This Amendment No. 1 to the Report on Form 6-K is filed to correct and replace the Original Report on Form 6-K filed on November 3, 2026
(the “Original Report”). Accordingly, this Amendment supersedes the Original Report, including all exhibits thereto, in its
entirety.
Pursuant to the requirements
of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto
duly authorized.
Exhibit 99.1
/C O R R E C T I O N - Silvercorp Metals Inc./
In the news release, Silvercorp Announces Project
Update for El Domo, issued 03-Nov-2026 by Silvercorp Metals Inc. over PR Newswire, we are advised by the company that changes have been
made. The complete, corrected release follows, with additional details at the end:
Silvercorp Announces Project Update for El Domo
VANCOUVER, BC, Nov. 3, 2026 /CNW/ -- Silvercorp Metals
Inc. ("Silvercorp" or the "Company") (TSX/NYSE American: SVM) is providing minor corrections to yesterday's press
release. The corrections are mainly related to announces an update for its budget and construction schedule for the construction of the
El Domo Project (the "Project").
The construction budget for the
Project has been updated to $298.2 million, a net increase of $14.6 million compared to the $283.6 million estimate disclosed by the Company
on February 4, 2026 (for reference, the 2021 Feasibility Study Budget was $248 million). The main items of increase or decrease are as
follows:
| 1. | Diesel fuel adjustment: Ecuador eliminated diesel
subsidies, resulting in, together with other factors, the diesel price increasing from under $3/gallon in December 2024 to $5.64/gallon
in October 2026, an increase of $2.7/gallon. As a result, the fuel adjustment for Package #1 is $3.6 million and for Package #2 is $4.7
million, totaling $8.3 million for remaining construction. |
| 2. | Enhancement work for Water Management Related Infrastructure:
Due to heavy rainfall experienced at the Project, additional work to upgrade the designs and enhance the construction for reinforcement
results in an increase of $3.5 million, plus site cleaning costs of $1.2 million, for a $4.7 million budget addition. This is added to
the Package #1 TSF budget. |
| 3. | Equipment and Facilities for Site Power Supply: $2.4
million increase mainly due to the additional demand for the power cables and power distribution facilities based on the detailed engineering
design. |
| 4. | Construction on Processing Plant: $3.7 million increase
following execution of the Package #3 construction contract, reflecting further refinement of the quantities and unit rates in the contract
bill of quantities. |
| 1. | Two cofferdams and pipes beneath the TSF Starter Dam to drain
the water from the impoundment area during the Construction Period, plus cemented roadside ditches are required to divert water from the
construction site, at a cost of nearly $2 million. This is added to the Package #1 TSF budget. |
| 2. | Two new Reactive Power Compensators (SVG) are estimated
at $2 million plus other power supply related items of $1.3 million, for a total increase of $3.3 million. |
| 6. | Offsetting budget reductions of $9.8 million were
mainly achieved through, among other things: (i) using rocks from the process plant site preparation for haul road construction instead
of purchasing replacement materials for $1.8 million; (ii) eliminating the West Non-contact Water Channel for $1.5 million, as the explosives
magazine site has effectively diverted surface water, (iii) reducing the permanent camp size for $0.7 million as the Construction Camp
currently in use is satisfactory for long-term use, and (iv) reducing of contingency for $2.7 million. The reduction in contingency is
not a direct cost saving, but a reduction in the Company's allowance for future cost increases, of which $14.3 million remains. |
Due to the extended rainfall
experienced at site caused by Super El Nino, the El Domo completion date is currently expected to be delayed by four months. The Company
is now targeting production at El Domo in November 2027, subject to, among other things, weather conditions, and contractor performance.
There can be no assurance that production will commence when targeted.
