Tartisan Nickel Corp. Completes Phase 2 Construction on the Kenbridge Nickel All-Season Access Road, Receives Critical Realignment Road Permit

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tartisan Nickel Corp. (TTSRF) has completed Phase 2 construction of the Kenbridge Nickel Project access road and received approval for Phase 3 realignment. The project has transformed access to the previously difficult-to-reach Kenbridge site from floatplane/ATV-only to all-season pickup truck access. Phase 2 improvements included installing 37 cross-drain culverts, implementing erosion control measures, and stabilizing winter-built road sections. The Kenbridge Project, spanning 4,273 ha with 93 patents and 153 mining claims, is located 40 km from Highway 71. The newly approved Phase 3 realignment permit will enable low-bed transport and fuel delivery vehicles access, featuring bridge approach reconstruction, rock cuts, and environmentally conscious route adjustments, including avoiding a natural spring identified by Indigenous Knowledge Keepers.
Tartisan Nickel Corp. (TTSRF) ha completato la costruzione della Fase 2 della strada di accesso al progetto Kenbridge Nickel e ha ottenuto l'approvazione per la riallineamento della Fase 3. Il progetto ha trasformato l'accesso al sito Kenbridge, precedentemente raggiungibile solo con idrovolante o ATV, rendendolo accessibile tutto l'anno con pickup. I miglioramenti della Fase 2 hanno incluso l'installazione di 37 cunette di drenaggio trasversale, l'implementazione di misure di controllo dell'erosione e la stabilizzazione delle sezioni della strada costruite in inverno. Il progetto Kenbridge, che si estende su 4.273 ettari con 93 brevetti e 153 concessioni minerarie, si trova a 40 km dall'autostrada 71. Il permesso appena approvato per il riallineamento della Fase 3 consentirà l'accesso a veicoli per il trasporto su rimorchio basso e per la consegna di carburante, con la ricostruzione degli approcci ai ponti, tagli di roccia e aggiustamenti del percorso rispettosi dell'ambiente, inclusa l'evitazione di una sorgente naturale identificata dai Custodi del Sapere Indigeno.
Tartisan Nickel Corp. (TTSRF) ha completado la construcción de la Fase 2 del camino de acceso al Proyecto Kenbridge Nickel y ha recibido la aprobación para la realineación de la Fase 3. El proyecto ha transformado el acceso al sitio Kenbridge, que antes solo se podía alcanzar en hidroavión o ATV, a un acceso durante todo el año con camionetas pickup. Las mejoras de la Fase 2 incluyeron la instalación de 37 alcantarillas transversales, la implementación de medidas de control de erosión y la estabilización de secciones de la carretera construidas en invierno. El Proyecto Kenbridge, que abarca 4,273 hectáreas con 93 patentes y 153 concesiones mineras, está ubicado a 40 km de la autopista 71. El permiso recién aprobado para la realineación de la Fase 3 permitirá el acceso de vehículos de transporte de cama baja y de entrega de combustible, con la reconstrucción de los accesos a puentes, cortes en roca y ajustes de ruta ambientalmente conscientes, incluyendo evitar un manantial natural identificado por los Guardianes del Conocimiento Indígena.
Tartisan Nickel Corp.(TTSRF)는 Kenbridge Nickel 프로젝트 접근 도로의 2단계 건설을 완료하고 3단계 재조정 승인을 받았습니다. 이 프로젝트는 이전에 수상비행기나 ATV로만 접근 가능했던 Kenbridge 현장에 연중 픽업 트럭 접근이 가능하도록 접근성을 혁신적으로 개선했습니다. 2단계 개선사항에는 37개의 횡단 배수관 설치, 침식 제어 조치 시행, 겨울에 건설된 도로 구간 안정화가 포함되었습니다. Kenbridge 프로젝트는 4,273헥타르에 걸쳐 93개의 특허와 153개의 광산 채굴권을 보유하고 있으며 고속도로 71에서 40km 떨어진 곳에 위치해 있습니다. 새로 승인된 3단계 재조정 허가는 저상 트레일러 운송 및 연료 공급 차량의 접근을 가능하게 하며, 교량 진입로 재건, 암석 절단, 그리고 토착 지식 보유자들이 확인한 천연 샘을 피하는 등 환경을 고려한 경로 조정이 포함됩니다.
Tartisan Nickel Corp. (TTSRF) a terminé la construction de la Phase 2 de la route d'accès au projet Kenbridge Nickel et a obtenu l'approbation pour le réalignement de la Phase 3. Le projet a transformé l'accès au site Kenbridge, auparavant difficile d'accès uniquement par hydravion ou VTT, en un accès toute l'année pour camionnettes. Les améliorations de la Phase 2 comprenaient l'installation de 37 ponceaux transversaux, la mise en œuvre de mesures de contrôle de l'érosion et la stabilisation des sections de route construites en hiver. Le projet Kenbridge, qui s'étend sur 4 273 hectares avec 93 brevets et 153 concessions minières, est situé à 40 km de l'autoroute 71. Le permis récemment approuvé pour le réalignement de la Phase 3 permettra l'accès aux véhicules de transport sur plateau bas et aux véhicules de livraison de carburant, avec la reconstruction des approches de ponts, des coupes dans la roche et des ajustements de parcours respectueux de l'environnement, incluant l'évitement d'une source naturelle identifiée par les Gardiens du Savoir Autochtones.
Tartisan Nickel Corp. (TTSRF) hat den Bau der Phase-2-Zufahrtsstraße zum Kenbridge Nickel Projekt abgeschlossen und die Genehmigung für die Phase-3-Neuausrichtung erhalten. Das Projekt hat den Zugang zum zuvor schwer erreichbaren Kenbridge-Gelände von einem nur mit Wasserflugzeug oder ATV erreichbaren Standort zu einem ganzjährigen Zugang mit Pickup-Trucks umgewandelt. Die Verbesserungen in Phase 2 umfassten die Installation von 37 Querabläufen, die Umsetzung von Erosionsschutzmaßnahmen und die Stabilisierung im Winter gebaute Straßenabschnitte. Das Kenbridge-Projekt erstreckt sich über 4.273 Hektar mit 93 Patenten und 153 Bergbaulizenzen und liegt 40 km von der Highway 71 entfernt. Die neu genehmigte Phase-3-Neuausrichtung ermöglicht den Zugang für Tieflader-Transportfahrzeuge und Kraftstofflieferfahrzeuge, einschließlich der Wiederherstellung der Brückenanfahrten, Felsenschnitte und umweltbewusster Routenanpassungen, darunter die Vermeidung einer natürlichen Quelle, die von indigenen Wissensbewahrern identifiziert wurde.
Positive
  • Completion of Phase 2 construction improves year-round accessibility to the Kenbridge site, potentially reducing operational costs
  • Approval of Phase 3 realignment permit enables future heavy equipment and fuel delivery access
  • Strong collaboration with Indigenous communities demonstrates positive stakeholder relations
  • Implementation of 37 cross-drain culverts and erosion control measures ensures long-term road stability
Negative
  • Additional costs incurred due to environmental route adjustments
  • Project still requires completion of Phase 3 before heavy equipment access is possible

