Westbridge Renewable Energy Provides Update on International Solar and Battery Storage Portfolio
Rhea-AI Summary
Westbridge Renewable Energy (WEGYF) provided an update on its international solar and battery storage portfolio. The company reported significant achievements in FY2024, including the sale of Alberta Georgetown and Sunnynook projects, generating over $62 million in non-dilutive cash. The company has achieved 30x portfolio growth to >9GW under development.
Key developments include: repayment of over $35m debt, $10m capital returned to shareholders (12% yield), and AUC approval for Project Dolcy. The company has definitive agreements with Metlen Energy & Metals for five Alberta-based projects totaling 1.4 GW. Additionally, Westbridge added 5 new standalone BESS projects in Alberta with 536 MWh total capacity, and maintains international presence with projects in USA (including 221 MWdc Accalia Point), UK (106 MWh Fiskerton BESS), and Italy (62 MW solar projects).
Positive
- Sale of Georgetown and Sunnynook projects generated $62M non-dilutive cash
- Portfolio growth to >9GW under development (30x increase)
- Repaid $35M of debt improving balance sheet strength
- Returned $10M capital to shareholders (12% yield)
- Added 5 new BESS projects totaling 536 MWh capacity
- Secured agreements for sale of 1.4 GW Alberta-based projects
Negative
- Extension of closing dates for multiple project sales to April 30, 2025
The Company is delighted to provide Investors a comprehensive update on its international portfolio of utility scale projects.
Fiscal year 2024 was our first year realizing gains from our large maturing portfolio with the sale of the Alberta Georgetown and Sunnynook projects as previously announced on November 5, 2024 and December 14, 2023. These two projects added more than
In the three years since the RTO, we have surpassed many of our strategic milestones and remain fully committed to our mission of delivering utility scale solar and battery storage projects, with exceptional returns on capital invested.
Highlights:
- 30x portfolio growth to >9GW under development
- Sold 2 projects totalling more than 600 MW of solar and 400 MWh of potential BESS
of non-dilutive cash added to our balance sheet$62 million - Project Dolcy received AUC approval, continuing our impressive approval track record
- Repaid over
of debt, positioning our balance sheet for future growth$35m of capital returned to shareholders, equivalent to$10m 12% yield
Portfolio Update
The Company announced definitive agreements to sell five
- The Georgetown Project was sold to Metlen Energy & Metals and closed in December 2023 generating non-dilutive cash of
for the Company. See press release dated December 14, 2023.$39m - The Sunnynook Project was sold to Metlen Energy & Metals and closed in November 2024 generating non-dilutive cash of
for the Company. See press release dated November 05, 2024.$23m
The Company is pleased to provide an update on the progress on the remaining four
- Dolcy Solar (375 MWdc solar, 200 MWh BESS (Battery Energy Storage System)), located in
Alberta ; the project received Alberta Utilities Commission ("AUC") approval alongside a related substation and BESS, announced Sept 17, 2024. The transmission line to connect the facility to the grid is now in permitting. The previously announced definitive agreement for Metlen Energy & Metals to purchase all of the issued and outstanding shares of Dolcy Solar Inc. has been amended to extend the outside date of the agreement to April 30, 2025. - Eastervale Solar (345 MWdc solar, 400 MWh BESS), located in
Alberta ; the project has an application for Power Plant and BESS Approval and Substation Permit and License pending before the AUC, and in stage 3 of the AESO interconnection process which includes permitting the transmission line to connect the facility to the grid. The previously announced definitive agreement for Metlen Energy & Metals to purchase all of the issued and outstanding shares of Eastervale Solar Inc. has been amended to extend the outside date of the agreement to April 30, 2025. - Red Willow Solar (290 MWdc solar, 200 MWh BESS), located in
Alberta ; the project submitted an application for Power Plant and BESS Approval and a Substation Permit and License to the AUC in August 2024, and the project entered stage 3 of the AESO interconnection process in Q4 2024. The previously announced definitive agreement for Metlen Energy & Metals to purchase all of the issued and outstanding shares of Red Willow Solar Inc. has been amended to extend the outside date of the agreement to April 30, 2025. - Normandeau Solar, (325 MWdc solar, 200 MWh BESS), located in Lac Le Biche County,
Alberta, Canada . The project has secured site control and field work is due to start in Q2 2025. The project is in the AESO's Cluster 2 interconnection process.
New BESS Projects
The Company added 5 stand-alone BESS projects located in
- Horizon Line Energy Storage, is a 33.6 MWh BESS project utilizing a 2 hour battery system located in
Alberta, Canada . The project has secured control of the 8.8 acre site. The project has completed feasibility studies and is currently in the AESO's Cluster 2 interconnection process. - Lodgepole Energy Storage, is a 200 MWh BESS project utilizing a 2 hour battery system located in
Alberta, Canada . The project has secured control of the 3.6 acre site. The project has completed feasibility studies and is currently in the AESO's Cluster 2 interconnection process. - Heritage Trail Energy Storage, is a 90 MWh BESS project utilizing a 2 hour battery system located in
Alberta, Canada . The project has secured control of the 9 acre site. The project has completed feasibility studies and is currently in the AESO's Cluster 2 interconnection process. - Silverbury Energy Storage, is a 200 MWh BESS project utilizing a 2 hour battery system located in
Alberta, Canada . The project has secured control of the 4 acre site. The project has completed feasibility studies and is currently in the AESO's Cluster 2 interconnection process. - Swift Fox Energy Storage, is a 15.2 MWh BESS project utilizing a 2 hour battery system located in
Alberta, Canada . The project has secured control of the 7.3 acre site. The project has completed feasibility studies and is currently in the AESO's Cluster 2 interconnection process.
The Company continues to evaluate further opportunities for investment into
- Accalia Point (221 MWdc solar), located in
Cameron County, Texas ; the project has completed all development work and is approaching shovel-ready stage. - The Company has secured land rights and completed feasibility assessments for 9 additional mid and early-stagesolar PV and BESS projects. These projects total 5.2 GW in aggregate and are located in the markets of SPP, WECC, MISO and SERC.
- Fiskerton (106 MWh BESS), located in
Lincoln ; the project has secured a grid connection and site control, and has submitted a planning application.
- Gierre Solare (32 MW solar), located in
Lazio ; the project has secured land and grid access, completed feasibility studies, and submitted a planning application. - NM Solare (30 MW solar), located in
Lazio andUmbria ; the project has secured land and grid access, completed feasibility studies, and submitted a planning application.
About Westbridge Renewable Energy
For more information, please visit: www.westbridge.energy | Twitter | LinkedIn
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Forward-Looking Statements
Certain information set forth in this document contains forward-looking information and statements including, without limitation, expected permitting, approvals, anticipated satisfaction of the conditions to close the sale of shares of the
View original content to download multimedia:https://www.prnewswire.com/news-releases/westbridge-renewable-energy-provides-update-on-international-solar-and-battery-storage-portfolio-302368810.html
SOURCE Westbridge Renewable Energy Corp.