Fermi Announces New Agreements with Investment-Grade Hyperscaler and Third Quarter 2026 Financial Results

Customer funding commitments precede a final lease, while the TensorWave lease and associated AMD credit support have ended.

Sentiment and the balance of points

Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

Tags

Fermi (FRMI) signed agreements with an investment-grade hyperscale customer to advance 600 MW of power capacity at Project Matador beginning in 2027. The agreements provide for a $200 million prepayment and $15 million of early construction and site development commitments. A $90 million materials purchase agreement and a definitive long-term lease remain unfinished. Fermi and TensorWave terminated their lease; the associated AMD credit support agreement also ended.

Third-quarter 2026 net loss narrowed to $141.599 million, or $0.22 per share, from $346.812 million, or $0.84 per share, a year earlier. General and administrative expenses rose to $142.161 million from $37.776 million. At September 30, cash and restricted cash totaled $315.517 million, while net debt was $958.353 million. Quarterly property and equipment investment was $133.4 million. Fermi remains pre-revenue, with land-lease conditions preceding vertical construction.

Loading...
Loading translation...
9 points · 1 major

How this balance works

Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.

It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.

Rhea-AI Sentiment measures something else, the tone of the wording.

2 major · 19 points

Hollow bars mark forward-looking points. How the balance works

Positive

  • Major point. Forward-looking: it has not happened yet and may not happen.Customer prepayment agreement provides for $200 million in upfront development funding. 17% of market cap
  • Moderate point. Forward-looking: it has not happened yet and may not happen.Customer agreements advance 600 MW at Project Matador beginning in 2027.
  • Moderate point. Forward-looking: it has not happened yet and may not happen.Proposed materials purchase agreement contemplates $90 million for structural steel and building materials. 7.8% of market cap
  • Moderate pointThird-quarter net loss narrowed to $141.599 million from $346.812 million a year earlier.
  • Moderate pointMacquarie Term Loan repayment totaled $144.294 million during the nine months ended September 30, 2026. 12% of market cap
4 minor points
  • Minor pointEarly construction and site development agreement adds $15 million in customer commitments.
  • Minor pointBasic and diluted quarterly loss per share narrowed to $0.22 from $0.84 a year earlier.
  • Minor pointFermi invested $133.4 million in property and equipment during the third quarter.
  • Minor point. Forward-looking: it has not happened yet and may not happen.Fermi says converting its prospective customer pipeline into leases would fill 2.2 GW of current capacity.

Negative

  • Major pointNet debt reached $958.353 million at September 30, 2026, versus $109.799 million at December 31, 2025.
  • Major pointNine-month property and equipment investment consumed $759.549 million of cash.
  • Moderate pointHyperscaler development remains subject to a definitive long-term lease that has not been finalized.
  • Moderate pointThe $90 million materials purchase agreement remains unfinished. 7.8% of market cap
  • Moderate pointFermi and TensorWave terminated their Data Center Lease and Services Agreement signed in August 2026.
  • Moderate point. Forward-looking: it has not happened yet and may not happen.Land-lease conditions with Texas Tech must precede vertical construction at Project Matador.
  • Moderate pointFermi remains pre-revenue and in its development phase.
  • Moderate pointQuarterly general and administrative expenses rose to $142.161 million from $37.776 million a year earlier.
  • Moderate pointCommon stock issuance settled $21.5 million of quarterly financial advisory fees, diluting holders. 1.9% of market cap
  • Moderate pointCash and restricted cash declined $93.012 million during the first nine months to $315.517 million.
  • Moderate pointNine-month operating cash use was $110.554 million, versus $8.291 million from inception through September 2025.
  • Moderate pointNine-month net loss was $356.098 million, versus $353.180 million from inception through September 2025.
  • Moderate pointStockholders' equity declined to $958.460 million at September 30, 2026, from $1,095.872 million at December 31, 2025.
6 minor points
  • Minor pointTensorWave's associated AMD credit support agreement also terminated.
  • Minor pointNine-month debt extinguishment loss totaled $24.753 million.
  • Minor pointPreviously capitalized construction in progress incurred a $6.918 million write-off during the first nine months.
  • Minor pointDebt issuance costs consumed $18.953 million during the first nine months.
  • Minor pointCapped call option payments consumed $34.747 million during the first nine months.
  • Minor pointOutstanding common shares increased to 646,138,173 at September 30, 2026, from 629,839,790 at December 31, 2025.

