Silvercorp Reports Operational Results and Financial Results Release Date for the Second Quarter, Fiscal 2027

Ying ended the quarter at a 90% operating rate, while GC production resumption is targeted for November 2027.

(Neutral)

Sentiment and the balance of points

Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

Tags

Silvercorp Metals (SVM) reported second-quarter fiscal 2027 revenue of $72.1 million, down 13% year over year as production declined. Consolidated silver production was 0.9 million ounces versus 1.7 million a year earlier, while gold output fell to 1,371 ounces from 2,085. Higher realized silver and gold prices partly offset lower production.

Ying resumed production and ended the quarter at a 90% operating rate after safety improvements costing approximately $13.4 million. GC remains suspended, with production resumption targeted for November 2027 following design approval and upgrades. Ying's No. 3 mill expansion advanced as planned, while heavy rainfall interrupted El Domo construction and damaged completed works. Kuanping and Chaarat construction also progressed. Unaudited financial results for the quarter ended September 30, 2026 are expected on November 5, 2026, after market close.

Loading...
Loading translation...
12 points · 0 major

How this balance works

Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.

It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.

Rhea-AI Sentiment measures something else, the tone of the wording.

0 major · 27 points

Hollow bars mark forward-looking points. How the balance works

Positive

  • Moderate pointYing production resumed, reaching a 90% operating rate at quarter-end.
  • Moderate pointAverage realized silver price rose 82% to $61.83 per ounce versus Q2 fiscal 2026.
  • Moderate pointAverage realized gold price rose 32% to $3,955 per ounce versus Q2 fiscal 2026.
  • Minor pointYing safety improvement works were substantially completed, inspected by government and approved for operations to resume.
  • Minor pointYing's No. 3 mill expansion advanced as planned, with main plant foundations completed.
7 minor points
  • Minor pointKuanping construction advanced with 1,507 metres of ramp development, alongside exploration tunneling and drilling.
  • Minor pointEl Domo plant building and main equipment foundations were completed; initial long-lead equipment reached Ecuador's port.
  • Minor pointEl Domo substation and external power line construction commenced.
  • Minor pointChaarat access road reached the Tulkubash ore body, and pit pre-stripping commenced.
  • Minor pointChaarat heap-leach site preparation was completed, with 0.93 million cubic metres of material removed.
  • Minor pointChaarat processing plant preliminary designs were completed; equipment tender bids are in progress.
  • Minor pointSix-month gold sales rose to 4,028 ounces from 3,984 in the corresponding prior-year period.

