Fortuna Advances Diamba Sud Gold Project in Senegal with Updated Mineral Resources; PEA Completion Targeted for Q4 2025
Fortuna Mining (NYSE: FSM) has announced an updated Mineral Resource estimate for its Diamba Sud Gold Project in Senegal as of July 7, 2025. The project now contains 724,000 gold ounces in Indicated Resources (14.2 Mt at 1.59 g/t gold), representing a 53% increase from year-end 2024, and 285,000 gold ounces in Inferred Resources (6.2 Mt at 1.44 g/t gold), showing a 93% increase.
The update includes first-time Inferred Resource estimates for two new deposits: Southern Arc (194,000 ounces) and Moungoundi (31,000 ounces). The estimate incorporates data from 243 new drill holes totaling 31,652 meters completed between July 2024 and July 2025. A Preliminary Economic Analysis (PEA) is underway, with completion targeted for Q4 2025.
Fortuna Mining (NYSE: FSM) ha annunciato un aggiornamento della stima delle Risorse Minerarie per il suo Progetto Aurifero Diamba Sud in Senegal, aggiornato al 7 luglio 2025. Il progetto ora contiene 724.000 once d'oro in Risorse Indicate (14,2 Mt a 1,59 g/t oro), rappresentando un aumento del 53% rispetto alla fine del 2024, e 285.000 once d'oro in Risorse Inferred (6,2 Mt a 1,44 g/t oro), con un incremento del 93%.
L'aggiornamento include per la prima volta stime di Risorse Inferred per due nuovi giacimenti: Southern Arc (194.000 once) e Moungoundi (31.000 once). La stima incorpora dati provenienti da 243 nuovi fori di sondaggio per un totale di 31.652 metri, completati tra luglio 2024 e luglio 2025. È in corso un'Analisi Economica Preliminare (PEA), con completamento previsto per il quarto trimestre del 2025.
Fortuna Mining (NYSE: FSM) ha anunciado una actualización de la estimación de Recursos Minerales para su Proyecto de Oro Diamba Sud en Senegal al 7 de julio de 2025. El proyecto ahora contiene 724,000 onzas de oro en Recursos Indicados (14.2 Mt a 1.59 g/t de oro), lo que representa un aumento del 53% respecto a finales de 2024, y 285,000 onzas de oro en Recursos Inferidos (6.2 Mt a 1.44 g/t de oro), mostrando un incremento del 93%.
La actualización incluye por primera vez estimaciones de Recursos Inferidos para dos nuevos depósitos: Southern Arc (194,000 onzas) y Moungoundi (31,000 onzas). La estimación incorpora datos de 243 nuevos taladros que suman 31,652 metros, completados entre julio de 2024 y julio de 2025. Se está llevando a cabo un Análisis Económico Preliminar (PEA), con finalización prevista para el cuarto trimestre de 2025.
Fortuna Mining (NYSE: FSM)은 2025년 7월 7일 기준 세네갈 디암바 수드 금 프로젝트의 최신 광물 자원 추정치를 발표했습니다. 이 프로젝트는 현재 724,000 온스의 금을 표시 자원(14.2 Mt, 금 함량 1.59 g/t)으로 보유하고 있으며, 2024년 말 대비 53% 증가한 수치입니다. 또한 285,000 온스의 금을 추정 자원(6.2 Mt, 금 함량 1.44 g/t)으로 보유하고 있으며, 93% 증가를 보여줍니다.
이번 업데이트에는 신규 매장지 두 곳인 Southern Arc(194,000 온스)와 Moungoundi(31,000 온스)에 대한 추정 자원이 처음으로 포함되었습니다. 이 추정치는 2024년 7월부터 2025년 7월까지 완료된 243개의 신규 시추공 총 31,652미터의 데이터를 반영한 것입니다. 현재 예비 경제성 분석(PEA)이 진행 중이며, 2025년 4분기 완료를 목표로 하고 있습니다.
Fortuna Mining (NYSE: FSM) a annoncé une mise à jour de l'estimation des ressources minérales de son projet aurifère Diamba Sud au Sénégal, en date du 7 juillet 2025. Le projet contient désormais 724 000 onces d'or en ressources indiquées (14,2 Mt à 1,59 g/t or), soit une augmentation de 53 % par rapport à la fin 2024, et 285 000 onces d'or en ressources inférées (6,2 Mt à 1,44 g/t or), affichant une hausse de 93 %.
