Osisko Gold Provides Construction Progress Update on the Cariboo Gold Project
Valley portal excavation constraints lowered the expected year-end underground development rate, while production targets remain unchanged.
Sentiment and the balance of points
Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.
Rhea-AI Summary
Osisko Gold (OGG) reported construction progress at its Cariboo Gold Project, with first gold pour still targeted for Q1 2029. The company expects commercial production in H2 2029. Its 100%-owned British Columbia project was approximately 28% complete based on costs incurred through September 30, 2026. Cumulative spending was approximately C$355 million; the estimated remaining construction cost was approximately C$907 million, net of incurred costs, leases and estimated pre-production revenue.
Detailed engineering was approximately 42% complete, over 50% of procurement packages were awarded and commitments reached approximately C$360 million. Osisko Gold reduced its expected year-end underground development rate to approximately 360 metres monthly from 500, reflecting slower Valley portal excavation and construction constraints. The transmission-line occupation licence is expected in Q4 2026.
How this balance works
Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.
It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.
Rhea-AI Sentiment measures something else, the tone of the wording.
Hollow bars mark forward-looking points. How the balance works
Positive
- Moderate pointJDS received the continuing underground development contract in October 2026, following its construction management agreement.
- Minor point. Forward-looking: it has not happened yet and may not happen.Cariboo remains on schedule for targeted Q1 2029 first gold and expected H2 2029 commercial production.
- Minor pointProject completion reached approximately 28%, based on costs incurred through September 30, 2026.
- Minor pointDetailed engineering reached approximately 42% completion.
- Minor pointProcurement awards exceeded 50% of packages, with principal long-lead items largely secured.
16 minor points
- Minor pointUnderground development completed approximately 3.4 kilometres, advancing into the Lowhee and Cow Mountain zones.
- Minor point. Forward-looking: it has not happened yet and may not happen.Valley portal earthworks reached 85%, up from 1%; portal completion is expected in Q4 2026.
- Minor pointSite-wide earthworks reached 15%, up from 5%.
- Minor pointBonanza Ledge water pipelines reached 40%, up from 5%.
- Minor pointBonanza Ledge sediment control pond civil works reached 100%.
- Minor point. Forward-looking: it has not happened yet and may not happen.Bonanza Ledge water treatment expansion construction reached 100%; full operation is expected in Q4 2026.
- Minor point. Forward-looking: it has not happened yet and may not happen.Waste rock storage Phase 1a reached 95%, up from 40%; full completion is anticipated in mid-2027.
- Minor pointPermanent site camp upgrade and expansion are complete.
- Minor pointMain water treatment plant excavation is complete, with rebar and concrete placement underway.
- Minor point. Forward-looking: it has not happened yet and may not happen.Willow River bridge installation began; operation is expected in Q4 2026.
- Minor point. Forward-looking: it has not happened yet and may not happen.Underground equipment deliveries are expected from late 2026, with most scheduled during 2027.
- Minor point. Forward-looking: it has not happened yet and may not happen.Transmission-line long-lead items remain on track for site delivery in Q3 2027.
- Minor pointAll major construction, operation and closure permits were obtained in Q4 2024.
- Minor point. Forward-looking: it has not happened yet and may not happen.Cow drill gallery infill drilling is expected to commence in Q4 2026.
- Minor pointExploration has 16 active drill rigs: seven on project drilling and nine on regional targets.
- Minor point. Forward-looking: it has not happened yet and may not happen.Osisko expects approximately half of planned 160,000 project metres and approximately 50,000 regional metres drilled by year-end.
Negative
- Major point. Forward-looking: it has not happened yet and may not happen.Estimated remaining construction spending is approximately C$907 million, net of incurred costs, leases and estimated pre-production revenue.
- Moderate pointProject commitments total approximately C$360 million, including procurement across long-lead contract packages.
- Moderate point. Forward-looking: it has not happened yet and may not happen.Year-end underground development target fell to approximately 360 metres monthly from 500 amid Valley portal excavation constraints.
- Minor pointTransmission-line occupation licence remains pending, with receipt expected in Q4 2026.
News Explained
The update reports that in October Osisko Gold entered a project and construction management services agreement with JDS and awarded it the continuing underground development and related works contract, putting those roles with JDS.
