STOCK TITAN

North Bay Resources Announces April Gold Concentrate Sales and Mobilization at Fran Gold Project, British Columbia

Rhea-AI Impact
(Moderate)
Rhea-AI Sentiment
(Neutral)
Tags
North Bay Resources (OTC: NBRI) reported results from its April 2025 gold concentrate test shipments from the Fran Gold Project processed at Bishop Gold Mill. The company completed two shipments totaling 667 wet lbs, with settlement values of $1,836.88 and $1,298.62 respectively. After upgrades to the mill's raker/classifier system, recovery improved to within 10% of the first shipment. The company aims to increase production to 100 tons per week initially, scaling to 100 tons per day. At the Fran Gold Project, crews will mobilize in June for development and stockpile processing. The project's resource estimate shows 323,170 oz Au in the Main Zone (20M tonnes at 0.50 g/t) and 474,001 oz Au total including East Extension (43.8M tonnes at 0.34 g/t). With gold at $3,100/oz, estimated gross value is $50/tonne against $9/tonne processing costs.
North Bay Resources (OTC: NBRI) ha riportato i risultati delle spedizioni di prova di concentrato d'oro di aprile 2025 dal progetto Fran Gold, trattate presso il Bishop Gold Mill. L'azienda ha completato due spedizioni per un totale di 667 libbre umide, con valori di liquidazione rispettivamente di $1.836,88 e $1.298,62. Dopo gli aggiornamenti al sistema raker/classificatore del mulino, il recupero è migliorato fino a raggiungere il 90% del valore della prima spedizione. L'azienda punta a incrementare la produzione inizialmente a 100 tonnellate a settimana, per arrivare a 100 tonnellate al giorno. Al progetto Fran Gold, le squadre si mobiliteranno a giugno per lo sviluppo e la lavorazione delle scorte. La stima delle risorse del progetto indica 323.170 oz Au nella Main Zone (20 milioni di tonnellate a 0,50 g/t) e 474.001 oz Au totali includendo l'East Extension (43,8 milioni di tonnellate a 0,34 g/t). Con l'oro a $3.100/oz, il valore lordo stimato è di $50/tonnellata rispetto ai costi di lavorazione di $9/tonnellata.
North Bay Resources (OTC: NBRI) informó los resultados de los envíos de prueba de concentrado de oro de abril de 2025 del Proyecto Fran Gold, procesados en Bishop Gold Mill. La compañía completó dos envíos que sumaron 667 libras húmedas, con valores de liquidación de $1,836.88 y $1,298.62 respectivamente. Tras mejoras en el sistema raker/clasificador del molino, la recuperación mejoró hasta alcanzar el 90% del primer envío. La empresa busca aumentar la producción inicialmente a 100 toneladas por semana, escalando a 100 toneladas por día. En el Proyecto Fran Gold, los equipos se movilizarán en junio para el desarrollo y procesamiento de reservas. La estimación de recursos del proyecto muestra 323,170 oz Au en la Zona Principal (20 millones de toneladas a 0,50 g/t) y 474,001 oz Au en total incluyendo la Extensión Este (43,8 millones de toneladas a 0,34 g/t). Con el oro a $3,100/oz, el valor bruto estimado es de $50/tonelada frente a costos de procesamiento de $9/tonelada.
North Bay Resources(OTC: NBRI)는 2025년 4월 프랜 골드 프로젝트에서 Bishop Gold Mill에서 처리한 금 농축물 시험 선적 결과를 보고했습니다. 회사는 총 667파운드의 습중량을 두 차례 선적했으며, 정산 가치는 각각 $1,836.88와 $1,298.62였습니다. 제분소의 레이커/분류기 시스템 업그레이드 후 회수율이 첫 번째 선적의 90% 수준까지 개선되었습니다. 회사는 초기 생산량을 주당 100톤으로 늘리고, 이후 일일 100톤까지 확대하는 것을 목표로 하고 있습니다. 프랜 골드 프로젝트에서는 6월에 작업팀이 개발 및 재고 처리 작업을 위해 동원될 예정입니다. 프로젝트 자원 추정치는 메인 존에서 323,170 온스 Au(2,000만 톤, 0.50 g/t)이며, 동부 확장 구역을 포함한 총량은 474,001 온스 Au(4,380만 톤, 0.34 g/t)입니다. 금 가격이 온스당 $3,100일 때, 톤당 예상 총 가치는 $50이며 처리 비용은 톤당 $9입니다.
North Bay Resources (OTC : NBRI) a annoncé les résultats des expéditions tests d'avril 2025 de concentré d'or du projet Fran Gold, traitées à la Bishop Gold Mill. La société a réalisé deux expéditions totalisant 667 livres humides, avec des valeurs de règlement de 1 836,88 $ et 1 298,62 $ respectivement. Après des améliorations du système raker/classificateur du moulin, le taux de récupération s'est amélioré pour atteindre environ 90 % de celui de la première expédition. L'entreprise vise à augmenter la production initialement à 100 tonnes par semaine, puis à passer à 100 tonnes par jour. Sur le projet Fran Gold, les équipes seront mobilisées en juin pour le développement et le traitement des stocks. L'estimation des ressources du projet indique 323 170 oz Au dans la zone principale (20 millions de tonnes à 0,50 g/t) et 474 001 oz Au au total, incluant l'extension Est (43,8 millions de tonnes à 0,34 g/t). Avec l'or à 3 100 $/oz, la valeur brute estimée est de 50 $/tonne, contre des coûts de traitement de 9 $/tonne.
North Bay Resources (OTC: NBRI) berichtete über die Ergebnisse der Goldkonzentrat-Testlieferungen vom April 2025 aus dem Fran Gold Projekt, verarbeitet in der Bishop Gold Mill. Das Unternehmen führte zwei Lieferungen mit insgesamt 667 nassen Pfund durch, mit Abrechnungswerten von jeweils 1.836,88 $ und 1.298,62 $. Nach Verbesserungen am Raker-/Klassifikatorsystem der Mühle verbesserte sich die Rückgewinnung auf etwa 90 % der ersten Lieferung. Das Unternehmen plant, die Produktion zunächst auf 100 Tonnen pro Woche zu steigern und später auf 100 Tonnen pro Tag auszubauen. Am Fran Gold Projekt werden die Teams im Juni für Entwicklungsarbeiten und die Verarbeitung von Lagerbeständen mobilisiert. Die Ressourcenschätzung des Projekts zeigt 323.170 Unzen Au in der Hauptzone (20 Mio. Tonnen bei 0,50 g/t) und 474.001 Unzen Au insgesamt einschließlich der Ost-Erweiterung (43,8 Mio. Tonnen bei 0,34 g/t). Bei einem Goldpreis von 3.100 $/Unze beträgt der geschätzte Bruttowert 50 $/Tonne gegenüber Verarbeitungskosten von 9 $/Tonne.
Positive
  • Mill upgrades improved recovery and reduced moisture content by 60%
  • Resource estimate shows significant gold potential with 474,001 oz Au total
  • Favorable economics with $50/tonne value vs $9/tonne processing costs
  • Strategic location near major mines (Centerra's Mt. Milligan and Artemis Gold's Blackwater)
  • Plans for production ramp-up to 100 tons per day
Negative
  • Current production volumes remain small with only 667 wet lbs processed in April
  • Equipment issues affected second shipment's recovery rates
  • Resource estimate is non-NI 43-101 compliant
  • Relatively low grade deposit (0.34-0.50 g/t Au)

