STOCK TITAN

K92 Mining Announces Strong Q3 Production Results – 44,323 oz AuEq Produced Plus 4,893 oz AuEq in Commissioning Stockpile and Significant Stage 3 Expansion Progress Achieved

Rhea-AI Impact
(Moderate)
Rhea-AI Sentiment
(Neutral)
Tags

K92 Mining (OTCQX: KNTNF) reported Q3 2025 production of 44,323 oz AuEq (42,244 oz gold, 1,323,538 lbs copper, 34,831 oz silver) and quarterly sales of 45,006 oz gold. Q3 processed 137,172 tonnes (31% above Q3 2024) at a head grade of 11.2 g/t AuEq. Metallurgical recoveries were strong at 95.0% Au and 94.6% Cu, exceeding Updated DFS parameters for six consecutive quarters.

Construction of the 1.2 Mtpa Stage 3 process plant is complete, commissioning is well advanced, and first gold pour and concentrate production remain on track for the first half of Q4 2025. As of Sept 30, 2025, 90% of Stage 3 growth capital is spent or committed and remains on budget. The company reported a 4,893 oz AuEq commissioning stockpile and said it has achieved >80% of the lower end of 2025 guidance through three quarters.

K92 Mining (OTCQX: KNTNF) ha riportato la produzione del Q3 2025 di 44.323 oz AuEq (42.244 oz d'oro, 1.323.538 lb di rame, 34.831 oz di argento) e vendite trimestrali di 45.006 oz d'oro. Il Q3 ha processato 137.172 tonnellate (31% in più rispetto al Q3 2024) a una testa di giacimento di 11,2 g/t AuEq. I rendimenti metallurgici sono stati forti con 95,0% Au e 94,6% Cu, superando i parametri DFS aggiornati per sei trimestri consecutivi.

La costruzione della Stage 3 da 1,2 Mtpa per impianto di processo è completa, l'avvio è ben avanzato, e la prima fusione d'oro e la produzione di concentrato rimangono in linea con la prima metà del Q4 2025. Al 30 settembre 2025, il 90% degli investimenti per la crescita della Stage 3 è speso o impegnato e resta nel budget. L'azienda ha riportato una scorta di commissioning di 4.893 oz AuEq e ha affermato di aver raggiunto oltre l'80% della fascia inferiore della guidance 2025 entro tre trimestri.

K92 Mining (OTCQX: KNTNF) informó la producción del 3er trimestre de 2025 de 44,323 oz AuEq (42,244 oz de oro, 1,323,538 lb de cobre, 34,831 oz de plata) y ventas trimestrales de 45,006 oz de oro. El 3T procesó 137,172 toneladas (31% más que el 3T 2024) a una ley de cabeza de 11,2 g/t AuEq. Los aprovechamientos metalúrgicos fueron fuertes, con 95,0% Au y 94,6% Cu, superando los parámetros de DFS Actualizados durante seis trimestres consecutivos.

La construcción de la planta de proceso Stage 3 de 1,2 Mtpa está completa, la puesta en marcha está bastante avanzada, y el primer vertido de oro y la producción de concentrado siguen en camino para la primera mitad del Q4 2025. Al 30 de septiembre de 2025, el 90% del capital de crecimiento de Stage 3 ya se ha gastado o comprometido y permanece dentro del presupuesto. La empresa reportó una existencia de cumplimiento de 4,893 oz AuEq y dijo haber alcanzado >80% del extremo inferior de la guía para 2025 tras tres trimestres.

K92 Mining (OTCQX: KNTNF)는 2025년 3분기 생산으로 44,323 oz AuEq를 보고했습니다(금 42,244 oz, 구리 1,323,538 lb, 은 34,831 oz) 및 분기 매출은 45,006 oz의 금이었습니다. 3분기는 137,172톤을 가공했으며(Q3 2024 대비 31% 증가), 헤드 등급은 11.2 g/t AuEq였습니다. 광석 선광 회수율은 강했고 95.0% Au, 94.6% Cu로 업데이트된 DFS 매개변수를 6분기 연속으로 상회했습니다.