Negative

  • Moderate pointQ2 fiscal 2027 revenue declined 13% year over year to $72.1 million due to lower production.
  • Moderate pointGC remains suspended, pending an updated mine development design, government acceptance and safety-related construction.
  • Moderate point. Forward-looking: it has not happened yet and may not happen.GC design completion is expected by December 2026, approval in March 2027 and production resumption by November 2027.
  • Moderate pointYing safety improvement works incurred approximately $13.4 million in Q2 fiscal 2027.
  • Moderate pointEl Domo construction was suspended during 77 days of rain; completed works required repeated repairs.
  • Moderate point. Forward-looking: it has not happened yet and may not happen.Chaarat spring 2027 heap-leach construction depends on design adaptation and legalization and qualified contractor selection.
  • Moderate pointQuarterly consolidated silver production fell to 0.9 million ounces from 1.7 million a year earlier.
20 minor points
  • Minor pointEl Domo tailings storage construction was affected by water accumulation, requiring drainage works beyond the original design.
  • Minor point. Forward-looking: it has not happened yet and may not happen.Ying waste-rock dump construction requires environmental, safety and land permitting; its aggregate plant cannot process all tunneling waste.
  • Minor pointQuarterly consolidated ore processed fell to 213,797 tonnes from 341,251 tonnes a year earlier.
  • Minor pointQuarterly gold production fell to 1,371 ounces from 2,085 ounces a year earlier.
  • Minor pointQuarterly consolidated silver-equivalent production fell to 1.0 million ounces from 1.8 million a year earlier.
  • Minor pointQuarterly consolidated lead production fell to 7.8 million pounds from 14.2 million a year earlier.
  • Minor pointQuarterly consolidated zinc production fell to 0.8 million pounds from 5.6 million a year earlier.
  • Minor pointQuarterly consolidated silver sales fell to 0.9 million ounces from 1.7 million a year earlier.
  • Minor pointQuarterly gold sales fell to 1,574 ounces from 2,033 ounces a year earlier.
  • Minor pointQuarterly consolidated lead sales fell to 7.5 million pounds from 14.8 million a year earlier.
  • Minor pointQuarterly consolidated zinc sales fell to 1.1 million pounds from 5.7 million a year earlier.
  • Minor pointSix-month consolidated ore processed fell to 600,250 tonnes from 699,475 tonnes in the corresponding prior-year period.
  • Minor pointSix-month consolidated silver production fell to 2.4 million ounces from 3.5 million in the corresponding prior-year period.
  • Minor pointSix-month gold production fell to 3,907 ounces from 4,135 ounces in the corresponding prior-year period.
  • Minor pointSix-month consolidated silver-equivalent production fell to 2.6 million ounces from 3.9 million in the corresponding prior-year period.
  • Minor pointSix-month consolidated lead production fell to 21.2 million pounds from 30.0 million in the corresponding prior-year period.
  • Minor pointSix-month consolidated zinc production fell to 5.2 million pounds from 10.9 million in the corresponding prior-year period.
  • Minor pointSix-month consolidated silver sales fell to 2.4 million ounces from 3.5 million in the corresponding prior-year period.
  • Minor pointSix-month consolidated lead sales fell to 21.2 million pounds from 30.0 million in the corresponding prior-year period.
  • Minor pointSix-month consolidated zinc sales fell to 5.3 million pounds from 10.9 million in the corresponding prior-year period.

News Explained

For the suspended GC Mine, Silvercorp reports that it contributes less than 10% of total revenue and says the suspension is not expected to have a material impact on overall operations or financial performance during this period.

Key Figures

Revenue: $72.1 million, down 13% Silver produced: 0.9 million ounces, down 41% Gold produced: 1,371 ounces, down 34% +5 more
Revenue
$72.1 million, down 13%
Q2 Fiscal 2027 versus Q2 Fiscal 2026
Silver produced
0.9 million ounces, down 41%
Q2 Fiscal 2027 versus Q2 Fiscal 2026
Gold produced
1,371 ounces, down 34%
Q2 Fiscal 2027 versus Q2 Fiscal 2026
Silver equivalent produced
1.0 million ounces, down 42%
Q2 Fiscal 2027 versus Q2 Fiscal 2026
Ore processed
213,320 tonnes, down 20%
Ying Mining District, Q2 Fiscal 2027 versus Q2 Fiscal 2026
Operating rate
90%
Ying Mining District at quarter end
Safety improvement works
$13.4 million
Incurred in Q2 Fiscal 2027
GC Mine production resumption
November 2027
Company expectation

Previous Earnings Reports

1 past event · Latest: Aug 10
Same Type 1 event
  1. Aug 10

    Q1 earnings

    24h Move
    +3.3%

    Disclosed an expected 40–50% Q2 Ying output impact from safety upgrades.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

Key Terms

tailing storage facility (tsf)
1 terms
tailing storage facility (tsf) technical
"This has especially impacted the construction of the Tailing Storage Facility (TSF)"
A tailing storage facility (TSF) is a purpose-built engineered containment area—usually formed by dams, embankments or lined impoundments—designed to store the fine-grained waste (tailings) and process water produced after ore is processed at a mine. Tailings are typically a slurry of ground rock, residual chemicals and water; a TSF holds that material, manages decant and seepage, and is operated, monitored and eventually closed and rehabilitated to limit environmental release and structural failure. TSFs vary by construction method (for example upstream, downstream or centreline raises) and are subject to specific engineering, monitoring and regulatory requirements because their long-term stability and water management have safety and environmental consequences.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Silvercorp Metals Inc. Logo

Trading Symbol: TSX/NYSE American: SVM

VANCOUVER, BC, Oct. 19, 2026 /PRNewswire/ -- Silvercorp Metals Inc. ("Silvercorp" or the "Company") (TSX: SVM) (NYSE American: SVM) reports production and sales figures for the second quarter ended September 30, 2026 ("Q2 Fiscal 2027"). Silvercorp expects to release its Q2 Fiscal 2027 unaudited interim financial results on Thursday, November 5, 2026, after market close.

