STOCK TITAN

Taseko Provides Construction Update on Florence Copper Project

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags

Taseko Mines reports significant progress on its Florence Copper project in Arizona, with overall completion reaching 78% as of March 31, 2025. The project remains on schedule for first copper production before year-end 2025. Key achievements include completion of 80 out of 90 planned production wells, finished electrowinning facility structure, and advancement in solvent extraction area.

Construction highlights include completed hydrotesting of field tanks, installation of cathode stripping machine, and progress on substation equipment. The project has logged 670,000 total hours with no reportable injuries or environmental incidents. Notably, Taseko secured authorization to reuse surplus process water for agriculture, replacing about 25% of current irrigation water needs.

The company maintains its original capital cost guidance and has hedged most of Gibraltar's copper production at a minimum price of US$4.00 per pound for the remainder of 2025, protecting against market volatility while maintaining positive long-term copper market outlook.

Taseko Mines comunica importanti progressi nel progetto Florence Copper in Arizona, con un completamento complessivo del 78% al 31 marzo 2025. Il progetto rimane in linea con la tabella di marcia per la prima produzione di rame entro la fine del 2025. Tra i risultati chiave, la realizzazione di 80 pozzi di produzione su 90 previsti, il completamento della struttura dell’impianto di elettrodeposizione e l’avanzamento nell’area di estrazione con solventi.

I punti salienti della costruzione includono il completamento dei test idraulici sui serbatoi di campo, l’installazione della macchina per la rimozione dei catodi e i progressi nell’attrezzatura della sottostazione. Il progetto ha raggiunto 670.000 ore totali di lavoro senza infortuni segnalabili o incidenti ambientali. Di rilievo, Taseko ha ottenuto l’autorizzazione a riutilizzare l’acqua di processo in eccesso per l’agricoltura, sostituendo circa il 25% del fabbisogno attuale di irrigazione.

L’azienda conferma le previsioni originali dei costi di capitale e ha coperto la maggior parte della produzione di rame di Gibraltar con un prezzo minimo di 4,00 dollari USA per libbra per il resto del 2025, proteggendosi dalla volatilità del mercato e mantenendo una prospettiva positiva a lungo termine sul mercato del rame.

Taseko Mines informa sobre avances significativos en su proyecto Florence Copper en Arizona, con un progreso total del 78% al 31 de marzo de 2025. El proyecto sigue en camino para iniciar la producción de cobre antes de fin de año 2025. Los logros clave incluyen la finalización de 80 de los 90 pozos de producción planificados, la estructura terminada de la planta de electroobtención y avances en el área de extracción con solventes.

Entre los aspectos destacados de la construcción están la finalización de las pruebas hidráulicas de los tanques de campo, la instalación de la máquina para pelar cátodos y el progreso en el equipo de la subestación. El proyecto ha acumulado 670,000 horas totales sin lesiones reportables ni incidentes ambientales. Cabe destacar que Taseko obtuvo autorización para reutilizar el agua excedente del proceso para la agricultura, reemplazando aproximadamente el 25% de las necesidades actuales de riego.

La compañía mantiene su guía original de costos de capital y ha cubierto la mayor parte de la producción de cobre de Gibraltar con un precio mínimo de US$4.00 por libra para el resto de 2025, protegiéndose contra la volatilidad del mercado y manteniendo una perspectiva positiva a largo plazo para el mercado del cobre.

Taseko Mines는 애리조나에 위치한 Florence Copper 프로젝트에서 2025년 3월 31일 기준 전체 완료율 78%라는 중요한 진전을 보고했습니다. 이 프로젝트는 2025년 말 이전에 첫 구리 생산을 시작할 예정대로 진행 중입니다. 주요 성과로는 계획된 90개의 생산정공 중 80개 완료, 전해제련 시설 구조 완성, 용매 추출 구역의 진전이 포함됩니다.

건설 주요 사항으로는 현장 탱크의 수압 시험 완료, 음극 박리 기계 설치, 변전소 장비 진행 상황이 있습니다. 프로젝트는 총 67만 시간의 작업을 기록했으며 보고할 만한 부상이나 환경 사고는 없었습니다. 특히 Taseko는 농업용으로 잉여 공정수를 재사용할 수 있는 허가를 받아 현재 관개용수 수요의 약 25%를 대체하게 되었습니다.

회사는 원래의 자본 비용 가이던스를 유지하며, 2025년 남은 기간 동안 지브롤터 구리 생산량 대부분을 파운드당 최소 4.00달러로 헤지하여 시장 변동성에 대비하고 장기적으로 구리 시장에 대해 긍정적인 전망을 유지하고 있습니다.