1.2 Mtpa Stage 3 공정 플랜트의 건설이 완료되었고 시운전이 상당히 진척되었으며, 4분기 2025년 상반기에 최초의 금 주입 및 농축물 생산이 예정대로 진행 중입니다. 2025년 9월 30일 기준으로, Stage 3 성장 자본의 90%가 지출되었거나 약정되었으며 예산 내에 있습니다. 회사는 커미셔닝 재고 4,893 oz AuEq를 보고했고 2025년 가이드의 하단 구간의 >80%를 3분기 만에 달성했다고 밝혔습니다.

K92 Mining (OTCQX: KNTNF) a annoncé la production du T3 2025 de 44 323 oz AuEq (42 244 oz d’or, 1 323 538 lb de cuivre, 34 831 oz d’argent) et des ventes trimestrielles de 45 006 oz d’or. Le T3 a traité 137 172 tonnes (55% de plus que le T3 2024) à une teneur en tête de 11,2 g/t AuEq. Les récupérations métallurgiques ont été solides avec 95,0% Au et 94,6% Cu, dépassant les paramètres DFS mis à jour pour six trimestres consécutifs.

La construction de la Stage 3 de 1,2 Mtpa pour l’usine de traitement est terminée, la mise en service est bien avancée et le premier coulage d’or ainsi que la production de concentré restent prévues pour la première moitié du T4 2025. Au 30 septembre 2025, 90% du capital de croissance de Stage 3 est dépensé ou engagé et reste dans le budget. La société a déclaré disposer d’un stock de commissioning de 4 893 oz AuEq et a indiqué avoir atteint >80% du bas de la fourchette de guidance 2025 après trois trimestres.

K92 Mining (OTCQX: KNTNF) meldete die Produktion im Q3 2025 von 44.323 oz AuEq (42.244 oz Gold, 1.323.538 lb Kupfer, 34.831 oz Silber) sowie den Quartalsumsatz von 45.006 oz Gold. Im Q3 wurden 137.172 Tonnen verarbeitet (31% mehr als Q3 2024) bei einer Kopfrate von 11,2 g/t AuEq. Die metallurgischen Ausbeuten waren stark mit 95,0% Au und 94,6% Cu, und schnitten bei den aktualisierten DFS-Parametern sechs Quartale in Folge besser ab.

Der Bau der 1,2 Mtpa Stage 3-Verarbeitungsanlage ist abgeschlossen, die Inbetriebnahme ist fortgeschritten, und der erste Goldguss sowie die Konzentratauslieferung liegen im Plan für die erste Hälfte des Q4 2025. Bis zum 30. Sept. 2025 wurden 90% des Stage 3-Wachstums-Kapitals ausgegeben oder vertraglich gebunden und liegen im Budget. Das Unternehmen meldete einen Commissioning-Stockpile von 4.893 oz AuEq und gab an, >80% des unteren Endes der Jahresprognose 2025 nach drei Quartalen erreicht zu haben.

K92 Mining (OTCQX: KNTNF) أبلغت عن إنتاج الربع الثالث 2025 بمقدار 44,323 أوقية AuEq (42,244 أوقية ذهب، 1,323,538 رطل نحاس، 34,831 أوقية فضة) وإيرادات ربع سنوية من 45,006 أوقية ذهب. المعالجة في الربع الثالث بلغت 137,172 طنًا (زيادة 31% عن الربع الثالث 2024) عند معدل تركيز رأس من 11.2 g/t AuEq. معدلات الاستخلاص المعدنية كانت قوية عند 95.0% Au و 94.6% Cu، متجاوزةً معايير DFS المحدثة لستة أرباع متتالية.

