Taseko Announces Start of Wellfield Operations at Florence Copper and Third Quarter Gibraltar Operational Results
Taseko (NYSE: TGB) announced that final regulatory approvals for the 100%‑owned Florence Copper project have been received and the operator has commenced wellfield operations, starting the commercial production phase. The SX/EW plant reached substantial completion on Sept 19 and commissioning will run in parallel with wellfield start-up. First copper cathode is expected in about three months. At Gibraltar, Q3 production was 27.6M lbs Cu (including 0.9M lbs cathode) and 560k lbs Mo, up 39% and 211% QoQ respectively; mill throughput hit design 85,300 tpd and copper recoveries averaged 77% Q3 (83% in Sept). 2025 annual copper guidance is now 100–105M lbs.
Taseko (NYSE: TGB) ha annunciato che sono stati ottenuti gli ultimi permessi regolamentari per il progetto Florence Copper, di proprietà al 100%, e l'operatore ha avviato le operazioni del giacimento, dando inizio alla fase di produzione commerciale. L'impianto SX/EW ha raggiunto la sostanziale completamento il 19 settembre e la messa in servizio procederà in parallelo con l'avvio del giacimento. La prima lamina di rame a catodo è prevista entro circa tre mesi. A Gibraltar, la produzione nel terzo trimestre è stata di 27,6 milioni di libbre di Cu (inclusi 0,9 milioni di libbre di catodo) e 560k libbre di Mo, in aumento rispettivamente del 39% e del 211% QoQ; la capacità di molatura ha raggiunto il design 85,300 tpd e i recuperi del rame hanno mediamente toccato 77% Q3 (83% a settembre). La guidance annua 2025 per il rame è ora di 100–105M libbre.
Taseko (NYSE: TGB) anunció que se han recibido las últimas aprobaciones regulatorias para el proyecto Florence Copper, 100% propiedad, y el operador ha iniciado operaciones del yacimiento, dando inicio a la fase de producción comercial. La planta SX/EW alcanzó una finalización sustancial el 19 de septiembre y la puesta en marcha se realizará en paralelo con el inicio del yacimiento. Se espera la primera lámina de cobre a catodo en aproximadamente tres meses. En Gibraltar, la producción del 3er trimestre fue de 27,6 millones de libras de Cu (incluidas 0,9 millones de libras de catodo) y 560 mil libras de Mo, con aumentos del 39% y 211% QoQ respectivamente; el rendimiento de la molienda alcanzó el diseño de 85.300 tpd y las recuperaciones de cobre promediaron 77% Q3 (83% en septiembre). Las guías anuales de cobre para 2025 son ahora de 100–105 millones de libras.
Taseko (NYSE: TGB)는 Florence Copper 프로젝트에 대한 최종 규제 승인 100% 소유가 확보되었으며 운영자가 우필드 운영을 시작해 상업 생산 단계를 시작했다고 발표했습니다. SX/EW 공장은 9월 19일에 실질적 완공에 도달했으며 시운전은 우필드 시작과 병행될 예정입니다. 처음 구리 양극은 약 3개월 내에 예상됩니다. 기브롤타에서 3분기 생산은 Cu 2700만 파운드(0.9백만 파운드의 카토드 포함)와 Mo 56만 파운드로 각각 QoQ 39% 및 211% 증가했으며, 제련 통과량은 설계치인 85,300 tpd에 도달했고 구리 회수율은 3분기 평균 77%이며 9월에는 83%였습니다. 2025년 연간 구리 가이던스는 현재 100–105M lbs입니다.
Taseko (NYSE: TGB) a annoncé que les dernières autorisations réglementaires pour le projet Florence Copper, entièrement détenu, ont été reçues et que l'exploitant a commencé les opérations du puits, entamant la phase de production commerciale. L'usine SX/EW a atteint un état d'achèvement substantiel le 19 septembre et la mise en service s'effectuera en parallèle avec le démarrage du puits. La première cathode de cuivre est attendue dans environ trois mois. À Gibraltar, la production du T3 s'élevait à 27,6 Mlb Cu (dont 0,9 Mlb de cathode) et 560k lb Mo, en hausse respectivement de 39% et 211% QoQ; le débit de la moulinette a atteint le design 85 300 t/j et les récupérations de cuivre ont été en moyenne de 77% T3 (83% en septembre). Les prévisions annuelles de cuivre pour 2025 sont désormais de 100–105 Mlb.