La mise à jour inclut pour la première fois des estimations de ressources inférées pour deux nouveaux gisements : Southern Arc (194 000 onces) et Moungoundi (31 000 onces). L'estimation intègre les données de 243 nouveaux forages totalisant 31 652 mètres, réalisés entre juillet 2024 et juillet 2025. Une analyse économique préliminaire (PEA) est en cours, avec une finalisation prévue au quatrième trimestre 2025.
Fortuna Mining (NYSE: FSM) hat eine aktualisierte Schätzung der Mineralressourcen für sein Diamba Sud Goldprojekt in Senegal zum 7. Juli 2025 veröffentlicht. Das Projekt enthält nun 724.000 Unzen Gold in den angezeigten Ressourcen (14,2 Mio. Tonnen mit 1,59 g/t Gold), was eine Steigerung von 53 % gegenüber Ende 2024 bedeutet, sowie 285.000 Unzen Gold in den abgeleiteten Ressourcen (6,2 Mio. Tonnen mit 1,44 g/t Gold), was eine Erhöhung um 93 % darstellt.
Das Update umfasst erstmals Schätzungen der abgeleiteten Ressourcen für zwei neue Lagerstätten: Southern Arc (194.000 Unzen) und Moungoundi (31.000 Unzen). Die Schätzung basiert auf Daten von 243 neuen Bohrlöchern mit insgesamt 31.652 Metern, die zwischen Juli 2024 und Juli 2025 abgeschlossen wurden. Eine vorläufige Wirtschaftlichkeitsanalyse (PEA) ist im Gange und soll im vierten Quartal 2025 abgeschlossen werden.
- Indicated Resources increased by 53% to 724,000 gold ounces
- Inferred Resources grew by 93% to 285,000 gold ounces
- Two new deposits added to resource estimate: Southern Arc (194,000 oz) and Moungoundi (31,000 oz)
- Higher long-term gold price assumption of $2,600/oz improving project economics
- PEA completion not expected until Q4 2025
- Resources remain in Indicated and Inferred categories, with no Measured Resources yet established
Insights
Fortuna's 53% increase in indicated gold resources at Diamba Sud significantly expands project scale and economic potential ahead of 2025's PEA.
Fortuna Mining's updated mineral resource estimate for its Diamba Sud Gold Project in Senegal represents a substantial enhancement to the project's scale and value proposition. The 53% increase in Indicated Resources to
The resource growth stems from both effective infill drilling that upgraded existing resources and expansion drilling that delivered entirely new deposits. The maiden resource estimates for Southern Arc (
The quality of these resources appears robust, with consistent grades averaging 1.59 g/t gold for Indicated and 1.44 g/t for Inferred material. These grades are commercially viable in an open-pit mining scenario, especially considering the
The planned Preliminary Economic Assessment in Q4 2025 will be the crucial next step, as it will translate these geological resources into potential economic values by incorporating mining methods, processing recoveries, capital requirements, and operating costs. The diverse deposit portfolio now consisting of seven distinct zones provides operational flexibility that could optimize the eventual mining plan.
What's particularly promising is that mineralization remains open at Southern Arc, suggesting further resource growth potential from the planned Q4 2025 drilling campaign. The methodical approach to resource estimation, with appropriate drilling density (25m grid for Indicated, 50m for Inferred) and robust QA/QC protocols, provides confidence in the reliability of these figures.
VANCOUVER, British Columbia, Aug. 05, 2025 (GLOBE NEWSWIRE) -- Fortuna Mining Corp. (NYSE: FSM | TSX: FVI) is pleased to report an updated Mineral Resource estimate as of July 7, 2025, for the Diamba Sud Gold Project located in Senegal. All dollar amounts in this news release are expressed in US dollars.