أُكملت إقامة مصنع العملية Stage 3 بسعة 1.2 Mtpa، والتشغيل الأول وتكوين النحاس لا يزالان في المسار ذاته للنصف الأول من الربع الرابع 2025. اعتبارًا من 30 سبتمبر 2025، تم إنفاق أو الالتزام بـ90% من رأس مال نمو Stage 3 وما زال ضمن الميزانية. أشارت الشركة إلى وجود مخزون تكميلي قدره 4,893 أوقية AuEq وقالت إنها حققت >80% من الحد الأدنى للتوجيه لعام 2025 عبر ثلاثة أرباع.

K92 Mining (OTCQX: KNTNF) 报告2025年第三季度产量为 44,323 oz AuEq(其中金 42,244 oz,铜 1,323,538 lb,银 34,831 oz)及季度销售额为 45,006 oz 金。第三季度加工量为 137,172 吨(较2024年第三季度增长 31%),头部品位为 11.2 g/t AuEq。选冶回收率强劲,金回收率 95.0%,铜回收率 94.6%,连续六个季度超出更新的 DFS 参数。 

阶段 3 1.2 Mtpa 的处理厂建设已完成,投产调试进展顺利,预计在 2025 年第四季度前半段实现第一轮金浇铸及精矿产出。至 2025 年 9 月 30 日,阶段 3 增长资本的 90% 已支出或承诺,且仍在预算内。公司显示有一个 4,893 oz AuEq 的调试备料,并表示在三季度内已达到 2025 年指引下限的 >80%。

Positive
  • Q3 production of 44,323 oz AuEq
  • Processed tonnage +31% versus Q3 2024 (137,172 t)
  • Gold recovery 95.0% and copper recovery 94.6%, exceeding DFS
Negative
  • 90% of Stage 3 growth capital spent or committed, leaving ~10% unspent
  • Pastefill commissioning targeted later (mid-2026) to complete full Stage 3 infrastructure

VANCOUVER, British Columbia, Oct. 08, 2025 (GLOBE NEWSWIRE) -- K92 Mining Inc. (“K92” or the “Company”) (TSX: KNT; OTCQX: KNTNF) is pleased to announce production results for the third quarter (“Q3”) of 2025 from its Kainantu Gold Mine in Papua New Guinea.

Q3 2025 Production Results

  • Strong quarterly production of 44,323 ounces gold equivalent (“AuEq”)(1) or 42,244 oz gold, 1,323,538 lbs copper and 34,831 oz silver (Figure 1). Quarterly sales of 45,006 oz gold, 1,480,151 lbs copper and 43,271 oz silver. With more than 80% of the lower end of annual guidance achieved in the first three quarters, plus ending Q3 with a 4,893 oz AuEq commissioning stockpile in line with the Stage 3 Expansion requirements (28,702 tonnes at 5.3 g/t AuEq or 5.0 g/t gold, 0.24% copper, and 11.9 g/t silver), the Company remains on track to meet its 2025 production guidance of 160,000–185,000 oz AuEq.

  • Quarterly ore processed of 137,172 tonnes, a 31% increase from Q3 2024, with a head grade of 11.2 grams per tonne (“g/t”) AuEq, or 10.7 g/t gold, 0.47% copper and 10.3 g/t silver. Head grade during the quarter was above budget, benefitting from a positive gold grade reconciliation versus the latest independent mineral resource estimate (September 12, 2023 effective date for Kora and Judd).

  • Strong metallurgical recoveries in Q3 of 95.0% for gold and 94.6% for copper (Figure 2). The process plant has now delivered six consecutive quarters exceeding the updated definitive feasibility study (“Updated DFS”) recovery parameters for both gold (92.6%) and copper (94.2%) (January 1, 2024 effective date).

  • Record total material mined (ore plus waste) of 353,770 tonnes, with multiple tonnes to surface daily records (ore plus waste) in late-September, including 5,769 tonnes on September 27 and 6,404 tonnes on September 29, demonstrating the increased material movement benefits realized from the commissioning of the first material pass during the quarter combined with the commencement of surface trucks operating in the twin incline. Total mine development was 2,477 metres. The operation continues to balance lateral development priorities between the completion of key underground projects, including prioritizing low equivalent lateral advance jumbo activities such as the Puma Ventilation Drive and the underground pastefill chamber.

