Pulsar Helium Advances Appraisal Programme with Completion of Jetstream #3 And Commencement of Testing; Rig Mobilised to Jetstream #4, Topaz Project, Minnesota, USA
Pulsar Helium (OTCQB: PSRHF) announced successful completion of the Jetstream #3 appraisal well at the Topaz Project, Minnesota, reaching a total depth of 3,507 ft (1,069 m) on 7 November 2025 and penetrating the interpreted helium-bearing interval.
The rig was mobilised and Jetstream #4 was spudded on 9 November 2025 targeting a TD of 3,000 ft (914 m). Multiple pressurised gas zones returned a calculated bottom-hole pressure of approximately 960 psi, compared with prior well-head pressures of 185 psi (Jetstream #1) and 205 psi (Jetstream #2).
Next steps include open-hole wireline logging, optical televiewer imaging, proposed controlled flow-testing and pressure build-up, and an active campaign of up to 10 wells with a resource update and a Preliminary Economic Assessment targeted in H1 2026.
Pulsar Helium (OTCQB: PSRHF) ha annunciato il successo del completamento del pozzo di valutazione Jetstream #3 nel Progetto Topaz, Minnesota, raggiungendo una profondità totale di 3.507 ft (1.069 m) il 7 novembre 2025 e penetrando l'intervallo contenente elio interpretato.
La piattaforma è stata mobilitata e Jetstream #4 è stato avviato l'9 novembre 2025 con obiettivo di una profondità totale di 3.000 ft (914 m). Diverse zone di gas pressurizzate hanno restituito una pressione di fondo calcolata di circa 960 psi, rispetto alle precedenti pressioni di testa del pozzo di 185 psi (Jetstream #1) e 205 psi (Jetstream #2).
I prossimi passi includono logging in foro aperto con wireline, imaging ottico televiewer, test di flusso controllato e incremento di pressione, e una campagna attiva fino a 10 pozzi con un aggiornamento delle risorse e una Preliminary Economic Assessment prevista per H1 2026.
Pulsar Helium (OTCQB: PSRHF) anunció la finalización exitosa del pozo de tasación Jetstream #3 en el Proyecto Topaz, Minnesota, alcanzando una profundidad total de 3.507 ft (1.069 m) el 7 de noviembre de 2025 e atravesando el intervalo interpretado que contiene helio.
La plataforma fue movilizada y Jetstream #4 se inició el 9 de noviembre de 2025, con objetivo de una profundidad total de 3.000 ft (914 m). Varias zonas de gas presurizadas devolvieron una presión en fondo calculada de aproximadamente 960 psi, en comparación con las presiones de cabeza anteriores de 185 psi (Jetstream #1) y 205 psi (Jetstream #2).
Los próximos pasos incluyen registros en pozo abierto con wireline, imágenes ópticas televiewer, pruebas de flujo controlado y aumento de presión, y una campaña activa de hasta 10 pozos con una actualización de recursos y una Evaluación Económica Preliminar prevista para la mitad de 2026.
Pulsar Helium (OTCQB: PSRHF)는 미네소타주 토파즈 프로젝트의 Jetstream #3 평가 유정이 성공적으로 마무리되었음을 발표했고, 2025년 11월 7일에 총 깊이 3,507 ft (1,069 m)에 도달하며 해석된 헬륨 보유 구간을 관통했습니다.
시추대는 동원되었고 Jetstream #4는 2025년 11월 9일에 착수되었으며 TD 3,000 ft (914 m)를 목표로 합니다. 여러 개의 압력이 있는 가스 구역이 960 psi의 계산된 심부 압력을 반환했으며, 이는 이전 우물 머리압 185 psi (Jetstream #1) 및 205 psi (Jetstream #2)와 비교됩니다.
다음 단계로는 개방 구멀 소형 로그킹(open-hole wireline logging)과 광학 텔레뷰어 이미징, 제어된 유동 시험 및 압력 상승 검토, 최대 10개 유정의 활성 시추 캠페인과 자원 업데이트 및 예비 경제성 평가를 2026년 상반기를 목표로 진행합니다.
Pulsar Helium (OTCQB: PSRHF) a annoncé la réussite de l'achèvement du puits d'évaluation Jetstream #3 dans le projet Topaz, Minnesota, atteignant une profondeur totale de 3 507 ft (1 069 m) le 7 novembre 2025 et traversant l'intervalle contenant du helium interprété.
