Nova Minerals (NYSE American: NVA, ASX: NVA) provided a detailed update on its 2026 field season at the Estelle Gold and Critical Minerals Project in Alaska. Three diamond drill rigs are operating continuously, with active drilling at the Styx, RPM, Stibium and Train prospects, including bulk sampling of over 50 tons of stibnite-rich material for processing through the Whiskey Bravo ore sorter as initial feed for the Port MacKenzie antimony pilot plant.

Nova reported progress on permitting, submitting a detailed plan of operations for the antimony project to the Alaska Department of Natural Resources and completing surveys to support about 30 miles of additional access trails. Military-grade antimony trisulfide and antimony metal have been produced at laboratory scale, and more than 40 containers of process equipment are in transit ahead of plant construction expected to start in 2026. Infrastructure work such as gravel quarrying, Stibium trail construction, runway extension, geologic reconnaissance, a property-wide ZTEM survey and board site visits are also underway, supporting a path toward domestic antimony supply and ongoing gold resource development.

Loading...
Loading translation...

Positive

  • None.

Negative

  • None.

Market Context

CEO Christopher Gerteisen reported net buying totaling 2,012 shares in the prior 90 days. That insid...
Analysis

CEO Christopher Gerteisen reported net buying totaling 2,012 shares in the prior 90 days. That insider context adds support to the field update, while permitting remained under final review and laboratory samples awaited independent analysis.

Key Figures

Operating drill rigs: three drill rigs Completed Styx holes: two drill holes Quartz-stibnite vein thickness: 1 m-thick +5 more
8 metrics
Operating drill rigs three drill rigs 2026 field season at Estelle
Completed Styx holes two drill holes Styx prospect
Quartz-stibnite vein thickness 1 m-thick Styx prospect
Stibnite-rich material more than 50 tons Transported to camp for processing
RPM strike tested more than 3 km RPM drilling
Gold assay up to 128 g/t Au Previous Train surface sampling
Access trails under permitting approximately 30 miles Korbel and RPM trails
U.S. Department of War award US$43.4 million Funding for domestic antimony supply chain

Historical Context

5 past events · Latest: Jul 24 (Neutral)
Pattern 5 events
Date Event Sentiment 24h Move Catalyst
Jul 24 Strategic alignment update Neutral -1.1% Company linked antimony strategy to U.S. defense supply-chain priorities
Jul 13 Pilot plant engineering Positive +9.3% Engineering and design completed for fully funded antimony pilot plant
Jul 01 Board appointment Positive +4.7% Former metals and mining finance professional joined the board
Jun 30 Market capitalization clarification Neutral +8.5% Company corrected reported post-redomiciliation capitalization and share count
Jun 29 Gold flotation results Positive -5.8% Bench-scale testing produced high-grade concentrate with recoveries exceeding 95%

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

Pattern Detected

Nova's recent execution and corporate announcements produced mixed outcomes, with positive reactions to pilot-plant engineering and board news but divergence on other favorable updates.

Key Terms

stibnite, ore sorter, antimony trisulfide, hydrometallurgical
4 terms
stibnite technical
"the 1 m-thick quartz-stibnite vein"
Stibnite is a naturally occurring mineral made of antimony and sulfur (chemical formula Sb2S3) and is the main ore from which the metal antimony is extracted. It matters to investors because antimony is a raw material used in flame retardants, batteries, alloys and some electronic components, so discoveries, mining output or supply disruptions of stibnite can influence commodity prices and the prospects of mining and manufacturing companies — like finding a concentrated vein of a useful metal.
ore sorter technical
"processing through the Whiskey Bravo ore sorter"
An ore sorter is an automated machine that scans individual rocks or chunks of mined material with sensors (like X-rays, cameras, or lasers) and separates pieces that contain valuable minerals from waste rock, acting like a high‑tech sieve that checks each rock for value. For investors, ore sorters can raise the concentration of payable material sent to a mill, cut hauling and processing costs, reduce waste and environmental impact, and therefore improve project economics and cash flow.
antimony trisulfide technical
"Military-grade antimony trisulfide and antimony metal"
Antimony trisulfide is a chemical compound made from the metal antimony combined with sulfur; think of it as a stable material created by mixing two basic elements. It is used in products ranging from flame retardants and pigments to certain electronic and ammunition components, so changes in its supply, regulation, or production costs can affect manufacturers, miners and downstream businesses — making it a commodity of interest to investors tracking raw-material risk and price swings.
hydrometallurgical technical
"a proprietary hydrometallurgical processing method"
Hydrometallurgical describes methods that use water-based chemistry to dissolve, separate and recover metals from ores, concentrates or recycled materials, much like dissolving sugar to separate it from tea and then collecting the sugar back out. It matters to investors because these processes determine how much metal a project can realistically produce, the operating cost and environmental footprint, and therefore influence revenue potential, capital needs and regulatory risk.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Anchorage, Alaska, Aug. 12, 2026 (GLOBE NEWSWIRE) -- Nova Minerals Corp (“Nova Minerals” or the “Company”) (NYSE American: NVA | ASX: NVA) is pleased to provide an update on its 2026 field season activities at its Estelle Gold and Critical Minerals Project (“Estelle” or the “Project”) in Alaska.