  • Total ore mined of 152,485 tonnes, the second highest on record, with mining activity across 13 levels, including the 1090, 1110, 1225, 1325, 1345, and 1365 levels at Kora, and the 1010, 1030, 1050, 1170, 1185, 1325, 1345 and 1385 levels at Judd – long hole open stoping performed to design.

Stage 3 Expansion – Significant Progress Made. Construction of Stage 3 Plant Complete, Commissioning Well-Advanced, First Gold Pour and First Concentrate Production on Track for First Half of Q4 2025

  • Construction of the new 1.2 million tonnes-per-annum Stage 3 Expansion Process Plant is complete and was delivered under the capital expenditure budget, marking a major milestone for the construction team. Crushing, grinding and flotation circuits are now being commissioned with ore, with first gold pour, first gold-copper-silver concentrate production and completion of plant commissioning on schedule for the first half of Q4 2025. As at September 30, 2025, 90% of Stage 3 Expansion growth capital has either been spent or committed and remains on budget.

  • During Q3, the major construction contracts were awarded for the pastefill plant. The surface tailings filtration plant detailed engineering and design is complete, early earthworks are complete and civil works have commenced. The surface storage facility near the underground mine is rapidly advancing, with site clearing complete, early earthworks underway, and detailed engineering nearly complete. The underground pastefill plant bulk excavations made significant progress during the quarter, and detailed engineering and design is nearly complete. Long-lead items for the various paste infrastructure projects are now arriving on site. Commissioning remains on schedule to commence mid-Q1 2026, with practical completion of commissioning of the pastefill circuit remaining on schedule for mid-2026.

  • During the quarter, several key Stage 3 Expansion underground construction and operational excellence projects were completed or are approaching completion, including:

    • Material Pass – Construction and commissioning completed in Q3, connecting the main mine via gravity to the highly productive twin incline haulage route. In late-Q3, multiple surface haulage daily records were delivered as noted above, driven by the commissioning of the material pass, combined with the commencement of surface haul trucks operating in the twin incline that transport material directly from underground to surface stockpiles, eliminating the need for rehandle. The next material pass is planned to commence development in Q4 and become operational in Q1 2026, enabling a dedicated pass for both ore and waste, respectively.

    • Phase 2 Ventilation Upgrade – Development of two raisebored ventilation raises was completed in Q3, with the full ventilation upgrade planned for the second half of October. This upgrade is expected to deliver a +30% increase in primary mine airflow (150 m3/s to 200 m3/s), enabling two major productivity improvements: i) reduced re-entry times after blasting, and; ii) reduced blast initiation time with the introduction of a centralized blasting system which enables remote initiation from surface – these two combined improvements will enable firing twice a day (currently once a day).

    • Phase 3 Ventilation Upgrade - Puma Ventilation Drive on schedule for Q4 completion and is now within 70m of surface breakthrough. Surface works are complete ahead of the breakthrough, and upon breakthrough, primary mine airflow is expected to increase to 250 m3/s, further reducing blast re-entry times and meeting the airflow requirements for the Stage 3 Expansion. Once complete, the vent circuit will be modified, so that the twin incline will operate under highly efficient one-way traffic flow that utilizes both inclines.

    • Stage 4 Expansion Ventilation Upgrade – Installation of two x 2 MW variable speed drive fans is currently underway and scheduled for completion in Q4. Electrification is planned to be opportunistically completed in H1 2026 as it is not required for the Stage 3 Expansion.

    • Decline-Incline Convergence Project connecting the Main Mine with the Twin Incline via internal ramp access – Significant progress was delivered in Q3 with 258 metres of advance achieved, leaving less than 370 metres of development required for completion. Upon completion scheduled for Q1 2026, this project is expected to deliver major operational efficiency improvements as the Main Mine will now also become accessible by the highly productive twin incline, and all mining fronts will be connected via an internal ramp, allowing for one-way traffic flow.