Taseko (NYSE: TGB) gab bekannt, dass die endgültigen behördlichen Genehmigungen für das zu 100% im Besitz befindliche Florence Copper-Projekt erteilt wurden und der Betreiber Bohrfeldbetriebe aufgenommen hat, womit die kommerzielle Produktionsphase eingeleitet wird. Die SX/EW-Anlage erreichte am 19. September einen erheblichen Fertigstellungsgrad, und die Inbetriebnahme läuft parallel zum Start des Bohrfelds. Der erste Kupferkathodenstab wird voraussichtlich in ca. drei Monaten erwartet. In Gibraltar lag die Produktion im Q3 bei 27,6 Mio. lb Cu (einschließlich 0,9 Mio. lb Kathode) und 560k lb Mo, jeweils um 39% bzw. 211% QoQ gestiegen; der Mahlvorgang erreichte die Designleistung 85.300 tpd und die Kupfer-Rückgewinnung lag im Durchschnitt bei 77% Q3 (83% im Sept.). Die jährliche Kupfer-Leitlinie für 2025 liegt nun bei 100–105 Mio. lb.
Taseko (NYSE: TGB) أعلنت أن الموافقات التنظيمية النهائية لمشروع Florence Copper المملوك بنسبة 100% قد تم تلقيها وأن المشغل بدأ عمليات الحقل، مما يمهّد لبدء مرحلة الإنتاج التجاري. وصلت وحدة SX/EW إلى الإنهاء الهام في 19 سبتمبر وسيتم التشغيل بالتوازي مع بدء عمل الحقل. من المتوقع أن تكون أول لوحة كاثود نحاسية خلال حوالي ثلاثة أشهر. في جليبريتر، كانت إنتاجية الربع الثالث 27.6 مليون رطل من النحاس (بما في ذلك 0.9 مليون رطل كاثود) و560 ألف رطل من موليبيدنوم، بارتفاع 39% و211% على أساس ربع سنوي؛ بلغت قدرة الطاحونة على التدفق التصميم 85,300 طن/يوم وتوسعت معدلات استرداد النحاس في الربع الثالث بمعدل 77% (83% في سبتمبر). الدليل السنوي لإنتاج النحاس لعام 2025 أصبح الآن 100–105 مليون رطل.
Taseko (NYSE: TGB) 宣布,Florence Copper 项目已获得最终监管批准,100%自有,运营方已开始 井场作业,进入商业生产阶段。SX/EW 工厂于9月19日达到实质性竣工,调试将与井场启动并行进行。预计大约三个月内将出第一块铜阳极板。在直布罗陀,第三季度产量为2700万磅Cu(包括0.9百万磅阳极板)和56万磅Mo,分别较上季增长39%和211%;磨矿产出达到设计值85,300吨/日,铜回收率在3季度平均为77%(9月为83%)。2025年年度铜供应指引现为1.00–1.05亿磅。
- Florence wellfield operations commenced, enabling commercial start-up
- First copper cathode expected in ~3 months
- Gibraltar Q3 production 27.6M lbs Cu (+39% QoQ)
- Mill throughput at design 85,300 tpd; recoveries 77% Q3 (83% Sept)
- 2025 annual production guidance set to 100–105M lbs Cu
- Copper head grade of 0.22% at Gibraltar was behind plan
- Company expects Q4 increase but will not recover prior production shortfall
- Drawdown of Florence construction financing is subject to meeting required conditions
Insights
Florence begins wellfield operations and Gibraltar shows stronger throughput and recoveries; near-term copper production ramp imminent.