Highlights of the Inpit Mineral Resource Update
- Indicated Mineral Resource of 724,000 gold ounces, representing a 53 percent increase since year-end 2024
- Inferred Mineral Resource of 285,000 gold ounces, reflecting a 93 percent increase since year-end 2024
- Initial Inferred Mineral Resource estimates for the Southern Arc and Moungoundi deposits, containing 194,000 ounces and 31,000 ounces of gold, respectively
- Preliminary Economic Analysis (PEA) underway, with completion targeted for the fourth quarter of 2025
- Exploration drilling at Southern Arc continues focusing on:
- Infilling drilling to upgrade Inferred Resources
- Expansion drilling where mineralization remains open at shallow depths to the south and east of the defined deposit limits
Diamba Sud Gold Project, Senegal
Fortuna estimates that the Diamba Sud Gold Project comprises an Indicated Mineral Resource of 14.2 Mt at an average gold grade of 1.59 g/t, containing 724,000 ounces of gold, and an Inferred Mineral Resource of 6.2 Mt at an average gold grade of 1.44 g/t containing 285,000 ounces of gold.
The updated Mineral Resource estimate is based on new drilling completed between July 2024 to July 2025, comprising 243 holes totaling 31,652 meters. The data collected improved the geological interpretation and resource modelling for Area A, Area D, Karakara, Western Splay, and Kassassoko. It also contributed to the expansion of Diamba Sud´s pipeline of emerging deposits, with the first-time resource estimates for Southern Arc and Moungoundi. Expansion drilling at these deposits, along with the drilling of new targets, is planned for the fourth quarter of 2025.
Changes from the previous estimate are due to the following:
- Infill drilling at Area A, Area D, Karakara, Western Splay, and Kassassoko improved the geological interpretation and supported the conversion of Inferred Resources to Indicated Resources
- Exploration drilling at Southern Arc and Moungoundi resulted in the first-time estimation of Inferred Mineral Resources
- An increase in the long-term gold price assumption, now at
$2,600 /oz, along with refinements to projected mining and processing costs, contributed to updated pit shell optimization and cut-off grade determination
Diamba Sud Gold Project Mineral Resources by deposit
Mineral Resources – Indicated | Contained Metal | |||
Classification | Deposit | Tonnes (000) | Au (g/t) | Au (koz) |
Indicated | Area A | 3,891 | 1.47 | 184 |
Area D | 4,877 | 1.75 | 274 | |
Karakara | 2,476 | 1.79 | 143 | |
Western Splay | 1,615 | 1.65 | 86 | |
Kassassoko | 1,294 | 0.90 | 38 | |
Total Indicated | 14,153 | 1.59 | 724 |
Mineral Resources – Inferred | Contained Metal | |||
Classification | Deposit | Tonnes (000) | Au (g/t) | Au (koz) |
Inferred | Area A | 61 | 1.02 | 2 |
Area D | 600 | 1.10 | 21 | |
Karakara | 510 | 1.61 | 26 | |
Western Splay | 101 | 2.11 | 7 | |
Kassassoko | 123 | 0.85 | 3 | |
Southern Arc | 3,854 | 1.57 | 194 | |
Moungoundi | 922 | 1.06 | 31 | |
Total Inferred | 6,171 | 1.44 | 285 |
Notes:
- Mineral Reserves and Mineral Resources are as defined by the 2014 CIM Definition Standards for Mineral Resources and Mineral Reserves
- Mineral Resources are exclusive of Mineral Reserves.
- Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
- Factors that could materially affect the reported Mineral Resources include changes in metal price and exchange rate assumptions; changes in local interpretations of mineralization; changes to assumed metallurgical recoveries, mining dilution and recovery; and assumptions as to the continued ability to access the site, extend and/or retain mineral and surface rights, titles and permits, maintain environmental and other regulatory permits, and maintain the social license to operate.
- Mineral Resources are reported as of July 7, 2025.
- Mineral Resources for Diamba Sud are reported pit constrained on a
100% ownership basis at selective mining unit block sizes and at an incremental gold cutoff grade for oxide/transitional material of 0.31 g/t Au, with fresh material reported based on a cutoff of 0.35 g/t Au for Area A, 0.42 g/t Au for Area D, 0.35 g/t Au for Karakara, 0.41 g/t Au for Western Splay, 0.35 g/t Au for Kassassoko, 0.37 g/t Au for Southern Arc, and 0.39 g/t Au for Moungoundi in accordance with the varying ore differential parameters and varying metallurgical recoveries for oxide, transitional and fresh rock within pit shell optimizations, assuming a long-term gold metal price of$2,600 /oz and metallurgical recoveries based on metallurgical testwork. - Eric Chapman, P. Geo. (EGBC #36328), is the Qualified Person responsible for Mineral Resources, being an employee of Fortuna Mining Corp.