    • Surface Tele-Remote Loader System – Completed in Q3, leveraging the underground fiber optic backbone (Wi-Fi), to enable the operation of underground loaders from surface. This system maximizes the available operating time over a 24-hour period by enabling tele-remote loading operations during shift change and re-entry. In late-Q3, the underground fleet was also fully integrated with onboard Wi-Fi capability to enable real-time data-collection for short interval control planning, productivity monitoring, and fleet diagnostics to further drive operational improvements.

    • Primary Power Station – Phase 1, 8.8 MW of generation capacity was installed and commissioned in Q3. Phase 2 has significantly progressed with intended expansion to 15.2 MW. Long-lead orders have been placed and completion is planned for H1 2026. This will provide standby power during any unexpected outages from the local grid (hydroelectricity).

  • Two new mining fronts have also been significantly developed, including five new sublevels in the Twin Incline mining front, and two new sublevels in the Lower Kora mining front, which will facilitate the ramp-up in long-hole stoping over the coming quarters for the Stage 3 Expansion.

Note (1): Gold equivalent production for Q3 2025 is calculated based on: gold $3,507 per ounce; silver $38.71 per ounce; and copper $4.49 per pound. Gold equivalent grade for Q3 incorporates realized recoveries of 95.0% for Au, 94.6% for Cu and 81.3% for Ag.

John Lewins, K92 Chief Executive Officer and Director, stated, “The third quarter marked another strong period of progress for K92 both in terms of production and continued execution of the Stage 3 Expansion. With the commissioning of the new 1.2 million tonnes-per-annum Stage 3 Expansion Process Plant nearing completion, this marks an exciting period in the Company’s history as K92 transitions into a Tier-1, mid-tier producer. Notably, ore has already been introduced into the crushing, grinding, and flotation circuits of the new process plant, keeping us firmly on track for practical completion of commissioning and the first gold pour and concentrate production in the first half of Q4 2025. Importantly, the team has built the process plant under-budget, representing a significant achievement.

We are also very pleased with the significant advancement we have made across a multitude of projects, de-risking the delivery of the Stage 3 Expansion and positioning the underground mine for Stage 4 and beyond. The recent string of daily records in total tonnes to surface moved (ore + waste) demonstrates that productivity and efficiency projects are now having a tangible impact on mine performance. Additionally, critical contracts were awarded, and construction works advanced, for all major pastefill infrastructure, with commissioning targeted to commence mid-Q1 2026. With 90% of Stage 3 growth capital already spent or committed, the expansion remains fully funded and on budget.

Having already delivered 80% of the lower end of our annual guidance within the first three quarters plus a commissioning stockpile of 4,893 oz AuEq at the end of Q3, we are well-positioned to achieve our 2025 production guidance.”

See Figure 1: Quarterly Production, Cash Cost and AISC Chart
See Figure 2: Gold and Copper Recoveries Chart

Table 1 – 2025 & 2024 Annual Production Data

  Q3 2024Q4 20242024Q1 2025Q2 2025Q3 2025
Tonnes ProcessedT104,99296,614427,821103,449130,337137,172
Feed Grade Aug/t13.017.310.714.38.310.7
Feed Grade Cu%0.58%0.47%0.55%0.50%0.55%0.47%
Recovery (%) Au%95.3%96.4%94.6%95.8%93.3%95.0%
Recovery (%) Cu%95.1%94.7%94.1%95.1%94.9%94.6%
Metal in Conc & Doré Prod Auoz41,70251,371139,12345,73532,37542,244
Metal in Conc Prod CuT5804352,235518697600
Metal in Conc Prod Agoz37,61341,992142,06334,08542,96634,831
Gold Equivalent Productionoz44,30453,401149,51547,81734,81644,323


Notes –Gold equivalent for Q3 2025 is calculated based on: 
gold $3,507 per ounce; silver $38.71 per ounce; and copper $4.49 per pound.

Gold equivalent for Q2 2025 is calculated based on:
gold $3,299 per ounce; silver $33.41 per ounce; and copper $4.31 per pound.