Highlights

  • Three Drill Rigs Currently Operating: The Company currently has three diamond drill rigs operating onsite, conducting drilling 24 hours a day, seven days a week throughout the Alaskan summer.
  • Bulk Sampling and Drilling at the Styx Prospect: Two diamond drill holes have now been completed from a newly constructed drill pad on the eastern side of Styx to test the down-dip extent of the 1 m-thick quartz-stibnite vein. In parallel, more than 50 tons of stibnite-rich material has been transported to camp for processing through the Whiskey Bravo ore sorter. This ore sorted coarse concentrate will provide initial feed material for the Port MacKenzie antimony pilot plant.
  • RPM Drilling Ongoing: Several drill pads have been established along the ridgeline and in the eastern valley to test more than 3 km of strike at RPM. Drilling conducted at RPM so far this year has resulted in several newly discovered mineralized instrusives, and we eagerly await the assay results from these holes. Furthermore, at RPM Valley, several pads have been established to support infill and expansion of the existing resource.
  • Stibium Drilling Ongoing: Due to difficult drilling conditions encountered from the top of the ridge, a new pad was established on the south face of Stibium lower down on the slope and 200m closer to the target zone. Drilling is ongoing.
  • Further Train Drilling Completed: Two additional exploratory drill holes have been completed from a newly established pad at Train to test the depth and extent of outcropping mineralized quartz-arsenopyrite-chalcopyrite veining. Previous surface sampling returned high-grade gold assays of up to 128 g/t Au, providing a strong target for follow-up drilling.
  • Permitting Progress: A detailed plan of operations for the antimony project has been submitted to the Alaska Dept of Natural Resources for final review and approval. Civil, wetlands and cultural resource surveys have also been completed along the Korbel and RPM trails, supporting the permitting process for approximately 30 miles of additional access trails.
  • Antimony Trisulfide Production: Military-grade antimony trisulfide and antimony metal have been successfully produced at laboratory scale using a proprietary hydrometallurgical processing method. Samples have been submitted for independent analysis.
  • Infrastructure Work Ongoing: Gravel quarrying activities are continuing, supported by the new machinery mobilized to site via the snow road this season. Construction of the Stibium trail has progressed to mile 6 and the first half mile of road sub-base has been laid, while the runway extension is also well underway.
  • Plant Equipment Nearing Delivery: Over 40 containers of process equipment are in transit and being consolidated in Seattle ahead of a scheduled late-August barge shipment to Port MacKenzie, Alaska. Plant construction is expected to commence in 2026.
  • Geologic Reconnaissance Ongoing: Geologic mapping and sampling have been ongoing with a detailed focus at RPM and Train. Property scale sampling is underway to provide more coverage over the ~200 sq mile Estelle Gold and Critical Minerals Project claim block.
  • Geophysics: A ZTEM (Z-Axis Tipper Electromagnetic) survey has been flown across the entire claim block. The data is currently under evaluation and will help refine targeting for drilling and reconnaissance, with the potential to unlock further discoveries.
  • Board and Management Site Visits: Independent Directors Avi Gellar and Dovi Berger visited the Estelle Project site late last month. Independent Chairman Richard Beazley, Executive Director Craig Bentley and Nova CFO Ashlie Thorburn are currently in Alaska visiting the site and meeting with State and other government officials.

Nova CEO, Mr Christopher Gerteisen, commented:

“This field season is the clearest evidence yet that Estelle is moving from exploration into execution. With three rigs running around the clock, permitting advancing across our mine plans and processing facilities, and mill equipment already in transit, every workstream is converging toward Estelle' first antimony production.

“We are converting years of exploration success into a near-term, funded path to production for antimony while also progressing Estelle’s Gold Project, one of the world’s largest undeveloped gold resources.

“Having successfully produced military-grade antimony trisulfide and antimony metal at laboratory scale, we are taking tangible steps toward securing a domestic supply of antimony for the United States, positioning Nova at the centre of America’s critical minerals strategy.”