News Explained

The company reports that $21.5 million of third-quarter financial-advisory fees were settled by issuing common shares, which increases the share count and reduces existing holders’ percentage ownership absent offsets.

Argus 15 min delay 16 alerts
+2.21% vs previous close $1.85 last price 35.3x rel. volume Open Argus
Details

Market Reaction – FRMI

+11.0% Peak Tracked
-16.0% Trough Tracked
$1.68 – $2.20 Day Range
$1.19B Mkt Cap at Last Price

On Nov 12, the day this news came out, the latest delayed price for FRMI is 2.21% above the previous close. Argus tracked a peak move of +11.0% during the session. Argus tracked a trough of -16.0% from its starting point during tracking. Our momentum scanner has recorded 16 alerts for this stock so far that day. The latest delayed price is $1.85. Relative volume is exceptionally heavy at 35.3x what this stock usually trades by this time of day.

Data tracked by StockTitan Argus (15 min delayed). Upgrade to Gold for real-time data.

Key Figures

Initial power capacity: 600 MW Customer prepayment: $200 million Early construction agreement: $15 million +5 more
Initial power capacity
600 MW
Hyperscaler agreements; development beginning in 2027
Customer prepayment
$200 million
Prepayment agreement for the proposed 600 MW development
Early construction agreement
$15 million
Site preparation and construction activities
Structural materials purchase agreement
$90 million
Contemplated; parties were finalizing the agreement
Cash and restricted cash
$315.5 million
As of September 30, 2026
Outstanding debt, net
$958.4 million
As of September 30, 2026
Net loss
$141.6 million
Third quarter 2026
Net loss per share
$0.22 per basic and diluted share
Third quarter 2026

Previous Earnings Reports

1 past event · Latest: Aug 13
Same Type 1 event
  1. Aug 13

    Q2 earnings

    24h Move
    -13.2%

    Q2 report disclosed a 15-year, 222 MW TensorWave lease, which Fermi now says was terminated.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

Key Terms

investment-grade, restricted cash, convertible senior notes, behind the meter
4 terms
investment-grade financial
"an undisclosed investment-grade hyperscale customer"
Investment-grade describes bonds or other debt judged by credit agencies to have relatively low risk of failing to make promised interest and principal payments; think of it as a lender's report card showing financial stability. It matters to investors because these securities usually pay lower yields but reduce the chance of loss, affect portfolio risk and credit exposure, and influence how cheaply an issuer can borrow—similar to choosing a reliable car with lower repair risk over a cheaper, uncertain one.
restricted cash financial
"$315.5 million of total cash and restricted cash on hand"
Cash that a company holds but cannot use for day-to-day operations because it is set aside for a specific purpose—such as meeting loan covenants, serving as collateral, funding an escrow, or complying with regulations. Like money in a locked savings account earmarked for a bill, restricted cash reduces the cash available to run the business and pay dividends or debts, so investors treat it differently when assessing a company’s true short-term financial strength.
convertible senior notes financial
"borrowings under the convertible senior notes and equipment financing facilities"
Convertible senior notes are a type of loan that a company issues to investors, which can be turned into company shares later on. They are called "senior" because they are paid back before other debts if the company runs into trouble. This allows investors to earn interest like a loan but also have the chance to own part of the company if its value rises.
behind the meter technical
"delivered behind the meter and on a private grid built and operated on site"
Energy generation or equipment located on a customer’s side of the utility meter, such as rooftop solar panels, battery storage, electric vehicle chargers or energy-saving controls. It matters to investors because it reduces the amount of electricity bought from utilities, can lower operating costs for businesses, change utility revenue patterns, and shift demand in energy markets—like a homeowner installing a rain barrel that cuts water bought from the city and alters suppliers’ sales.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

DALLAS, TX / ACCESS Newswire / November 12, 2026 / Fermi Inc. (NASDAQ:FRMI)(LSE:FRMI), operating as Fermi America™ ("Fermi" or the "Company"), today announced its third quarter 2026 financial results and multiple new agreements with an investment-grade hyperscaler to advance 600 megawatts ("MW") of power capacity at Project Matador. A conference call is scheduled for 9 a.m. Eastern Time / 2 p.m. British Time today, November 12, 2026. Accompanying slides and prepared remarks can be found at https://investor.fermiamerica.com. Participation details are included in this release.