BISHOP, Calif., May 28, 2025 (GLOBE NEWSWIRE) -- North Bay Resources, Inc. (the “Company” or “North Bay”) (OTC: NBRI) is pleased to announce final acceptance and settlement of the Company’s 2nd and 3rd gold concentrate test shipments from the Company’s Fran Gold Project processed at the Company’s Bishop Gold Mill. Results of April test shipments are as follows:

Refinery Settlement #2
    
 LBS. (WET)265 
 MOISTURE16.20% 
 LBS (DRY)222 
 DST0.111 
    
 Au oz/dst5.614 
 Ag oz/dst2.506 
    
 Au:0.623 oz 
 Ag:0.278 oz 
    
 Metal Price May 20, 2025  
 Au$3,261.55 
 Ag$32.50 
    
 Total Value$1,836.88 
    


Refinery Settlement #3
    
 LBS. (WET)342 
 MOISTURE7.15% 
 LBS (DRY)318 
 DST0.159 
    
 Au oz/dst2.770 
 Ag oz/dst1.516 
    
 Au:0.440 oz 
 Ag:0.241 oz 
    
 Metal Price May 20, 2025  
 Au$3,261.55 
 Ag$32.50 
    
 Total Value$1,298.62 
    
    

Bishop Gold Mill Operations

Gold concentrate shipments in April, 2025 to the Company’s refinery partner Just Refiners, Reno, NV totaled 667 wet lbs. These are the second and third gold concentrate test shipments from the Bishop Gold Mill. Approximately 8 and 4 gross tons were processed for shipments #2 and #3 with an average recovered grade of 0.08 and 0.11 ounces per ton respectively reflecting a per ton value of $260 and $360 per ton. The low value per ton of the 2nd shipment reflected a breakdown period of the raker/classifier where heavy and inconsistent grind size occurred. Upgrades and repairs were made to the raker/classifier throughout the month of April including removal and hot welding of the attenuator and fabrication and installation of a new control arm. This resulted in a greatly increased consistency and reduction in size of material feed to the centrifuge and marked improvement in produced gold per ton between shipment #2 and #3 reflecting the upgrades and return to recovery within 10% of shipment #1. Final optimization is being made to increase grind size from 150-200 US Mesh to 80-100 US Mesh to further increase recovery. The upgrades to the raker/classifier may have resulted in overgrinding and this final optimization of size and targeted total dissolved solids percentage of 30% is underway. Implementation of the drying circuit reduced moisture content by 60% from 16.20% between shipment #2 and shipment #3. Focus remains ramp-up in preparation for increased deliveries of 100 tons per week in the short term and full commercial production of 100 tons per day thereafter.