Figure 1. Estelle property map with 2026 field season progress highlighted


Figure 2. Stibium drilling


Figure 3. Gravel quarrying for the Stibium trail, airstrip expansion and ore sorter site


Figure 4. RPM ridge drilling


Figure 5. Large Caribou class aircraft landing at the Whiskey Bravo airstrip


Figure 6. New pad being built at the bottom of the ridge at RPM

 

Figure 7. Nova CEO, Christopher Gerteisen, and Independent Chairman, Richard Beazley examining some of the stibnite rich material brought down from the Styx prospect

About Nova Minerals Corp

Nova Minerals Corp is advancing one of the world’s largest undeveloped gold deposits into production and securing a US domestic supply of the critical mineral antimony. The Company is focused on the exploration and development of the Estelle Gold and Critical Minerals Project, located in Alaska, a tier-one mining jurisdiction.

Estelle hosts two defined multi-million-ounce gold resources, and more than 20 prospects distributed along a 35-kilometre mineralized trend, in the prolific Tintina Gold Belt, a province which hosts a >220 million ounce (Moz) documented gold endowment and some of the world's largest gold mines and discoveries including, Kinross Gold Corporation's Fort Knox Gold Mine. In parallel, Nova is advancing its critical minerals strategy, fully-funded by a US$43.4 million U.S. Department of War award to develop a domestic antimony supply chain, targeted for production in 2027.

Further discussion and analysis of the Estelle Project is available through the interactive Vrify 3D animations, presentations, and videos, all available on the Company’s website www.novamineralscorp.com.

Forward Looking Statements

This press release contains “forward-looking statements” within the meaning of Section 27A of the Securities Act, and Section 21E of the Exchange Act which are subject to the “safe harbor” created by those sections. All statements, other than statements of historical fact, contained in this press release are forward-looking statements and that are subject to substantial risks and uncertainties. Forward-looking statements contained in this press release may be identified by the use of words such as “anticipate,” “believe,” “contemplate,” “could,” “estimate,” “expect,” “intend,” “seek,” “may,” “might,” “plan,” “potential,” “predict,” “project,” “target,” “aim,” “should,” “will,” “would,” or the negative of these words or other similar expressions, although not all forward-looking statements contain these words. Forward-looking statements are based on Nova Minerals Corp’s current expectations and are subject to inherent uncertainties, risks and assumptions that are difficult to predict. Further, certain forward-looking statements are based on assumptions as to future events that may not prove to be accurate. Forward-looking statements contained in this announcement are made as of this date, and Nova Minerals Corp undertakes no duty to update such information except as required under applicable law.

For further information:

Nova Minerals: Media:Investor Relations:
Craig BentleyJenna ShindermanDave Gentry, CEO
DirectorSodali & CoRedChip Companies, Inc.
Ph: 1-720-550-4223Ph: 1-631-918-4047Ph: 1-407-644-4256
E: craig@novamineralscorp.comE: jenna.shinderman@sodali.comE: NVA@redchip.com

Attachments


FAQ

What 2026 field activities is Nova Minerals (NVA) carrying out at the Estelle Project?

Nova Minerals is running three diamond drill rigs continuously and conducting bulk sampling, geologic mapping, geophysics, and infrastructure work at Estelle. According to Nova Minerals, drilling targets Styx, RPM, Stibium and Train, alongside quarrying, trail building and runway extension to support long-term project development.

How is Nova Minerals advancing its antimony project and pilot plant in 2026 (NVA)?

Nova Minerals has transported over 50 tons of stibnite-rich material for ore sorting and initial pilot plant feed. According to Nova Minerals, laboratory-scale production of military-grade antimony trisulfide and antimony metal has been achieved, with a detailed antimony plan of operations submitted for state review.

When is Nova Minerals targeting antimony production and how is it funded (NYSE American: NVA)?

Nova Minerals is targeting antimony production in 2027, supported by a US$43.4 million U.S. Department of War award. According to Nova Minerals, this funding fully backs development of a domestic antimony supply chain linked to its Estelle Gold and Critical Minerals Project in Alaska.

What drilling progress has Nova Minerals reported at RPM, Styx, Stibium and Train in 2026?

Nova Minerals has completed multiple drill pads and holes across RPM, Styx, Stibium and Train during the 2026 season. According to Nova Minerals, new mineralized intrusives were intersected at RPM, two down-dip holes were drilled at Styx, and exploratory holes tested mineralized veining at Train.

What permitting milestones has Nova Minerals (NVA) reached for Estelle access and antimony operations?

Nova Minerals submitted a detailed plan of operations for the antimony project to the Alaska Department of Natural Resources. According to Nova Minerals, civil, wetlands and cultural resource surveys along the Korbel and RPM trails support permitting for approximately 30 miles of additional access trails.

What infrastructure and plant equipment developments has Nova Minerals announced for 2026?

Nova Minerals continues gravel quarrying, Stibium trail construction to mile 6, and a runway extension at Estelle. According to Nova Minerals, over 40 containers of process equipment are being consolidated in Seattle for barge shipment to Port MacKenzie, with plant construction expected to begin in 2026.