Gold equivalent for Q1 2025 is calculated based on:
gold $2,855 per ounce; silver $31.73 per ounce; and copper $4.26 per pound

Gold equivalent for Q4 2024 is calculated based on: 
gold $2,658 per ounce; silver $31.52 per ounce; and copper $4.25 per pound.

Gold equivalent for Q3 2024 is calculated based on:
gold $2,474 per ounce; silver $29.43 per ounce; and copper $4.17 per pound.
  

Qualified Person

K92 Mine Chief Geologist, Andrew Kohler, PGeo, a qualified person under the meaning of Canadian National Instrument 43-101 – Standards of Disclosure for Mineral Projects, has reviewed and is responsible for the technical content of this news release. Data verification by Mr. Kohler includes significant time onsite reviewing drill core, face sampling, underground workings, and discussing work programs and results with geology and mining personnel.

Technical Report

The Updated DFS and mineral resource estimate for the Kainantu Gold Mine Project in Papua New Guinea is presented in a technical report, titled, “Independent Technical Report, Kainantu Gold Mine, Updated Definitive Feasibility Study, Kainantu Project, Papua New Guinea” dated March 21, 2025, with an effective date of January 1, 2024.

About K92

K92 Mining Inc. is engaged in the production of gold, copper and silver at the Kainantu Gold Mine in the Eastern Highlands province of Papua New Guinea, as well as exploration and development of mineral deposits in the immediate vicinity of the mine. The Company declared commercial production from Kainantu in February 2018, is in a strong financial position, and is working to become a Tier 1 mid-tier producer through ongoing plant expansions. A maiden resource estimate on the Blue Lake copper-gold porphyry project was completed in August 2022. K92 is operated by a team of mining company professionals with extensive international mine-building and operational experience.

On Behalf of the Company,

John Lewins, Chief Executive Officer and Director

For further information, please contact David Medilek, P.Eng., CFA, President and Chief Operating Officer at +1-604-416-4445

CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION: This news release includes certain “forward-looking statements” under applicable Canadian securities legislation. Such forward-looking statements include, without limitation: (i) the results of the Kainantu Mine Definitive Feasibility Study, including the Stage 3 Expansion, a new standalone 1.2 million tonnes-per-annum process plant and supporting infrastructure; (ii) statements regarding the expansion of the mine and development of any of the deposits; (iii) the Kainantu Stage 4 Expansion, operating two standalone process plants, larger surface infrastructure and mining throughputs; and (iv) the potential extended life of the Kainantu Mine.

All statements in this news release that address events or developments that we expect to occur in the future are forward-looking statements. Forward-looking statements are statements that are not historical facts and are generally, although not always, identified by words such as “expect”, “plan”, “anticipate”, “project”, “target”, “potential”, “schedule”, “forecast”, “budget”, “estimate”, “intend” or “believe” and similar expressions or their negative connotations, or that events or conditions “will”, “would”, “may”, “could”, “should” or “might” occur. All such forward-looking statements are based on the opinions and estimates of management as of the date such statements are made. Forward-looking statements are necessarily based on estimates and assumptions that are inherently subject to known and unknown risks, uncertainties and other factors, many of which are beyond our ability to control, that may cause our actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking information. Such factors include, without limitation, Public Health Crises, including the epidemic or pandemic viruses; changes in the price of gold, silver, copper and other metals in the world markets; fluctuations in the price and availability of infrastructure and energy and other commodities; fluctuations in foreign currency exchange rates; volatility in price of our common shares; inherent risks associated with the mining industry, including problems related to weather and climate in remote areas in which certain of the Company’s operations are located; failure to achieve production, cost and other estimates; risks and uncertainties associated with exploration and development; uncertainties relating to estimates of mineral resources including uncertainty that mineral resources may never be converted into mineral reserves; the Company’s ability to carry on current and future operations, including development and exploration activities at the Arakompa, Kora, Judd and other projects; the timing, extent, duration and economic viability of such operations, including any mineral resources or reserves identified thereby; the accuracy and reliability of estimates, projections, forecasts, studies and assessments; the Company’s ability to meet or achieve estimates, projections and forecasts; the availability and cost of inputs; the availability and costs of achieving the Stage 3 Expansion or the Stage 4 Expansion; the ability of the Company to achieve the inputs the price and market for outputs, including gold, silver and copper; failures of information systems or information security threats; political, economic and other risks associated with the Company’s foreign operations; geopolitical events and other uncertainties, such as the conflicts in Ukraine, Israel and Palestine; compliance with various laws and regulatory requirements to which the Company is subject to, including taxation; the ability to obtain timely financing on reasonable terms when required; the current and future social, economic and political conditions, including relationship with the communities in Papua New Guinea and other jurisdictions it operates; other assumptions and factors generally associated with the mining industry; and the risks, uncertainties and other factors referred to in the Company’s Annual Information Form under the heading “Risk Factors”.

