JFB Construction Announces Commencement of Phase 1 of 3 and Approval and Issuance of $18.9 Million Bond to act as General Contractor for Public High School in DeSoto County, Fla.
JFB Construction (NASDAQ: JFB) was approved to issue an $18.9 million bond to act as general contractor for Phase 1 of a three-phase public high school project in DeSoto County, Florida.
The overall contract is valued at $100 million for a ~100,000 sq ft campus across 40+ acres adding capacity for 1,379 students. JFB said it has >$34 million in working capital and has started Phase 1 construction, targeted for completion in January 2026. Phase 2 is valued at >$30 million with planned start in June 2026. CEO Joseph F. Basile III signed a personal guarantee tied to the contract.
JFB Construction (NASDAQ: JFB) è stato approvato per emettere una obbligazione da 18,9 milioni di dollari per agire come appaltatore generale per la Fase 1 di un progetto pubblico di scuola superiore in tre fasi nella Contea di DeSoto, Florida.
Il contratto complessivo è valutato 100 milioni di dollari per un campus di ~100.000 piedi quadrati su oltre 40 acri, aumentando la capienza di 1.379 studenti. JFB ha dichiarato di disporre di oltre 34 milioni di dollari di capitale circolante e ha avviato la costruzione della Fase 1, con completamento previsto per gennaio 2026. La Fase 2 è valutata > 30 milioni di dollari con inizio pianificato per giugno 2026. Il CEO Joseph F. Basile III ha firmato una garanzia personale legata al contratto.
JFB Construction (NASDAQ: JFB) recibió aprobación para emitir una bono de 18,9 millones de dólares para actuar como contratista general de la Fase 1 de un proyecto público de escuela secundaria de tres fases en el condado de DeSoto, Florida.
El contrato total tiene un valor de 100 millones de dólares para un campus de ~100,000 pies cuadrados repartido en más de 40 acres, aumentando la capacidad para 1,379 estudiantes. JFB indicó que dispone de más de 34 millones de dólares en capital de trabajo y ya ha iniciado la construcción de la Fase 1, con finalización prevista en enero de 2026. La Fase 2 tiene un valor de > 30 millones de dólares y su inicio está planificado para junio de 2026. El CEO Joseph F. Basile III firmó una garantía personal vinculada al contrato.
JFB Construction (나스닥: JFB)은 플로리다주 DeSoto 카운티의 3단계 공립 고등학교 프로젝트 1단계의 일반 도급자로 활동하기 위해 1,890만 달러의 채권을 발행하도록 승인받았다.
전체 계약은 약 1억 달러 규모로, 40에이커가 넘는 토지에 걸친 약 10만 평방피트 규모의 캠퍼스가 구성되며 1,379명의 학생을 수용하게 된다. JFB는 3,400만 달러의 운전자본을 보유하고 있으며 1단계 공사를 시작했고 2026년 1월 완공을 목표로 한다. 2단계는 > 3천만 달러 규모로 평가되며 시작은 2026년 6월로 계획되어 있다. CEO Joseph F. Basile III는 계약과 관련된 개인 보증서를 서명했다.
JFB Construction (NASDAQ: JFB) a été approuvée pour émettre une obligation de 18,9 millions de dollars afin d'agir en tant qu'entrepreneur général pour la phase 1 d'un projet public de lycée en trois phases dans le comté de DeSoto, Floride.
Le contrat global est évalué à 100 millions de dollars pour un campus d'environ 100 000 pieds carrés sur plus de 40 acres, augmentant la capacité pour 1 379 élèves. JFB a indiqué disposer de plus de 34 millions de dollars de fonds de roulement et a commencé les travaux de la phase 1, avec une achèvement prévu en janvier 2026. La phase 2 est évaluée à > 30 millions de dollars et le démarrage prévu est juin 2026. Le PDG Joseph F. Basile III a signé une garantie personnelle liée au contrat.
JFB Construction (NASDAQ: JFB) wurde genehmigt, eine Anleihe über 18,9 Millionen USD auszugeben, um als Generalunternehmer für Phase 1 eines dreiphasigen öffentlichen High-School-Projekts im DeSoto County, Florida, zu fungieren.
Der Gesamtvertrag ist mit 100 Millionen USD bewertet und umfasst einen Campus von ca. 100.000 Quadratfuß auf über 40 Acres, der Kapazität für 1.379 Schüler schafft. JFB gab an, über mehr als 34 Millionen USD Betriebskapital zu verfügen und mit dem Bau der Phase 1 begonnen zu haben, dessen Fertigstellung voraussichtlich im Januar 2026 liegt. Phase 2 ist mit > 30 Millionen USD bewertet und der geplante Start ist Juni 2026. Der CEO Joseph F. Basile III hat eine persönliche Garantie in Zusammenhang mit dem Vertrag unterschrieben.