Taseko Mines annonce des progrès significatifs sur son projet Florence Copper en Arizona, avec un taux d’achèvement global de 78 % au 31 mars 2025. Le projet reste conforme au calendrier pour une première production de cuivre avant la fin de l’année 2025. Parmi les réalisations clés figurent l’achèvement de 80 des 90 puits de production prévus, la structure terminée de l’usine d’électroobtention et les avancées dans la zone d’extraction par solvant.

Les points forts de la construction incluent la réalisation des tests hydrauliques des réservoirs de terrain, l’installation de la machine de décapage des cathodes et les progrès sur l’équipement de la sous-station. Le projet a cumulé 670 000 heures de travail sans blessures déclarables ni incidents environnementaux. Notamment, Taseko a obtenu l’autorisation de réutiliser l’eau excédentaire du procédé pour l’agriculture, remplaçant environ 25 % des besoins actuels en eau d’irrigation.

La société maintient ses prévisions initiales de coûts en capital et a couvert la majeure partie de la production de cuivre de Gibraltar à un prix minimum de 4,00 USD la livre pour le reste de 2025, se protégeant ainsi contre la volatilité du marché tout en conservant une perspective positive à long terme sur le marché du cuivre.

Taseko Mines berichtet über bedeutende Fortschritte bei seinem Florence Copper-Projekt in Arizona, mit einem Gesamtfortschritt von 78 % zum 31. März 2025. Das Projekt liegt weiterhin im Zeitplan für die erste Kupferproduktion vor Jahresende 2025. Zu den wichtigsten Erfolgen zählen die Fertigstellung von 80 von 90 geplanten Produktionsbohrungen, der Abschluss der Struktur der Elektrowinning-Anlage und Fortschritte im Bereich der Lösungsmittel-Extraktion.

Zu den Bauhöhepunkten gehören der abgeschlossene Hydrauliktest der Feldtanks, die Installation der Kathoden-Abstreifmaschine sowie Fortschritte bei der Ausrüstung der Umspannstation. Das Projekt hat insgesamt 670.000 Arbeitsstunden ohne meldepflichtige Verletzungen oder Umweltvorfälle erreicht. Bemerkenswert ist, dass Taseko die Genehmigung erhalten hat, überschüssiges Prozesswasser für die Landwirtschaft wiederzuverwenden, wodurch etwa 25 % des aktuellen Bewässerungsbedarfs ersetzt werden.

Das Unternehmen hält an seiner ursprünglichen Kapitalaufwandsprognose fest und hat den Großteil der Kupferproduktion von Gibraltar für den Rest des Jahres 2025 zu einem Mindestpreis von 4,00 US-Dollar pro Pfund abgesichert, um sich gegen Marktschwankungen zu schützen und gleichzeitig eine positive langfristige Markterwartung für Kupfer beizubehalten.

Positive
  • Project construction 78% complete and on schedule for 2025 production
  • No reportable injuries or environmental incidents in 670,000 work hours
  • Secured water reuse authorization, improving resource efficiency
  • Copper price hedging protection at US$4.00/lb minimum for 2025
  • Construction costs tracking within original guidance
Negative
  • Exposure to potential construction delays and cost overruns
  • Dependent on successful completion of remaining 10 production wells
  • Subject to market volatility and copper price fluctuations beyond 2025

Insights

Florence Copper Project at 78% completion, on schedule for 2025 production with excellent safety record and new water sustainability permit.

Taseko's Florence Copper Project has achieved 78% completion as of March 31, 2025, with construction advancing precisely on schedule. The wellfield development has made substantial progress with 80 of 90 planned production wells already drilled and constructed, with the remaining drilling set to conclude in May. This keeps the project firmly on track for first copper production before year-end 2025.

Several critical construction milestones have been reached in Q1, including completion of point of compliance well drilling, near-completion of the electrowinning facility building structure, commencement of cathode stripping machine installation, and advancement of the solvent extraction area focusing on pipe and settler welding. All field-erected tanks have successfully completed hydrotesting, with sandblasting and painting of carbon steel tanks now finished.

The project's safety performance has been exemplary, reporting zero recordable injuries across approximately 670,000 total project hours with about 440 contract personnel on site. During Q1 alone, the project logged 230,000 work hours.

A significant environmental advancement was recently achieved with authorization to reuse surplus process water from operations for agricultural purposes. This permit allows excess process water to replace irrigation water currently drawn from other sources across approximately 25% of the Florence Copper property used for agriculture. This sustainable water management approach increases overall water availability for other users in the project area – a meaningful enhancement for operations in Arizona's water-constrained environment.

Florence Copper remains on budget with production timeline intact; strategic US market positioning and $4.00/lb copper hedges provide stability.

Taseko's Florence Copper Project remains financially disciplined with construction expenditures tracking precisely to expectations. Management explicitly confirms their "previous capital cost guidance remains unchanged" – a notable achievement given the inflationary pressures facing the mining sector.

