Kamoa-Kakula Management are Advancing Works to Reopen the Western Side of Kakula Mine

Rhea-AI Impact
(Low)
Rhea-AI Sentiment
(Neutral)
Tags
Ivanhoe Mines (IVPAF) is progressing with plans to reopen the Kakula Mine following its temporary suspension on May 20, 2025. The company has completed Stage One of its dewatering plan, installing temporary underground pumping infrastructure that increased capacity to 4,400 litres per second. Stage Two, involving installation of four high-capacity surface pumps (650 litres/second each), is underway with expected completion in 90 days. The Phase 1 and 2 concentrators continue operating at 50% capacity using stockpiled ore. The western side of the mine remains dry with 1,000 litres per second pumping capacity and is expected to restart operations this month. The eastern side will resume after complete dewatering. The Kamoa underground mine and Phase 3 concentrator operations remain unaffected. Management will announce detailed restart plans next week.
Ivanhoe Mines (IVPAF) sta avanzando con i piani per riaprire la miniera di Kakula dopo la sospensione temporanea avvenuta il 20 maggio 2025. L'azienda ha completato la Fase Uno del piano di drenaggio, installando un'infrastruttura temporanea di pompaggio sotterraneo che ha aumentato la capacità a 4.400 litri al secondo. La Fase Due, che prevede l'installazione di quattro pompe di superficie ad alta capacità (650 litri al secondo ciascuna), è in corso e si prevede il completamento entro 90 giorni. I concentratori delle Fasi 1 e 2 continuano a operare al 50% della capacità utilizzando minerale accumulato. Il lato occidentale della miniera rimane asciutto con una capacità di pompaggio di 1.000 litri al secondo e si prevede la ripresa delle operazioni entro questo mese. Il lato orientale riprenderà le attività dopo il completo drenaggio. Le operazioni della miniera sotterranea di Kamoa e del concentratore della Fase 3 non sono state influenzate. La direzione annuncerà i piani dettagliati per la riapertura la prossima settimana.
Ivanhoe Mines (IVPAF) avanza con los planes para reabrir la mina Kakula tras su suspensión temporal el 20 de mayo de 2025. La compañía ha completado la Etapa Uno de su plan de desagüe, instalando una infraestructura temporal de bombeo subterráneo que aumentó la capacidad a 4.400 litros por segundo. La Etapa Dos, que incluye la instalación de cuatro bombas de superficie de alta capacidad (650 litros/segundo cada una), está en proceso y se espera que finalice en 90 días. Los concentradores de las Fases 1 y 2 continúan operando al 50% de su capacidad usando mineral almacenado. El lado occidental de la mina permanece seco con una capacidad de bombeo de 1.000 litros por segundo y se espera que reanude operaciones este mes. El lado oriental se reanudará tras el drenaje completo. Las operaciones de la mina subterránea Kamoa y del concentrador de la Fase 3 no se han visto afectadas. La gerencia anunciará los planes detallados de reapertura la próxima semana.
Ivanhoe Mines(IVPAF)는 2025년 5월 20일 일시 중단된 카쿨라 광산 재개 계획을 진행 중입니다. 회사는 1단계 배수 계획을 완료하여 임시 지하 펌프 시설을 설치했고, 용량을 초당 4,400리터로 늘렸습니다. 2단계는 고용량 지상 펌프 4대(각 650리터/초) 설치를 포함하며, 90일 내 완료될 예정입니다. 1단계와 2단계 농축 시설은 재고 광석을 사용해 50% 용량으로 계속 가동 중입니다. 광산 서쪽은 1,000리터/초 펌핑 용량으로 건조 상태를 유지하며 이번 달 내에 작업 재개가 예상됩니다. 동쪽은 완전 배수 후 재개할 예정입니다. 카모아 지하 광산과 3단계 농축 시설 운영은 영향받지 않았습니다. 경영진은 다음 주에 상세한 재개 계획을 발표할 예정입니다.
Ivanhoe Mines (IVPAF) progresse dans ses plans de réouverture de la mine de Kakula suite à sa suspension temporaire le 20 mai 2025. La société a achevé la première étape de son plan de drainage, en installant une infrastructure temporaire de pompage souterrain qui a porté la capacité à 4 400 litres par seconde. La deuxième étape, qui consiste à installer quatre pompes de surface à haute capacité (650 litres/seconde chacune), est en cours et devrait être terminée dans 90 jours. Les concentrateurs des phases 1 et 2 continuent de fonctionner à 50 % de leur capacité en utilisant du minerai stocké. Le côté ouest de la mine reste sec avec une capacité de pompage de 1 000 litres par seconde et devrait reprendre ses opérations ce mois-ci. Le côté est reprendra après un drainage complet. Les opérations de la mine souterraine de Kamoa et du concentrateur de la phase 3 ne sont pas affectées. La direction annoncera les plans détaillés de redémarrage la semaine prochaine.
Ivanhoe Mines (IVPAF) macht Fortschritte bei den Plänen zur Wiedereröffnung der Kakula-Mine nach ihrer vorübergehenden Stilllegung am 20. Mai 2025. Das Unternehmen hat die erste Phase seines Entwässerungsplans abgeschlossen und eine temporäre unterirdische Pumpeninfrastruktur installiert, die die Kapazität auf 4.400 Liter pro Sekunde erhöhte. Die zweite Phase, die die Installation von vier leistungsstarken Oberflächenpumpen (je 650 Liter/Sekunde) umfasst, ist im Gange und soll in 90 Tagen abgeschlossen sein. Die Konzentratoren der Phasen 1 und 2 arbeiten weiterhin mit 50 % Kapazität unter Verwendung von gelagertem Erz. Die westliche Seite der Mine bleibt trocken mit einer Pumpkapazität von 1.000 Litern pro Sekunde und soll diesen Monat den Betrieb wieder aufnehmen. Die östliche Seite wird nach vollständiger Entwässerung wieder in Betrieb genommen. Der unterirdische Kamoa-Bergbau und die Phase-3-Konzentratoroperationen sind nicht betroffen. Die Geschäftsleitung wird nächste Woche detaillierte Pläne zur Wiederaufnahme bekanntgeben.
Positive
  • Successful completion of Stage One dewatering with increased pumping capacity to 4,400 litres per second
  • Western side of mine remains dry and could restart operations this month
  • 18 months of advance underground development provides operational flexibility
  • Phase 1 and 2 concentrators continue operating at 50% capacity using stockpiles
  • Kamoa underground mine and Phase 3 concentrator remain unaffected and operating normally
Negative
  • Eastern side operations remain suspended pending complete dewatering
  • Stage Two dewatering requires 90 days for surface pump installation
  • Concentrators operating at only 50% of combined capacity
  • Temporary suspension impacts overall mine production

