i-80 Gold Receives Construction Permits and Initiates Underground Development at Archimedes
i-80 Gold (NYSE:IAUX) has secured all necessary permits and commenced construction at its Archimedes underground mining project in Nevada. The project, located at the Ruby Hill property, represents a significant milestone in the company's Phase One growth strategy. Key highlights include:
The project hosts 436,000 ounces of Indicated gold resources at 7.6 g/t and 988,000 ounces of Inferred resources at 7.3 g/t. Production is expected to begin in Q4 2026, with an anticipated average annual gold output of 100,000 ounces and a 10-year mine life. The project's economics show an after-tax NPV of $644 million with an 81% IRR at $3,000/oz gold.
Construction capital is estimated at $47 million, with development and closure costs of $106 million. The company has accelerated its feasibility study timeline to Q1 2027, with comprehensive infill drilling programs planned.
i-80 Gold (NYSE:IAUX) ha ottenuto tutte le autorizzazioni necessarie e ha avviato i lavori al suo progetto minerario sotterraneo Archimedes in Nevada. Il progetto, ubicato nella proprietà Ruby Hill, rappresenta un traguardo importante nella strategia di crescita Fase Uno della società. Punti principali:
Il deposito contiene 436.000 once di risorse gold indicate a 7,6 g/t e 988.000 once di risorse inferite a 7,3 g/t. La produzione è prevista per il 4° trimestre 2026, con una produzione media annua stimata di 100.000 once e una vita utile della miniera di 10 anni. L’analisi economica del progetto indica un NPV after-tax di 644 milioni di dollari con un IRR dell’81% assumendo un prezzo dell’oro di 3.000 $/oz.
Il capitale per la costruzione è stimato in 47 milioni di dollari, con costi di sviluppo e chiusura pari a 106 milioni di dollari. La società ha accelerato il calendario dello studio di fattibilità al 1° trimestre 2027 e ha in programma programmi completi di perforazione di infill.
i-80 Gold (NYSE:IAUX) ha obtenido todos los permisos necesarios y ha iniciado la construcción de su proyecto minero subterráneo Archimedes en Nevada. El proyecto, ubicado en la propiedad Ruby Hill, representa un hito importante en la estrategia de crecimiento de Fase Uno de la compañía. Aspectos destacados:
El yacimiento contiene 436.000 onzas de recursos Indicados a 7,6 g/t y 988.000 onzas de recursos Inferidos a 7,3 g/t. Se espera que la producción comience en el 4T de 2026, con una producción anual promedio estimada de 100.000 onzas y una vida útil de la mina de 10 años. La economía del proyecto muestra un VAN después de impuestos de 644 millones de dólares con una TIR del 81% con un precio del oro de 3.000 $/oz.
El capital de construcción se estima en 47 millones de dólares, con costos de desarrollo y cierre de 106 millones de dólares. La compañía ha acelerado el calendario del estudio de factibilidad a 1T de 2027 y planea programas integrales de perforación de densificación.
i-80 Gold (NYSE:IAUX)는 모든 필요한 허가를 확보하고 네바다에 위치한 Archimedes 지하광산 프로젝트의 건설을 착수했습니다. 루비 힐(Ruby Hill) 광산 부지에 위치한 이 프로젝트는 회사의 1단계 성장 전략에서 중요한 이정표입니다. 주요 내용은 다음과 같습니다:
해당 광산은 표준 등급(Indicated) 금 자원 436,000온스(7.6 g/t) 및 추정 등급(Inferred) 금 자원 988,000온스(7.3 g/t)를 보유하고 있습니다. 생산은 2026년 4분기에 시작될 예정이며, 연평균 약 100,000온스의 금 생산과 10년의 채광 수명을 예상합니다. 프로젝트 경제성은 금 가격을 3,000달러/온스로 가정할 때 세후 NPV 6.44억 달러와 내부수익률 81%를 제시합니다.
건설 자본비는 4,700만 달러로 추정되며, 개발 및 폐광 비용은 1억 600만 달러입니다. 회사는 타당성 조사 일정을 2027년 1분기로 앞당겼고, 포괄적인 간극 보완(infill) 시추 프로그램을 계획하고 있습니다.
i-80 Gold (NYSE:IAUX) a obtenu toutes les autorisations nécessaires et a lancé la construction de son projet minier souterrain Archimedes au Nevada. Le projet, situé sur la propriété Ruby Hill, constitue une étape importante dans la stratégie de croissance Phase Un de la société. Points clés :
Le gisement contient 436 000 onces de ressources aurifères indiquées à 7,6 g/t et 988 000 onces de ressources inférées à 7,3 g/t. La production devrait débuter au 4e trimestre 2026, avec une production annuelle moyenne estimée de 100 000 onces et une durée de vie de la mine de 10 ans. L’analyse économique du projet affiche un VAN après impôts de 644 millions de dollars avec un TRI de 81 % pour un prix de l’or de 3 000 $/oz.