Capital Cost Estimate Details:
The table below compares the Updated Budget to the
Budget released on February 4, 2026, and also the Total Actual Expenditures as of September 30, 2026:
| |
4-Feb-26 |
3-Nov-26 |
30-Sep-26 |
Total Remaining |
| Budget |
Updated Budget |
Total Actual
Expenditures |
| (million) |
(million) |
(million) |
(million) |
| Package #1 Site preparation /Roads /Channels /TSF /SWD |
57.4 |
57.2 |
26.7 |
30.5 |
| Package #2 Open Pit Mining and Stripping |
35.0 |
40.0 |
2.4 |
37.6 |
| Package #3 Processing Plant Construction and Equipment |
54.8 |
62.2 |
14.1 |
48.1 |
| Construction and Permanent Camps |
7.0 |
6.3 |
3.2 |
3.1 |
| Packages #4&5 - Site Infrastructure (bypass roads, powerline, standby diesel generators, water treatment plant) |
45.4 |
49.3 |
16.6 |
32.7 |
| Direct costs sub-total |
199.3 |
215.1 |
63.0 |
152.1 |
| Owner's Contingency |
17.0 |
14.3 |
0.0 |
14.3 |
| Owner's Cost |
32.1 |
32.0 |
19.1 |
12.9 |
| Value added tax (VAT) |
35.2 |
36.7 |
8.8 |
27.9 |
| Grand Total |
283.6 |
298.2 |
90.9 |
207.3 |
Progress Achieved by September 30, 2026:
For Package #1: the main delay includes delays
relating to TSF construction and Non-contact Water Channel. Site preparation for the process plant has been completed and construction
of foundations for the processing plant is well underway.
|
Package #1 |
4-Feb-26 |
3-Nov-26 |
30-Sep-26 |
Total
Remaining
|
|
| Budget |
Updated
Budget |
Total Actual
Expenditures |
|
| (million) |
(million) |
(million) |
(million) |
|
| |
|
|
|
|
|
| Site Preparation |
8.3 |
8.3 |
7.0 |
1.3 |
|
| TSF |
Original Budget |
9.0 |
1.4 |
2.4 |
6.5 |
|
| Enhancement work for Water Management |
|
4.7 |
|
4.7 |
|
| New Items for water management |
|
2.0 |
|
2.0 |
|
| Roads |
10.0 |
8.2 |
8.2 |
0.0 |
|
| Channels |
12.3 |
10.8 |
5.4 |
5.4 |
|
| SWD |
4.8 |
4.6 |
0.8 |
3.8 |
|
| Crusher station |
0.7 |
0.7 |
0.7 |
0.0 |
|
| Others |
12.3 |
5.3 |
2.2 |
3.1 |
|
| Diesel fuel adjustment |
|
3.6 |
|
3.6 |
|
| Sub-total |
57.4 |
57.2 |
26.7 |
30.5 |
|
| |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
Package #2 - Open Pit Mining and Stripping
| Package #2 |
4-Feb-26 |
3-Nov-26 |
30-Sep-26 |
Total
Remaining |
| Budget |
Updated
Budget |
Total Actual
Expenditures |
| (million) |
(million) |
(million) |
(million) |
| Stripping |
25.5 |
33.5 |
2.3 |
31.2 |
| Ore Mining |
0.1 |
0.1 |
- |
0.1 |
| Other |
9.4 |
1.7 |
0.1 |
1.6 |
| Diesel fuel adjustment |
|
4.7 |
|
4.7 |
| Sub-total |
35.0 |
40.0 |
2.4 |
37.6 |
The Company awarded the Mining
Contract for the Package #2 Project to China Railway 19th Bureau Group Co., Ltd. ("CRCC 19") on a "Unit Cost" basis,
valued at $35 million for mining and stripping. This Updated Budget increases by $5.0 million, of which $4.7 million reflects the diesel
price increase.
