Jet.AI Announces StratGrid’s Proposed Wheatland AI Campus Designed for Closed Loop Cooling and Non-Potable Industrial Water

(Very High)

Sentiment and the balance of points

Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

Tags
AI

Jet.AI (JTAI) announced StratGrid's conceptual cooling and water design for a proposed 240 MW off-grid data infrastructure campus in Wheatland County, Alberta. Jet.AI owns approximately 15% of StratGrid and holds an approximate 15% economic interest in the Wheatland project through the same investment vehicle, in which it holds a majority interest.

Subject to final engineering and design, the campus is expected to use closed-loop liquid cooling with dry coolers instead of evaporative towers. The power island is expected to use air-cooled condensers. StratGrid expects to draw non-potable water from an existing industrial pipeline. Environmental and regulatory assessments are underway ahead of an Alberta Utilities Commission application, including a noise assessment to evaluate compliance with the commission's Rule 012.

Loading...
Loading translation...
1 point · 1 major

How this balance works

Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.

It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.

Rhea-AI Sentiment measures something else, the tone of the wording.

0 major · 2 points

Hollow bars mark forward-looking points. How the balance works

Positive

  • Major point. Forward-looking: it has not happened yet and may not happen.Proposed 240 MW off-grid campus in Wheatland County is a project in which Jet.AI holds an approximate 15% economic interest.

Negative

  • Minor pointCampus cooling design remains conceptual and is subject to final engineering and design.
  • Minor pointAlberta Utilities Commission application is still ahead, with environmental and regulatory assessments underway.

News Explained

The Wheatland campus remains proposed, and its planned Alberta Utilities Commission application is expected to include a third-party decommissioning-cost estimate and reclamation-funding plan; these are planned disclosures, not a stated funding commitment.

Key Figures

Proposed campus capacity: 240 MW StratGrid ownership: approximately 15% Project economic interest: approximately 15%
Proposed campus capacity
240 MW
Wheatland off-grid data infrastructure campus
StratGrid ownership
approximately 15%
Held through SG Canada InvestCo LLC
Project economic interest
approximately 15%
Wheatland Project

Previous AI Reports

3 past events · Latest: Nov 17
Same Type 3 events
  1. Nov 17

    Quarterly results

    24h Move
    -9.4%

    Quarterly update reported Jet.AI’s approximate 15% economic interest in the proposed 240 MW Wheatland project.

  2. Nov 12

    Wheatland project update

    24h Move
    -6.5%

    StratGrid outlined up to 240 MW capacity and anticipated a first-quarter 2027 AUC filing.

  3. Jul 29

    StratGrid investment

    24h Move
    +2.8%

    Jet.AI invested $1.75 million in StratGrid; Wheatland was designed for about 200 MW.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

Key Terms

closed-loop liquid cooling, evaporative cooling, non-potable
3 terms
closed-loop liquid cooling technical
"use a closed-loop liquid cooling system"
Closed-loop liquid cooling is a sealed system that circulates a coolant through pipes and contact plates to carry heat away from electronic equipment, then returns the warmed fluid to a radiator or heat exchanger to be cooled and reused. For investors, it matters because this method lets data centers and high-performance computing gear run faster and denser with lower long‑term energy and maintenance costs—similar to how a car’s radiator keeps an engine from overheating—potentially improving operating margins and asset utilization.
evaporative cooling technical
"rather than evaporative cooling towers"
Evaporative cooling is the process where a liquid (usually water) absorbs heat as it turns into vapor, lowering the temperature of nearby air or surfaces — like how sweating cools your skin. Investors should care because it offers a low-energy, lower-cost alternative to traditional refrigeration used in buildings, data centers and industry; adopting it can reduce operating expenses, capital needs, regulatory risks and improve sustainability metrics that affect company profitability and valuation.
non-potable technical
"use non-potable raw water supplied for industrial use"
Non-potable describes water or other liquids that are not safe for drinking or cooking because they may contain contaminants, pathogens, or chemicals. For investors, the label matters because using, storing, or distributing non-potable water usually triggers different regulations, permits, treatment needs, separate plumbing and signage, and potential cleanup or liability costs — like a product clearly marked “do not drink” that must be handled in a separate lane of operations.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Closed-loop cooling design and environmental and regulatory assessments underway ahead of Alberta Utilities Commission application.

LAS VEGAS, Nov. 23, 2026 (GLOBE NEWSWIRE) -- Jet.AI Inc. (Nasdaq: JTAI) ("Jet.AI" or the "Company"), an emerging provider of high-performance GPU infrastructure and AI cloud services, today announced that StratGrid Inc. ("StratGrid") has outlined the conceptual cooling, water, and environmental design of its proposed Wheatland Power Island and Digital Infrastructure Project (the "Project"), a 240 MW off-grid data infrastructure campus in Wheatland County, Alberta. Jet.AI owns approximately 15% of StratGrid through SG Canada InvestCo LLC, an investment vehicle in which Jet.AI holds a majority interest, and through this same vehicle holds an approximate 15% economic interest in the Project.

Subject to final front-end engineering and design, the digital infrastructure campus is expected to use a closed-loop liquid cooling system that rejects heat through dry coolers rather than evaporative cooling towers. The power island is expected to use air-cooled condensers. The proposed water supply is expected to be sourced from an existing industrial raw water pipeline. Environmental and regulatory field surveys and assessments are underway, including a noise impact assessment to evaluate compliance with Alberta Utilities Commission ("AUC") Rule 012.

