Allied Gold reported strong first-quarter 2026 operating performance while progressing its sale to Zijin Gold. Gold production rose to 96,016 ounces from 84,040, driven mainly by higher output at Bonikro and Agbaou. Revenue reached $394.1 million, supported by a sharp increase in realized gold prices, although unit costs also rose, with all-in sustaining costs averaging $2,264 per ounce.

The company generated net cash from operating activities of $57.3 million, with operating cash flow before working capital of $162.7 million, and ended the quarter with $424.2 million in cash and cash equivalents and an undrawn $50.0 million revolving facility. Reported net loss attributable to shareholders was $58.3 million (loss of $0.47 per share), largely driven by non-cash items, while Adjusted Net Earnings were $48.6 million ($0.39 per share) and Adjusted EBITDA was $173.3 million, highlighting strong underlying cash generation.

Operationally, Bonikro delivered standout results after prior years of heavy stripping, and Sadiola’s Phase 1 expansion ramp-up continued, with plans to exceed 200,000 ounces in 2026 and a staged expansion toward 9 Mt/y of throughput. Construction of the Kurmuk project in Ethiopia is tracking to first gold in mid‑2026, with targeted long-term AISC below $950 per ounce and an expanded processing capacity of up to 6.4 Mt/y.

Strategically, Allied is advancing a court-approved plan of arrangement under which Zijin Gold will acquire all shares for C$44 in cash, valuing the transaction at approximately C$5.5 billion. All required shareholder and court approvals have been obtained, and both parties are working with regulators toward closing by the outside date of May 29, 2026, subject to extensions under the agreement.

Positive

  • Zijin Gold cash acquisition at C$44 per share (~C$5.5B value) provides significant, immediate value realization for shareholders, with all shareholder and court approvals obtained and only regulatory conditions remaining under the arrangement agreement.
  • Strong underlying profitability and cash generation, with Q1 2026 Adjusted Net Earnings of $48.6 million, Adjusted EBITDA of $173.3 million, and operating cash flow before working capital of $162.7 million, supported by higher realized gold prices and improved mine performance.

Negative

  • Shift from profit to reported net loss, with net loss attributable to shareholders of $58.3 million in Q1 2026 versus net earnings of $15.1 million a year earlier, driven by higher taxes, share-based compensation, and revaluation losses on financial instruments.
  • Higher unit costs per ounce, as consolidated AISC rose to $2,264/oz from $1,811/oz and cash costs to $2,048/oz from $1,656/oz, reflecting royalty impacts from higher gold prices and mine‑specific cost factors.

Insights

Strong underlying cash generation and growth projects, with sale to Zijin setting valuation anchor.

Allied Gold delivered solid Q1 2026 fundamentals, with revenue of $394.1 million and Adjusted EBITDA of $173.3 million. Production increased to 96,016 ounces while maintaining mine plans, and operating cash flow before working capital rose to $162.7 million, showing strong leverage to higher gold prices despite lower sales volumes.

Reported net loss of $58.3 million reflects sizeable non‑cash items such as $37.8 million of losses on revaluation of financial instruments and $55.2 million of share‑based compensation, while Adjusted Net Earnings of $48.6 million show healthier core profitability. Unit costs moved higher (AISC $2,264/oz versus $1,811/oz a year earlier), influenced by higher royalties from much stronger prices and mine‑specific factors, but management notes costs were in line with plan.

Growth remains a key theme. Sadiola’s phased expansion toward over 9 Mt/y and the Kurmuk project, expected to reach average production of 290,000 ounces per year in its first four years at AISC below $950/oz, provide substantial medium‑term volume and margin potential. Concurrently, the court‑approved Zijin Gold transaction at C$44 per share, valuing the company around C$5.5 billion, effectively crystallizes value for shareholders, subject to completion of remaining regulatory approvals by the agreed outside date of May 29, 2026.