Taseko has started wellfield operations at Florence Copper, marking the transition to commercial plant commissioning while the SX/EW plant completes handover. The company schedules commissioning to run in parallel with wellfield startup and expects first copper cathode in about
Operational metrics show mill throughput at design capacity of 85,300 tons per day and improving recoveries averaging
Watch the synchronized milestones over the next quarter: successful SX/EW commissioning and first cathode production in about
VANCOUVER, British Columbia, Oct. 15, 2025 (GLOBE NEWSWIRE) -- Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the "Company") is pleased to provide an update on progress at its
Final regulatory approvals have been received and the operating team at Florence is now in the process of commencing wellfield operations, which marks the start up of the commercial production facility.
In the SX/EW plant area, the general contractor achieved substantial completion on September 19 and began to de-mobilize construction crews at that time. Taseko’s owners’ team is supervising the remaining contractors as they wrap up the final construction activities and systematically hand over sections of the plant area to the operating team for commissioning. The commissioning phase for the SX/EW plant is scheduled to run in parallel with the start of wellfield operations. First copper cathode is expected to be produced in about three months.
Stuart McDonald, President & CEO of Taseko, commented, “Commencement of wellfield operations is a fantastic milestone for Florence Copper, and a great achievement that our construction team in Arizona has accomplished in less than two years. We have successfully executed on this major capital project and look forward to first copper production and a successful ramp-up of the operation in the months ahead.”
At the Gibraltar Mine, third quarter production was 27.6 million pounds of copper, including 900 thousand pounds of copper cathode, and 560 thousand pounds of molybdenum. This represents an increase of
Mr. McDonald added, “At Gibraltar, mining is advancing deeper into the Connector pit, and we continue to see steady improvement in copper grades and ore quality, as most of the secondary mineralization is now behind us. We expect another significant production increase in the fourth quarter, but will not recover the production shortfall from recent months. Annual production for 2025 is now expected to be 100 to 105 million pounds of copper.”
“With copper prices approaching record levels, and a growing focus on security of critical mineral supply, the timing is ideal to bring on a major new source of refined copper inside the United States. With first copper cathode expected to be produced from Florence in about three months, and increasing production from our Gibraltar Mine, we’re becoming a more diversified copper miner in top tier mining jurisdictions,” concluded Mr. McDonald.
For further information on Taseko, see the Company’s website at tasekomines.com or contact:
- Investor enquiries Brian Bergot, Vice President, Investor Relations – 778-373-4554
Stuart McDonald
President and CEO
No regulatory authority has approved or disapproved of the information contained in this news release
Caution Regarding Forward-Looking Information
This document contains “forward-looking statements” that were based on Taseko’s expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “outlook”, “anticipate”, “project”, “target”, “believe”, “estimate”, “expect”, “intend”, “should” and similar expressions.
Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These included but are not limited to:
- uncertainties about the future market price of copper and the other metals that we produce or may seek to produce;
- changes in general economic conditions, the financial markets and in the market price for our input costs including due to inflationary impacts, such as diesel fuel, acid, steel, concrete, electricity and other forms of energy, mining equipment, and fluctuations in exchange rates, particularly with respect to the value of the U.S. dollar and Canadian dollar, and the continued availability of capital and financing;
- inherent risks associated with mining operations, including our current mining operations at Gibraltar and our planned mining operations at Florence Copper, and their potential impact on our ability to achieve our production estimates;
- uncertainties as to our ability to achieve reduced costs for Gibraltar (as defined below) and to otherwise control our operating costs without impacting our planned copper production;
- our high level of indebtedness and its potential impact on our financial condition and the requirement to generate cash flow to service our indebtedness and refinance such indebtedness from time to time;
- the increases in interest rates, by central banks may increase our borrowing costs and impact the profitability of our operations;
- our ability to draw down on our financing arrangements for the construction of Florence Copper is subject to our meeting the required conditions for drawdown;
- the amounts we are required to pay for our acquisition of Cariboo will increase with higher copper prices;
- the risk of inadequate insurance or inability to obtain insurance to cover our business risks;
- uncertainties related to the accuracy of our estimates of Mineral Reserves (as defined below), Mineral Resources (as defined below), production rates and timing of production, future production and future cash and total costs of production and milling;