"The Wheatland project is expected to use non-potable raw water supplied for industrial use, not water assigned to agriculture or household use," said David Sealock, CEO of StratGrid. “Air cooling and innovative closed-loop systems should keep our water use very low, and our emission controls are being designed to meet Alberta’s air quality standards. We are committed to evaluating and implementing best available technologies in support of a sustainable design, with a global engineering firm providing technical guidance on our long-term ESG vision."

The Project's AUC application is expected to include a third-party decommissioning cost estimate and a plan to fund reclamation. StratGrid has begun stakeholder consultation and intends to hold a community open house in early 2027.

About Jet.AI

Jet.AI Inc. (NASDAQ: JTAI) is a technology-driven company focused on deploying artificial intelligence tools and high-performance GPU infrastructure to enhance decision-making, efficiency, and performance across complex systems. The Company is listed on the NASDAQ Capital Market under the ticker symbol "JTAI." To learn more, visit www.jet.ai.

About StratGrid

StratGrid Inc. is a Calgary-based company developing natural gas-powered digital infrastructure to support growing demand for hyperscale computing. The project is designed to combine on-site power generation with digital infrastructure, providing reliable electricity without relying on Alberta's electricity grid or passing infrastructure costs to existing ratepayers. To learn more, visit www.stratgrid.ca.

Forward-Looking Statements

This press release contains certain statements that may be deemed to be "forward-looking statements" within the meaning of the federal securities laws, including the safe harbor provisions of the Private Securities Litigation Reform Act of 1995, Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934. Forward-looking statements relate to future events or our future performance or future financial condition. These forward-looking statements are not historical facts, but rather are based on current expectations, estimates and projections about our Company, our industry, our beliefs and our assumptions. Forward-looking statements include, without limitation, statements regarding the proposed Wheatland Power Island and Digital Infrastructure Project, its expected generation, storage and digital infrastructure capacity, proposed cooling and water-supply design, estimated capital expenditure, employment, operating life, regulatory and municipal filings and approvals, rezoning, construction start and commercial operations date, and the expected benefits from the Project. Words such as "believe," "project," "expect," "anticipate," "estimate," "intend," "strategy," "future," "opportunity," "plan," "may," "should," "will," "would," "will be," "will continue," "will likely result," and similar expressions or the negative of these terms or other similar expressions, but the absence of these words does not mean that a statement is not forward-looking. These statements are predictions, projections and other statements about future events that are based on current expectations and assumptions and, as a result, are subject to risks and uncertainties that could cause actual results to differ materially from the expected results. As a result, caution must be exercised in relying on forward-looking statements, which speak only as of the date they were made.

Factors that could cause actual results to differ materially from those expressed or implied in forward-looking statements include, among others: the Project has not received approval from the AUC, Wheatland County or any other authority, and may never receive it; the proposed rezoning may not be approved; stakeholder consultation may lead to design changes, delays or opposition; natural gas supply beyond current arrangements may not be secured on acceptable terms or at all; StratGrid may be unable to obtain financing for the Project on acceptable terms or at all; construction may face cost overruns, supply chain constraints, labour shortages or delays; capital expenditure, capacity, employment and schedule figures are preliminary estimates and subject to change; customers for the digital infrastructure may not be secured; all requisite water supply arrangements with Wheatland County may not be finalized; further engineering work may require changes to the proposed cooling and water-supply plans; changes in Alberta energy, environmental or data centre policy may affect the Project; and Jet.AI may not realize the expected economic benefits of its interest in the Project. Jet.AI's interest is held through SG Canada InvestCo LLC, and Jet.AI does not control StratGrid or the Project. Additional risks appear in the "Risk Factors" section of Jet.AI's most recent Annual Report on Form 10-K and subsequent reports filed with the Securities and Exchange Commission. These filings identify and address other important risks and uncertainties that could cause actual events and results to differ materially from those contained in the forward-looking statements. Readers are cautioned not to put undue reliance on forward-looking statements, and Jet.AI assumes no obligation and does not intend to update or revise these forward-looking statements, whether because of new information, future events, or otherwise, except as provided by law.

Contacts
Jet.AI Investor Relations
Gateway Group, Inc.
949-574-3860
Jet.AI@gateway-grp.com

StratGrid Investor Relations
info@stratgrid.ca
1-855-689-4743


FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

How much of the Wheatland AI campus project does Jet.AI own?

Jet.AI holds an approximate 15% economic interest in the Wheatland project. It holds that stake and owns approximately 15% of StratGrid through SG Canada InvestCo, an investment vehicle in which Jet.AI holds a majority interest.

What cooling and water systems are planned for the Wheatland AI campus announced by Jet.AI?

Subject to final engineering and design, the campus is expected to use closed-loop liquid cooling with dry coolers rather than evaporative towers. The power island is expected to use air-cooled condensers, and StratGrid expects to source non-potable water from an existing industrial pipeline.

What is expected in the Alberta Utilities Commission application for the Wheatland project announced by Jet.AI?

The application is expected to include a third-party decommissioning cost estimate and a plan to fund reclamation, or restoration of the site.

When does StratGrid plan to hold a public open house for the Wheatland project announced by Jet.AI?

StratGrid intends to hold a community open house in early 2027. Stakeholder consultation has already begun.