Installation of additional underground pumping complete; water levels set to stabilize

Phase 1 and 2 concentrators continue to be supplied by stockpiles, and will be supported by ore from western side of Kakula Mine

Ivanhoe Mines to provide next week plans for reopening the western side and restart of the eastern side of Kakula Mine

Kolwezi, Democratic Republic of the Congo--(Newsfile Corp. - June 2, 2025) - Ivanhoe Mines (TSX: IVN) (OTCQX: IVPAF) announces today that following the temporary suspension of underground operations at the Kakula Mine announced on May 20, 2025, senior management continues to work alongside world-leading engineering experts to safely and conservatively restart mining operations.

Kamoa Copper's engineering teams are currently updating the short-, medium-, and long-term plans to resume operations on both the western and eastern sides of the Kakula Mine. Subject to dewatering progress, underground mining is expected to restart later this month on the western side of the mine, which remains dry and supported by over 1,000 litres per second of operational pumping capacity.

Operations on the eastern side of the Kakula Mine are expected to restart once dewatering is complete. Kamoa Copper has implemented a two-stage plan to dewater the entire Kakula Mine:

Stage One involves the installation of temporary underground pumping infrastructure to stabilize and maintain current water levels. Stage One was completed today, with total underground pumping capacity increasing to approximately 4,400 litres per second, sufficient to manage water inflows.

Stage Two involves the installation of high-capacity, surface-mounted pumps and new permanent infrastructure to fully dewater the entire Kakula Mine. Stage Two is already underway. Kamoa Copper has ordered four high-capacity pumps, each rated at 650 litres per second. Additional pumps will also be ordered as part of the long term pumping infrastructure plan. These pumps will be deployed in pairs and installed in existing ventilation shafts that access the water catchment areas of the Kakula Mine. Delivery and installation of the surface pumps is expected within 90 days.

Meanwhile, the Phase 1 and 2 concentrators continue to operate at approximately 50% of their combined capacity, processing ore from surface stockpiles. Ore from the western side of the Kakula Mine will be fed into the concentrators once underground operations restart.

Since mining operations began at Kakula in 2021, crews have completed over 18 months' worth of underground development ahead of the mine plan. This extensive advance development provides significant operational flexibility, allowing access to multiple production areas as they are deemed safe for re-entry.

Mining operations at the Kamoa underground mine and ore processing at the adjacent Phase 3 concentrator remain unaffected and continue as normal.

Ivanhoe Mines to provide next week plans for reopening the western side and the restart of the eastern side of the Kakula Mine 

Senior management from Ivanhoe Mines and the Kamoa Copper joint venture, together with world-class geotechnical specialists, are in the process of concluding their thorough, conservative geotechnical assessment of the Kakula Mine. The results of the assessment, as well as the restart plans for the western and eastern sides of the Kakula Mine are expected next week.

About Ivanhoe Mines

Ivanhoe Mines is a Canadian mining company focused on advancing its three principal projects in Southern Africa; the expansion of the Kamoa-Kakula Copper Complex in the DRC, the ramp-up of the ultra-high-grade Kipushi zinc-copper-germanium-silver mine, also in the DRC; and the phased development of the tier-one Platreef platinum-palladium-nickel-rhodium-gold-copper Mine in South Africa.