- Totals may not add due to rounding
The Mineral Resource is comprised of seven deposits: Area A, Area D, Karakara, Western Splay, Kassassoko, Southern Arc, and Moungoundi. It incorporates data from a total of 1,178 diamond and reverse circulation (RC) drill holes, totaling 154,814 meters, completed at these deposits since 2019 (see Figure 1).
Figure 1: Location of Deposits Included in the Mineral Resource Estimate
All RC drilling at Diamba Sud was conducted using a 5.25-inch face sampling pneumatic hammer, with samples collected into 60-liter plastic bags. To maintain sample integrity, sufficient air pressure was used to keep samples dry and prevent groundwater inflow. If water ingress exceeded air pressure capacity, RC drilling was halted, and drilling converted to diamond core tails. Samples were collected at 1-meter intervals from an onboard cyclone and split on site to produce two 1.5-kilogram sub-samples. The first sample was submitted for laboratory analysis, while the second was retained at the core yard as a field duplicate.
The majority of diamond drill holes at Diamba Sud were drilled with either HQ or NQ sized diamond drill bits. Core was logged and marked for sampling using standard lengths of one meter or to geological boundaries as appropriate. Samples were cut into equal halves using a diamond saw. One half of the core was retained in the original core box and stored in a secure facility at the project site’s core yard. The other half was sampled, catalogued, and placed into sealed bags which were securely stored on site until shipment.
All RC and diamond core samples form Diamba Sud were shipped to ALS Global’s laboratory in Kedougou, Senegal, for preparation and then sent, via commercial courier, to ALS’s facility in Ouagadougou, Burkina Faso, for final analysis. Routine gold analysis was performed using a 50-gram charge with fire assay and atomic absorption finish. Quality control procedures included the systematic insertion of blanks, duplicates, and certified reference standards into the sample stream. Additionally, ALS implemented its own quality control protocols.
The Mineral Resource estimate for Diamba Sud was prepared using data with an effective cut-off date of July 7, 2025. Three-dimensional wireframes were constructed for the host lithologies, including the weathering profile, as well as for mineralized zones. The mineralized envelopes were defined using nominal cut-off grades of approximately 0.1 g/t and 0.3 g/t Au, respectively.
Wireframes for each mineralized envelope were used to select and flag drillhole samples. Samples were preferentially sampled at 1-meter intervals, regardless of drilling technique based on the deposit characteristics, and therefore composited to this length. Composites for each mineralized domain were evaluated both individually and collectively using histograms, log-probability plots, and box-and-whisker plots.
Input composite data for each domain were assessed for outliers, and grade capping was applied on a semi-quantitative basis. This process was guided by statistical tools, including histograms, log-probability plots, and mean-variance plots. Grade caps were generally applied at or above the
98th percentile.
Where sufficient data existed, experimental semi-variograms were generated for each domain and modelled accordingly. These were typically characterized by a moderate to high nugget effect and two nested spherical structures.
A block model was built for each of the Diamba Sud deposits. Models were aligned with the national UTM coordinate system used for the input data and were designed with block dimensions reflecting the likely selective mining unit.
Mineralized wireframes were treated as hard boundaries during grade interpolation, meaning only assay data within each domain was used to interpolate grades within that domain. Grade interpolation was performed using either inverse distance weighting or ordinary kriging, depending on the quality and robustness of the modeled variograms. The Qualified Person considers the interpolation methods appropriate for the style of mineralization at Diamba Sud.
All estimates were carried out on a parent block basis. Estimation search parameters were informed by Kriging Neighborhood Analysis (KNA), utilizing a single-block KNA approach within well-drilled areas. An oriented ellipsoid search was applied to select composites for interpolation, with orientations derived from variogram models. Gold grade estimation was completed using a three-pass search strategy within each mineralized domain, based on the respective variogram ranges.
Fixed bulk density values were assigned by lithology and weathering profile, based on more than 25,000 water immersion measurements of drill core collected across the Diamba Sud property.