La plate-forme a été mobilisée et Jetstream #4 a été spudé le 9 novembre 2025 visant une profondeur totale de 3 000 ft (914 m). Plusieurs zones de gaz sous pression ont produit une pression bottom-hole calculée d'environ 960 psi, comparable aux pressions en tête de puits antérieures de 185 psi (Jetstream #1) et 205 psi (Jetstream #2).
Les prochaines étapes incluent des mesures open-hole wireline, l'imagerie optique téléviewer, des tests de flux contrôlés et montée en pression proposées, et une campagne active jusqu'à 10 puits avec une mise à jour des ressources et une évaluation économique préliminaire prévue pour le 1er semestre 2026.
Pulsar Helium (OTCQB: PSRHF) gab den erfolgreichen Abschluss des Jetstream-#3-Bewertungsbohrlochs im Topaz-Projekt, Minnesota, bekannt, wobei eine Gesamttiefe von 3.507 ft (1.069 m) am 7. November 2025 erreicht und der interpretierte Helium-tragende Abschnitt durchdrungen wurde.
Die Bohranlage wurde mobilisiert und Jetstream #4 wurde am 9. November 2025 gestartet, mit Ziel einer TD von 3.000 ft (914 m). Mehrere unter Druck stehende Gaszonen ergaben einen berechneten Bohrlochboden-Druck von ca. 960 psi, verglichen mit früheren Bohrlochkopfdrücken von 185 psi (Jetstream #1) und 205 psi (Jetstream #2).
Zu den nächsten Schritten gehören Open-Hole-Wireline-Logging, optische Televiewer-Bilder, vorgeschlagene kontrollierte Fließtests und Druckaufbau sowie eine aktive Kampagne von bis zu 10 Bohrlöchern mit einer Ressourcenaktualisierung und einer vorläufigen Wirtschaftsbetrachtung, geplant für H1 2026.
Pulsar Helium (OTCQB: PSRHF) أعلن عن إكمال ناجح لبئر Jetstream #3 التقييمي في مشروع Topaz، مينيسوتا، محققاً عمقاً إجمالياً قدره 3,507 قدم (1,069 م) في 7 نوفمبر 2025 واجتياز النطاق المحتمل الحاوي لغاز helium.
تم نشر الحفارة وتم حفر Jetstream #4 في 9 نوفمبر 2025 مستهدفة عمقاً نهائياً قدره 3,000 قدم (914 م). عدة مناطق غاز مضغوطة أعادت ضغطاً قاعياً محسوباً يقدّر بـ 960 psi، مقارنةً بضغط رأس البئر السابق (185 psi لـ Jetstream #1 و 205 psi لـ Jetstream #2).
الخطوات التالية تشمل التسجيلات في بئر مفتوح مع خط السلك، التصوير البصري التلفازي، اختبارات تدفق محكومة وتراكم الضغط، وحملة نشطة حتى 10 آبار مع تحديث للموارد وتقييم اقتصادي مبدئي مقرّ له في الربع الأول من 2026.
- Jetstream #3 TD of 3,507 ft reached on 7 Nov 2025
- Jetstream #4 spudded on 9 Nov 2025, targeting 3,000 ft
- Bottom-hole pressure ~960 psi indicates a highly pressurised reservoir
- Active programme of up to 10 wells aiming to update Topaz resource
- No flow-test results yet; well deliverability remains unproven
- PEA and resource update pending in H1 2026, so commercial metrics are not yet available
THIS ANNOUNCEMENT AND THE INFORMATION CONTAINED HEREIN IS RESTRICTED AND IS NOT FOR RELEASE, PUBLICATION OR DISTRIBUTION, IN WHOLE OR IN PART, DIRECTLY OR INDIRECTLY, IN, INTO OR FROM AUSTRALIA, JAPAN OR THE REPUBLIC OF SOUTH AFRICA OR TO BE TRANSMITTED, DISTRIBUTED TO, OR SENT BY, ANY NATIONAL OR RESIDENT OR CITIZEN OF ANY SUCH COUNTRIES OR ANY OTHER JURISDICTION IN WHICH SUCH RELEASE, PUBLICATION OR DISTRIBUTION MAY CONTRAVENE LOCAL SECURITIES LAWS OR REGULATIONS.
