program activities include:
- Finalizing detailed engineering, including completion of P&IDs, HAZOP reviews, and as-built mechanical scans.
- Restarting piping, electrical, and instrumentation work, including procurement and reactivation of critical mechanical and electrical components such as valves and control systems.
- Issuing major mechanical, electrical, and instrumentation packages for tender and award of the contract.
- Upgrading existing conveyor systems and electrical infrastructure to align with the updated design.
- Advancing project controls, budget and schedule updates, and logistics planning to support full construction mobilization in early 2026.
- Site preparation and materials handling installations, including laydown areas, warehousing, and logistics support for equipment and materials.
The workforce is expected to increase substantially once major mechanical, electrical, and instrumentation contracts are awarded, positioning the site for full-scale construction in early 2026. The Company’s team is currently reviewing the construction schedule and capital estimates. The previous 2023 re-baseline estimate of US
The restart of construction marks a key milestone in Electra’s strategy to onshore the midstream of North America’s critical minerals supply chain. Once commissioned, the refinery will be the only cobalt sulfate production facility in North America and one of just two major facilities outside China, capable of producing 6,500 tonnes of battery-grade cobalt sulfate annually. Its output will supply a critical input for lithium-ion battery manufacturing and strengthen domestic industrial, defense, and energy storage supply chain resilience.
The construction and commissioning of Electra’s cobalt refinery project is fully funded through a combination of equity financing, as announced in October 2025, and government support. It has received previously announced commitments totaling approximately US
Electra has an offtake arrangement with LG Energy Solution, one of the world’s largest battery manufacturers, underscoring its strategic role in the North American battery materials supply chain. The refinery will process responsibly sourced cobalt feedstock supplied by Glencore and Eurasian Resources Group (ERG), with whom Electra already has commercial agreements in place, into high-purity cobalt sulfate that meets the stringent specifications of tier-one battery cell manufacturers. Test work is also underway on North American feedstocks, including cobalt from the Idaho Cobalt Belt, to assess their suitability for future processing. The refinery features a modular and flexible design to accommodate future expansion opportunities.
Electra’s operations are aligned with U.S. and Canadian industrial policy aimed at reshoring critical minerals processing, strengthening economic and national security, and reducing dependence on overseas supply chains. As part of a broader vision for a vertically integrated critical minerals supply chain, the refinery provides a crucial midstream link connecting upstream mining to downstream cell manufacturing in North America.
About Electra Battery Materials
Electra is a leader in advancing North America’s critical minerals supply chain for lithium-ion batteries. The Company’s primary focus is constructing North America’s only cobalt sulfate refinery, as part of a phased strategy to onshore critical minerals refining and reduce reliance on foreign supply chains. In addition to the Refinery, Electra holds a significant land package in Idaho’s Cobalt Belt, including its Iron Creek project and surrounding properties, positioning the Company as a potential cornerstone for North American cobalt and copper production.
Electra is also advancing black mass recycling opportunities to recover critical materials from end-of-life batteries, while continuing to evaluate growth opportunities in nickel refining and other downstream battery materials. For more information, please visit www.ElectraBMC.com.
Contact
Heather Smiles
Vice President, Investor Relations & Corporate Development
Electra Battery Materials
info@ElectraBMC.com
1.416.900.3891
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Cautionary Note Regarding Forward-Looking Statements
This news release may contain forward-looking statements and forward-looking information (together, “forward-looking statements”) within the meaning of applicable securities laws and the United States Private Securities Litigation Reform Act of 1995. All statements, other than statements of historical facts, are forward-looking statements,. including those concerning the completion of funding from the Government of Canada and Invest Ontario, Generally, forward-looking statements can be identified by the use of terminology such as “plans”, “expects”, “estimates”, “intends”, “anticipates”, “believes” or variations of such words, or statements that certain actions, events or results “may”, “could”, “would”, “might”, “occur” or “be achieved”. Forward-looking statements are based on certain assumptions, and involve risks, uncertainties and other factors that could cause actual results, performance, and opportunities to differ materially from those implied by such forward-looking statements. Among the bases for assumptions with respect to the potential for additional government funding are discussions and indications of support from government actors based on certain milestones being achieved. Factors that could cause actual results to differ materially from these forward-looking statements are set forth in the management discussion and analysis and other disclosures of risk factors for Electra Battery Materials Corporation, filed on SEDAR+ at www.sedarplus.com and with EDGAR at www.sec.gov. Other factors that could lead actual results to differ materially include changes with respect to government or investor expectations or actions as compared to communicated intentions, and general macroeconomic and other trends that can affect levels of government or private investment. Although the Company believes that the information and assumptions used in preparing the forward-looking statements are reasonable, undue reliance should not be placed on these statements, which only apply as of the date of this news release, and no assurance can be given that such events will occur in the disclosed times frames or at all. Except where required by applicable law, the Company disclaims any intention or obligation to update or revise any forward-looking statement, whether as a result of new information, future events or otherwise.