The Illuminating Company Marks Reliability Milestone with Two New Transformers in Lakewood

(Neutral)
(Neutral)
Tags

FirstEnergy (NYSE: FE) announced that The Illuminating Company delivered the first of two new 55-ton transformers to the Lakewood Substation, each representing about $1.85 million in investment. Once both are energized later in 2026, the project is expected to enhance reliability for nearly 11,000 customers in Lakewood and West Cleveland.

The work supports broader upgrades, including breaker replacements, pole-top equipment improvements, smart meter installations, and proactive tree trimming, which have already helped cut December 2025 outage time by 98% versus December 2024 and reduced overall outage time on local lines by 25%.

Loading...
Loading translation...

Positive

  • Approximately $3.7 million invested in two new Lakewood transformers
  • Reliability improvements expected for nearly 11,000 Lakewood and West Cleveland customers
  • December 2025 outage time down 98% versus December 2024
  • Local lines served by Lakewood Substation saw 25% decrease in outage time
  • Equipment upgrades completed on or around 167 utility poles since October 2024
  • Proactive tree trimming at nearly 100 locations to reduce outage risk

Negative

  • None.

News Market Reaction – FE

+0.40%
+0.40% News Effect

On the day this news was published, FE gained 0.40%, reflecting a mild positive market reaction.

Data tracked by StockTitan Argus on the day of publication.

Market Context

This announcement highlights concrete reliability upgrades in Lakewood, including two new transforme...
Analysis

This announcement highlights concrete reliability upgrades in Lakewood, including two new transformers and a 98% drop in outage time. It fits FirstEnergy’s broader grid investment strategy, with ongoing capital needs under its $3.0B shelf a key risk to monitor.

Key Figures

Transformer weight: 55 tons Transport distance: 500 miles Transformer investment: $1.85 million +5 more
8 metrics
Transformer weight 55 tons Single new transformer delivered to Lakewood Substation
Transport distance 500 miles Truck haul from Roanoke, VA, to Lakewood Substation over five days
Transformer investment $1.85 million Approximate cost per transformer including equipment, transport and installation
Customers impacted 11,000 customers Lakewood Substation reliability upgrades expected to benefit these customers
Pole equipment work 167 poles Neighborhood pole equipment work completed since October 2024
Tree trimming sites 100 locations Proactive pruning to reduce outages from falling limbs
Outage time reduction 98% Drop in total outage time in December 2025 vs. December 2024
Lakewood outage decrease 25% Decrease in overall outage time on lines served by Lakewood Substation

Historical Context

5 past events · Latest: Jun 18 (Neutral)
Pattern 5 events
Date Event Sentiment 24h Move Catalyst
Jun 18 Leadership changes Neutral +0.7% Senior leadership appointments focused on transformation, ethics, compliance and security.
Jun 17 Leadership changes Neutral +0.7% New senior leaders appointed to drive operations, safety and technology performance.
Jun 17 Storm preparedness Neutral +0.7% Ohio utilities detailed readiness and resources for potential severe‑weather outages.
Jun 17 Storm preparedness Neutral -3.3% Pennsylvania utilities preparing for a fourth severe storm system in 12 days.
Jun 02 Debt exchange offer Neutral -0.1% Extension of exchange offer for multiple JCP&L senior note series.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

Pattern Detected

Recent operational and financing news has usually led to small moves, with one larger negative reaction to storm‑related grid commentary.

Key Terms

smart meters, mobile substation, transmission lines, investor-owned electric systems
4 terms
smart meters technical
"Smart Meter Installations: We've started to install smart meters, a step toward a more modernized electric system"
Smart meters are digital devices that replace traditional utility meters to record and transmit electricity, gas, or water use in near real time. Like a fitness tracker for a home’s energy, they give detailed, time-stamped usage data and can communicate with the utility to enable remote readings and demand management. Investors care because smart meters change revenue and cost dynamics for utilities, enable new services and tariffs, and drive spending on infrastructure, data analytics, and cybersecurity.
mobile substation technical
"the mobile substation will continue operating until the new equipment is fully installed and energized"
A mobile substation is a self-contained, truck- or trailer-mounted unit that temporarily does the job of a fixed electrical substation — stepping voltage up or down and routing power so electricity keeps flowing during repairs, upgrades, or outages. For investors it signals how a utility or grid operator manages reliability and project timing: using mobile substations can shorten outages, reduce costly delays, and affect capital and operating costs much like renting a spare piece of critical machinery instead of waiting for a permanent replacement.
transmission lines technical
"The company's transmission subsidiaries operate more than 24,000 miles of transmission lines"
High-voltage towers and cables that carry electricity from power plants to cities and substations, like highways that move energy rather than cars. For investors, transmission lines are long-lived, capital-intensive assets whose condition, capacity and regulatory treatment affect utility revenues, reliability and the ability to connect new generation; bottlenecks or upgrades can change costs, permit timelines and future returns.
investor-owned electric systems financial
"one of the nation's largest investor-owned electric systems, serving more than six million customers"
Investor-owned electric systems are private, for-profit companies that generate, transmit or distribute electricity and are owned by shareholders rather than by the government or customers. They matter to investors because their earnings depend on regulated rates, infrastructure spending and customer demand—similar to a landlord who earns rent for maintaining a building—so changes in regulation, rate approvals or large capital projects can directly affect profits, dividends and stock value.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Equipment supports ongoing reliability improvements to help reduce outages for customers

LAKEWOOD, Ohio, June 25, 2026 /PRNewswire/ -- FirstEnergy Corp. (NYSE: FE) electric company The Illuminating Co. has reached a key milestone in its efforts to improve electric reliability in Lakewood and West Cleveland with the delivery of its first new transformer to the Lakewood Substation. Transformers are critical pieces of equipment that regulate voltage and help deliver electricity safely and reliably to homes and businesses.