Q2 Fiscal 2027 Operational Highlights: 

  • During the quarter, 213,320 tonnes of ore were processed at the Ying Mining District and produced 0.9 million ounces of silver, 1,371 ounces of gold, or 1.0 million ounces of silver equivalent, 7.6 million pounds of lead, and 0.7 million pounds of zinc, representing decreases of 41%, 34%, 42%, 41%, and 51% in silver, gold, silver equivalent, lead and zinc, respectively, over the same quarter last year ("Q2 Fiscal 2026"), in line with an expected 40-50% impact previously disclosed on June 29, 2026. Production resumed at the Ying Mining District and ended the quarter at a 90% operating rate;

  • Revenue of $72.1 million, representing a decrease of 13% over Q2 Fiscal 2026 due to lower production, was partially offset by an 82% higher average realized silver price of $61.83 per ounce and a 32% higher gold price of $3,955 per ounce;

  • Safety Compliance Progressing: Major safety improvement works at the Ying Mining District have been substantially completed, inspected by the government and approved to resume operations, which include tunnel enlargement and support, equipment upgrades, replacing all flame-retardant power cables with halogen-free, flame-retardant cables, and expanding the "Six Major Safety Systems" to all tunnels. Approximately $13.4 million were incurred in Q2 Fiscal 2027 for these improvement works. The company is also working on permitting of environment, safety and land, to build several waste rock dumps at the Ying Mining district to accommodate material from extensive tunneling, as the aggregate plant cannot process and sell all the waste rock from the tunnels. Meanwhile the GC Mine remains under suspension pending a new mine development design approval and additional work completed;

  • Mill Expansion on Track: Construction of the No. 3 mill at the Ying Mining District is advancing as planned, with most of the drawings having been completed and delivered to the construction team, and the foundations for the machine shop, crushed ore silo, and main plant have been completed, welding for the elevated water tank is finished, and excavation for the tailings thickener is currently underway.

Mine Development & Construction Updates:

    • Kuanping mine construction continued, with 1,507 metres ("m") of ramp development, 462 m of exploration tunneling and 4,759 m of drilling completed;

    • El Domo mine construction was impacted by persistent heavy rainfall throughout Q2 Fiscal 2027, which is typically dry season, but due to the effects of this year's Super El Niño. During the quarter, approximately 1,009,239  cubic metres of excavation and pre-stripping were completed, despite precipitation of 620 millimetres—489% higher than the six-year average. Not only were construction works suspended during 77 days of rain, but many finished engineering works were repeatedly damaged by the heavy rainfall and required repeated repairing. This has especially impacted the construction of the Tailing Storage Facility (TSF), as all surface water runs to the low point of the initial dam site. Significant efforts were put into the water management systems, such as building more water drainage and diversion systems, beyond the original engineering design.

      Civil works at the Process Plant are progressing well as this site is protected by the Northeast Water Channel. The foundations for the plant buildings and main equipment were completed, waiting for installation. The pre-fabricated structural steel for the Process Plant has been shipped from the factory, and the first batch of major long lead-time equipment has also arrived in the Ecuador port.

      Construction of a Substation at the El Domo site and the external power line to connect to the power grid has also commenced, while 10 gen-sets of 17 MW capacity are ready to be shipped to site as an independent power supply, as required by Ecuador regulations.

      Open-pit pre-stripping has also been impacted by heavy rainfall and progressed across three working areas, with a fleet of ten 60-tonne haul trucks and twenty to thirty 30-tonne trucks from local community members;
    • Chaarat ZAAV project: A camp with 110 beds for our site management team and 290 beds for contractors with winter heating facilities has been constructed and is in use. Since mid May 2026, CRCC19 has advanced 1,880 m of a 15-metre wide access road and has reached the Tulkubash ore body, and pit pre-stripping has commenced.