"Hyperscalers want sites that are ready with permitted power, and Fermi's Project Matador is one of few that can meet that demand today," said Lee McIntire, Fermi Chief Executive Officer. "Our headstart in speed to power is a key reason an investment-grade hyperscaler has signed up for 600 megawatts and committed more than $200 million up front to accelerate construction at Project Matador with an additional $90 million contemplated. We believe this is just the start of converting our strong pipeline of customers. If we successfully turn this pipeline of prospective customers into leases, it would completely fill our 2.2 gigawatts of current capacity. This gives us growing confidence in our path forward and puts us in strong position to evolve from pre-revenue, pre-lease to the next phase of growth."

Tenant Agreement Updates

Investment-Grade Hyperscaler Agreements. Fermi has entered into agreements with an undisclosed investment-grade hyperscale customer to advance development of an initial 600 MW of power capacity beginning in 2027 at Project Matador. The customer is making financial and development commitments ahead of finalizing a lease, reflecting the importance of securing access to power within its targeted delivery timeline. These financial and development commitments include:

  • $200 million prepayment agreement: Provides for substantial upfront customer funding in connection with the proposed 600 MW development.
  • $15 million early construction and site development agreement: Establishes a framework for advancing site preparation and construction activities as soon as possible to maintain the customer's desired schedule.

Additionally, Fermi and the customer are finalizing a $90 million structural steel and building materials purchase agreement, which would enable the customer to leverage critical long-lead materials Fermi secured in advance, accelerating the customer's planned construction of multiple data center facilities on Project Matador.

These agreements demonstrate Fermi's strategy of investing early in infrastructure readiness to enable faster customer development, attract customer capital earlier in the project lifecycle, and translate our power and infrastructure advantages into long-term revenue opportunities with little or no dilution.

The customer intends to use Fermi's infrastructure and advance development work to accelerate its deployment at Project Matador. The parties continue to work toward a definitive long-term lease and finalization of the steel purchase agreement. The customer's identity remains confidential.

TensorWave Lease Termination. Fermi and TensorWave have terminated the Data Center Lease and Services Agreement signed in August 2026. The AMD credit support agreement associated with TensorWave is also terminated.

Texas Tech University Partnership

Fermi and the Texas Tech University System maintain a strong relationship and continue to work together to advance Project Matador, including the conditions under the land lease that precede vertical construction. Earlier this week, Texas Tech University System Chancellor, Brandon Creighton, issued a statement reaffirming the partnership: "Texas Tech is proud of our partnership with Fermi and remains firmly committed to the success of Project Matador."

Third Quarter Financial Highlights (as of and for the three months ended September 30, 2026)

  • $315.5 million of total cash and restricted cash on hand.
  • $133.4 million of capital invested in Property, Plant, and Equipment ($759.5 million for the nine months ended September 30, 2026), bringing the net balance to approximately $1.67 billion. Fermi remains focused on disciplined capital deployment matched to commercial progress.
  • $958.4 million of outstanding debt, net, reflecting a $463.0 million net increase in borrowings under the convertible senior notes and equipment financing facilities.
  • $141.6 million net loss, or $0.22 per basic and diluted share. General and administrative expenses of $142.2 million drove most of that result and included $65.8 million of non-cash stock compensation and $21.5 million of financial advisory fees settled through the issuance of common stock. Fermi remains pre-revenue and in its development phase, so spending tracks buildout rather than operations.

Conference Call Information

Fermi plans to host a conference call and webcast at 9 a.m. Eastern Time / 2 p.m. British Time today, November 12, 2026, to discuss its third quarter results and recent milestone execution.

To participate, dial (888) 506-0062 in the U.S. or +1 973-528-0011 internationally approximately 15 minutes prior to the scheduled start time and refer to conference code 176575. The call will also be webcast in a listen-only mode and can be accessed through the Investor Relations Events & Presentations page of Fermi's website. A replay of the webcast will be available for a period of one year.

Financial Results and SEC Filings

Fermi's report on Form 10-Q for the quarter ended September 30, 2026, will be filed with the U.S. Securities and Exchange Commission and made available through the SEC's website and the Investor Relations section of Fermi's website.

About Fermi's Project Matador

Fermi America is where AI gets power. Fermi America is developing one of the world's largest advanced energy and AI ecosystems in the Texas Panhandle. The site, called Project Matador, is secured or under long-term lease with nearly $1.7 billion invested in buildout to date. Fermi designed the project to solve the single biggest constraint in AI infrastructure: access to large-scale, reliable power on a timeline that meets customer demand - delivered behind the meter and on a private grid built and operated on site. Subject to entering into binding customer agreements, the project is expected to ramp to approximately 17 GW, with capital deployment matched to commercial commitments.