Package #3 - Processing Plant Construction and
Equipment
| Package #3 |
4-Feb-26 |
3-Nov-26 |
30-Sep-26 |
Total Remaining |
| Budget |
Updated
Budget |
Total Actual
Expenditures |
| (million) |
(million) |
(million) |
(million) |
| General Layout |
11.6 |
12.8 |
0.9 |
11.9 |
| ROM Platform +Ore Shed+Crushing Workshop Facilities |
2.3 |
2.3 |
1.5 |
0.8 |
| Grinding and Grading Facilities |
2.2 |
2.2 |
0.6 |
1.6 |
| Flotation Workshop Facilities |
2.1 |
2.1 |
0.2 |
1.9 |
| Concentrate/Tailing Dewatering Facility |
1.7 |
1.7 |
0.1 |
1.6 |
| Water Supply and Drainage Facilities |
1.5 |
1.5 |
- |
1.5 |
| Others |
3.5 |
6.0 |
0.2 |
5.8 |
| Sub-total |
24.9 |
28.6 |
3.5 |
25.1 |
Foundations for the fine ore
bin were 92% complete, 45% for the grinding & flotation plant, 21% for the thickener, 86% for the dewatering plant, 75% for the warehouse,
and 35% for the oil depot. Buildings were 78% and 46% complete for the lab and office, respectively. The plant site is well protected
by the Northeast Non-contact Water Channel.
As most costs are related to
the pre-fabricated structural steel for the Process Plant which has been ordered and shipped from the factories, and payment is pending
on arrival at Ecuador port and final installation, Total Actual Expenditures as of September 30, 2026 are not significant.
| Package #3 Equipment |
4-Feb-26 |
3-Nov-26 |
30-Sep-26 |
Total
Remaining |
| Budget |
Updated
Budget |
Total Actual
Expenditures |
| (million) |
(million) |
(million) |
(million) |
| Ball Mill, Semi-Autogenous Mill |
3.3 |
3.3 |
1.7 |
1.6 |
| Flotation Column |
2.2 |
2.2 |
1.1 |
1.1 |
| Flotation Machine, Stirring Tank |
1.0 |
1.9 |
1.6 |
0.3 |
| Filters (4 sets) |
1.7 |
1.7 |
1.4 |
0.3 |
| Vertical Stirred Regrinding Mill, Ultrafine Mill |
2.1 |
2.0 |
1.4 |
0.6 |
| Thickeners (8 sets ) |
1.6 |
1.4 |
1.0 |
0.4 |
| Equipment and Facilities for Power Supply |
2.2 |
4.6 |
- |
4.6 |
| Logistics |
4.0 |
4.3 |
1.1 |
3.2 |
| Others |
11.5 |
12.1 |
1.1 |
11 |
| Sub-total |
29.9 |
33.6 |
10.6 |
23.0 |
Most equipment has been ordered
and the Company has paid an approximate 30% down payment, which totals approximately $10.6 million.
Packages #4,5 -Site Infrastructure (bypass roads,
powerline, standby diesel generators, water treatment plant)
| Package #4 & #5 |
4-Feb-26 |
3-Nov-26 |
30-Sep-26 |
Total Remaining |
| Budget |
Updated Budget |
Total Actual
Expenditures |
| (million) |
(million) |
(million) |
(million) |
| External Powerline |
Original External Powerline |
17.3 |
15.3 |
4.0 |
11.3 |
| Added Compensators |
|
2.8 |
|
2.8 |
| Generator Sets |
4.2 |
4.7 |
2.5 |
2.2 |
| Access roads upgrade and maintenance |
5.0 |
5.0 |
2.5 |
2.5 |
| East & West Bypass Roads |
2.0 |
2.4 |
- |
2.4 |
| Two Water Treatment Plants |
3.1 |
3.1 |
- |
3.1 |
| On-Site Power Supply, Environment, TSF Construction EoR and CQA team |
6.4 |
6.1 |
2.7 |
3.4 |
| Local Purchases |
2.8 |
2.8 |
0.1 |
2.7 |
| Other Project |
4.6 |
7.1 |
4.8 |
2.4 |
| Sub-total |
45.4 |
49.3 |
16.6 |
32.7 |
Construction of the Powerline
has been delayed as more reviews and approvals have been required from CNEL. Only construction of a Substation at the El Domo site has
commenced. Meanwhile, 10 gen-sets of 17 MW capacity have been manufactured and are ready to be shipped to site as an independent power
supply. Continued delays in the construction of the Powerline would require that the Project rely on the gen-sets for longer, which may
increase operating costs.