      Site preparation, surface clearing and earthworks for the construction of the Heap Leach Pad are completed by CRCC19, with 0.93 million cubic metres of material being cut and removed under the supervision of independent QA/QC agents, UK-based SLR Engineering and locally-based Ken-Too. The site is now largely ready for drainage and liner installation and facility construction, scheduled for the Spring of 2027 after completion of Kyrgyz local adaptation and legalization of the 2021 Ausenco design and after selection of the qualified contractors.

      Preliminary design for the ADR and crushing plants by Beijing-based BGRIMM, assisted by a Kyrgyzstan engineering firm to comply with Kyrgyz standards, has been completed. The equipment tender bids for the ADR and crushing plants are in progress.

Consolidated Operational Results for Q2 Fiscal 2027 and 2026


Q2 Fiscal 2027


Q2 Fiscal 2026


Ying Mining
District

GC

Consolidated


Ying Mining
District

GC

Consolidated

Silver-lead Ore Processed (tonnes)

188,061

477

188,538


235,168

76,249

311,417

Silver (grams/tonne)

157

51



207

64


Lead (%)

2.0

1.1



2.6

0.9


Zinc (%)

0.3

1.9



0.4

2.8










Gold Ore Processed (tonnes)

25,259

—

25,259


29,834

—

29,834

   Gold (grams/tonne)

1.1

—



1.4

—


Silver (grams/tonne)

46

—



81

—


Lead (%)

0.6

—



0.9

—


Total Ore Processed (tonnes)

213,320

477

213,797


265,002

76,249

341,251









Recovery Rates








Silver (%)

94.1

83.6



94.8

85.8


Gold (%)*

92.9

—



94.2

—


Lead (%)

90.4

94.8



93.5

89.0


Zinc (%)

57.7

87.8



65.8

91.1










Metals Produced








Silver (million ounces)

0.9

0.01

0.9


1.5

0.1

1.7

Gold (ounces)

1,371

—

1,371


2,085

—

2,085

Silver equivalent (million ounces)

1.0

0.01

1.0


1.7

0.1

1.8

Lead (million pounds)

7.6

0.2

7.8


12.9

1.3

14.2

Zinc (million pounds)

0.7

0.1

0.8


1.4

4.2

5.6









Metals Sold








Silver (million ounces)

0.9

0.02

0.9


1.5

0.1

1.7

Gold (ounces)

1,574

—

1,574


2,033

—

2,033

Lead (million pounds)

7.3

0.2

7.5


13.5

1.3

14.8

Zinc (million pounds)

0.9

0.2

1.1


1.4

4.2

5.7

*Only representing the gold recovery rate for Gold Ore.

The Ying Mining District processed 213,320 tonnes of ore, down 20% over Q2 Fiscal 2026,,affected by the safety system improvements. Approximately 0.9 million ounces of silver, 1,371 ounces of gold, or 1.0 million ounces of silver equivalent1, plus 7.6 million pounds of lead and 0.7 million pounds of zinc were produced, representing decreases of 41%, 34% , 42%, 41%, and 51% in silver, gold, silver equivalent, lead and zinc, respectively, over Q2 Fiscal 2026.

GC Mine to Remain Suspended Until New Mine Development Design Approval

The GC Mine processed 477 tonnes of stockpiled ore, and produced  0.01 million ounces of silver, 0.2 million pounds of lead and 0.1 million pounds of zinc.

Mining activities have been suspended since late June 2026 as the company has not updated its 2014 China-standard technical design for mining operation to reflect changes in geology and tunneling advancement. Safety inspections by the government have been rigidly focused on any deviation of the actual development from the original mine design or any updated mine design. Accordingly, resumption of production at the GC Mine is pending the completion of an updated mine development design by a qualified Chinese engineering firm, and then a completed filing with the National Safety Production Administration Bureau and Department of Emergency Management of Guangdong Province. Once the filing is accepted by government authorities, the GC Mine will be able to construct safety-related production facilities, with the Phase 1 intended to upgrade the existing mining areas, and the Phase 2 to develop new, deeper levels below -300 m elevation. 

