Ivanhoe Mines Announces Stage Two Dewatering of Kakula Mine to Commence Imminently

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags

Ivanhoe Mines (OTCQX:IVPAF) announced operational updates for dewatering and rehabilitation at its Kamoa-Kakula Copper Complex following seismic activity in May 2025. The company has completed "Stage One" dewatering and is set to begin "Stage Two," which involves installing four new high-capacity submersible pumps (650 liters/second each) to dewater the eastern side of Kakula Mine.

Two of the four 4.2 MW pumps are expected to be operational by month-end, with the remaining two operational by mid-September. The company anticipates improved copper grades towards year-end as water levels subside, with selective mining in eastern workings to commence in Q1 2026. Kamoa-Kakula will reinstate its 2026/2027 production guidance in September 2025, with an updated long-term mine plan expected in Q1 2026.

Ivanhoe Mines (OTCQX:IVPAF) ha comunicato aggiornamenti operativi sul drenaggio e la riabilitazione del suo Kamoa-Kakula Copper Complex a seguito dell’attività sismica di maggio 2025. La società ha completato la "Fase Uno" del drenaggio e si prepara ad avviare la "Fase Due", che prevede l’installazione di quattro nuove pompe sommergibili ad alta capacità (650 litri/secondo ciascuna) per dewaterare il lato orientale della miniera di Kakula.

Due delle quattro pompe da 4,2 MW dovrebbero entrare in funzione entro la fine del mese, mentre le restanti due saranno operative entro la metà di settembre. L’azienda prevede un miglioramento delle grade di rame verso fine anno con il calo dei livelli d’acqua, e l’avvio dell’estrazione selettiva nelle aree orientali nel primo trimestre 2026. Il Kamoa-Kakula ripristinerà le previsioni di produzione 2026/2027 a settembre 2025, con un piano minerario a lungo termine aggiornato atteso nel Q1 2026.

Ivanhoe Mines (OTCQX:IVPAF) anunció novedades operativas sobre el desagüe y la rehabilitación en su Kamoa-Kakula Copper Complex tras la actividad sísmica de mayo de 2025. La compañía ha completado la "Fase Uno" de desagüe y está lista para iniciar la "Fase Dos", que incluye la instalación de cuatro nuevas bombas sumergibles de alta capacidad (650 litros/segundo cada una) para desaguar el lado este de la mina Kakula.

Se espera que dos de las cuatro bombas de 4,2 MW estén en funcionamiento a fin de mes y que las otras dos lo estén a mediados de septiembre. La empresa prevé una mejora en las leyes de cobre hacia fin de año conforme bajen los niveles de agua, y que la minería selectiva en los trabajos orientales comience en el primer trimestre de 2026. Kamoa-Kakula restablecerá su guía de producción 2026/2027 en septiembre de 2025, y se espera un plan minero a largo plazo actualizado en el Q1 de 2026.

Ivanhoe Mines (OTCQX:IVPAF)는 2025년 5월 발생한 지진 활동 이후 Kamoa-Kakula 동광산 단지의 배수 및 복구에 대한 운영 현황을 발표했습니다. 회사는 "1단계" 배수를 완료했으며, 동부 Kakula 광구의 배수를 위해 각각 초당 650리터 용량의 고성능 잠수펌프 4대를 설치하는 "2단계"를 시작합니다.

4.2MW급 펌프 4대 중 2대는 이달 말까지 가동될 것으로 예상되며, 나머지 2대는 9월 중순까지 가동될 예정입니다. 수위가 내려감에 따라 연말로 갈수록 구리 품위가 개선될 것으로 예상되며, 동부 작업구역에서의 선택적 채굴은 2026년 1분기에 시작될 예정입니다. Kamoa-Kakula는 2025년 9월에 2026/2027 생산 가이던스를 복원하고, 2026년 1분기에 장기 광산 계획 업데이트를 발표할 예정입니다.

Ivanhoe Mines (OTCQX:IVPAF) a publié des informations opérationnelles sur le drainage et la réhabilitation de son Kamoa-Kakula Copper Complex suite à l’activité sismique de mai 2025. La société a achevé la "Phase Un" de drainage et s’apprête à lancer la "Phase Deux", qui consiste à installer quatre nouvelles pompes submersibles haute capacité (650 litres/seconde chacune) pour assécher le flanc est de la mine de Kakula.