Toronto, Ontario--(Newsfile Corp. - June 19, 2025) - Tartisan Nickel Corp. (CSE: TN) (OTCQB: TTSRF) (FSE: 8TA) ("Tartisan", or the "Company") is pleased to announce that work on the Kenbridge Nickel Project access corridor has achieved Phase 2 completion and has made significant improvements to the operational access road.

The Kenbridge Nickel-Copper-Cobalt Project consists of 93 contiguous patents, 153 single cell mining claims and 4 Mining Licenses of Occupation totaling 4,273 ha. The Kenbridge Property is 40 kms from paved Highway 71 via the Maybrun gravel road. The Kenbridge Property turnoff is approximately 28 kms into the Maybrun Road. The Kenbridge Project is then approximately 12.7 kms to the Kenbridge 622-meter shaft and the Kenbridge core shack. The Kenbridge Critical Minerals Project was historically only accessible by floatplane or by ATV, which made Project logistics expensive and difficult.

Phase 2 of the Kenbridge Road Project prioritized establishing reliable year-round pickup access to the Kenbridge site and core shack. This phase prioritized stabilizing key road infrastructure following winter construction.

With spring break-up complete, winter-built road sections were reshaped and compacted to address settling and ensure safe all-season access. Rehabilitation activities included subgrade shaping, grade capping, and gravel placement, with additional material added to steep approaches to improve vehicle traction and safety.

A significant focus was on drainage improvements:

  • 37 cross-drain culverts were installed to support proper water flow and preserve long-term road stability and environmental integrity.
  • Erosion control and environmental protection measures were implemented throughout the corridor to safeguard sensitive areas.