Silvercorp has engaged Changsha Institute of Mining Research Co., Ltd. to update the mine development plan design, including the safety facilities, which is expected to be completed by the end of December 2026 and then approved by the Guangdong Provincial Department of Emergency Management in March 2027. It may take 6-8 months to upgrade the Phase 1 development and to get the mine to resume production by November of 2027. As the GC Mine contributes less than 10% to total revenue, the Company does not expect the suspension to have a material impact on its overall operations or financial performance during this period.

Most technical personnel at GC have been reassigned to operations at the Ying Mining District, the BYP project permitting process, and construction of the El Domo and Condor projects in Ecuador and the Chaarat project in Kyrgyzstan.

Consolidated Operational Results for the Six months ended September 30, 2026 and 2025


Six months ended September 30, 2026


Six months ended September 30, 2025


Ying Mining
District

GC

Consolidated


Ying Mining
District

GC

Consolidated

Silver-lead Ore Processed (tonnes)

478,125

63,714

541,839


488,126

151,118

639,244

Silver (grams/tonne)

159

56



213

66


Lead (%)

2.0

0.9



2.7

0.8


Zinc (%)

0.3

2.4



0.5

2.6










Gold Ore Processed (tonnes)

58,411

—

58,411


60,231

—

60,231

   Gold (grams/tonne)

1.2

—



1.4

—


Silver (grams/tonne)

47

—



66

—


Lead (%)

0.8

—



0.8

—


Total Ore Processed (tonnes)

536,536

63,714

600,250


548,357

151,118

699,475









Recovery Rates








Gold (%)*

91.5

—



93.8

—


Silver (%)

94.5

85.5



94.7

85.6


Lead (%)

91.6

93.3



93.8

89.5


Zinc (%)

62.7

90.5



64.9

90.6










Metals Produced








Silver (million ounces)

2.3

0.1

2.4


3.2

0.3

3.5

Gold (ounces)

3,907

—

3,907


4,135

—

4,135

Silver equivalent (million ounces)

2.6

0.1

2.6


3.6

0.3

3.9

Lead (million pounds)

20.1

1.2

21.2


27.5

2.4

30.0

Zinc (million pounds)

2.3

3.0

5.2


3.3

7.6

10.9









Metals Sold








Silver (million ounces)

2.3

0.1

2.4


3.2

0.3

3.5

Gold (ounces)

4,028

—

4,028


3,984

—

3,984

Lead (million pounds)

20.0

1.1

21.2


27.6

2.4

30.0

Zinc (million pounds)

2.2

3.1

5.3


3.3

7.6

10.9

*Only representing the gold recovery rate for Gold Ore.

About Silvercorp
Silvercorp is a Canadian mining company producing silver, gold, lead, and zinc with a long history of profitability and growth potential. The Company's strategy is to create shareholder value by 1) focusing on generating free cash flow from long life mines; 2) organic growth through extensive drilling for discovery; 3) ongoing merger and acquisition efforts to unlock value; and 4) long term commitment to responsible mining and ESG. For more information, please visit our website at www.silvercorpmetals.com.

For further information
Silvercorp Metals Inc.                                                                  
Lon Shaver
President
Phone: (604) 669-9397
Toll Free 1(888) 224-1881
Email: investor@silvercorp.ca
Website: www.silvercorpmetals.com

CAUTIONARY DISCLAIMER - FORWARD-LOOKING STATEMENTS
This news release includes "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information" within the meaning of applicable securities laws relating to, among other things statements regarding the timing of release the Company's Q2 Fiscal 2027 unaudited interim financial results;   timing of commissioning of the El Domo mine; permitting and construction of waste rock dumps and the No. 3 mill at the Ying Mining District; development of the Kuanping mine; the timing of heap leach pad construction at the Chaarat project; Kyrgyz adaption and legalization of the 2021 Ausenco design, contractor selection and procurement of the ADR and crushing plant equipment; the timing of completion and approval of an updated mine development design for the GC Mine, the Phase 1 and Phase 2 development, and the expected resumption of production;  and the expected impact of the GC Mine suspension on the Company's operations and financial performance.  By their very nature, forward-looking statements involve known and unknown risks, uncertainties and other factors that may cause our actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements.  Forward-looking information may in some cases be identified by words such as "will", "anticipates", "expects", "intends" and similar expressions suggesting future events or future performance.