Deux des quatre pompes de 4,2 MW devraient être opérationnelles d’ici la fin du mois, les deux restantes d’ici la mi-septembre. L’entreprise prévoit une amélioration des teneurs en cuivre vers la fin de l’année à mesure que les niveaux d’eau baisseront, et le démarrage d’un travail minier sélectif dans les zones est au T1 2026. Kamoa-Kakula rétablira ses prévisions de production 2026/2027 en septembre 2025, et un plan minier à long terme mis à jour est attendu au T1 2026.

Ivanhoe Mines (OTCQX:IVPAF) gab betriebliche Updates zum Entwässerungs- und Rehabilitationsfortschritt seines Kamoa-Kakula Copper Complex nach seismischer Aktivität im Mai 2025 bekannt. Das Unternehmen hat die "Phase Eins" der Entwässerung abgeschlossen und beginnt nun mit "Phase Zwei", die die Installation von vier neuen, leistungsstarken Tauchpumpen (je 650 Liter/Sekunde) zum Entwässern der östlichen Bereiche der Kakula-Mine umfasst.

Zwei der vier 4,2-MW-Pumpen sollen bis Monatsende in Betrieb gehen, die übrigen zwei bis Mitte September. Das Unternehmen rechnet mit verbesserten Kupfergehalten gegen Jahresende, wenn die Wasserstände zurückgehen, und plant, mit selektivem Abbau in den östlichen Bereichen im ersten Quartal 2026 zu beginnen. Kamoa-Kakula wird seine Produktionsprognose für 2026/2027 im September 2025 wieder aufnehmen; ein aktualisierter langfristiger Bergbauplan wird für Q1 2026 erwartet.

Positive
  • Rehabilitation of currently accessible underground areas at Kakula is complete
  • Western side dewatering expected to complete within 8 weeks, enabling quick access to high-grade areas
  • Copper grades expected to improve notably towards year-end
  • No seismic activity experienced in Western side of Kakula Mine
Negative
  • Seismic activity in May 2025 caused flooding requiring extensive dewatering operations
  • Eastern side mining operations delayed until Q1 2026
  • Additional rehabilitation measures required for eastern side of the mine
  • Production guidance suspended until September 2025

Kamoa-Kakula 2026/2027 production guidance to be reinstated in September, updated long-term integrated mine plan targeted for Q1 2026

Copper grades from the Kakula Mine expected to improve towards year-end as underground water levels subside, enabling access to higher-grade areas

Selective mining within existing Kakula Mine eastern workings expected to commence in Q1 2026

Completion of 178 MW Turbine #5 refurbishment at Inga II hydroelectric facility expected in coming weeks

Johannesburg, South Africa--(Newsfile Corp. - August 25, 2025) - Ivanhoe Mines' (TSX: IVN) (OTCQX: IVPAF) Executive Co-Chair Robert Friedland and President and Chief Executive Officer Marna Cloete announced today an operational update on dewatering and rehabilitation activities at the Kamoa-Kakula Copper Complex.

Following the seismic activity that occurred at the Kakula Mine in May 2025, Kamoa-Kakula's engineering team implemented a three-stage plan to dewater the Kakula Mine. "Stage One" dewatering activities to stabilize and maintain current water levels were completed on June 2, 2025. "Stage Two" dewatering activities are expected to commence imminently. Stage Two dewatering consists of the installation of four new high-capacity, submersible pumps and new permanent surface infrastructure to dewater the eastern side of the Kakula Mine from surface.

Kamoa-Kakula's engineering team ordered the Stage Two high-capacity, submersible pumps, each rated with a pumping capacity of 650 litres per second, from Hefei Hengda Jianghai Pump Co., Ltd. of Anhui Province, China. Four of the five pumps have been delivered and are undergoing installation. The remaining pump will be shipped at a later date and kept in reserve as a spare.