About Fermi America™

Fermi America™ (Nasdaq & LSE: FRMI) develops next-generation private electric grids that deliver highly redundant power at gigawatt scale to support next-generation intelligence and AI compute. Fermi America™ combines cutting-edge technology with a deep bench of proven world-class multi-disciplinary leaders with a combined 25 GW of experience, to create one of the world's largest, 17 GW next-gen private grid, helping ensure America's energy and AI dominance. The behind-the-meter Project Matador campus is expected to integrate the nation's biggest combined-cycle natural gas project, one of the largest clean, new nuclear power complexes in America, utility grid power, solar power, and battery energy storage, to support hyperscale AI and advanced computing. For additional information visit www.fermiamerica.com.

About the Texas Tech University System

Established in 1996, the Texas Tech University System is one of the top public university systems in the nation, consisting of five universities - Texas Tech University, Texas Tech University Health Sciences Center, Angelo State University, Texas Tech University Health Sciences Center El Paso and Midwestern State University.

Headquartered in Lubbock, Texas, the TTU System is a more than $3 billion enterprise focused on advancing higher education, health care, research and outreach with approximately 21,000 employees and 64,000 students, more than 400,000 alums, a statewide economic impact of $19.2 billion and an endowment valued at $3 billion. In its short history, the TTU System has grown tremendously and is nationally acclaimed, operating at 20 academic locations in 16 cities (15 in Texas, 1 international).

In addition, the TTU System is one of only nine in the nation to offer programs for undergraduate, medical, law, nursing, pharmacy, dental and veterinary education among other academic areas.

Investor Contact

Rodrigo Acuna | IR@fermiamerica.com

Media Contact
Fermi Inc. Communications | media@fermiamerica.com

Forward-Looking Statements

This press release contains forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. All statements that do not relate to matters of historical fact should be considered forward-looking statements, including, without limitation, statements regarding our letter of intent and related agreements, development plans, construction timelines, permitting and regulatory approvals, binding customer agreements, strategic partnerships and alliances, joint ventures, financing activities, generation capacity, future expansion of Project Matador, equipment delivery and installation, first power timing, leadership transition, and anticipated operational milestones.

These statements are based on current expectations and assumptions and are subject to known and unknown risks, uncertainties, and other important factors that could cause actual results to differ materially from those expressed or implied by such forward-looking statements. These factors include, among others: our ability to obtain and maintain required permits and regulatory approvals, including from the NRC and TCEQ; our ability to secure and maintain binding customer agreements and creditworthy counterparties; our ability to complete strategic partnerships and joint ventures on acceptable terms; the availability of project financing and capital on acceptable terms; risks associated with large-scale construction and infrastructure development; interconnection availability and grid constraints; supply chain and equipment procurement risks; commodity availability and pricing, including natural gas and water; risks associated with nuclear development and licensing; counterparty performance; leadership transition risks; litigation and governance matters; and broader economic, regulatory, and market conditions.

Statements regarding potential generation capacity in excess of currently permitted levels, including any reference to expansion beyond approximately 6 GW or up to 11 GW or 17 GW, are subject to the successful receipt of additional permits and approvals, financing, interconnection capacity, land acquisition, and other factors, and there can be no assurance that such capacity will be developed or achieved.

Statements regarding total site acreage, including any reference to expansion beyond currently controlled or leased land, are subject to the closing of pending acquisitions, land availability, and other factors, and there can be no assurance that such acreage will be realized.

These forward-looking statements represent management's expectations as of the date of this release. Except as required by law, the Company undertakes no obligation to update or revise these statements. Additional information regarding these and other risks is included in the Company's Form 10-K and other filings with the Securities and Exchange Commission.

Fermi Inc.
Condensed Consolidated Balance Sheets
(in thousands, except par value amounts and share numbers)
(unaudited)

As of September 30, 2026 As of December 31, 2025
Assets

Property, plant, and equipment, net

$1,669,639 $935,295

Cash and cash equivalents

286,327 408,529

Restricted cash

29,190 -

Prepaid expenses and other assets

71,053 47,753

Operating lease right-of-use assets

44,876 21,737

Total assets

$2,101,085 $1,413,314
Liabilities and stockholders' equity

Debt, net

$958,353 $109,799

Accounts payable and accrued liabilities

126,728 176,572

Operating lease liabilities

57,544 21,320

Other liabilities

- 9,751

Total liabilities

1,142,625 317,442

Commitments and contingencies

Stockholders' equity

Common stock, $0.001 par value; 2,400,000,000 shares authorized, 646,138,173 and 629,839,790 shares issued and outstanding as of September 30, 2026 and December 31, 2025, respectively

