STOCK TITAN

NioCorp to Begin Construction of Mine Portal at Its Elk Creek Critical Minerals Project

Rhea-AI Impact
(High)
Rhea-AI Sentiment
(Neutral)
Tags

NioCorp (Nasdaq: NB) announced Board approval of a Mine Portal Project at the Elk Creek critical minerals site to establish the main underground mine entrances. Work is expected to begin in Q1 2026 and the current estimated capital cost is approximately $44.6 million. The scope covers excavation to bedrock, drilling and blasting to form twin ramps, on-site access roads, and supporting infrastructure.

The portal will enable implementation of the electric Railveyor™ bulk-handling system (previously announced), replacing a twin-shaft design and aiming to reduce initial capital and shorten pre-development timing. Management said advancing the portal moves a critical-path schedule item forward while the company continues working to secure the remaining financing needed for Elk Creek.

Loading...
Loading translation...

Positive

  • Board-approved Portal Project advances critical-path development
  • Construction planned to start in Q1 2026
  • Estimated capital cost of approximately $44.6 million
  • Portal enables Railveyor™ electric system, reducing diesel use

Negative

  • Project advancement remains contingent on securing the remaining financing
  • Portal excavation represents a major pre-construction activity with execution risk

News Market Reaction

-0.70%
22 alerts
-0.70% News Effect
+5.6% Peak in 15 min
-$5M Valuation Impact
$748M Market Cap
0.1x Rel. Volume

On the day this news was published, NB declined 0.70%, reflecting a mild negative market reaction. Argus tracked a peak move of +5.6% during that session. Our momentum scanner triggered 22 alerts that day, indicating elevated trading interest and price volatility. This price movement removed approximately $5M from the company's valuation, bringing the market cap to $748M at that time.

Data tracked by StockTitan Argus on the day of publication.

Key Figures

Portal Project capex: $44.6 million Portal start timing: Q1 2026 Railveyor announcement year: 2024
3 metrics
Portal Project capex $44.6 million Current estimated capital cost for the Mine Portal Project
Portal start timing Q1 2026 Expected commencement of Mine Portal Project construction
Railveyor announcement year 2024 Year Railveyor bulk material handling system was named preferred solution

Market Reality Check

Price: $5.80 Vol: Volume 2,959,440 is below...
normal vol
$5.80 Last Close
Volume Volume 2,959,440 is below the 20-day average of 3,812,421, suggesting no outsized trading relative to recent norms. normal
Technical Shares at $5.69 are trading above the 200-day moving average of $4.29, indicating a pre-existing upward trend into this news.

Peers on Argus

NB gained 5.33% while peers showed mixed moves: UAMY up 8.75%, NAK up 2.2%, TMQ ...

NB gained 5.33% while peers showed mixed moves: UAMY up 8.75%, NAK up 2.2%, TMQ up 1.7%, but LZM and WRN slightly negative. With no peers in the momentum scanner and mixed directions, today’s move appears more stock-specific.

Historical Context

5 past events · Latest: Dec 11 (Positive)
Pattern 5 events
Date Event Sentiment Move Catalyst
Dec 11 Community support events Positive +2.7% Nebraska town halls showing resident and political support for Elk Creek.
Dec 08 Investor conference Positive +1.8% CEO presentation on Elk Creek and U.S. critical minerals onshoring role.
Nov 25 Town hall preview Positive +1.9% Announcement of Senator and Governor speaking at Elk Creek town halls.
Nov 21 Rights plan adopted Positive +9.2% Limited-duration shareholder rights plan to address potential takeovers.
Nov 20 Supply-chain commentary Neutral -0.6% CEO comments on China export controls and U.S. critical mineral risks.
Pattern Detected

Recent Elk Creek–focused announcements and governance actions have generally been followed by positive price reactions, with only one mild divergence on a risk-focused commentary.

Recent Company History

Over the past two months, NioCorp has steadily highlighted progress and support for the Elk Creek Critical Minerals Project. Town halls on Dec 5, 2025 drew strong community and political backing, and conference participation underscored its onshoring role. A shareholder rights plan adopted on Nov 21, 2025 coincided with a notable positive move. Today’s mine portal decision fits this pattern of advancing Elk Creek toward anticipated 2026 construction activity.