Representatives from Hefei Hengda Jianghai Pump Co., Ltd are currently on-site overseeing the installation of the submersible pumps, alongside Kamoa-Kakula's project engineering team. The 4.2 megawatt (MW) submersible pumps are being installed in pairs down two adjacent, existing 400-metre shafts that access a deep section of the eastern side of the Kakula Mine, as shown in Figure 1. The pumps, as well as the associated valves and piping, are currently being lowered into place from the surface.

The submersible pumps will be fully submerged until the end of November, when the majority of the dewatering is expected to be complete and the water level reaches near the bottom of the Stage Two dewatering shafts, as illustrated in Figure 1.

The submersible pumps will be powered by a separate, dedicated 20 MW generator, primarily to minimize any disruption risk from the electrical grid.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/3396/263714_ivanhoe1_550.jpg

The installation of the Stage Two submersible pumps commenced on August 15. Since then, two out of the four pumps have been hoisted into place and are on schedule to be operational by month-end. The remaining two pumps are expected to be operational in mid-September.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/263714_ivanhoe1.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/3396/263714_adf0a850b46a98c0_003.jpg

Kamoa-Kakula received four 4.2 megawatt, 650-litre-per-second, submersible pumps in early August, each measuring 12 metres in length with the motor assembly, and a diameter of 1.28 metres.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/263714_adf0a850b46a98c0_003full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/3396/263714_adf0a850b46a98c0_004.jpg

Figure 1. A schematic of the projected decrease in underground water levels at the Kakula Underground mine from today (light blue) to November 2025 (dark blue). All mining areas above the water level are now fully accessible.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/263714_adf0a850b46a98c0_004full.jpg

The rehabilitation of the currently accessible areas underground at Kakula is now complete, restoring access to all areas of the mine up to the current water levels. Once the new Stage Two high-capacity, submersible pumps, located on the eastern side of the Kakula Mine, are operational, the Stage One temporary underground pumping infrastructure will be remobilized to assist with the Stage Two dewatering activities.

Dewatering the Western side of the Kakula Mine is expected to be completed within eight weeks. No seismic activity was experienced in the Western side of the Kakula Mine; therefore, regaining access to the high-grade areas on this side of the mine, as shown in Figure 2, is expected to be relatively quick, as no additional rehabilitation measures will be required. Therefore, mining grades from the Kakula Mine are expected to improve notably towards year-end.

In addition, as water levels subside on the eastern side of the Kakula Mine, rehabilitation will commence immediately as required. Selective mining within the existing workings on the eastern side of the mine is expected in Q1 2026.

"Stage Three" dewatering activities will start in late 2025, consisting of the rehabilitation and recommissioning of major existing pump stations on the eastern side of the Kakula Mine that are currently underwater. Stage Three will be the final dewatering stage, which will use the existing horizontal pumping infrastructure to dewater the remaining areas deep on the eastern side.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/3396/263714_adf0a850b46a98c0_005.jpg

Leonard Tshikuta, Supervisor, and Manix Diur, Miner, are surveying the recently installed Osro straps, which are being used to support areas of the Kakula Mine that have had fractured sidewalls from the seismic activity reported in May.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/263714_adf0a850b46a98c0_005full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/3396/263714_adf0a850b46a98c0_006.jpg

Figure 2. An illustration of the Kakula Mine's existing underground infrastructure, showing the areas on the western side of the mine currently being mined, the copper grade profile, as well as the location of the two access drives (red arrows) to the new far eastern mining area. Mining of the higher-grade areas of the Kakula Mine will resume as underground water levels subside in the fourth quarter.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/263714_adf0a850b46a98c0_006full.jpg

Notes: Existing underground development as at July 2025. Illustration is based on the 2023 Kamoa-Kakula IDP showing the estimated average grade of each vertical stack of blocks above a 2% total copper cut-off. A minimum 6-metre thickness is applied.

2026 and 2027 production guidance to be released in September

Kamoa-Kakula's engineering team is expected to provide Kamoa-Kakula's 2026 and 2027 copper production guidance in mid-late September 2025. A life of mine plan, to be included in an updated technical report, is also expected to be released in late Q1 2026.