We caution that all forward-looking information is inherently subject to change and uncertainty and that actual results may differ materially from those expressed or implied by the forward-looking information. A number of risks, uncertainties and other factors, including  fluctuating commodity prices; recent market events and condition; estimation of mineral resources, mineral reserves and mineralization and metal recovery; interpretations and assumptions of mineral resource and mineral reserve estimates; exploration and development programs; climate change; economic factors affecting the Company; timing, estimated amount, capital and operating expenditures and economic returns of future production; integration of future acquisitions into existing operations; permits and licences for mining and exploration in China; title to properties; non-controlling interest shareholders; acquisition of commercially mineable mineral rights; financing; competition; operations and political conditions; regulatory environment in China; regulatory environment and political climate in Bolivia, Ecuador and Kyrgyzstan;  ability to obtain all necessary permits, licenses and regulatory approvals in a timely manner; Government safety inspections and suspensions; integration and operations of Adventus and Chaarat ZAAV CJSC; environmental risks; natural disasters; dependence on management and key personnel; foreign exchange rate fluctuations; insurance; risks and hazards of mining operations(including flooding and severe weather); conflicts of interest; internal control over financial reporting as per the requirements of the Sarbanes-Oxley Act; outcome of current or future litigation or regulatory actions; bringing actions and enforcing judgments under U.S. securities laws; cyber-security risks; uncertainties in geopolitical conditions; public health crises; the Company's investment in New Pacific Metals Corp. and Auro Metals Inc.; and the other risk factors described in the Company's Annual Information Form and in the Company's Annual Report on Form 40-F, and other filings with Canadian and U.S. regulators on www.sedarplus.ca and www.sec.gov; could cause actual results and events to differ materially from those expressed or implied in the forward-looking information or could cause our current objectives, strategies and intentions to change. Although the Company has attempted to identify important factors that could cause actual results to differ materially, there may be other factors that cause results not to be as anticipated, estimated, described or intended. Accordingly, we warn investors to exercise caution when considering statements containing forward-looking information and that it would be unreasonable to rely on such statements as creating legal rights regarding our future results or plans. We cannot guarantee that any forward-looking information will materialize and you are cautioned not to place undue reliance on this forward-looking information. Any forward-looking information contained in this news release represents expectations as of the date of this news release and is subject to change after such date. However, we are under no obligation (and we expressly disclaim any such obligation) to update or alter any statements containing forward-looking information, the factors or assumptions underlying them, whether as a result of new information, future events or otherwise, except as required by law. All of the forward-looking information in this news release is qualified by the cautionary statements herein.

A comprehensive discussion of other risks that impact Silvercorp can also be found in its public reports and filings which are available under its profile at www.sedarplus.ca.

i Silver equivalent is calculated by converting the gold metal quantity to its silver equivalent using the ratio between the net realized selling prices of gold and silver achieved, and then adding the converted amount expressed in silver ounces to the ounces of silver.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/silvercorp-reports-operational-results-and-financial-results-release-date-for-the-second-quarter-fiscal-2027-302913195.html

SOURCE Silvercorp Metals Inc.

FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

When does Silvercorp expect the GC Mine to resume production?

Silvercorp targets GC production resumption by November 2027, following design approval and safety upgrades. The company expects design completion by the end of December 2026 and approval in March 2027. Phase 1 upgrades may take 6-8 months; GC contributes less than 10% of total revenue.

How much rain affected Silvercorp's El Domo construction?

El Domo received 620 millimetres of precipitation during Q2 fiscal 2027, 489% above the six-year average. Construction was suspended during 77 days of rain. Approximately 1,009,239 cubic metres of excavation and pre-stripping were nevertheless completed, while additional drainage and diversion systems were built.