Ivanhoe Mines is exploring for copper in its highly prospective, 54-100% owned exploration licences in the Western Forelands, covering an area over six times larger than the adjacent Kamoa-Kakula Copper Complex, including the high-grade discoveries in the Makoko District. Ivanhoe is also exploring for new sedimentary copper discoveries in new horizons including Angola, Kazakhstan, and Zambia.

Follow Robert Friedland (@robert_ivanhoe) and Ivanhoe Mines (@IvanhoeMines_) on X.

Information contact

Investors

Vancouver: Matthew Keevil +1.604.558.1034

London: Tommy Horton +44 7866 913 207

Media

Tanya Todd +1.604.331.9834

Forward-looking statements

Certain statements in this news release constitute "forward-looking statements" or "forward-looking information" within the meaning of applicable securities laws. Such statements and information involve known and unknown risks, uncertainties, and other factors that may cause the actual results, performance, or achievements of the company, its projects, or industry results to be materially different from any future results, performance, or achievements expressed or implied by such forward-looking statements or information. Such statements can be identified using words such as "may", "would", "could", "will", "intend", "expect", "believe", "plan", "anticipate", "estimate", "scheduled", "forecast", "predict" and other similar terminology, or state that certain actions, events, or results "may", "could", "would", "might" or "will" be taken, occur or be achieved. These statements reflect the company's current expectations regarding future events, performance, and results and speak only as of the date of this news release.

Such statements include, without limitation: i) statements that water levels are set to stabilize; ii) statements regarding the operating capacity of the Phase 1 and 2 concentrators, processing of stockpiles and that Ore from the western side of the Kakula Mine will be fed into the concentrators once underground operations restart; iii) statements regarding plans to resume mining operations in the western section of Kakula; iv) statements regarding the water inflow rate and the pumping capacity being sufficient to stabilize current water levels; v) statements regarding the procurement, deployment, installation and delivery of high-capacity pumps; vi) statements regarding the timing of conclusions by senior management and geotechnical specialists, as well as the timing and the stages for restart plans for the western and eastern sides of Kakula mine; and (vii) statements that the company will provide plans for reopening the western and eastern sides of Kakula Mine next week.

Forward-looking statements and information involve significant risks and uncertainties, should not be read as guarantees of future performance or results, and will not necessarily be accurate indicators of whether such results will be achieved. Many factors could cause actual results to differ materially from the results discussed in the forward-looking statements or information, including, but not limited to: (i) uncertainty around the rate of water ingress into underground workings; (ii) the ability, and speed with which, additional equipment can be secured; (iii) the continuation of seismic activity; (iv) the state of underground infrastructure; (v) uncertainty around when future underground access can be secured; (vi) future mine stability cannot be guaranteed; and (vii) future mining methods, may differ the impact on Kakula operations. Additionally, the factors discussed above and under the "Risk Factors" section in the company's MD&A for the three months ended March 31, 2025, and its current annual information form, and elsewhere in this news release, as well as unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; changes in the rate of water ingress into underground workings; the continuation of seismic activity; the state of underground infrastructure; delays in securing underground access; changes to the mining methods required in the future; the failure of parties to contracts with the company to perform as agreed; social or labour unrest; changes in commodity prices; and the failure of exploration programs or studies to deliver anticipated results or results that would justify and support continued exploration, studies, development or operations.

Although the forward-looking statements contained in this news release are based upon what management of the company believes are reasonable assumptions, the company cannot assure investors that actual results will be consistent with these forward-looking statements. These forward-looking statements are made as of the date of this news release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this news release.

The company's actual results could differ materially from those anticipated in these forward-looking statements as a result of the factors outlined in the "Risk Factors" section in the company's MD&A for the three months ended March 31, 2025, and its current annual information form.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/254168

FAQ

When will Ivanhoe Mines (IVPAF) restart operations at the Kakula Mine?

The western side of Kakula Mine is expected to restart later in June 2025, while the eastern side will resume after complete dewatering. Detailed restart plans will be announced next week.

What is the current status of IVPAF's Kakula Mine dewatering plan?

Stage One is complete with 4,400 litres/second pumping capacity. Stage Two is underway, involving installation of four high-capacity surface pumps, expected to complete in 90 days.

How is the temporary suspension affecting IVPAF's production?

Phase 1 and 2 concentrators are operating at 50% capacity using stockpiles. The Kamoa underground mine and Phase 3 concentrator remain unaffected and continue normal operations.

What measures has Ivanhoe Mines taken to manage the Kakula Mine water situation?

The company has installed temporary underground pumping infrastructure and is implementing a two-stage dewatering plan, including the installation of high-capacity surface pumps rated at 650 litres per second each.

How will IVPAF maintain production during the Kakula Mine restart?

The company is utilizing stockpiled ore for concentrators and has 18 months of advance underground development, providing operational flexibility for accessing multiple production areas.
Ivanhoe Mines Ltd

OTC:IVPAF

IVPAF Rankings

IVPAF Latest News

IVPAF Stock Data

14.47B
562.55M
44.91%
35.46%
Other Industrial Metals & Mining
Basic Materials
Link
Canada
Vancouver