About Silvercorp
Silvercorp is a Canadian mining
company producing silver, gold, lead, and zinc with a long history of profitability and growth potential. The Company's strategy is to
create shareholder value by 1) focusing on generating free cash flow from long life mines; 2) organic growth through extensive drilling
for discovery; 3) ongoing merger and acquisition efforts to unlock value; and 4) long term commitment to responsible mining and ESG. For
more information, please visit our website at www.silvercorpmetals.com.
For further information Silvercorp Metals Inc.
Lon Shaver
President
Phone: (604) 669-9397
Toll Free 1(888) 224-1881
Email: investor@silvercorp.ca
Website: www.silvercorpmetals.com
CAUTIONARY DISCLAIMER - FORWARD-LOOKING STATEMENTS
This news release includes "forward-looking
statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information"
within the meaning of applicable securities laws (collectively, "forward-looking information") relating to, among other things
statements regarding the recovery of the VAT as a tax credit, the construction schedule, duration, and costs for the development of the
Project, the date which the Project is scheduled to be in production; the updated construction budget and its components; anticipated
cost savings; diesel prices; timing of execution of mining contract and mobilization of personnel and equipment to the Project, timing
of completion of detailed engineering design, delivery of diesel generators, and completion of the external powerline; reliance on gen-sets;
and the funding of remaining construction costs. By their very nature, forward-looking information involves known and unknown risks, uncertainties
and other factors that may cause our actual results, performance or achievements to be materially different from any future results, performance
or achievements expressed or implied by the forward-looking information . Forward-looking information may in some cases be identified
by words such as "will", "anticipates", "expects", "intends" and similar expressions suggesting
future events or future performance.
We caution that all forward-looking
information is inherently subject to change and uncertainty and that actual results may differ materially from those expressed or implied
by the forward-looking information. A number of risks, uncertainties and other factors, including but not limited to: fluctuating commodity
prices; recent market events and condition; activities of anti-mining groups; estimation of mineral resources, mineral reserves and mineralization
and metal recovery; interpretations and assumptions of mineral resource and mineral reserve estimates; exploration and development programs;
climate change; severe weather, including flooding and extended rainfall; fuel and input cost increases, including as a result of changes
to government subsidies or taxes; delays by third parties; construction risks and cost overruns; economic factors affecting the Company;
timing, estimated amount, capital and operating expenditures and economic returns of future production; integration of future acquisitions
into existing operations; permits and licences for mining and exploration in China; title to properties; non-controlling interest shareholders;
acquisition of commercially mineable mineral rights; financing; competition; operations and political conditions; regulatory environment
in Ecuador and China; regulatory environment and political climate in Bolivia and Ecuador; integration and operations of Adventus; environmental
risks; natural disasters; dependence on management and key personnel; foreign exchange rate fluctuations; insurance; risks and hazards
of mining operations; conflicts of interest; internal control over financial reporting as per the requirements of the Sarbanes-Oxley Act;
outcome of current or future litigation or regulatory actions; bringing actions and enforcing judgments under U.S. securities laws; cyber-security
risks; public health crises; the Company's investment in New Pacific Metals Corp. and Auro Metals Inc.; and the other uncertainties, risks
and other factors described in the Company's Annual Information Form and other filings with Canadian and U.S. regulators on www.sedarplus.ca
and www.sec.gov; could cause actual results and events to differ materially from those expressed or implied in the forward-looking information
or could cause our current objectives, strategies and intentions to change. Accordingly, we warn investors to exercise caution when considering
statements containing forward-looking information. We cannot guarantee that any forward-looking information will materialize and you are
cautioned not to place undue reliance on this forward-looking information. Any forward-looking information contained in this news release
represents expectations as of the date of this news release and is subject to change after such date. However, we are under no obligation
(and we expressly disclaim any such obligation) to update or alter any statements containing forward-looking information, the factors
or assumptions underlying them, whether as a result of new information, future events or otherwise, except as required by law. All of
the forward-looking information in this news release is qualified by the cautionary statements herein.
A comprehensive discussion of
other risks that impact Silvercorp can also be found in its public reports and filings which are available under its profile at www.sedarplus.ca.
and on EDGAR at www.sec.gov.
Correction: This press release
cancels and replaces the one issued earlier on November 3, 2026, at 5:05 p.m. (EST), which contained clerical errors.