Le capital de construction est estimé à 47 millions de dollars, avec des coûts de développement et de fermeture de 106 millions de dollars. La société a avancé le calendrier de l’étude de faisabilité au 1er trimestre 2027 et prévoit des programmes complets de forage d’infill.
i-80 Gold (NYSE:IAUX) hat alle erforderlichen Genehmigungen erhalten und mit dem Bau seines Archimedes Untertagebergwerksprojekts in Nevada begonnen. Das Projekt auf dem Ruby Hill-Grundstück stellt einen wichtigen Meilenstein in der Phase-eins-Wachstumsstrategie des Unternehmens dar. Wichtige Punkte:
Das Projekt weist 436.000 Unzen an angezeigten Goldressourcen bei 7,6 g/t und 988.000 Unzen an vermuteten Ressourcen bei 7,3 g/t auf. Die Produktion soll im 4. Quartal 2026 beginnen, mit einer erwarteten durchschnittlichen Jahresproduktion von 100.000 Unzen und einer Bergbau-Lebensdauer von 10 Jahren. Die Wirtschaftlichkeitsrechnung zeigt einen nach Steuern abgezinsten Kapitalwert (NPV) von 644 Mio. USD mit einem IRR von 81% bei einem Goldpreis von 3.000 USD/oz.
Die Baukosten werden auf 47 Mio. USD geschätzt, die Entwicklungs- und Schließungskosten auf 106 Mio. USD. Das Unternehmen hat den Zeitplan für die Machbarkeitsstudie auf 1. Quartal 2027 vorgezogen und plant umfassende Infill-Bohrprogramme.
- Secured all required environmental permits for underground mining activities
- Project economics show strong after-tax NPV of $644M and 81% IRR
- Significant resource base with 436,000 oz Indicated and 988,000 oz Inferred gold
- Lower zone remains open for exploration potential to extend 10-year mine life
- Part of larger growth strategy to increase gold output from 50,000 to 150,000-200,000 oz by 2028
- Accelerated drill program increases costs by $10-25M due to longer drill holes
- Initial processing requires third-party facility until Lone Tree commissioning in 2028
- High AISC of $1,877 per ounce during steady-state production
- Additional permits still needed for mining below 5100-foot elevation
Insights
i-80 Gold's permitting milestone at Archimedes advances Phase One growth strategy, targeting 4x production increase by 2028.
i-80 Gold's receipt of crucial environmental permits for its Archimedes underground project represents a significant development milestone in the company's three-phase growth strategy. With construction already underway, the company has cleared key regulatory hurdles from both the Nevada Division of Environmental Protection and Bureau of Land Management, allowing underground mining activities to proceed.
The project economics outlined in the Preliminary Economic Assessment are compelling - an after-tax NPV of $644 million with an 81% IRR at a $3,000 gold price. Archimedes is expected to contribute to production starting Q4 2026, initially targeting approximately 100,000 ounces annually at an all-in-sustaining cost of $1,877 per ounce. The mine construction capital is relatively modest at $47 million with additional life-of-mine development costs of $106 million.
Perhaps most strategically important is how Archimedes fits into i-80's broader production roadmap. This project represents a critical component of the company's Phase One growth plan, which aims to increase annual gold production from under 50,000 ounces currently to 150,000-200,000 ounces by 2028 - a 3-4x increase. The three-phase plan ultimately targets 600,000 ounces annually by the early 2030s.
The company has accelerated its timeline for the infill drilling program and feasibility study by approximately 12 months compared to the original PEA schedule, targeting completion in Q1 2027. While this accelerated timeline increases drilling costs by $10-25 million due to longer drill holes from higher elevations, it could potentially advance the production timeline and reduce overall development timeframes.
The resource base provides a solid foundation with 436,000 ounces indicated at 7.6 g/t and 988,000 ounces inferred at 7.3 g/t. These are impressive grades for a Nevada project. Additionally, the lower zone remains open to expansion north and south, suggesting potential to extend beyond the current 10-year mine life through ongoing exploration.
