Waste Energy Corp (NASDAQ:WAST) completed a single-day installation of approximately 175,000 pounds of core thermal processing equipment at its Midland, Texas facility on May 7, 2026, marking transition from heavy construction to final integration.

With heavy civil work concluded, the company will focus on electrical, piping, welding, controls integration, and system testing as it advances toward initial commissioning and first revenue-generating operations.

Loading...
Loading translation...

Positive

  • Single-day installation of 175,000 pounds of core equipment
  • Heavy civil and structural phase concluded at Midland
  • First commercial-scale deployment of modular waste conversion technology
  • Location in Permian Basin offers proximity to feedstock and energy demand

Negative

  • Facility still requires electrical, piping, welding, controls integration, and testing
  • Commissioning and initial revenue have not yet occurred

News Market Reaction – WAST

+23.91%
+23.91% Session close to close

In the May 8 session, WAST gained 23.91%, reflecting a significant positive market reaction.

Data tracked by StockTitan Argus on the day of publication.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

"Crane Day" Marks Transition From Construction to Final Integration as Company Approaches First Revenue-Generating Operations

MIDLAND, TX / ACCESS Newswire / May 8, 2026 / Waste Energy Corp. ("WEC" or the "Company"), a resource recovery and alternative energy company focused on converting non-recyclable waste into usable fuel and renewable energy products, today announced that it has successfully installed the core equipment for its first commercial-scale waste conversion system at its Midland, Texas facility - a defining operational milestone that moves the Company materially closer to commissioning and revenue-generating operations.

On May 7, 2026, WEC's construction team lifted and positioned approximately 175,000 pounds of primary waste-to-energy conversion equipment onto the system foundation - a combined weight comparable to that of a fully loaded Boeing 737 commercial aircraft. The installation included the Company's core thermal processing units and supporting system components. The single-day operation, internally designated "Crane Day," represents one of the most significant construction milestones in the Company's history and concludes the heavy civil and structural phase of the Midland buildout.

"Crane Day is the moment this project stopped being a construction site and started becoming an operating facility," said Scott Gallagher, CEO of Waste Energy Corp. "Setting the core system in a single day is the culmination of years of planning, disciplined site preparation, and engineering work by our team, and it puts us on a direct path to commissioning. Midland is our first commercial deployment, but it's also our template - every milestone we hit here accelerates the timeline for our next sites."

With the heavy equipment now in place, the Company's focus shifts to final interconnection work, including electrical, piping, welding, controls integration, and system testing. WEC expects these activities to progress over the coming weeks as the facility advances toward initial commissioning.

Strategic Position in the Permian Basin

The Midland facility represents the Company's first commercial-scale deployment of its modular waste conversion technology platform, designed to convert waste tires and other non-recyclable waste streams into usable energy products while supporting landfill diversion. The Company believes Midland's location offers strategic advantages through its proximity to feedstock supply, established energy infrastructure, and industrial fuel demand within the Permian Basin.

WEC has previously announced agreements and relationships supporting feedstock supply, recovered material sales, and participation in regional cleanup and landfill diversion initiatives, including the Basin Beautification Project.

A Platform Built to Scale

The modular design of WEC's waste conversion technology is intended to allow future deployments to benefit from the operational experience, engineering refinements, and process efficiencies developed during the Midland buildout and commissioning process. Concurrently, the Company is advancing planning for additional facilities and evaluating expansion opportunities in regions with strong feedstock availability and energy demand as management believes WEC is approaching a meaningful operational inflection point in its transition toward revenue-generating operations.

About Waste Energy Corp.

Waste Energy Corp. (OTCQB:WAST) is a resource recovery and alternative energy company developing waste-to-energy infrastructure and assets in the United States. The Company is a fully reporting SEC Exchange Act registrant. For more information, visit www.WEC.eco. Investor disclosures are available at www.sec.gov.

Forward-Looking Statements

This press release contains forward-looking statements within the meaning of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934, including statements regarding the timing of Crane Day, commissioning and related operational activities, the timing of SEC filings, and the Company's transition to revenue-generating operations. Actual results may differ materially due to risks including delays or cost overruns in installation, integration, or commissioning; the Company's ability to complete its audit and timely file required SEC reports; the need for additional capital; the realization of anticipated revenue streams; and the additional risk factors described in the Company's filings with the SEC at www.sec.gov. These forward-looking statements speak only as of the date of this release, and the Company undertakes no obligation to update them except as required by law. Investors are encouraged to review the Company's filings with the SEC, including the risk factors disclosed therein, before making any investment decision.

Investor Contact:

Waste Energy Corp.
Email: IR@WEC.eco
Phone: (727) 417-7807
Website: www.WEC.eco

SOURCE: Waste Energy Corp.



View the original press release on ACCESS Newswire

FAQ

What did Waste Energy Corp (WAST) install at the Midland facility on May 7, 2026?

The company installed approximately 175,000 pounds of primary waste-to-energy equipment in a single day. According to the company, this included core thermal processing units and supporting components and concluded the heavy civil and structural phase.

What are the next steps for WAST at the Midland facility after the "Crane Day" installation?

Next steps include electrical, piping, welding, controls integration, and system testing before commissioning. According to the company, these final interconnection activities will progress over the coming weeks toward initial commissioning.

Does the Midland installation mean Waste Energy Corp (WAST) is already generating revenue?

No, the Midland facility is not yet generating revenue; commissioning remains pending. According to the company, the heavy equipment is set and the site is advancing toward initial commissioning and first revenue-generating operations.

Why is the Midland location strategically important for Waste Energy Corp (WAST)?

Midland provides proximity to feedstock supply, energy infrastructure, and industrial fuel demand in the Permian Basin. According to the company, that location supports feedstock access and recovered material sales opportunities.

Will the Midland buildout help Waste Energy Corp (WAST) expand to additional sites?

Yes, the modular design is intended to serve as a template for future deployments. According to the company, operational experience and engineering refinements from Midland should accelerate timelines for subsequent facilities.