Flotation circuit design has been finalized and an additional mixing tank is being added to augment the flotation circuit. The new mixing tank will be used for the addition of gold and sulphide promoter where slurry resides prior to the addition of frother and flow to the flotation cells. The reagents provide a hydrophobic response to the water and rise on the air bubbles where the gold is pushed by rotating paddles from the surface of the cells into a concentrate collector. The concentrate is then re-circulated through the centrifuge to produce a high grade concentrate for shipment to the Company’s refinery partner for gold sale. Metallurgical testing has shown a high affinity for flotation and significant additional recovery of fine gold is anticipated.

Fran Gold Mobilization

Mobilization for development at Fran Gold is underway and crews will be on-site in early June. Work will consist of exploration for further development and preparation for additional shipments of ore from existing stockpiles throughout the Summer. The Company will implement grade control on the stockpiles to increase per tonnage value and maximize head grade at the mill, while providing sufficient ore for continuous throughput. In preparation for mining, once stockpiles are depleted, the Company will focus in and around surface trenches B + C as well as trench A. Trenches B + C have shown consistent grade of 0.5 ounces per ton over 30 meters (100 feet).

Fran Gold Project

As a result of the recently discovered bulk tonnage deposit and associated resource estimate (see Press Release dated May 13, 2025), the Company has implemented a two-pronged approach to the Fran Gold Project,   In addition to providing feedstock to the Company’s Bishop Gold Mill from stockpiles and the high grade surface oxide zone, exploration will now occur in the infill area between the Main Bullion Alley Zone and East Zone as well as further to the East and North-east and at a number of other known discoveries on the property Re-analyses of Au soil grids has shown a number of anomalies within or in close proximity to the Main and East Zones showing both gold and, of particular note a significant increase in copper grade, in a NE trending direction. A very large geological intrusion exists and geomagnetic halo exists to the East, common with porphyry style deposits, along with the noted increase in base metal grades with gold. The goal is to further expand the known mineralized zone with current resource estimate (non-NI 43-101) as follows:

Bullion Alley - Main Zone
    
Mass
(tonnes)
Average (g/t)Total
(grams)
Total
(tr. ounces)
20,035,1460.5010,051,730323,170
    


Bullion Alley - Main Zone + East Extension
    
Mass
(tonnes)
Average
(g/t)
Total
(grams)
Total
(tr. ounces)
43,797,2340.3414,743,070474,001
    
    

Using a gold price of $3,100 per ounce, gross value in the Main Zone is estimated at $50 per tonne. Mining costs at the nearby Blackwater Gold Mine are $9 per tonne processed. As a result, the Company is proceeding with the development of the bulk tonnage deposit and has begun consultation with Mine Engineering firms regarding detailed economics, mine plan, and development.

Past exploration and development, including over 18,000m (55,000ft.) of diamond drilling, has shown large intercepts of mixed vein and disseminated gold. The deposit area has been identified to be in excess of 1000m x 100m x 300m within a known strike length of 1700m. The Fran Gold Project is next to Centerra Gold’s Mt. Milligan Project, with Reserves of 264Mt grading 0.3 gram per tonne gold and 0.2% copper and proximate to Artemis Gold’s Blackwater Mine, with Proven and Probable Reserves of 334Mt grading 0.8 grams per tonne gold. Both Mt. Milligan and the Blackwater Mine are two of the largest new copper/gold and gold mines respectively, in North America.

On behalf of the Board of Directors of

NORTH BAY RESOURCES INC.

Jared Lazerson
CEO

info@northbay-resources.com
northbay-resources.com

X: @NorthBayRes
YouTube: North Bay Resources - YouTube
LinkedIn: North Bay Resources Inc | LinkedIn

This news release may contain certain “Forward-Looking Statements” within the meaning of the United States Private Securities Litigation Reform Act of 1995 and applicable Canadian securities laws.


FAQ

What were NBRI's April 2025 gold concentrate shipment results?

NBRI completed two shipments totaling 667 wet lbs, with settlement values of $1,836.88 and $1,298.62, processed from approximately 8 and 4 gross tons respectively.

What is the current resource estimate for NBRI's Fran Gold Project?

The non-NI 43-101 resource estimate shows 323,170 oz Au in the Main Zone (20M tonnes at 0.50 g/t) and 474,001 oz Au total including East Extension (43.8M tonnes at 0.34 g/t).

What is NBRI's production target for the Bishop Gold Mill?

NBRI aims to increase production to 100 tons per week in the short term, with plans to scale up to full commercial production of 100 tons per day.

What are the estimated economics for NBRI's Fran Gold Project?

Using $3,100/oz gold price, the project has an estimated gross value of $50 per tonne, with mining costs of $9 per tonne processed.

Where is NBRI's Fran Gold Project located?

The Fran Gold Project is located in British Columbia, adjacent to Centerra Gold's Mt. Milligan Project and near Artemis Gold's Blackwater Mine.
North Bay Resour

OTC:NBRI

NBRI Rankings

NBRI Latest News

NBRI Stock Data

6.06M
3.85B
Other Precious Metals & Mining
Basic Materials
Link
United States
Skippack