Hombre Muerto West (HMW) Phase 1 Construction Update - 92% Complete
Rhea-AI Summary
Galan Lithium (GLNLF) reports Phase 1 construction at Hombre Muerto West is approximately 92% complete, with nanofiltration plant assembly progressing and >25 personnel mobilised on site.
The project will move to testing and commissioning in the short term, with first processed brine targeted in early Q2 2026 and first lithium chloride concentrate expected in H1 2026. Phase 1 is designed for a 5,200 tpa LCE rate and has substantial brine inventory in evaporation ponds to support initial processing.
Positive
- Phase 1 ~92% complete
- Nanofiltration plant assembly progressing on schedule
- Mobilised >25 personnel at HMW site
- Design capacity 5,200 tpa LCE for Phase 1
- First lithium chloride concentrate targeted in H1 2026
- Substantial brine inventory ready for processing
Negative
- Construction not yet finished (~8% remaining)
- Commissioning dependent on successful testing and system integrity
- First shipment dependent on commissioning and concentrate production (target H2 2026)
- Nanofiltration commissioning with raw brine pending completion of testing
Highlights:
Phase 1 construction now approximately
92% completeNanofiltration plant assembly progressing to plan
Construction expected to complete in the short term, transitioning to testing and commissioning
Nanofiltration plant commissioning with raw brine expected to follow successful testing
Significant brine inventory ready for processing
First lithium chloride concentrate in H1 2026, first shipment H2 2026
PERTH, AU / ACCESS Newswire / March 1, 2026 / Galan LithiumLimited (ASX:GLN) (Galan or the Company) is pleased to provide an update on construction progress at its
Figure 1. Nanofiltration Plant at HMW

Construction Progress Update
Assembly of the nanofiltration plant, a critical component of the Phase 1 processing flowsheet, is progressing on schedule following its recent delivery to site. With more than 25 personnel currently mobilised at HMW, structural, mechanical and electrical installation activities are advancing rapidly. The plant is being assembled on an accelerated timeline following fabrication and pre-installation testing in Sydney.
The strong technical collaboration between Galan and Authium, established since execution of the Offtake and Operating Agreement in April 2025, continues to support disciplined, safe and efficient execution at site.
Upon finalisation of Phase 1 construction activities, which are now approximately
Galan has accumulated a substantial brine inventory in its evaporation ponds, positioning the Company to transition efficiently into processing once commissioning is complete. The nanofiltration plant has been designed with flexibility to support production beyond the 5,200 tpa LCE Phase 1 rate.
Figure 2. Nanofiltration Plant Assembly

Commenting from the HMW site Galan's Managing Director, Juan Pablo (JP) Vargas de la Vega,said:
"Phase 1 execution continues to track in line with our development schedule. Assembly of the nanofiltration plant is progressing smoothly and the integration with our evaporation and processing systems is well advanced.
With construction now around
Figure 3. Nanofiltration Plant

The Galan Board has authorised this release.
For further information contact:
COMPANY | MEDIA |
About Galan
Galan Lithium Limited (ASX:GLN) is an ASX-listed lithium exploration and development business. Galan's flagship assets comprise two world-class lithium brine projects, HMW and Candelas, located on the Hombre Muerto Salar in Argentina, within South America's 'lithium triangle'. Galan is distinguished by:
The size of its mineral resource. HMW is placed within the top 10 producing or development lithium projects globally;[1]
The purity of its mineral resource. The HMW mineral resource has the lowest impurity profile of any published lithium brine resource in Argentina;
Positioning on the cost curve. When in production, HMW is profiled to be in the first quartile of the industry cost curve;[2]
Near term production with permitted expansion. Galan is on track for first lithium chloride production in 2026, has the construction permits to expand HMW to 21 ktpa LCE and has potential to expand production up to 60 ktpa LCE in HMW Phases 3 and 4;
The RIGI. The RIGI is a large scale investment framework in Argentina which provides income tax benefits, 30 years of fiscal stability and a range of other financial benefits. Galan and Rio Tinto are the only recipients of the RIGI within the lithium industry in Argentina; and
Exploration licences at Greenbushes South in Western Australia, close to and just south of the Tier 1 Greenbushes Lithium Mine.
[1] S&P Global Metals & Mining.
[2] Wood Mackenzie, iLi Markets
SOURCE: Galan Lithium Limited
View the original press release on ACCESS Newswire