The environmental permits secured from both the Nevada Division of Environmental Protection and the Bureau of Land Management allow the Company to proceed with underground mining activities. Located on the Ruby Hill property (the "Property") in
"The receipt of permits and commencement of construction at Archimedes marks a major milestone for i-80 Gold as we advance Phase One of our growth strategy in
The Company's three-phase development plan is expected to increase gold output to an annual target of 600,000 ounces in the early 2030s1. Phase One of the development plan includes the ramp up of Granite Creek underground, construction of Archimedes, as well as the refurbishment and commissioning of the Lone Tree autoclave and CIL processing facility. The Lone Tree refurbishment Class 3 engineering study remains on schedule for completion in the fourth quarter of 2025, followed by the feasibility study for Granite Creek Underground planned for completion in the first quarter of 2026.
Unless otherwise stated, all amounts referred to herein are in |
Permitting
The current phase of permitting and development at Archimedes covers mining activities above the 5100-foot elevation, a threshold consistent with previously approved permits for open pit mining on the Property (see Figure 3 in Appendix). This phase of the Project is anticipated to provide development and production mining into the first half of 2028. Permitting activities below the 5100-foot elevation are underway with an estimated completion in the first half of 2027. This phased approach to permitting allows the Company to begin mining the Archimedes upper zone while simultaneously pursuing the remaining technical work and permits for the lower zone.
Development Work
The construction of surface infrastructure, such as a maintenance shop and offices, to support the Archimedes underground portal is complete (see Figure 4 in Appendix). Utilities such as water, power and compressed air are in place, and the highwall around the portals has been secured. Small Mine Development, L.L.C. ("SMD") has been contracted to develop Archimedes to the 5100-foot elevation and is currently mobilized to advance the development drift. Underground development above the 5100-foot elevation is expected to be completed by mid-2027 and will include two underground portals, the main haulage decline, a series of raises for ventilation and secondary access, exploration bays and supporting infrastructure. The development contract with SMD is consistent with the cost estimates outlined in the Preliminary Economic Assessment of the Ruby Hull Project ("PEA") filed on March 31, 2025.
Preliminary Economic Assessment Highlights
Based on the PEA, Archimedes is expected to have an after-tax net present value of
Beginning in the fourth quarter of 2026, material mined at Archimedes is expected to be processed at a third-party autoclave processing facility in the region. Once Lone Tree is commissioned in early 2028 as anticipated, material mined at Archimedes will then be processed at Lone Tree. Additionally, operations at the Property are expected to be supplemented by on-site heap leaching during the initial years.
Archimedes hosts 436,000 ounces of gold in the Indicated mineral resource category at 7.6 grams per tonne and 988,000 ounces in the Inferred mineral resource category at 7.3 grams per tonne. Planned infill drilling and exploration are expected to further upgrade and expand resources providing potential to extend the current mine life. The lower zone (Ruby Deeps) at Archimedes is open to the north and south, offering substantial exploration potential (see Figure 3 in Appendix).
Next Steps to Feasibility Study
The timing of the infill drill program and Archimedes feasibility study has been accelerated by approximately 12 months compared to the timing outlined in the PEA. Accelerating the drill program and feasibility study is expected to increase the cost of drilling by a range of approximately
Initial infill drilling of the upper zone is scheduled to begin from underground in the fourth quarter of 2025, followed by underground infill drilling of the lower zone planned in the first quarter of 2026. Collectively, these infill programs are anticipated to include more than 175 holes for approximately 60,000 meters of core. Results from the infill drilling will be included in a feasibility study which is targeted for completion in the first quarter of 2027.
The next steps will focus on three areas: resource drilling, permitting, and metallurgical testing. Resource conversion drilling will commence as the underground decline advances with results incorporated into an updated resource model. On permitting, related actions to meet National Environmental Policy Act and Nevada Department of Environmental Protection requirements for mining below the 5100-foot elevation will be carried out. Metallurgical test work will target initial Ruby Hill production areas to confirm metallurgical recoveries with the anticipated Lone Tree process conditions, including comminution, pressure oxidation under both alkaline and acidic conditions, and CIL testing on oxide material.
This anticipated Archimedes feasibility study will be prepared in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") and Subpart 1300 of Regulation S-K ("S-K 1300") with an updated mineral resource estimate.