- the risk that we may not be able to expand or replace Mineral Reserves as our existing Mineral Reserves are mined;
- the risk that the results from our development of Florence Copper will not meet our estimates of remaining construction costs, operating expenses, revenue, rates of return and cash flows from operations which have been projected by the technical report for Florence;
- the risk of cost overruns or delays in our construction of the commercial facilities at Florence Copper, resulting in not commencing commercial production within our current projected timeline or within our current projected cost estimates;
- uncertainties related to the execution plan for the construction of Florence Copper and the commencement of commercial operations resulting from inflation risk, supply chain disruptions, material and labour shortages or other execution risks;
- our ability to comply with all conditions imposed under the APP and UIC permits for the construction and operation of Florence Copper;
- the availability of, and uncertainties relating to, any additional financing necessary for the continued operation and development of our projects, including with respect to our ability to obtain any additional construction financing, if needed, to complete the construction and commencement of commercial operations at Florence Copper;
- shortages of water supply, critical spare parts, maintenance service and new equipment and machinery or our ability to manage surplus water on our mine sites may materially and adversely affect our operations and development projects;
- our ability to comply with the extensive governmental regulation to which our business is subject;
- uncertainties related to our ability to obtain necessary title, licenses and permits for our development projects and project delays due to third party opposition;
- uncertainties related to Indigenous people’s claims and rights, and legislation and government policies regarding the same;
- our reliance on the availability of infrastructure necessary for development and on operations, including on rail transportation and port terminals for shipping of our copper concentrate production from Gibraltar, and rail transportation and power for the feasibility of our other British Columbia development projects;
- uncertainties related to unexpected judicial or regulatory proceedings;
- changes in, and the effects of, the laws, regulations and government policies affecting our exploration and development activities and mining operations;
- potential changes to the mineral tenure system in British Columbia, which is undergoing reform for compliance with the Declaration Act (British Columbia);
- our dependence solely on our
100% interest in Gibraltar for our revenues and our operating cash flows; - our ability to extend existing concentrate off-take agreements or enter into new agreements;
- environmental issues and liabilities associated with mining including processing and stockpiling ore;
- labour strikes, work stoppages, or other interruptions to, or difficulties in, the employment of labour in markets in which we operate mines, industrial accidents, equipment failure or other events or occurrences, including third party interference that interrupt the production of minerals in our mines;
- environmental hazards and risks associated with climate change, including the potential for damage to infrastructure and stoppages of operations due to extreme cold, forest fires, flooding, drought, earthquakes or other natural events in the vicinity of our operations;
- litigation risks and the inherent uncertainty of litigation;
- our actual costs of reclamation and mine closure may exceed our current estimates of these liabilities;
- our ability to renegotiate our existing union agreement for Gibraltar when it expires in May 2027;
- the capital intensive nature of our business both to sustain current mining operations and to develop any new projects including Florence Copper;
- our ability to develop new mining projects may be adversely impacted by potential indigenous joint decision-making and consent agreements being implemented by the Government of British Columbia under the B.C. Declaration on the Rights of Indigenous Peoples Act;
- our reliance upon key personnel;
- the competitive environment in which we operate;
- the effects of forward selling instruments to protect against fluctuations in copper prices and other input costs including diesel and acid;
- the risk of changes in accounting policies and methods we use to report our financial condition, including uncertainties associated with critical accounting assumptions and estimates;
- uncertainties relating to the war in Ukraine, the Israel-Hamas conflict and other future geopolitical events including social unrest, which could disrupt financial markets, supply chains, availability of materials and equipment and execution timelines for any project development;
- recent changes to U.S. trade policies and tariff risks may adversely impact overall economic conditions, copper markets, supply chains, metal prices and input costs; and
- other risks detailed from time-to-time in our annual information forms, annual reports, MD&A, quarterly reports and material change reports filed with and furnished to securities regulators, and those risks which are discussed under the heading “Risk Factors”.
For further information on Taseko, investors should review the Company’s annual Form 40-F filing with the United States Securities and Exchange Commission www.sec.gov and home jurisdiction filings that are available at www.sedarplus.ca, including the “Risk Factors” included in our Annual Information Form.