Estimates of mineral resources are also forward-looking statements because they constitute projections, based on certain estimates and assumptions, regarding the amount of minerals that may be encountered in the future and/or the anticipated economics of production. The estimation of mineral resources and mineral reserves is inherently uncertain and involves subjective judgments about many relevant factors. Mineral resources that are not mineral reserves do not have demonstrated economic viability. The accuracy of any such estimates is a function of the quantity and quality of available data, and of the assumptions made and judgments used in engineering and geological interpretation, Forward-looking statements are not a guarantee of future performance, and actual results and future events could materially differ from those anticipated in such statements. Although we have attempted to identify important factors that could cause actual results to differ materially from those contained in the forward-looking statements, there may be other factors that cause actual results to differ materially from those that are anticipated, estimated, or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. The Company disclaims any intention or obligation to update or revise any forward-looking statements, whether as a result of new information, future events or otherwise, except as required by law.

Figure 1: Quarterly Production, Co-Product Cash Cost and Co-Product AISC Chart

Figure 1 - Quarterly Production, Co-Product Cash Cost and Co-Product AISC Chart

Figure 2: Gold and Copper Recoveries Chart

Figure 2 - Gold and Copper Recoveries Chart

Photos accompanying this announcement are available at

https://www.globenewswire.com/NewsRoom/AttachmentNg/72bbafe4-1519-4e66-8f75-77d06748b04f

https://www.globenewswire.com/NewsRoom/AttachmentNg/1ce69a80-051d-4ed1-b931-2ceaced93d64


FAQ

What did K92 Mining (KNTNF) report for Q3 2025 production?

K92 reported 44,323 oz AuEq produced in Q3 2025 (42,244 oz gold; recoveries: Au 95.0%, Cu 94.6%).

Is the Stage 3 1.2 Mtpa process plant for KNTNF complete and when will it start producing?

Construction of the Stage 3 plant is complete; commissioning is advanced with first gold pour and concentrate production on track for the first half of Q4 2025.

How much of the Stage 3 expansion capital for KNTNF is committed or spent as of Sept 30, 2025?

As of Sept 30, 2025, 90% of Stage 3 growth capital has been spent or committed and the project remains on budget.

How close is K92 to meeting its 2025 production guidance (KNTNF)?

K92 has achieved more than 80% of the lower end of its 2025 guidance after three quarters and holds a 4,893 oz AuEq commissioning stockpile.

What operational improvements did KNTNF report in Q3 2025?

The company reported record daily tonnes to surface after commissioning a material pass and starting twin-incline surface haul trucks, plus tele-remote loader integration and new power capacity.

When will the pastefill circuit for K92 be commissioned?

The pastefill commissioning is targeted to commence mid-Q1 2026 with practical completion of the pastefill circuit on schedule for mid-2026.
K92 Mining

OTC:KNTNF

KNTNF Rankings

KNTNF Latest News

KNTNF Stock Data

2.95B
237.44M
1.75%
52.9%
Gold
Basic Materials
Link
Canada
Vancouver