STOCK TITAN

Graphite One Enters FAST-41 60-Day Planning and Timetable Period

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags
Graphite One (GPHOF) has entered the FAST-41 60-day planning period for its Graphite Creek project, requiring a Coordinated Project Plan to be posted on the Federal Permitting Dashboard by August 1st, 2025. FAST-41 projects typically achieve Record of Decision 25% faster than non-FAST-41 projects. The project, led by the U.S. Army Corps of Engineers, is the first Alaska mining project on FAST-41 and comes as IEA reports China controls 97% of global graphite market, exceeding its 93% control of Rare Earths. Graphite One aims to develop a complete U.S.-based graphite supply chain, including the Graphite Creek deposit in Alaska and a manufacturing plant in Warren, Ohio, addressing U.S.'s 100% import dependence on graphite.
Graphite One (GPHOF) è entrata nel periodo di pianificazione di 60 giorni FAST-41 per il progetto Graphite Creek, che richiede la pubblicazione di un Piano di Progetto Coordinato sul Federal Permitting Dashboard entro il 1° agosto 2025. I progetti FAST-41 ottengono solitamente la Record of Decision con un anticipo del 25% rispetto ai progetti non FAST-41. Il progetto, guidato dall'U.S. Army Corps of Engineers, è il primo progetto minerario dell'Alaska incluso in FAST-41 e arriva mentre l'IEA segnala che la Cina controlla il 97% del mercato globale del grafite, superando il 93% di controllo delle Terre Rare. Graphite One punta a sviluppare una filiera completa del grafite basata negli Stati Uniti, comprendente il giacimento di Graphite Creek in Alaska e uno stabilimento produttivo a Warren, Ohio, affrontando la dipendenza totale degli USA dalle importazioni di grafite.
Graphite One (GPHOF) ha entrado en el período de planificación FAST-41 de 60 días para su proyecto Graphite Creek, que requiere la publicación de un Plan de Proyecto Coordinado en el Federal Permitting Dashboard antes del 1 de agosto de 2025. Los proyectos FAST-41 suelen obtener la Record of Decision un 25% más rápido que los proyectos que no son FAST-41. El proyecto, liderado por el Cuerpo de Ingenieros del Ejército de EE. UU., es el primer proyecto minero de Alaska en FAST-41 y llega mientras la IEA informa que China controla el 97% del mercado global de grafito, superando su control del 93% en tierras raras. Graphite One busca desarrollar una cadena de suministro completa de grafito basada en EE. UU., que incluye el depósito de Graphite Creek en Alaska y una planta de fabricación en Warren, Ohio, abordando la dependencia total de EE. UU. de las importaciones de grafito.
Graphite One(GPHOF)는 Graphite Creek 프로젝트를 위해 FAST-41 60일 계획 기간에 진입했으며, 2025년 8월 1일까지 연방 허가 대시보드에 조정된 프로젝트 계획(Coordinated Project Plan)을 게시해야 합니다. FAST-41 프로젝트는 일반 프로젝트보다 의사 결정 기록(Record of Decision)을 25% 더 빠르게 달성하는 경향이 있습니다. 미국 육군 공병대가 주도하는 이 프로젝트는 알래스카 최초의 FAST-41 광산 프로젝트이며, IEA가 중국이 전 세계 흑연 시장의 97%를 장악해 희토류의 93% 장악을 능가한다고 보고한 시점에 진행되고 있습니다. Graphite One은 알래스카의 Graphite Creek 광상과 오하이오 주 워런의 제조 공장을 포함한 미국 내 완전한 흑연 공급망을 구축하여 미국의 100% 흑연 수입 의존 문제를 해결하고자 합니다.
Graphite One (GPHOF) est entrée dans la période de planification de 60 jours FAST-41 pour son projet Graphite Creek, nécessitant la publication d'un Plan de Projet Coordonné sur le Federal Permitting Dashboard avant le 1er août 2025. Les projets FAST-41 obtiennent généralement la Record of Decision 25 % plus rapidement que les projets non FAST-41. Ce projet, dirigé par l'U.S. Army Corps of Engineers, est le premier projet minier de l'Alaska à intégrer FAST-41, alors que l'AIE rapporte que la Chine contrôle 97 % du marché mondial du graphite, dépassant son contrôle de 93 % sur les terres rares. Graphite One vise à développer une chaîne d'approvisionnement complète de graphite basée aux États-Unis, incluant le gisement de Graphite Creek en Alaska et une usine de fabrication à Warren, Ohio, répondant à la dépendance totale des États-Unis aux importations de graphite.
Graphite One (GPHOF) hat die 60-tägige Planungsphase von FAST-41 für sein Graphite Creek-Projekt begonnen, wobei bis zum 1. August 2025 ein Koordiniertes Projektplan auf dem Federal Permitting Dashboard veröffentlicht werden muss. FAST-41-Projekte erreichen in der Regel die Record of Decision 25 % schneller als Nicht-FAST-41-Projekte. Das vom U.S. Army Corps of Engineers geleitete Projekt ist das erste Bergbauprojekt Alaskas im FAST-41-Programm und erfolgt, während die IEA berichtet, dass China 97 % des globalen Graphitmarktes kontrolliert und damit seine 93 % Kontrolle bei Seltenen Erden übertrifft. Graphite One strebt den Aufbau einer vollständigen, in den USA ansässigen Graphitlieferkette an, einschließlich der Graphite Creek-Lagerstätte in Alaska und einer Produktionsanlage in Warren, Ohio, um die 100%ige Importabhängigkeit der USA von Graphit zu verringern.
Positive
  • First Alaska mining project to receive FAST-41 status, potentially accelerating permitting process by 25%
  • Project addresses U.S. strategic vulnerability with China controlling 97% of global graphite market
  • Development of complete domestic supply chain from mining to manufacturing and recycling
  • USGS recognition of Graphite Creek as largest U.S. graphite deposit
Negative
  • Project still requires extensive permitting and environmental reviews
  • Current 100% U.S. import dependence on graphite poses supply chain risks
  • Potential delays in coordinating multiple federal agencies for approvals
  • Competition with China's established graphite market dominance