Key Figures
- Project completion
- 28%
- Estimated as of September 30, 2026
- Cumulative costs incurred
- $355 million
- Through September 30, 2026; Canadian dollars
- Estimated remaining construction cost
- $907 million
- Incurred basis, net of costs incurred to date, leases and estimated pre-production revenue
- Project-to-date commitments
- $360 million
- Procurement commitments
- Detailed engineering
- 42% complete
- Cariboo Gold Project construction update
- Procurement packages awarded
- Over 50%
- Cariboo Gold Project construction update
- Underground development rate target
- 360 metres per month
- Expected by year-end 2026; previously 500 metres per month
- Production timeline
- First gold pour Q1 2029; commercial production H2 2029
- Company says the project remains on schedule
Key Terms
trifr technical
roadheader technical
ni 43-101 regulatory
fid financial
AI-generated analysis. How Rhea-AI works. Not financial advice.
(All dollar amounts are expressed in Canadian dollars, unless stated otherwise)
HIGHLIGHTS
|
TORONTO, Oct. 27, 2026 (GLOBE NEWSWIRE) -- Osisko Gold Group Inc. (NYSE: OGG, TSXV: OGG) ("Osisko Gold" or the "Company") is pleased to provide a construction update on progress made at the Company's
Sean Roosen, Chairman and CEO, commented: "We are pleased with the progress at the Cariboo Gold Project and continue to build construction momentum following our final investment decision announced in September. By making significant investments in critical path infrastructure, detailed engineering and procurement during the pre-construction phase, we've established a solid foundation for efficient execution as construction advances."
Key Highlights
- Overall project progress has reached approximately
28% , based on cumulative costs incurred through September 30, 2026, relative to the estimated go-forward capital obligation and incurred pre-construction costs (announced on September 14, 2026). - Approximately
$355 million has been incurred to September 30, 2026, including indirects and owners' costs, of which approximately$84 million was incurred from August 1 to September 30, 2026. - The estimated remaining cost to complete construction is approximately
$907 million on an incurred basis, net of costs incurred to date, leases and estimated pre-production revenue. - Detailed engineering is approximately
42% complete. - Over
50% of procurement packages have been awarded, with principal long-lead items largely secured and remaining contract packages being awarded or in progress, representing approximately$360 million in commitments project-to-date. - Safety performance remains a core pillar of project execution, with a year-to-date Total Recordable Injury Frequency Rate ("TRIFR") of 1.05 for 2026.
- On-site workforce currently exceeds 400 active personnel and continues to ramp up.
- Key recent progress includes: Valley Portal earthworks advanced to
85% complete (from1% ); Bonanza Ledge ("BL") water pipelines to40% (from5% ); site-wide earthworks to15% (from5% ); BL sediment control pond civil works to100% ; BL waste rock storage facility (Phase 1a) to95% (from40% ); BL water treatment plant expansion construction to100% , with final commissioning ongoing; and underground development to approximately11% (from8% ). Earthworks commenced on the Mine Site Complex ("MSC") water treatment plant pad, including the support site for the process plant area.
Virtual Site Tour
To view a 360-degree virtual site tour showcasing construction progress at the Cariboo Gold Project as of October 2026, please visit the Company's profile on the VRIFY platform: https://vrify.com/decks/24611.
Cariboo Gold Project Update
| Project Activity | Update |
| Health and Safety |
|
| Project Completion |
|
| Underground Development |
|
| Site Infrastructure |
|
| Earthworks |
|
| Equipment Fleet |
|
| Transmission Line |
|
| Engineering |
|
| Procurement |
|
| Construction Management |
|
| Operations Readiness |
|
| Permitting |
|
| Labour and workforce |
|
| First Nations and Stakeholder Engagement |
|
| Exploration |
|
Project Development Timeline to Commercial Production

Project Construction Photos
FIGURE 1: Mine Site Complex processing facility site earthworks underway.

FIGURE 2: Valley portal excavation with bedrock exposed at the Mine Site Complex.

FIGURE 3: Main water treatment plant foundation works at the Mine Site Complex.

FIGURE 4: Bonanza Ledge overview.

About The Cariboo Gold Project
The Cariboo Gold Project is a permitted,
Technical Reports
Scientific and technical information relating to the Cariboo Gold Project and the 2025 feasibility study on the Cariboo Gold Project is supported by the technical report, titled "NI 43-101 Technical Report, Feasibility Study for the Cariboo Gold Project, District of Wells, British Columbia, Canada" dated June 11, 2025 (with an effective date of April 25, 2025) (the "Cariboo Technical Report").