THIS ANNOUNCEMENT CONTAINS INSIDE INFORMATION FOR THE PURPOSES OF ARTICLE 7 OF THE UK VERSION OF REGULATION (EU) NO. 596/2014 ON MARKET ABUSE, AS IT FORMS PART OF UK DOMESTIC LAW BY VIRTUE OF THE EUROPEAN UNION (WITHDRAWAL) ACT 2018, AND REGULATION (EU) NO. 596/2014 ON MARKET ABUSE.
UPON THE PUBLICATION OF THIS ANNOUNCEMENT, THIS INSIDE INFORMATION IS NOW CONSIDERED TO BE IN THE PUBLIC DOMAIN AND SUCH PERSONS SHALL THEREFORE CEASE TO BE IN POSSESSION OF INSIDE INFORMATION.
CASCAIS, Portugal, Nov. 11, 2025 (GLOBE NEWSWIRE) --
Pulsar Helium Inc. (AIM: PLSR, TSXV: PLSR, OTCQB: PSRHF) (“Pulsar” or the “Company”), a primary helium development company, is pleased is pleased to announce the successful completion of drilling the Jetstream #3 appraisal well at its flagship Topaz Project in Minnesota, USA, with the drilling operation reaching a total depth (“TD”) of 3,507 feet.
Highlights:
- Successful Drilling: Jetstream #3 reached a total depth (“TD”) of 3,507 feet (1,069 meters) on November 7, 2025, successfully penetrating the entire interpreted helium-bearing interval.
- Commencement of drilling at Jetstream #4: Drill rig relocated and Jetstream #4 successfully ‘spudded’ on Sunday November 9, 2025, as progress begins toward achieving a TD of 3,000 feet (914 metres).
- Strong Pressure: Multiple pressurized gas zones throughout the drilling campaign with a calculated bottom-hole pressure of approximately 960 psi. This strong pressure reading indicates a robust, naturally pressurized, highly charged reservoir at the well location, providing further validation of the Topaz reservoir’s potential.
- For comparison, Jetstream #1 had a well-head pressure of 185 psi when drilled in 2024, and Jetstream #2 a well-head pressure of 205 psi.
- Next Steps: Jetstream #3 will, this week, undergo a comprehensive evaluation, with a suite of open-hole wireline logs running to collect detailed geological and petrophysical data. An optical televiewer will be used to image the well-bore wall geology, followed by a proposed controlled flow-testing and pressure build-up program to measure well deliverability.
The active drilling campaign consists of up to 10 wells and is designed to further define the geometry, extent, and productivity of the helium-bearing reservoir at Topaz. Field activities will be ongoing as the Company advances towards its objectives of updating the Topaz resource and conducting a Preliminary Economic Assessment (PEA) in H1 2026. Pulsar is fully committed to realising Topaz’s production potential with the aim of providing a new source of helium supply to the North American market.
Thomas Abraham-James, President & CEO of Pulsar Helium, commented on the drilling:
“It is my pleasure to report the successful completion of drilling the Jetstream #3 appraisal well at our Topaz project in Minnesota, USA. Initial bottom-hole pressure readings surpass expectation and reinforce our belief in the huge potential offered by this incredible multi-commodity gas discovery.
“With the drilling of Jetstream #4 underway and down-hole testing soon to commence at Jetstream #3, momentum continues to build at Topaz as we advance our drilling campaign and move steadily towards defining what we believe to be one of North America’s most significant primary helium discoveries.”
On behalf Pulsar Helium Inc.
“Thomas Abraham-James”
President, CEO and Director
Further Information:
Pulsar Helium Inc.
connect@pulsarhelium.com
+ 1 (218) 203-5301 (USA/Canada)
+44 (0) 2033 55 9889 (United Kingdom)
https://pulsarhelium.com
https://ca.linkedin.com/company/pulsar-helium-inc.
Yellow Jersey PR Limited
(Financial PR)
Charles Goodwin / Annabelle Wills
+44 777 5194 357
pulsarhelium@yellowjerseypr.com
Strand Hanson Limited
(Nominated & Financial Adviser, and Joint Broker)
Ritchie Balmer / Rob Patrick / Richard Johnson
+44 (0) 207 409 3494
OAK Securities*
(Joint Broker)
Richard McGlashan / Mungo Sheehan
+44 7879 646641 / +44 7788 266844
richard.mcglashan@oak-securities.com / mungo.sheehan@oak-securities.com
*OAK Securities is the trading name of Merlin Partners LLP, a firm incorporated in the United Kingdom and regulated by the UK Financial Conduct Authority.