FAST-41 process requires G1's coordinated project plan and timetable to be posted to the public Federal Permitting Dashboard no later than August 1st

FAST-41 projects receive Record of Decision on average 25% faster than non-FAST-41 projects

FAST-41 process commences as new IEA Report notes that global graphite dependence on China is greater than Rare Earth dependence

VANCOUVER, BC, June 16, 2025 /PRNewswire/ - Graphite One Inc. (TSXV: GPH) (OTCQX: GPHOF) ("Graphite One", "G1" or the "Company"), is pleased to provide this information update as the Company moves into the FAST-41 permitting process's 60-day period to develop Graphite Creek's Coordinated Project Plan ("CPP") and detailed permitting timetable. 

Administered by the Federal Permitting Improvements Steering Council ("FPISC"), the FAST-41 timetable includes intermediate and final completion dates for each required federal environmental review and authorization. 

The project's lead Federal agency – in the case of Graphite One, the U.S. Army Corps of Engineers – must work with other cooperating agencies to develop project-specific plans to document the steps they will take to coordinate public and tribal participation and complete the required environmental reviews and authorizations. 

This timetable will be published to the FAST-41 Federal Dashboard no later than August 1, 2025. 

Benefits of FAST-41

As the FPISC has reported:

"…on average, projects supported through FAST-41 achieved Record of Decision faster than those that did not leverage FAST-41 by nearly 25%.

Graphite Creek is the first Alaska mining project to be listed on the FAST-41 Federal Dashboard, and the 5th mining project overall. The FAST-41 Dashboard will mark its 10th year since being established by federal law on December 3, 2015.

Twenty-five additional mining projects are listed on the Federal Transparency dashboard, established by Presidential Executive Order on March 20, 2025. While transparency projects have elected to provide public visibility into their planning stages, they are not required to meet the listing requirements for FAST-41 covered projects. 

Infrastructure projects covered under FAST-41 benefit in the following ways:

Increased visibility and predictability. Agencies must develop and maintain a coordinated, project-specific timetable for all required environmental review and permitting actions. Scheduled and actual timeframes for these actions are publicly displayed and updated quarterly on the Permitting Dashboard. FAST-41 states that the lead Federal agency cannot revise or extend a timetable end date within 30 days of the original end date. FAST-41 also states that a final completion date for an environmental review or authorization must not be extended by more than 30 days without consulting with the project sponsor. 

Enhanced coordination. Within 60 days of a project becoming covered under FAST41, the lead Federal agency must work with other cooperating agencies to develop project-specific plans to document the steps they will take to coordinate public and tribal participation and complete the required environmental reviews and authorizations. Advanced coordination allows for early communication of project goals to the permitting agencies, early discussion of alternatives, and alignment of agency review schedules.

Increased accountability. The Permitting Council provides high-level oversight to ensure that Federal agencies adhere to established timetables. The Permitting Council must report to Congress when the total length of modifications to a permitting timetable delays the permitting process by more than 150% of the original schedule. In addition, an annual report to Congress is required to assess each agency's progress towards implementation of FAST-41 best practices, as well as their compliance with recommended performance schedules for covered projects.

The FAST-41 Federal Permitting Dashboard may be accessed here.