For readers to fully understand the information in the Cariboo Technical Report, reference should be made to the full text of the Cariboo Technical Report in its entirety, including all assumptions, parameters, qualifications, limitations and methods therein. The Cariboo Technical Report is intended to be read as a whole, and sections should not be read or relied upon out of context. The Cariboo Technical Report was prepared in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects ("NI 43-101") and is available electronically on SEDAR+ (www.sedarplus.ca) and on EDGAR (www.sec.gov) under Osisko Gold's issuer profile and on the Company's website at www.osiskogold.ca.
Qualified Persons
The scientific and technical information contained in this news release has been reviewed, verified and approved by Scott Smith, P. Geo., Vice President, Exploration of Osisko Gold, a "qualified person" within the meaning of NI 43-101.
| ABOUT OSISKO GOLD GROUP INC. Osisko Gold Group Inc. is a continental North American gold development company focused on past producing mining camps with district-scale potential. The Company's objective is to become an intermediate gold producer through the development of its flagship, fully permitted, For further information, visit our website at www.osiskogold.ca or contact: | ||
| Sean Roosen Chairman and CEO Email: sroosen@osiskogold.ca Tel: +1 (514) 940-0685 | Philip Rabenok Vice President, Investor Relations Email: prabenok@osiskogold.ca Tel: +1 (437) 423-3644 | |
CAUTION REGARDING FORWARD-LOOKING STATEMENTS
This news release contains "forward-looking information" (within the meaning of applicable Canadian securities laws) and "forward-looking statements" (within the meaning of the U.S. Private Securities Litigation Reform Act of 1995, as amended) (collectively, "forward-looking statements"). Such forward-looking statements, by their nature, require Osisko Gold to make certain assumptions and necessarily involve known and unknown risks and uncertainties that could cause actual results to differ materially from those expressed or implied in these forward-looking statements. Such forward-looking statements are not guarantees of performance and are identified with words such as "may", "will", "would", "could", "expect", "believe", "plan", "anticipate", "intend", "estimate", "potential", "propose", "project", "outlook", "foresee", "continue", "objective", "strategy", "scheduled", "target", "on track", variants of these words or the negative or comparable terminology, as well as terms usually used in the future and the conditional. Forward-looking statements in this news release include, but are not limited to, statements pertaining to: the expected timing of first gold pour, commercial production and key construction milestones at the Cariboo Gold Project, including underground development rates and targeted monthly advance rates, completion and collaring of the Valley portals, completion and full operation of the water treatment plants, completion of the waste rock storage facility, completion of the Willow River bridge, the arrival of transmission line long-lead packages, equipment deliveries, workforce ramp-up and operations readiness, including the expected timing of key hires; the ability to advance the Cariboo Gold Project through construction within the estimated budget, including the estimated project completion, the estimated remaining cost to complete construction, the expected leasing of equipment and estimated pre-production revenue, and the award of remaining contract packages; the expected performance of JDS under the project and construction management services agreement and the underground mine development contract; the Cariboo Gold Project's permitting status and the expected timing of receipt of the licence of occupation for the transmission line and of remaining authorizations, permit amendments and construction permits; continued engagement with First Nations and other stakeholders; the Company's planned drilling programs, including their scope, timing and the expected metres to be drilled by year-end, the timing of release of pending assay results, and the potential for resource conversion (if any); the Company's objective of becoming an intermediate gold producer; and the exploration potential and potential for future discoveries (if any) of its properties. Information contained in forward-looking statements is based upon certain material assumptions that were applied in drawing a conclusion or making a forecast or projection, including: construction proceeding on the anticipated schedule and within the estimated budget; the accuracy of the estimated remaining cost to complete and its underlying assumptions, including inflation, labour costs, exchange rates, the availability of equipment leasing on anticipated terms and gold prices realized on pre-production revenue; underground development rates improving as anticipated, including following the availability of additional headings through the Valley portals; the availability of personnel, contractors, equipment, supplies and infrastructure, including the timely delivery of long-lead items and mobile equipment; JDS and other contractors performing as expected; the absence of work stoppages or suspensions at the Cariboo Gold Project; the absence of unforeseen ground conditions or other geological challenges; required permits, authorizations and amendments being obtained and maintained in a timely manner; the continued support of First Nations and other stakeholders; the availability of drill rigs and personnel, and the ability of drilling and sampling to accurately predict mineralization; the Company's continued access to capital on acceptable terms; and the absence of material adverse changes in gold prices, foreign exchange rates and general economic and market conditions. Osisko Gold considers its assumptions to be reasonable based on information currently available but cautions the reader that its assumptions regarding future events, many of which are beyond the control of Osisko Gold, may ultimately prove to be incorrect since they are subject to risks and uncertainties that affect Osisko Gold and its business.