About Pulsar Helium Inc.
Pulsar Helium Inc. is a publicly traded company quoted on the AIM market of the London Stock Exchange and listed on the TSX Venture Exchange with the ticker PLSR, as well as on the OTCQB with the ticker PSRHF. Pulsar's portfolio consists of its flagship Topaz helium project in Minnesota, USA, and the Tunu helium project in Greenland. Pulsar is the first mover in both locations with primary helium occurrences not associated with the production of hydrocarbons identified at each.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Forward-Looking Statements
This news release contains forward-looking information within the meaning of Canadian securities legislation (collectively, "forward-looking statements") that relate to the Company's current expectations and views of future events. Any statements that express, or involve discussions as to, expectations, beliefs, plans, objectives, assumptions or future events or performance (often, but not always, through the use of words or phrases such as "will likely result", "are expected to", "expects", "will continue", "is anticipated", "anticipates", "believes", "estimated", "intends", "plans", "forecast", "projection", "strategy", "objective" and "outlook") are not historical facts and may be forward-looking statements. Forward-looking statements herein include, but are not limited to, statements relating to the statements regarding bringing the Topaz project to production, anticipated full plant construction contract in 2026, final investment decision being made in 2026, the potential impact of the drill results, flow testing and pressure testing on the next iteration of the resource estimate; the potential of CO2 and/or Helium-3 as a valuable by-product of the Company’s future helium production; and the potential for future wells. Forward-looking statements may involve estimates and are based upon assumptions made by management of the Company, including, but not limited to, the Company's capital cost estimates, management's expectations regarding the availability of capital to fund the Company's future capital and operating requirements and the ability to obtain all requisite regulatory approvals.
No reserves have been assigned in connection with the Company's property interests to date, given their early stage of development. The future value of the Company is therefore dependent on the success or otherwise of its activities, which are principally directed toward the future exploration, appraisal and development of its assets, and potential acquisition of property interests in the future. Un-risked Contingent and Prospective Helium Volumes have been defined at the Topaz Project. However, estimating helium volumes is subject to significant uncertainties associated with technical data and the interpretation of that data, future commodity prices, and development and operating costs. There can be no guarantee that the Company will successfully convert its helium volume to reserves and produce that estimated volume. Estimates may alter significantly or become more uncertain when new information becomes available due to for example, additional drilling or production tests over the life of field. As estimates change, development and production plans may also vary. Downward revision of helium volume estimates may adversely affect the Company's operational or financial performance.
Helium volume estimates are expressions of judgement based on knowledge, experience and industry practice. These estimates are imprecise and depend to some extent on interpretations, which may ultimately prove to be inaccurate and require adjustment or, even if valid when originally calculated, may alter significantly when new information or techniques become available. As further information becomes available through additional drilling and analysis the estimates are likely to change. Any adjustments to volume could affect the Company's exploration and development plans which may, in turn, affect the Company's performance. The process of estimating helium resources is complex and requires significant decisions and assumptions to be made in evaluating the reliability of available geological, geophysical, engineering, and economic date for each property. Different engineers may make different estimates of resources, cash flows, or other variables based on the same available data.
Forward-looking statements are subject to a number of risks and uncertainties, many of which are beyond the Company's control, which could cause actual results and events to differ materially from those that are disclosed in or implied by such forward- looking statements. Such risks and uncertainties include, but are not limited to, that Pulsar may be unsuccessful in drilling commercially productive wells; the uncertainty of resource estimation; operational risks in conducting exploration, including that drill costs may be higher than estimates ; commodity prices; health, safety and environmental factors; and other factors set forth above as well as risk factors included in the Company’s Annual Information Form dated July 31, 2025 for the year ended September 30, 2024 found under Company’s profile on www.sedarplus.ca.
Forward-looking statements contained in this news release are as of the date of this news release, and the Company undertakes no obligation to update or revise any forward-looking statements, whether as a result of new information, future events or otherwise, except as may be required by law. New factors emerge from time to time, and it is not possible for the Company to predict all of them or assess the impact of each such factor or the extent to which any factor, or combination of factors, may cause results to differ materially from those contained in any forward-looking statement. No assurance can be given that the forward-looking statements herein will prove to be correct and, accordingly, investors should not place undue reliance on forward-looking statements. Any forward-looking statements contained in this news release are expressly qualified in their entirety by this cautionary statement.