JFB Construction (بورصة ناسداك: JFB) تمت الموافقة عليها لإصدار سندات بقيمة 18.9 مليون دولار لتكون المقاول العام للمرحلة 1 من مشروع مدرسة ثانوية عامة من ثلاث مراحل في مقاطعة ديسوتو، فلوريدا.
يقدَّر العقد الإجمالي بـ 100 مليون دولار لبناء مجمع يبلغ حوالي 100,000 قدم مربع عبر مساحة تزيد عن 40 فداناً مع زيادة القدرة لـ 1,379 طالباً. قالت JFB إنها لديها أكثر من 34 مليون دولار كسيولة عاملة وبدأت أعمال المرحلة 1، على أن يكتمل في يناير 2026. المرحلة 2 مُقدَّر لها > 30 مليون دولار مع بدء مخطط في يونيو 2026. وقع المدير التنفيذي جوزيف ف. باسيل III ضماناً شخصياً مرتبطاً بالعقد.
- $100M total contract value
- Issued $18.9M bond enabling Phase 1 start
- $34M+ working capital strengthening bonding capacity
- Phase 1 start with Jan 2026 completion target
- Phase 2 contract valued >$30M planned for Jun 2026
- CEO signed a personal guarantee creating owner liability
- Aggressive Phase 1 timeline to complete by Jan 2026
Insights
JFB secured an $18.9M bond and started Phase 1 of a
JFB will act as general contractor under an
The business mechanism is straightforward: bonding reduces client risk and lets JFB secure public construction revenue streams while subcontractor payments gain assurance. Key dependencies include timely performance to meet the Phase 1
Total contract valued at
Lantana, Fla., Nov. 04, 2025 (GLOBE NEWSWIRE) -- JFB Construction Holdings (Nasdaq: JFB), a real estate development and construction company focused on hospitality, commercial, industrial, and residential property development, today announced that it has been approved for the issuance of an
“Last month we announced that we executed an
“I have signed a personal guarantee, demonstrating the confidence I have in JFB Construction and the financial ability of the company to complete this project on time and on budget. This approval and bond issuance will allow us to proceed with the contract, as the bond provides a financial guarantee to the client that the project will be completed and that subcontractors and suppliers will be paid.
“Our strong balance sheet, with over
“We have started construction and we plan to complete construction of Phase 1 in January 2026. The value of the Phase 2 contract is valued at over
About JFB Construction Holdings
JFB Construction Holdings (“JFB”) offers generations of combined experience in residential and commercial construction and development. Having the experience of building multifamily communities, shopping centers, national franchises, and exclusive estate and equestrian homes, with over 2 million square feet of commercial and retail space, JFB provides hands-on professional expertise, which has led to the quality and production we are known for.
JFB’s reputation has been built on our clients' trust and the value we bring to each project.
JFB is proud that most of our projects are obtained through referrals and repeat customers, and that to date we have provided general contracting and construction management services in 36 U.S. states.
Caution Regarding Forward-Looking Statements
Certain statements in this announcement are forward-looking statements. Investors can identify these forward-looking statements by words or phrases such as “may,” “will,” “expect,” “anticipate,” “aim,” “estimate,” “intend,” “plan,” “believe,” “is/are likely to,” “potential,” “continue” or other similar expressions. These statements are subject to uncertainties and risks including, but not limited to, the risk factors discussed in the Risk Factors and in Management’s Discussion and Analysis of Financial Condition and Results of Operations sections of our Forms 10-K, 10-Q and other reports filed with the SEC and available at www.sec.gov. Although the Company believes that the expectations expressed in these forward-looking statements are reasonable, it cannot assure you that such expectations will turn out to be correct, and the Company cautions investors that actual results may differ materially from the anticipated results and encourages investors to review other factors that may affect its future results in the Company’s registration statement and other filings with the SEC. Additional factors are discussed in the Company’s filings with the SEC, which are available for review at www.sec.gov. The Company undertakes no obligation to update or revise publicly any forward-looking statements to reflect subsequent occurring events or circumstances, or changes in its expectations that arise after the date hereof, except as may be required by law.
JFB Construction Holdings Contact:
Joseph F. Basile, III
561-582-9840.
joe@jfbconstruction.net
Investor Relations Contact:
CORE IR
Mike Mason
516 222 2560
investors@jfbconstruction.net