Regulatory & Risk Context

Active S-3 Shelf
Shelf Active
Active S-3 Shelf Registration 2025-10-10

An effective S-3ASR shelf registration filed on 2025-10-10 allows NioCorp to offer common shares, warrants, debt securities, and units in the future. The shelf has already been used at least once, as indicated by a 424B5 prospectus supplement on 2025-10-14, providing flexibility for additional capital raises as the Elk Creek Project advances.

Market Pulse Summary

This announcement detailed Board approval of NioCorp’s Mine Portal Project, a critical first step fo...
Analysis

This announcement detailed Board approval of NioCorp’s Mine Portal Project, a critical first step for underground access at the Elk Creek Critical Minerals Project, with an estimated cost of $44.6 million and work expected in Q1 2026. It follows months of community engagement and financing activities aimed at advancing Elk Creek. Investors may watch for updates on funding plans, execution of portal construction, and how these align with the broader project schedule.

Key Terms

national instrument 43-101
1 terms
national instrument 43-101 regulatory
"a Qualified Person as defined by National Instrument 43-101, has reviewed"
National Instrument 43-101 is a set of rules and guidelines that govern how mineral exploration and mining companies must report information about their projects. It ensures that the details shared with investors are accurate, consistent, and reliable—similar to how a detailed, verified blueprint ensures a building’s safety. This helps investors make informed decisions based on trustworthy information about a company's mineral resources.

AI-generated analysis. Not financial advice.

Portal Will Establish the Mine Entrances and is a Critical First Step in Enabling Underground Mine Access and Advancing the Project

Portal Project Expected to Commence in Q1 of Calendar Year 2026

CENTENNIAL, CO / ACCESS Newswire / December 22, 2025 / NioCorp Developments Ltd. ("NioCorp" or the "Company") (Nasdaq:NB), a leading U.S. critical minerals developer, today announced that its Board of Directors (the "Board") has approved the Company's Mine Portal Project (the "Portal Project"), a major initiative to advance the Elk Creek Critical Minerals Project (the "Elk Creek Project").

The Portal Project will establish the main entrances to the Elk Creek Project underground mine and will serve as the primary access point for personnel, equipment, and materials for the Company's planned underground mining operations. The Board-approved scope also includes excavating to bedrock, drilling and blasting to establish the twin mine ramps, on-site access road construction, as well as on-site supporting infrastructure. Work is expected to begin in Q1 of calendar year 2026 and the current estimated capital cost for the project is approximately $44.6 million.

The portal will provide access for the Company's planned implementation of the Railveyor system, which NioCorp announced in 2024 as the preferred bulk material handling solution for the Elk Creek Project. (See this announcement). Utilizing the Railveyor system replaces the previously planned twin-shaft design and, according to the scoping study, is expected to reduce initial capital costs through simplified underground infrastructure and a shorter pre-development schedule.

The Railveyor system will run on electricity, as will all of NioCorp's underground mining equipment, offering potential environmental, safety, and operational benefits when compared to conventional diesel-powered underground mining systems.

"Approval of the Portal Project is a significant milestone for NioCorp," said Mark A. Smith, CEO and Chairman of NioCorp. "This initiative allows us to advance one of the critical path schedule items for the project as we continue working toward securing the remaining financing needed for the Elk Creek Project. We greatly appreciate the strong support shown by Nebraskans and our project partners as we continue advancing."

"Given the size of this excavation work, the Portal Project really marks the beginning of a major pre-construction activity at the Elk Creek Project site and is an important step toward preparing for underground development," said Scott Honan, President and Chief Operating Officer of NioCorp. "Advancing this work now helps keep our schedule moving. It's going to be exciting for the community to see major activity at the site - something many of us have been looking forward to for quite some time."

Qualified Persons:

Scott Honan, M.Sc., SME-RM, COO of NioCorp Developments Ltd., a Qualified Person as defined by National Instrument 43-101, has reviewed and approved the technical information contained in this news release.