The transformer, weighing about 55 tons (equivalent to nine adult elephants), was transported by truck from Roanoke, VA, to the substation on Athens Avenue – nearly 500 miles and a five-day commute – and lifted into place by crane. The installation marks a visible step forward in a broader plan to strengthen the local electric system and help improve reliability for nearly 11,000 customers.

A second, identical transformer will be delivered to a local Illuminating Co. service center the week of June 29 before being moved to the Lakewood Substation later this summer. Each transformer represents an approximately $1.85 million investment, including equipment, transportation, installation, etc.

"The delivery of these transformers is an important step in building a stronger, more resilient electric system for Lakewood," said Torrence Hinton, President of FirstEnergy Ohio. "Our customers depend on reliable power, and these investments will help us deliver on that commitment and support the community's future needs."

Building Better Reliability for Customers
Once both transformers are installed at the Lakewood Substation, customers can expect improved grid reliability, including the potential for reduced outage durations and faster service restoration times.

The substation will also gain greater back up capacity. This added flexibility gives crews more options to shift load and restore power more efficiently during outages and periods of peak demand.

In addition to improving reliability for customers directly served by the Lakewood Substation, this upgrade may also benefit surrounding communities. With increased capacity and flexibility, Lakewood circuits could potentially be used to help restore service to customers supplied by neighboring substations during outages, further strengthening overall system reliability in the area.

Investments Already Making a Difference
The transformer installations are part of a series of upgrades already improving reliability in the Lakewood area, including:

  • Substation Upgrades: All four breakers have been replaced at a substation serving Lakewood, which helps strengthen the equipment that supplies power to Lakewood.
  • Neighborhood Equipment Upgrades: Crews have resolved voltage issues in several areas and continue replacing equipment on neighborhood utility poles to improve reliability and reduce the risk of outages. Since October 2024, we've completed work on equipment atop or around 167 poles.
  • Smart Meter Installations: We've started to install smart meters, a step toward a more modernized electric system that will enable automated meter readings and enhance our ability to respond to outages faster and more efficiently.
  • Proactive Tree Trimming: Crews have pruned trees in nearly 100 locations ahead of schedule to reduce outages caused by falling limbs, a top cause for outages in Ohio.

Recent work has also reduced the length of outages for customers, with the total time customers were without power dropping by 98% in December 2025 compared with December 2024. Local power lines served by the Lakewood Substation have also seen a 25% decrease in overall outage time.

What's Next
Crews will now begin the work to complete transformer installation in the coming weeks, and the transformers are on track to be energized later this year. To maintain service during construction, the mobile substation will continue operating until the new equipment is fully installed and energized.

The Illuminating Company serves more than 750,000 customers across Ashtabula, Cuyahoga, Geauga, Lake and Lorain counties. Follow The Illuminating Company on X @IlluminatingCo and on Facebook at facebook.com/IlluminatingCo.

FirstEnergy is dedicated to integrity, safety, reliability and operational excellence. Its electric distribution companies form one of the nation's largest investor-owned electric systems, serving more than six million customers in Ohio, Pennsylvania, New Jersey, West Virginia, Maryland and New York. The company's transmission subsidiaries operate more than 24,000 miles of transmission lines that connect the Midwest and Mid-Atlantic regions. Follow FirstEnergy online at firstenergycorp.com and on X @FirstEnergyCorp.

Editor's Note: Images and video of the transformer delivery are available to download from Flickr.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/the-illuminating-company-marks-reliability-milestone-with-two-new-transformers-in-lakewood-302811187.html

SOURCE FirstEnergy Corp.

FAQ

What did FirstEnergy (FE) announce about new transformers in Lakewood on June 25, 2026?

FirstEnergy announced delivery of the first of two new transformers for the Lakewood Substation. According to FirstEnergy, each 55-ton unit costs about $1.85 million and is part of a wider reliability program for nearly 11,000 customers in Lakewood and West Cleveland.

How will the new Lakewood transformers affect outage reliability for FE customers?

The new transformers are expected to improve grid reliability and service restoration times. According to FirstEnergy, added backup capacity will give crews more flexibility to shift load, reduce outage durations, and support neighboring substations during peak demand or outage events.

When will the two new Lakewood transformers for FirstEnergy be fully energized?

Both transformers are planned to be energized later in 2026 after installation work is completed. According to FirstEnergy, a mobile substation will maintain service during construction until the new equipment is fully installed, tested, and placed into regular operation.

How much is FirstEnergy investing in the new Lakewood transformers (FE stock)?

FirstEnergy reports each transformer represents about $1.85 million in investment, including equipment, transport, and installation. According to FirstEnergy, the two units total roughly $3.7 million, aimed at strengthening the local electric system for Lakewood and West Cleveland customers.

What other reliability upgrades has The Illuminating Company made in Lakewood for FE customers?

The Illuminating Company has replaced four breakers at a substation, upgraded equipment on 167 poles, started smart meter installations, and pruned trees at nearly 100 locations. According to FirstEnergy, these steps support reduced outage risk and faster restoration in Lakewood.

How have outage times changed for Lakewood-area FirstEnergy customers?

Outage durations have already declined before the new transformers are energized. According to FirstEnergy, total customer outage time fell 98% in December 2025 versus December 2024, while local lines served by the Lakewood Substation saw a 25% reduction in overall outage time.

How many customers does The Illuminating Company serve within FirstEnergy’s FE network?

The Illuminating Company serves more than 750,000 customers in five Ohio counties. According to FirstEnergy, its broader electric distribution companies collectively serve over six million customers across Ohio, Pennsylvania, New Jersey, West Virginia, Maryland, and New York.