Technical Disclosure and Qualified Persons
The technical information contained in this press release has been prepared under the supervision of, and has been reviewed and approved by Paul Chawrun P.Eng (
For a description of the data verification, assay procedures and the quality assurance program and quality control measures applied by the Company, please see the Company's Form 10-K for the fiscal year ended December 31, 2024. For further information about the PEA referenced in this news release, including information in respect of data verification, key assumptions, parameters, risks and other factors, please see the PEA. Both the Form 10-K and PEA are available on EDGAR at www.sec.gov/edgar and SEDAR+ at www.sedarplus.ca. Mineral resources do not have demonstrated economic viability and are not mineral reserves.
Endnotes | |
(1) | Consolidated production estimates and average annual production targets include the Cove Project, Archimedes Underground Project, Mineral Point Open Pit Project, Granite Creek Underground Project, and Granite Creek Open Pit Project and are based on the most recent life-of-mine production schedules disclosed in the latest technical studies filed for each respective project and related property. These anticipated production figures are preliminary in nature and are based on mineral resources, which do not have demonstrated economic viability, and which are not mineral reserves. In addition, each of the foregoing technical reports are preliminary economic assessments/initial assessment that are preliminary in nature and each include an economic analysis that is based, in part, on inferred mineral resources. Inferred mineral resources are considered too speculative geologically to have for the application of economic considerations applied to them that would enable them to be categorized as mineral reserves. As such, there is no certainty that the production targets will be realized. The production target is also pending the completion of the autoclave refurbishment Class 3 engineering study (where a series of trade-off scenarios will be considered comparing full autoclave refurbishment to alternate toll milling and ore purchase agreement options that could potentially be available), Board approval, and the successful funding, development, and commissioning of the Company's Lone Tree autoclave processing facility. The production target presented herein is a Company goal and not a projection of results and should not be taken as production guidance. |
(2) | Cash flow and net present value are calculated as of the start of construction. After tax metrics assume the Company consumes existing net operating losses sufficient to offset all tax liabilities. |
(3) | This all-in sustaining cost per ounce figure excludes the first and last year of the life of mine. The all-in sustaining cost of |
About i-80 Gold Corp.
i-80 Gold Corp. is a
CAUTIONARY STATEMENT ON FORWARD LOOKING INFORMATION
Certain information set forth in this press release, including but not limited to management's assessment of the Company's future plans and operations, the perceived merit of projects or deposits, and the impact and anticipated timing of the Company's development plan and recapitalization plan, outlook on gold output, the anticipated growth expenditures, the anticipated timing of permitting, production, project development or technical studies constitutes forward looking statements or forward-looking information within the meaning of applicable securities laws. All statements other than statements of historical fact are forward-looking statements. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "continues", "forecasts", "projects", "predicts", "intends", "anticipates" or "believes", or variations of, or the negatives of, such words and phrases, or state that certain actions, events or results "may", "could", "would", "should", "might" or "will" be taken, occur or be achieved. Readers are cautioned that the assumptions used in the preparation of information, although considered reasonable at the time of preparation, may prove to be inaccurate and, as such, reliance should not be placed on forward-looking statements. The Company's actual results, performance or achievement could differ materially from those expressed in, or implied by, these forward-looking statements and, accordingly, no assurance can be given that any of the events anticipated by the forward-looking statements will transpire or occur, or if any of them do so, what benefits, if any, that the Company will derive therefrom. By their nature, forward looking statements are subject to numerous risks and uncertainties, some of which are beyond the Company's control, including general economic and industry conditions, volatility of commodity prices, title risks and uncertainties, ability to access sufficient capital from internal and external sources such as selling assets, restructuring debt or obtaining additional equity capital on terms that may be onerous or highly dilutive. The Company's ability to refinance its indebtedness will depend on the capital markets and its financial condition at such time, currency fluctuations, construction and operational risks, licensing and permit requirements, environmental risks, competition from other industry participants, the lack of availability of qualified personnel or management, imprecision of mineral resource, or production estimates.
Please see "Risks Factors" in the Form 10-K for the fiscal year ended December 31, 2024 for more information regarding risks pertaining to the Company, which is available on EDGAR at www.sec.gov/edgar and SEDAR+ at www.sedarplus.ca. Readers are encouraged to carefully review these risk factors as well as the Company's other filings with the
Additional information relating to i-80 Gold can be found on i-80 Gold's website at www.i80gold.com, SEDAR+ at www.sedarplus.ca, and on EDGAR at www.sec.gov/edgar.
View original content to download multimedia:https://www.prnewswire.com/news-releases/i-80-gold-receives-construction-permits-and-initiates-underground-development-at-archimedes-302547630.html
SOURCE i-80 Gold Corp