# # #

FOR MORE INFORMATION:

Jim Sims, Chief Communications Officer, NioCorp Developments Ltd., (720) 334-7066, jim.sims@niocorp.com

Alex Guthrie, Director, Investor Relations, NioCorp Developments Ltd., (720) 334-7066, aguthrie@niocorp.com

@NioCorp $NB #Niobium #Scandium #rareearth #neodymium #dysprosium #terbium #ElkCreek

ABOUT NIOCORP

NioCorp is developing the Elk Creek Project that is expected to produce niobium, scandium, and titanium. The Company also is evaluating the potential to produce several rare earths from the Elk Creek Project. Niobium is used to produce specialty alloys as well as High Strength, Low Alloy steel, which is a lighter, stronger steel used in automotive, structural, and pipeline applications. Scandium is a specialty metal that can be combined with Aluminum to make alloys with increased strength and improved corrosion resistance. Scandium is also a critical component of advanced solid oxide fuel cells. Titanium is used in various lightweight alloys and is a key component of pigments used in paper, paint and plastics and is also used for aerospace applications, armor, and medical implants. Magnetic rare earths, such as neodymium, praseodymium, terbium, and dysprosium are critical to the making of neodymium-iron-boron magnets, which are used across a wide variety of defense and civilian applications.

Forward-Looking Statements

This press release contains forward-looking statements within the meaning of the United States Private Securities Litigation Reform Act of 1995 and forward-looking information within the meaning of applicable Canadian securities laws. Forward-looking statements may include, but are not limited to, statements regarding the expected scope, timing, sequencing, progression and capital cost of the Portal Project and related pre-construction work at the Elk Creek Project, including the anticipated start dates for access road construction, stormwater infrastructure, portal excavation, marine sediment drill-and-blast activities, ramp foundation work, and arch installation, as well as expectations regarding future underground development and advancement toward construction; NioCorp's expectation of producing niobium, scandium, and titanium, and the potential of producing rare earths, at the Elk Creek Project; and NioCorp's ability to secure sufficient project financing to complete construction of the Elk Creek Project and move it to commercial operation. Forward-looking statements are typically identified by words such as "plan," "believe," "expect," "anticipate," "intend," "outlook," "estimate," "forecast," "project," "continue," "could," "may," "might," "possible," "potential," "predict," "should," "would" and other similar words and expressions, but the absence of these words does not mean that a statement is not forward-looking.

The forward-looking statements are based on the current expectations of the management of NioCorp and are inherently subject to uncertainties and changes in circumstances and their potential effects and speak only as of the date of such statement. There can be no assurance that future developments will be those that have been anticipated. Forward-looking statements reflect material expectations and assumptions, including, without limitation, expectations and assumptions relating to: NioCorp's ability to receive sufficient project financing for the construction of the Elk Creek Project on acceptable terms, or at all; the future price of and demand for metals, including aluminum-scandium alloy; and the stability of the financial and capital markets. Such expectations and assumptions are inherently subject to uncertainties and contingencies regarding future events and, as such, are subject to change. Forward-looking statements involve a number of risks, uncertainties or other factors that may cause actual results or performance to be materially different from those expressed or implied by these forward-looking statements. These risks and uncertainties include, but are not limited to, those discussed and identified in public filings made by NioCorp with the Securities and Exchange Commission and with the applicable Canadian securities regulatory authorities and the following: NioCorp's requirement of significant additional capital; NioCorp's ability to receive sufficient project financing for the construction of the Elk Creek Project on acceptable terms, or at all; NioCorp's ability to achieve the required milestones and receive the full $10.0 million in reimbursement under the Project Sub-Agreement with Advanced Technology International, an entity acting on behalf of the Defense Industrial Base Consortium under the authority of the U.S. Department of War; NioCorp's ability to receive a final commitment of financing from the Export-Import Bank of the United States or other debt financing or financial support on acceptable timelines, on acceptable terms, or at all; NioCorp's ability to access the full amount of the expected net proceeds under the standby equity purchase agreement (the "Yorkville Equity Facility Financing Agreement") with YA II PN, Ltd., an investment fund managed by Yorkville Advisors Global, LP; NioCorp's ability to continue to meet the listing standards of The Nasdaq Stock Market LLC; risks relating to NioCorp's common shares, including price volatility, lack of dividend payments and dilution or the perception of the likelihood of any of the foregoing; the extent to which NioCorp's level of indebtedness and/or the terms contained in agreements governing NioCorp's indebtedness, if any, the Yorkville Equity Facility Financing Agreement or other agreements may impair NioCorp's ability to obtain additional financing, on acceptable terms, or at all; covenants contained in agreements with NioCorp's secured creditors that may affect its assets; NioCorp's limited operating history; NioCorp's history of losses; the material weaknesses in NioCorp's internal control over financial reporting, NioCorp's efforts to remediate such material weaknesses and the timing of remediation; the possibility that NioCorp may qualify as a passive foreign investment company under the U.S. Internal Revenue Code of 1986, as amended (the "Code"); the potential that the business combination with GX Acquisition Corp. II and other related transactions could result in NioCorp becoming subject to materially adverse U.S. federal income tax consequences as a result of the application of Section 7874 and related sections of the Code; cost increases for NioCorp's exploration and, if warranted, development projects; a disruption in, or failure of, NioCorp's information technology systems, including those related to cybersecurity; equipment and supply shortages; variations in the market demand for, and prices of, niobium, scandium, titanium and rare earth products; current and future offtake agreements, joint ventures, and partnerships, including NioCorp's ability to negotiate extensions to existing agreements or to enter into new agreements, on favorable terms or at all; NioCorp's ability to attract qualified management; estimates of mineral resources and reserves; mineral exploration and production activities; feasibility study results; the results of metallurgical testing; the results of technological research; changes in demand for and price of commodities (such as fuel and electricity) and currencies; competition in the mining industry; changes or disruptions in the securities markets; legislative, political or economic developments, including changes in federal and/or state laws that may significantly affect the mining and scandium alloy industries; trade policies and tensions, including tariffs; inflationary pressures; the impacts of climate change, as well as actions taken or required by governments related to strengthening resilience in the face of potential impacts from climate change; the need to obtain permits and comply with laws and regulations and other regulatory requirements; the timing and reliability of sampling and assay data; the possibility that actual results of work may differ from projections/expectations or may not realize the perceived potential of NioCorp's projects; risks of accidents, equipment breakdowns, and labor disputes or other unanticipated difficulties or interruptions; the possibility of cost overruns or unanticipated expenses in development programs; operating or technical difficulties in connection with exploration, mining, development or scandium-alloy production activities; management of the water balance at the Elk Creek Project site; land reclamation requirements related to the Elk Creek Project; the speculative nature of mineral exploration and development, including the risks of diminishing quantities of grades of reserves and resources; claims on the title to NioCorp's properties; the infringement or loss of NioCorp's intellectual property rights; potential future litigation; and NioCorp's lack of insurance covering all of NioCorp's operations.