Refurbishment of Inga II Hydroelectric facility nearing completion; mechanical installation complete and commissioning underway

Mechanical and electrical equipment installation for the refurbished Turbine #5 at the Inga II hydroelectric facility is now complete. Pre-commissioning activities have already commenced and are expected to be completed early in the fourth quarter.

Watch the progress gallery of Turbine #5 refurbishment from when refurbishment works started in 2022 up until today: 
https://www.ivanhoemines.com/wp-content/uploads/Ivanhoe_Inga-Progress-Gallery-August-2025-1.pdf

Cannot view this image? Visit: https://images.newsfilecorp.com/files/3396/263714_adf0a850b46a98c0_007.jpg

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/263714_adf0a850b46a98c0_007full.jpg

Disclosure of technical information

Disclosures of a scientific or technical nature in this news release, other than the technical information in Figure 2, have been reviewed and approved by Steve Amos, who is considered, by virtue of his education, experience, and professional association, a Qualified Person under the terms of NI 43-101. Mr. Amos is not considered independent under NI 43-101 as he is Ivanhoe Mines' Executive Vice President, Projects. Mr. Amos has verified the technical data disclosed in this news release.

Disclosures of a scientific or technical nature in Figure 2 of this news release have been reviewed and approved by Joshua Chitambala, who is considered, by virtue of his education, experience, and professional association, a Qualified Person under the terms of NI 43-101. Mr. Chitambala is not considered independent under NI 43-101 as he is the Resource Manager for Ivanhoe Mines. Mr. Chitambala has verified the scientific and technical information in Figure 2 disclosed in this news release.

About Ivanhoe Mines

Ivanhoe Mines is a Canadian mining company focused on advancing its three principal projects in Southern Africa: the Kamoa-Kakula Copper Complex in the DRC, the ultra-high-grade Kipushi zinc-copper-germanium-silver mine, also in the DRC; and the tier-one Platreef platinum-palladium-nickel-rhodium-gold-copper Mine in South Africa, which is set to start production in Q4 2025.

Ivanhoe Mines is exploring for copper in its highly prospective, 54-100% owned exploration licences in the Western Forelands, covering an area over six times larger than the adjacent Kamoa-Kakula Copper Complex, including the high-grade discoveries in the Makoko District. Ivanhoe is also exploring for new sedimentary copper discoveries in new horizons, including Angola, Kazakhstan, and Zambia.

Follow Robert Friedland (@robert_ivanhoe) and Ivanhoe Mines (@IvanhoeMines_) on X.

Information contact

Investors
Vancouver: Matthew Keevil +1.604.558.1034
London: Tommy Horton +44 7866 913 207

Media
Tanya Todd +1.604.331.9834

Forward-looking statements

Certain statements in this news release constitute "forward-looking statements" or "forward-looking information" within the meaning of applicable securities laws. Such statements and information involve known and unknown risks, uncertainties, and other factors that may cause the actual results, performance, or achievements of the company, its projects, or industry results to be materially different from any future results, performance, or achievements expressed or implied by such forward-looking statements or information. Such statements can be identified using words such as "may", "would", "could", "will", "intend", "expect", "believe", "plan", "anticipate", "estimate", "scheduled", "forecast", "predict" and other similar terminology, or state that certain actions, events, or results "may", "could", "would", "might" or "will" be taken, occur or be achieved. These statements reflect the company's current expectations regarding future events, performance, and results and speak only as of the date of this news release.

