Hombre Muerto West (HMW) Phase 1 Construction Update - Nanofiltration Plant Delivered to Site
Rhea-AI Summary
Galan Lithium (OTC:GLNLF) reports the nanofiltration plant for Phase 1 was delivered to the Hombre Muerto West (HMW) site and on-site assembly has begun. Phase 1 construction is ~85% complete with sylvinite evaporation ponds finished.
The company holds about 9,500 t LCE of brine inventory in ponds. First processed brine is targeted for early Q2 2026 and first lithium chloride concentrate is targeted in H1 2026. Phase 1 expanded production rate aims for 5,200 tpa LCE.
Positive
- Nanofiltration plant delivered and assembly started
- Sylvinite evaporation ponds completed
- Phase 1 construction ~85% complete
- On‑site brine inventory of ~9,500 t LCE
- First processed brine targeted early Q2 2026
- Phase 1 expanded production target of 5,200 tpa LCE
Negative
- None.
News Market Reaction – GLNLF
On the day this news was published, GLNLF gained 7.66%, reflecting a notable positive market reaction.
Data tracked by StockTitan Argus on the day of publication.
Highlights:
Nanofiltration plant successfully delivered to HMW site
Galan and Authium teams have commenced on-site assembly. Assembly expected to be completed over the coming weeks
Evaporation (sylvinite) ponds for Phase 1 operations completed
Overall Phase 1 construction now approximately
85% completeFirst processed brine expected early Q2 2026. First lithium chloride concentrate targeted in H1 2026
PERTH, AU / ACCESS Newswire / February 15, 2026 / Galan Lithium Limited (ASX:GLN) (Galan or the Company) is pleased to provide an update on construction progress at its
Commenting from the HMW site Galan's Managing Director, Juan Pablo (JP) Vargas de la Vega, said:
"Our HMW site team is very excited at the arrival of the nanofiltration plant. Over the past 2 years we have accumulated a lithium brine inventory of around 9,500 tonnes (LCE) in the HMW ponds. In the short term we plan to complete the nanofiltration plant assembly and commissioning, which will allow for the first processed lithium brine to be produced from HMW.
The nanofiltration plant has been designed, tested, constructed and transported on an accelerated project schedule. I would like to recognise Authium's and Galan's teams who have come together in a spirit of partnership to make this possible."
Nanofiltration Plant Delivered and Assembly Underway
The Company confirms that the nanofiltration plant for Phase 1 operations has successfully arrived at the HMW project site.
Galan's technical team, together with specialists from Authium Limited (Authium), have commenced on-site assembly of the plant. Installation and assembly activities are expected to continue over the coming weeks, after which commissioning activities will begin.
The nanofiltration plant is a key component of Galan's processing flowsheet and will enable the efficient treatment of brine as part of the Phase 1 production process.
Sylvinite Ponds Completed
Construction of the sylvinite ponds required for the commencement of Phase 1 operations has now been completed. These ponds have been designed to accelerate the evaporation of processed brine, which leads to quicker production of lithium chloride concentrate and product sales for Galan.
Following Galan's successful capital raising in January 2026, construction work on the evaporation ponds will continue after the nanofiltration plant has been commissioned, to allow for the expanded production rate of 5,200 tpa LCE.
Key Upcoming Milestones
Overall construction of Phase 1 at Hombre Muerto West is now approximately
the completion of nanofiltration plant assembly;
commissioning and testing of brine processing systems;
first processed brine (targeted in the first half of 2026); and
first lithium chloride concentrate production (targeted in the first half of 2026).
The Galan Board has authorised this release.
For further information contact:
COMPANY | MEDIA |
SOURCE: Galan Lithium Limited
View the original press release on ACCESS Newswire
FAQ
What does the nanofiltration plant delivery mean for Galan (GLNLF) operations?
When does Galan (GLNLF) expect first processed brine and lithium concentrate from HMW?
How much brine inventory does Galan (GLNLF) have at Hombre Muerto West?
What is the current construction progress and production target for HMW Phase 1 (GLNLF)?
Have the evaporation (sylvinite) ponds at HMW been finished ahead of production?
What are the next construction milestones for Galan (GLNLF) at HMW?