Initial validation of the block models included checks for unestimated mineralized blocks, incorrect or missing density assignments, and verification that no mineralized blocks or blocks with density values were present above the topographic surface. Visual validation included comparing the estimated block model grades to the composite grades for a series of cross sections sliced through each of the deposits.
Following the initial validation checks, swath plots were generated along the three principal axes to assess the representativeness of the estimated grade profiles relative to the input composite grades. These plots were prepared on a per-domain basis for each mineralized solid and demonstrate a satisfactory correlation between the estimated grades and the underlying composite data, supporting the reliability of the grade interpolation.
Mineral Resource classification considered several aspects affecting confidence in the estimation including geological continuity; data density and orientation; data accuracy and precision; and grade continuity. Indicated Mineral Resources have relied on a drilling grid of approximately 25 meters, with Inferred Mineral Resources based on an approximate 50-meter grid.
Mineral Resources are reported on a 100 percent ownership basis, using block sizes consistent with the anticipated selective mining unit. Resources are constrained by optimized pit shells and reported at incremental gold cut-off grades that reflect varying metallurgical recoveries and projected mining, processing, and general costs. A long-term gold price of
Qualified Person
Eric Chapman, Senior Vice President, Technical Services, is a Professional Geoscientist of the Association of Professional Engineers and Geoscientists of the Province of British Columbia (Registration Number 36328) and a Qualified Person as defined by National Instrument 43-101- Standards of Disclosure for Mineral Projects. Mr. Chapman has reviewed and approved the scientific and technical information contained in this news release and has verified the underlying data.
About Fortuna Mining Corp.
Fortuna Mining Corp. is a Canadian precious metals mining company with three operating mines and a portfolio of exploration projects in Argentina, Côte d’Ivoire, Mexico, and Peru, as well as the Diamba Sud Gold Project in Senegal. Sustainability is at the core of our operations and stakeholder relationships. We produce gold and silver while creating long-term shared value through efficient production, environmental stewardship, and social responsibility. For more information, please visit our website at www.fortunamining.com
ON BEHALF OF THE BOARD
Jorge A. Ganoza
President, CEO, and Director
Fortuna Mining Corp.
Investor Relations:
Carlos Baca | info@fmcmail.com | fortunamining.com | X | LinkedIn | YouTube
Forward looking Statements
This news release contains forward-looking statements which constitute “forward-looking information” within the meaning of applicable Canadian securities legislation and “forward-looking statements” within the meaning of the “safe harbor” provisions of the Private Securities Litigation Reform Act of 1995 (collectively, “Forward-looking Statements”). All statements included herein, other than statements of historical fact, are Forward-looking Statements and are subject to a variety of known and unknown risks and uncertainties which could cause actual events or results to differ materially from those reflected in the Forward-looking Statements. The Forward-looking Statements in this news release may include, without limitation, the Mineral Resource estimates at Diamba Sud; the Company’s proposed exploration plans at Diamba Sud; statements that a preliminary economic analysis is expected to be completed in the fourth quarter of 2025; statements about the Company’s business strategies, plans and outlook; the Company’s plans for its mines and mineral properties; changes in general economic conditions and financial markets; the impact of inflationary pressures on the Company’s business and operations; the future results of exploration activities; expectations with respect to metal grade estimates and the impact of any variations relative to metals grades experienced; assumed and future metal prices; the merit of the Company’s mines and mineral properties; and the future financial or operating performance of the Company. Often, but not always, these Forward-looking Statements can be identified by the use of words such as “estimated”, “potential”, “open”, “future”, “assumed”, “projected”, “proposed”, “used”, “detailed”, “has been”, “gain”, “planned”, “reflecting”, “will”, “anticipated”, “estimated” “containing”, “remaining”, “to be”, or statements that events, “could” or “should” occur or be achieved and similar expressions, including negative variations.