Additional work included:

  • Survey and ribboning for Phase 3 realignments to support safe and efficient low-bed and fuel trucks to the Kenbridge core shack
  • Site cleanup and removal of historical debris at the core shack
  • Safety barrier installation along steep embankments

Collaboration with Indigenous community members and land-based resource specialists continued through several field visits, helping guide and validate project progress. Environmental stewardship and respectful land management remain central to all ongoing and upcoming phases.

Kenbridge Road Realignment Permit Approval

A major milestone in June 2025 was the approval of the Kenbridge Road Realignment Permit (Phase 3)—a result of close collaboration with Indigenous communities and with the Minister of Natural Resources staff in Kenora, Ontario. These realignments are essential for enabling safe and efficient access for low-bed transport and fuel delivery vehicles.

Key Next Steps Phase 3 elements include:

  • Reconstruction of Atikwa River bridge approaches and departures
  • One significant rock cut on Tartisan Nickel-patented land
  • Two minor rock cuts
  • Two major realignments of existing road and trail corridors

Notably, one realignment shifts the corridor away from a natural spring identified by a local Indigenous Knowledge Keeper as important to the regional watershed. While this adds cost to the project, it reflects Tartisan's continued commitment to environmental care and respect for the Land.

Tartisan Nickel Corp. remains focused on environmental protection and Indigenous partnership as we move into the next phase of development.

Mark Appleby, CEO of Tartisan Nickel Corp. states, "The Kenbridge all-season access road work continued this spring with a highly effective construction program. With receiving the Kenbridge Road Realignment Permit from the Ministry of Natural Resources, Tartisan is now able to prepare for Phase 3 construction which will allow the Company to ultimately float large equipment including the delivery of fuel into site". Appleby goes onto state, "We are gearing up for this all-important Phase 3 and road completion. We look forward to sharing our 2025 next steps, as significant plans are being put in place to commence summer exploration at the Kenbridge critical metals project."

About Tartisan Nickel Corp.

Tartisan Nickel Corp. is a Canadian-based mineral exploration and development company which owns the Kenbridge Nickel Project near Sioux Narrows, Northwestern Ontario, the Night Danger Turtle Pond project near Dryden, Ontario as well as the Sill Lake Silver Property near Sault Ste. Marie, Ontario. Tartisan Nickel Corp. common shares are listed on the Canadian Securities Exchange (CSE: TN) (OTCQB: TTSRF) (FSE: 8TA). Currently, there are 130,995,782 shares outstanding (137,784,671 fully diluted).

For further information, please contact Mark Appleby, President & CEO, and a Director of the Company, at 416-804-0280 (info@tartisannickel.com). Additional information about Tartisan Nickel Corp. can be found at the Company's website at www.tartisannickel.com or on SEDAR at www.sedarplus.ca.

This news release may contain forward-looking statements including but not limited to comments regarding the timing and content of upcoming work programs, geological interpretations, receipt of property titles, potential mineral recovery processes, etc. Forward-looking statements address future events and conditions and therefore involve inherent risks and uncertainties. Actual results may differ materially from those currently anticipated in such statements.
The Canadian Securities Exchange (operated by CNSX Markets Inc.) has neither approved nor disapproved of the contents of this press release.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/256105

FAQ

What progress has Tartisan Nickel (TTSRF) made on the Kenbridge access road project?

Tartisan has completed Phase 2 construction, which includes all-season pickup access, 37 cross-drain culverts, and erosion control measures, and received approval for Phase 3 realignment permit.

What is the size and location of Tartisan's Kenbridge Nickel Project?

The Kenbridge Project spans 4,273 ha, consisting of 93 patents, 153 mining claims, and 4 Mining Licenses of Occupation, located 40 km from Highway 71 in Ontario.

What improvements will Phase 3 of TTSRF's Kenbridge road project include?

Phase 3 will include Atikwa River bridge approach reconstruction, rock cuts, and realignments to enable low-bed transport and fuel delivery vehicle access.

How is Tartisan Nickel working with Indigenous communities on the Kenbridge project?

Tartisan collaborates with Indigenous communities through field visits, land-based resource specialists, and has adjusted road alignment to protect a natural spring identified by Indigenous Knowledge Keepers.

What was the previous access method to the Kenbridge site before the road construction?

The Kenbridge Project was previously only accessible by floatplane or ATV, making project logistics expensive and difficult.
Tartisan Nickel

OTC:TTSRF

TTSRF Rankings

TTSRF Latest News

TTSRF Stock Data

14.26M
104.65M
20.42%
1.07%
Other Industrial Metals & Mining
Basic Materials
Link
Canada
Toronto