China's Control over Graphite exceeds its control over Rare Earths

Figure 1: Raw Material Ownership by Country 2024 1

Figure 1: Raw Material Ownership by Country 2024 (1) (CNW Group/Graphite One Inc.)

1 G1's entry into the FAST-41 process comes as a new International Energy Agency ("IEA") report indicates that China's control over graphite materials 97% of the global market – exceeds its control of all other renewable battery materials, and even exceeds China's control over global Rare Earth production (93%). "We've seen Rare Earths in the headlines during the U.S. tariff wars with China, as China suspended access to its Rare Earths as a non-tariff countermeasure," said Anthony Huston, CEO of G1. "With China's control over graphite exceeding the Rare Earths – and with the tighter export controls China placed on graphite last year – the message should be clear: Critical Mineral dependencies can become economic weapons without warning. Our listing on FAST-41 will bring us the predictability and accountability we need to bring our project into production, and end more than 30 years of total foreign graphite dependency." 

The full IEA Report may be found here.

______________________________

1

China's Lock on Rare Earths Dictated Path Toward Trade Truce; Wall Street Journal; June 11, 2025

Graphite One's Domestic Supply Chain Strategy
With the United States currently 100 percent import dependent for synthetic and natural graphite, Graphite One is developing a complete U.S.-based, advanced graphite supply chain solution anchored by the Graphite Creek deposit, recognized by the US Geological Survey as the largest graphite deposit in the U.S. "and among the largest in the world." The Graphite One Project plan includes building an advanced graphite material and battery anode material manufacturing plant located in Warren, Ohio. The plan also includes a recycling facility to reclaim graphite and the other battery materials, to be co-located at the Ohio site, the third link in Graphite One's circular economy strategy.

About Graphite One Inc.

GRAPHITE ONE INC. continues to develop its Graphite One Project (the "Project"), with the goal of becoming an American producer of natural and synthetic graphite anode materials that is integrated with a domestic graphite resource. The Project is proposed as a vertically integrated enterprise to mine, process and manufacture high grade anode materials primarily for the lithium–ion electric vehicle battery market.  

On Behalf of the Board of Directors

"Anthony Huston" (signed)

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Cautionary Note Regarding Forward-Looking Statements

All statements in this release, other than statements of historical facts, including those related to the Fast 41 listing and the anticipated impact of the FAST-41 status, any statements related to the planned production of any mineral reserves and resources, the construction of the Warren, Ohio facility, and events or developments that the Company intends, expects, plans, or proposes are forward-looking statements. Generally, forwardlooking information can be identified by the use of forwardlooking terminology such as "proposes", "expects", "is expected", "scheduled", "estimates", "projects", "plans", "is planning", "intends", "assumes", "believes", "indicates", "to be" or variations of such words and phrases that state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". The Company cautions that there is no certainty that the Fast 41 listing will impact the Company as set forth in this press release, that the Graphite Creek Project produces the minerals set out in the FS or that the facility will be built in Warren, Ohio. Although the Company believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include market prices, exploitation and exploration successes, continuity of mineralization, uncertainties related to the ability to obtain necessary permits, licenses and title and delays due to third party opposition, changes in government policies regarding mining and natural resource exploration and exploitation, and continued availability of capital and financing, and general economic, market or business conditions. Readers are cautioned not to place undue reliance on this forward-looking information, which is given as of the date it is expressed in this press release, and the Company undertakes no obligation to update publicly or revise any forward-looking information, except as required by applicable securities laws. For more information on the Company, investors should review the Company's continuous disclosure filings that are available at www.sedarplus.ca.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/graphite-one-enters-fast-41-60-day-planning-and-timetable-period-302481791.html

SOURCE Graphite One Inc.

FAQ

What is the significance of Graphite One (GPHOF) entering FAST-41 status?

FAST-41 status typically accelerates the Record of Decision process by 25% and provides increased visibility, predictability, and accountability in federal permitting processes

Where will Graphite One's facilities be located?

The company plans to develop the Graphite Creek deposit in Alaska and build an advanced graphite material manufacturing plant in Warren, Ohio

How does China's control of graphite compare to rare earths?

According to IEA, China controls 97% of the global graphite market, which exceeds its 93% control of global Rare Earth production

What is Graphite One's strategy to address U.S. graphite dependency?

The company is developing a complete U.S.-based supply chain including mining, manufacturing, and recycling facilities to address current 100% import dependence

When will Graphite One's project plan be published on the Federal Dashboard?

The Coordinated Project Plan must be posted to the FAST-41 Federal Permitting Dashboard no later than August 1st, 2025
Graphite One

OTC:GPHOF

GPHOF Rankings

GPHOF Latest News

GPHOF Stock Data

91.91M
67.65M
28.58%
0.3%
Other Industrial Metals & Mining
Basic Materials
Link
Canada
Vancouver