The company is strategically positioning Florence Copper as a domestic supplier of refined copper cathode within the US market. This positioning creates a potential competitive advantage, with management noting the project could "potentially benefit from premium COMEX copper pricing in the coming years" as a US-based producer.

To mitigate near-term market volatility, Taseko has implemented prudent risk management through copper hedges that establish a $4.00 per pound price floor for most of Gibraltar mine's production through the remainder of 2025. This provides revenue stability during the critical period as Florence approaches production.

The advancing Florence project represents significant diversification for Taseko, whose current production and operating cash flows rely solely on the Gibraltar mine. While management acknowledges "recent market volatility" in copper prices, they maintain that "long-term fundamentals for copper remain robust" – an important consideration for this development project approaching production.

With 78% overall completion and on-schedule progress toward year-end production, Florence Copper is advancing toward becoming "a major new supplier of copper cathode for the US market" as stated by CEO Stuart McDonald, representing a significant growth catalyst for Taseko.

VANCOUVER, British Columbia, April 21, 2025 (GLOBE NEWSWIRE) -- Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) ("Taseko" or the "Company") is pleased to update the progress at its 100%-owned Florence Copper project in Florence, Arizona.

Construction continues to advance on schedule and first copper production is still targeted before the end of 2025. Overall project completion was at 78% as of March 31, 2025. During the first quarter there were approximately 440 contract personnel on site and 230,000 project hours were worked. Total project hours to-date are roughly 670,000 and there have been no reportable injuries or environmental incidents.

Summary of key activities in the first quarter:

  • 29 production wells were drilled and constructed in the quarter, for a total of 80 out of the 90 wells planned to be drilled during the construction phase
  • Point of compliance well drilling was completed in the quarter
  • Work on the building structure for the electrowinning facility was completed except for the final roof and wall sections that will be installed after the electrowinning overhead crane is installed in April.
  • Installation of the cathode stripping machine started in March
  • The solvent extraction area continues to advance with a focus on pipe and settler welding and electrical installation
  • Hydrotesting of all the field erected tanks was completed
  • Sandblasting and painting of the carbon steel tanks was completed
  • Factory acceptance testing of the tank farm E-house was completed and it was delivered to site
  • Assembly of the modular office and dry buildings was completed, and work on the exterior finishing started
  • The substation area progressed and the installation of major equipment is well advanced
  • Work on surface infrastructure advanced and installation of high density polyethylene piping in the main pipeline corridor continued and the storm water box culvert under the pipe corridor was completed

Another significant recent milestone for Florence Copper is the authorization to reuse a portion of surplus process water from operations. Approximately 25% of the Florence Copper property is used for agriculture, and with the new permit, this excess process water will replace irrigation water that is currently drawn from other sources. This will result in more water available for other users in the project area.

Stuart McDonald, President & CEO of Taseko, commented, “After 15 months, construction progress continues to track to our original schedule. Wellfield drilling activity is now ramping down and will be completed on schedule in May, and we are steadily advancing towards first copper production later this year.   Construction expenditures have been in line with expectations and our previous capital cost guidance remains unchanged. The project is in great shape and Florence Copper will soon become a major new supplier of copper cathode for the US market. The project is uniquely positioned to produce and sell refined copper inside the United States and potentially benefit from premium COMEX copper pricing in the coming years.”

Mr. McDonald continued, “Despite the recent market volatility, the long-term fundamentals for copper remain robust. In the short-term, Taseko has copper hedges in place that protect a minimum copper sales price of US$4.00 per pound for most of Gibraltar’s production for the balance of 2025.”

Updated photos can be found on our website at https://tasekomines.com/properties/florence-copper/#construction-updates.

For further information on Taseko, see the Company’s website at www.tasekomines.com or contact:

Investor enquiries Brian Bergot, Vice President, Investor Relations – 778-373-4554

Stuart McDonald
President and CEO

No regulatory authority has approved or disapproved of the information contained in this news release.

Caution Regarding Forward-Looking Information

This document contains “forward-looking statements” that were based on Taseko’s expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “outlook”, “anticipate”, “project”, “target”, “believe”, “estimate”, “expect”, “intend”, “should” and similar expressions.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These included but are not limited to:

uncertainties about the future market price of copper and the other metals that we produce or may seek to produce;
changes in general economic conditions, the financial markets, inflation and interest rates and in the demand and market price for our input costs, such as diesel fuel, reagents, steel, concrete, electricity and other forms of energy, mining equipment, and fluctuations in exchange rates, particularly with respect to the value of the U.S. dollar and Canadian dollar, and the continued availability of capital and financing;
uncertainties resulting from the war in Ukraine, and the accompanying international response including economic sanctions levied against Russia, which has disrupted the global economy, created increased volatility in commodity markets (including oil and gas prices), and disrupted international trade and financial markets, all of which have an ongoing and uncertain effect on global economics, supply chains, availability of materials and equipment and execution timelines for project development;
inherent risks associated with mining operations, including our current mining operations at Gibraltar, and their potential impact on our ability to achieve our production estimates;
uncertainties as to our ability to control our operating costs, including inflationary cost pressures at Gibraltar without impacting our planned copper production;
the risk of inadequate insurance or inability to obtain insurance to cover material mining or operational risks;
uncertainties related to the feasibility study for Florence copper project (the “Florence Copper Project” or “Florence Copper”) that provides estimates of expected or anticipated capital and operating costs, expenditures and economic returns from this mining project, including the impact of inflation on the estimated costs related to the construction of the Florence Copper Project and our other development projects;
the risk that the results from our operations of the Florence Copper production test facility (“PTF”) and ongoing engineering work including updated capital and operating costs will negatively impact our estimates for current projected economics for commercial operations at Florence Copper;
uncertainties related to the accuracy of our estimates of Mineral Reserves (as defined below), Mineral Resources (as defined below), production rates and timing of production, future production and future cash and total costs of production and milling;
the risk that we may not be able to expand or replace reserves as our existing mineral reserves are mined;
the availability of, and uncertainties relating to the development of, additional financing and infrastructure necessary for the advancement of our development projects, including with respect to our ability to obtain any remaining construction financing potentially needed to move forward with commercial operations at Florence Copper;
our ability to comply with the extensive governmental regulation to which our business is subject;
uncertainties related to our ability to obtain necessary title, licenses and permits for our development projects and project delays due to third party opposition;
our ability to deploy strategic capital and award key contracts to assist with protecting the Florence Copper project execution plan, mitigating inflation risk and the potential impact of supply chain disruptions on our construction schedule and ensuring a smooth transition into construction;
uncertainties related to First Nations claims and consultation issues;
our reliance on rail transportation and port terminals for shipping our copper concentrate production from Gibraltar;
uncertainties related to unexpected judicial or regulatory proceedings;
changes in, and the effects of, the laws, regulations and government policies affecting our exploration and development activities and mining operations and mine closure and bonding requirements;
our dependence solely on Gibraltar (as defined below) for revenues and operating cashflows;
our ability to collect payments from customers, extend existing concentrate off-take agreements or enter into new agreements;
environmental issues and liabilities associated with mining including processing and stock piling ore;
labour strikes, work stoppages, or other interruptions to, or difficulties in, the employment of labour in markets in which we operate our mine, industrial accidents, equipment failure or other events or occurrences, including third party interference that interrupt the production of minerals in our mine;
environmental hazards and risks associated with climate change, including the potential for damage to infrastructure and stoppages of operations due to forest fires, flooding, drought, or other natural events in the vicinity of our operations;
litigation risks and the inherent uncertainty of litigation, including litigation to which Florence Copper could be subject to;
our actual costs of reclamation and mine closure may exceed our current estimates of these liabilities;
our ability to meet the financial reclamation security requirements for the Gibraltar mine and Florence Project;
the capital intensive nature of our business both to sustain current mining operations and to develop any new projects, including Florence Copper;
our reliance upon key management and operating personnel;
the competitive environment in which we operate;
the effects of forward selling instruments to protect against fluctuations in copper prices, foreign exchange, interest rates or input costs such as fuel; and
the risk of changes in accounting policies and methods we use to report our financial condition, including uncertainties associated with critical accounting assumptions and estimates; and Management Discussion and Analysis (“MD&A”), quarterly reports and material change reports filed with and furnished to securities regulators, and those risks which are discussed under the heading “Risk Factors”.

For further information on Taseko, investors should review the Company’s annual Form 40-F filing with the United States Securities and Exchange Commission www.sec.gov and home jurisdiction filings that are available at www.sedarplus.ca, including the “Risk Factors” included in our Annual Information Form.


FAQ

When will Taseko's Florence Copper project start production?

Taseko targets first copper production from the Florence Copper project before the end of 2025, with construction currently 78% complete as of March 31, 2025.

How many production wells has TGB completed at Florence Copper?

Taseko has completed 80 out of 90 planned production wells, with drilling expected to be completed in May 2025.

What is the water management plan for TGB's Florence Copper project?

The project received authorization to reuse surplus process water for agriculture, replacing approximately 25% of current irrigation water needs in the project area.

What hedging strategy does TGB have in place for 2025?

Taseko has secured copper hedges ensuring a minimum sales price of US$4.00 per pound for most of Gibraltar's production through 2025.

How is the safety record at TGB's Florence Copper construction site?

The project has recorded 670,000 total work hours with no reportable injuries or environmental incidents.
Taseko Mines

NYSE:TGB

TGB Rankings

TGB Latest News

TGB Stock Data

672.84M
307.47M
2.57%
28.41%
1.11%
Copper
Basic Materials
Link
Canada
Vancouver