646 628

Preferred stock, $0.001 par value; 10,000,000 shares authorized, and no shares issued or outstanding as of September 30, 2026 and December 31, 2025

- -

Additional paid-in capital

1,447,111 1,228,443

Accumulated deficit

(489,297) (133,199)

Total stockholders' equity

958,460 1,095,872

Total liabilities and stockholders' equity

$2,101,085 $1,413,314

Fermi Inc.
Condensed Consolidated Statements of Operations
(in thousands, except share and per share numbers)
(unaudited)

Three Months Ended September 30, For the period from January 10, 2025 (Inception) through September 30, 2025
2026 2025 For the period from January 10, 2025 (Inception) through September 30, 2025
Expenses:

General and administrative

$142,161 $37,776 $335,164 $43,463

Total expenses

142,161 37,776 335,164 43,463

Loss from operations

(142,161) (37,776) (335,164) (43,463)
Other income (expense):

Interest income (expense)

2,207 12 5,509 (669)

Other income (expense), net

(1,645) (309,048) (26,443) (309,048)

Total other income (expense)

562 (309,036) (20,934) (309,717)

Net loss

$(141,599) $(346,812) $(356,098) $(353,180)

Net loss per share - basic and diluted

$(0.22) $(0.84) $(0.56) $(0.95)

Weighted average shares outstanding - basic and diluted

642,652,819 466,493,415 636,652,949 416,237,306

Fermi Inc.
Condensed Consolidated Statements of Cash Flows
(in thousands)
(unaudited)

Nine Months Ended September 30, 2026For the period from January 10, 2025 (Inception) through September 30, 2025
Cash flows used in operating activities:
Net loss
$(356,098) $(353,180)
Adjustments to reconcile net loss to net cash used in operating activities:
Share-based compensation
184,475 24,814
Share-based compensation expense, related party
- 3,616
Share-based payments for professional services
21,988 -
Share-based charitable contribution expense
- 173,784
Loss on extinguishment of debt
24,753 -
Change in fair value as a result of fair value remeasurements
- 111,590
Series A and Series B Convertible Notes inducement expense
- 23,674
Write-off of previously capitalized construction in progress
6,918 -
Other
6,858 680
Changes in operating assets and liabilities:
Accounts payable and accrued liabilities
15,345 10,799
Prepaid expenses and other assets
(14,793) (4,068)
Net cash used in operating activities
$(110,554) $(8,291)
Cash flows used in investing activities:
Investments in property, plant, and equipment
(759,549) (96,321)
Net cash used in investing activities
$(759,549) $(96,321)
Cash flows from financing activities:
Proceeds from issuance of debt, net of discount
979,799 201,624
Repayment of Macquarie Term Loan
(144,294) -
Principal payments on debt
(3,152) (15,000)
Payment of debt issuance costs
(18,953) (1,012)
Payment for capped call options
(34,747) -
Proceeds from issuance of Preferred Units
- 107,552
Other financing activities
(1,562) (5,559)
Net cash provided by financing activities
$777,091 $287,605
Change in cash, cash equivalents and restricted cash
(93,012) 182,993
Cash, cash equivalents and restricted cash, at beginning of period
408,529 -
Cash, cash equivalents and restricted cash, at end of period
$315,517 $182,993
Cash, cash equivalents and restricted cash, at end of period:
Cash and cash equivalents
$286,327 $83,693
Restricted cash
29,190 99,300
Cash, cash equivalents and restricted cash, at end of period
$315,517 $182,993

SOURCE: Fermi Inc.



View the original press release on ACCESS Newswire

FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

What agreements did Fermi sign for the 600 MW Project Matador development?

Fermi signed a $200 million prepayment agreement and a $15 million early construction and site development agreement with an undisclosed investment-grade hyperscale customer. The development begins in 2027. The parties are still working toward a definitive long-term lease and finalizing a $90 million structural steel and building materials purchase agreement.

What were Fermi's third-quarter 2026 financial results?

Fermi reported a $141.599 million net loss, or $0.22 per basic and diluted share, compared with a $346.812 million loss, or $0.84 per share, a year earlier. General and administrative expenses increased to $142.161 million from $37.776 million.

How much non-cash stock compensation did Fermi report for the third quarter of 2026?

Fermi's third-quarter general and administrative expenses included $65.8 million of non-cash stock compensation. They also included $21.5 million of financial advisory fees settled through common stock issuance.