Such risks and uncertainties include, but are not limited to: risks associated with the development and construction of the Cariboo Gold Project, including construction delays, cost overruns, inflation and supply chain disruptions; underground development rates failing to improve as anticipated; work stoppages or suspensions at the Cariboo Gold Project; unforeseen ground, geotechnical or water management conditions; delays in commissioning of infrastructure, including the water treatment plants; contractor performance, including under the project and construction management services agreement and the underground mine development contract; delays or shortages in necessary equipment, supplies and infrastructure, including long-lead items; the inability to obtain equipment leasing on acceptable terms; pre-production revenue being lower than estimated; labour shortages, difficulties in recruiting key personnel and health and safety incidents; risks relating to third-party approvals, including the issuance of permits by governments, favourable regulatory conditions and approvals, capital market conditions and the Company's ability to access capital on terms acceptable to the Company for the contemplated exploration and development at the Company's properties; regulatory framework and presence of laws and regulations that may impose restrictions on mining; errors in management's geological modelling; the timing and ability of the Company to obtain and maintain required approvals and permits; the results of exploration activities, including the risk that further drilling does not support resource conversion; risks relating to exploration, development and mining activities; the global economic climate; fluctuations in metal and commodity prices; fluctuations in the currency markets; environmental risks; and community, non-governmental and governmental actions, including relationships with First Nations, and the impact of stakeholder actions. Readers are urged to consult the disclosure provided under the heading "Risk Factors" in the Company's annual information form for the year ended December 31, 2025 as well as those risks and factors disclosed in the Company's most recent financial statements and management's discussion and analysis and other public filings filed under Osisko Gold's issuer profile on SEDAR+ (www.sedarplus.ca) and on the SEC's EDGAR website (www.sec.gov), for further information regarding the risks and other factors facing the Company, its business and operations.
Although the Company believes the expectations conveyed by the forward-looking statements are reasonable based on information available as of the date hereof, no assurances can be given as to future results, levels of activity and achievements. Forward-looking statements are not guarantees of performance and there can be no assurance that these forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Readers are cautioned that the foregoing lists of assumptions, risks and uncertainties are not exhaustive. The forward-looking statements contained herein are made as of the date of this news release and, except as required by applicable law, the Company undertakes no obligation to update publicly or to revise any of the forward-looking statements, whether as a result of new information, future events or otherwise.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release. No stock exchange, securities commission or other regulatory authority has approved or disapproved the information contained herein.
Photos accompanying this announcement are available at:
https://www.globenewswire.com/NewsRoom/AttachmentNg/84970215-182d-4f92-8e41-3b561f05e93a
https://www.globenewswire.com/NewsRoom/AttachmentNg/c0fa1c58-4ce2-4cc3-ace6-323030ef70f0
https://www.globenewswire.com/NewsRoom/AttachmentNg/54ebdbbb-0ac7-4fac-8a53-3f4c47298bfd
https://www.globenewswire.com/NewsRoom/AttachmentNg/4372c834-f871-41d6-b446-d87984ee8829
https://www.globenewswire.com/NewsRoom/AttachmentNg/d1ef5117-4fc5-49fd-968b-4c958657aff6
FAQ
AI-generated questions and answers. How Rhea-AI works. Not financial advice.
When does Osisko Gold expect Cariboo to produce its first gold?
Osisko Gold targets Cariboo's first gold pour in Q1 2029 and expects commercial production in H2 2029. The project remains on schedule against those milestones.
How much construction spending remains at Osisko Gold's Cariboo project?
The estimated remaining construction cost is approximately C$907 million on an incurred basis, net of costs incurred to date, leases and estimated pre-production revenue. Approximately C$355 million had been incurred through September 30, 2026, including indirects and owners' costs.
Why did Osisko Gold reduce Cariboo's year-end underground development target?
Osisko Gold attributes the reduced target to slower Valley portal excavation involving competent rock, rockbreaking methods used to mitigate blasting noise, and concrete-curing measures in sub-zero temperatures. The company expects additional development headings through the Valley portal to improve advance rates in 2027 and beyond.
What safety performance did Osisko Gold report for Cariboo in 2026?
Cariboo's year-to-date Total Recordable Injury Frequency Rate was 1.05 for 2026. Approximately 1.02 million person-hours had been worked during that period.