Such statements include, without limitation: (i) statements that "Stage Two" dewatering activities are expected to commence imminently and that they consist of the installation of four new high-capacity, submersible pumps and new permanent surface infrastructure to dewater the eastern side of the Kakula Mine from surface; (ii) statements that two out of the four Stage Two pumps have been hoisted into place and are on schedule to be operational by month-end and that the remaining two pumps are expected to be operational in mid-September; (iii) statements that the submersible pumps will be fully submerged until the end of November, when the water level has reached the shaft bottom, as outlined in the schematic in Figure 1; (iv) statements that the submersible pumps will be powered by a separate, dedicated 20 megawatt generator, primarily to minimize any disruption risk from the electrical grid; (v) statements that once the Stage Two pumps are up and running, the Stage One temporary underground pumping infrastructure will be remobilized to focus on completing the dewatering of the remaining water on the western and eastern side of the Kakula Mine; (vi) statements that dewatering the Western side of the Kakula Mine is expected to be completed within 8 weeks; (vii) statements that regaining access to the high-grade areas on the western side of the mine is expected to be relatively quick, as no additional rehabilitation measures will be required; (viii) statements that mining grades from the Kakula Mine are expected to improve notably towards year-end as access to the higher grade areas is achieved; (ix) statements that, as water levels subside on the eastern side of the Kakula Mine, rehabilitation will commence immediately in areas as required and that selective mining within the existing workings of the Kakula mine is expected in Q1 2026; (x) statements that Kamoa-Kakula's engineering team is expected to provide 2026 and 2027 copper production guidance in mid-late September 2025 and that a life of mine plan to be included in a new technical report is also expected to be released in late Q1 2026; and (xi) statements that pre-commissioning activities have already commenced at Turbine #5 at Inga II, and are expected to be completed early in the fourth quarter.

Forward-looking statements and information involve significant risks and uncertainties, should not be read as guarantees of future performance or results, and will not necessarily be accurate indicators of whether such results will be achieved. Many factors could cause actual results to differ materially from the results discussed in the forward-looking statements or information, including, but not limited to: (i) uncertainty around the rate of water ingress into underground workings; (ii) the ability, and speed with which, additional equipment can be secured; (iii) the continuation of seismic activity; (iv) the state of underground infrastructure; (v) uncertainty around when future underground access can be secured; (vi) future mine stability cannot be guaranteed; and (vii) future mining methods, may differ the impact on Kakula operations. Additionally, the factors discussed above and under the "Risk Factors" section in the company's MD&A for the three and six months ended June 30, 2025, and its current annual information form, and elsewhere in this news release, as well as unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; changes in the rate of water ingress into underground workings; the continuation of seismic activity; the state of underground infrastructure; delays in securing underground access; changes to the mining methods required in the future; the failure of parties to contracts with the company to perform as agreed; social or labour unrest; changes in commodity prices; and the failure of exploration programs or studies to deliver anticipated results or results that would justify and support continued exploration, studies, development or operations.

Although the forward-looking statements contained in this news release are based upon what management of the company believes are reasonable assumptions, the company cannot assure investors that actual results will be consistent with these forward-looking statements. These forward-looking statements are made as of the date of this news release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this news release.

The company's actual results could differ materially from those anticipated in these forward-looking statements as a result of the factors outlined in the "Risk Factors" section in the company's MD&A for the three and six months ended June 30, 2025, and its current annual information form.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/263714

FAQ

What is the current status of Ivanhoe Mines' (IVPAF) Kakula Mine dewatering operation?

The mine has completed Stage One dewatering and is beginning Stage Two, which involves installing four new high-capacity submersible pumps (650 liters/second each) to dewater the eastern side of the mine.

When will Ivanhoe Mines (IVPAF) resume mining in the eastern workings of Kakula Mine?

Selective mining within the existing eastern workings is expected to resume in Q1 2026, following completion of dewatering and rehabilitation activities.

What is the timeline for Ivanhoe Mines' (IVPAF) Stage Two dewatering completion?

The majority of Stage Two dewatering is expected to be complete by the end of November 2025, with two pumps operational by August-end and two more by mid-September.

When will Ivanhoe Mines (IVPAF) release its updated production guidance?

The company will release its 2026/2027 copper production guidance in mid-late September 2025, with an updated technical report expected in Q1 2026.

How is the Western side of Ivanhoe Mines' (IVPAF) Kakula Mine affected?

The Western side experienced no seismic activity and is expected to be dewatered within eight weeks, allowing relatively quick access to high-grade areas without additional rehabilitation measures.
Ivanhoe Mines Ltd

OTC:IVPAF

IVPAF Rankings

IVPAF Latest News

IVPAF Stock Data

11.45B
719.96M
46.71%
36.33%
Other Industrial Metals & Mining
Basic Materials
Link
Canada
Vancouver