Forward-looking Statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance, or achievements of the Company to be materially different from any results, performance or achievements expressed or implied by the Forward-looking Statements. Such uncertainties and factors include, among others, operational risks associated with mining and mineral processing; uncertainty relating to Mineral Resource and Mineral Reserve estimates; uncertainty relating to capital and operating costs, production schedules and economic returns; risks relating to the Company’s ability to replace its Mineral Reserves; risks related to the conversion of Mineral Resources to Mineral Reserves; risks associated with mineral exploration and project development; uncertainty relating to the repatriation of funds as a result of currency controls; environmental matters including obtaining or renewing environmental permits and potential liability claims; uncertainty relating to nature and climate conditions; laws and regulations regarding the protection of the environment (including greenhouse gas emission reduction and other decarbonization requirements and the uncertainty surrounding the interpretation of omnibus Bill C-59 and the related amendments to the Competition Act (Canada); risks associated with political instability and changes to the regulations governing the Company’s business operations; changes in national and local government legislation, taxation, controls, regulations and political or economic developments in countries in which the Company does or may carry on business; risks associated with war, hostilities or other conflicts, such as the Ukrainian – Russian, and Israeli – Hamas conflicts, and the impacts they may have on global economic activity; risks relating to the termination of the Company’s mining concessions in certain circumstances; developing and maintaining relationships with local communities and stakeholders; risks associated with losing control of public perception as a result of social media and other web-based applications; potential opposition to the Company’s exploration, development and operational activities; risks related to the Company’s ability to obtain adequate financing for planned exploration and development activities; property title matters; risks related to the ability to retain or extend title to the Company’s mineral properties; risks relating to the integration of businesses and assets acquired by the Company; impairments; risks associated with climate change legislation; reliance on key personnel; adequacy of insurance coverage; operational safety and security risks; legal proceedings and potential legal proceedings; uncertainties relating to general economic conditions; risks relating to a global pandemic, which could impact the Company’s business, operations, financial condition and share price; competition; fluctuations in metal prices; risks associated with entering into commodity forward and option contracts for base metals production; fluctuations in currency exchange rates and interest rates; tax audits and reassessments; risks related to hedging; uncertainty relating to concentrate treatment charges and transportation costs; sufficiency of monies allotted by the Company for land reclamation; risks associated with dependence upon information technology systems, which are subject to disruption, damage, failure and risks with implementation and integration; labor relations issues; as well as those factors discussed under “Risk Factors” in the Company's Annual Information Form for the fiscal year ended December 31, 2024. Although the Company has attempted to identify important factors that could cause actual actions, events, or results to differ materially from those described in Forward-looking Statements, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended.
Forward-looking Statements contained herein are based on the assumptions, beliefs, expectations and opinions of management, including, but not limited to, the accuracy of the Company’s current Mineral Resource and Mineral Reserve estimates; that the Company’s activities will be conducted in accordance with the Company’s public statements and stated goals; that there will be no material adverse change affecting the Company, its properties or its production estimates (which assume accuracy of projected ore grade, mining rates, recovery timing, and recovery rate estimates and may be impacted by unscheduled maintenance, labor and contractor availability and other operating or technical difficulties); the duration and effect of global and local inflation; the duration and impacts of geo-political uncertainties on the Company’s production, workforce, business, operations and financial condition; the expected trends in mineral prices, inflation and currency exchange rates; that all required approvals and permits will be obtained for the Company’s business and operations on acceptable terms; that there will be no significant disruptions affecting the Company's operations and such other assumptions as set out herein. Forward-looking Statements are made as of the date hereof and the Company disclaims any obligation to update any Forward-looking Statements, whether as a result of new information, future events, or results or otherwise, except as required by law. There can be no assurance that these Forward-looking Statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, investors should not place undue reliance on Forward-looking Statements.
Cautionary Note to United States Investors Concerning Estimates of Reserves and Resources
All reserve and resource estimates included in this news release have been prepared in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101") and the Canadian Institute of Mining, Metallurgy, and Petroleum Definition Standards on Mineral Resources and Mineral Reserves. NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for public disclosure by a Canadian company of scientific and technical information concerning mineral projects. All Mineral Reserve and Mineral Resource estimates contained in the technical disclosure have been prepared in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum Definition Standards on Mineral Resources and Reserves. Canadian standards, including NI 43-101, differ significantly from the requirements of the Securities and Exchange Commission, and mineral reserve and resource information included in this news release may not be comparable to similar information disclosed by U.S. companies.
A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/b024ca04-3163-417e-8d16-67a472d7a69d
PDF available: http://ml.globenewswire.com/Resource/Download/716d36d2-553b-4036-bcc5-dd6e7d0a241d