Should one or more of these risks or uncertainties materialize or should any of the assumptions made by the management of NioCorp prove incorrect, actual results may vary in material respects from those projected in these forward-looking statements.

All subsequent written and oral forward-looking statements concerning the matters addressed herein and attributable to NioCorp or any person acting on its behalf are expressly qualified in their entirety by the cautionary statements contained or referred to herein. Except to the extent required by applicable law or regulation, NioCorp undertakes no obligation to update these forward-looking statements to reflect events or circumstances after the date hereof to reflect the occurrence of unanticipated events.

SOURCE: NioCorp Developments Ltd.



View the original press release on ACCESS Newswire

FAQ

What did NioCorp (NB) announce about the Elk Creek portal on December 22, 2025?

NioCorp announced Board approval of the Mine Portal Project for Elk Creek, with work expected to begin in Q1 2026 and an estimated capital cost of $44.6 million.

How much will the Elk Creek Portal Project cost and when does construction start for NB?

The company estimates the Portal Project capital cost at approximately $44.6 million, with construction expected to commence in Q1 2026.

What is the role of the Railveyor™ system in NioCorp's Elk Creek (NB) plan?

The portal will provide access to implement the electric Railveyor™ bulk-handling system, which replaces the previously planned twin-shaft design and is expected to reduce initial capital and shorten pre-development timing.

Does the Elk Creek Portal announcement for NB mention financing requirements?

Yes, management stated advancing the Portal helps schedule progress while the company continues working to secure the remaining financing needed for Elk Creek.

What scope of work is included in NioCorp's Portal Project at Elk Creek (NB)?

The Board-approved scope includes excavation to bedrock, drilling and blasting to form twin ramps, on-site access road construction, and supporting infrastructure.

Will NioCorp's underground mining equipment at Elk Creek (NB) use diesel or electric power?

NioCorp says the Railveyor™ and all planned underground mining equipment will run on electricity, offering potential environmental and safety benefits over diesel systems.
Niocorp Developm

NASDAQ:NB

NB Rankings

NB Latest News

NB Latest SEC Filings

NB Stock Data

726.86M
13.24M
Other Industrial Metals & Mining
Metal Mining
Link
United States
CENTENNIAL