Revenue $394.1M For three months ended March 31, 2026
Adjusted EBITDA $173.3M For three months ended March 31, 2026
Adjusted Net Earnings $48.6M Q1 2026, $0.39 per share
Cash and cash equivalents $424.2M As of March 31, 2026
Operating cash flow before working capital $162.7M For three months ended March 31, 2026
All-in sustaining costs $2,264/oz Consolidated AISC per gold ounce sold, Q1 2026
Zijin offer price C$44 per share Cash consideration under plan of arrangement
Transaction value C$5.5B Approximate value of Zijin–Allied Gold arrangement
All-in sustaining costs financial
"Total cost of sales(4), cash costs(1) and AISC(1) in the first quarter were $2,235, $2,048, and $2,264, respectively, per ounce sold"
All-in sustaining costs (AISC) is a per-unit measure used mainly in the mining sector that captures the full ongoing cost to produce a unit of metal, including operating expenses, sustaining capital (maintenance of current operations), and a share of corporate overhead and site-level costs. Investors use AISC to judge whether production generates real profit and sustainable cash flow—think of it as the total monthly household cost to keep a home running, not just the utility bill.
Adjusted EBITDA financial
"EBITDA(1) and Adjusted EBITDA(1) for the for the three months ended March 31, 2026 were $77.7 million and $173.3 million respectively"
Adjusted EBITDA is a way companies measure how much money they make from their core operations, like running a business, by removing certain costs or income that aren’t part of regular business activities. It helps investors see how well a company is doing without distractions from unusual expenses or gains, making it easier to compare companies or track performance over time.
Total Recordable Injury Rate other
"The Company’s Total Recordable Injury Rate (“TRIR”) for the three months ended March 31, 2026 was 1.80"
Proven and Probable Mineral Reserves financial
"As of December 31, 2025, Proven and Probable Mineral Reserves were reported at 11.2 million ounces of gold"
Proven and probable mineral reserves are the amounts of a mine’s minerals that engineers estimate can be economically extracted with current technology and market conditions; “proven” denotes high-confidence quantities based on detailed testing, while “probable” denotes lower-confidence but still likely quantities. For investors, these categories act like a company’s usable inventory — they underpin production forecasts, revenue estimates and lending or valuation decisions, and signal how certain future cash flows from the resource are.
plan of arrangement regulatory
"in cash, pursuant to the terms of a court-approved plan of arrangement under the Business Corporations Act (Ontario)"
A plan of arrangement is a formal, court-approved agreement that reorganizes ownership or assets of a company—such as merging businesses, exchanging shares for cash or other securities, or splitting off parts of the company. Investors should care because it can change the value, number, and rights of their holdings and is often binding once approved by both shareholders and a court, offering more legal certainty than a simple vote. Think of it as a legally supervised recipe for how a company will be reshaped and who ends up with what.
Non-GAAP financial performance measures financial
"The Company has included certain non-GAAP financial performance measures, which the Company believes"
Non-GAAP financial performance measures are company-reported metrics that remove or add certain items from standard accounting results to highlight how management thinks the business is performing, for example excluding one-time costs or stock-based pay. Investors care because these adjusted figures can reveal trends or cash-generation that official rules might hide, but they can also be shaped to look more favorable, so comparing across companies and checking the reconciliations to standard financial statements is important.


 
 
UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
 
FORM 6-K
 
REPORT OF FOREIGN PRIVATE ISSUER
PURSUANT TO RULE 13a-16 OR 15d-16
UNDER THE SECURITIES EXCHANGE ACT OF 1934
 
For the month of May 2026
 
Commission File Number 001-42672
 
ALLIED GOLD CORPORATION
(Exact name of Registrant as specified in its charter)
 
N/A
(Translation of Registrant’s name into English)
 
Royal Bank Plaza, North Tower
200 Bay Street, Suite 2200
Toronto, Ontario
M5J 2J3
Tel: 1-833-363-4435
(Address of principal executive offices)
 
Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F:
 
Form 20-F ¨ Form 40-F x
 
 
 
 




SIGNATURES
 
Pursuant to the requirements of the Securities Exchange Act of 1934, as amended, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.
 
ALLIED GOLD CORPORATION
Date: May 14, 2026By:/s/ Sofia Tsakos
Sofia Tsakos
Chief Legal Officer and Corporate Secretary
 
 


 
 



EXHIBIT INDEX
 
Exhibit NumberDescription
99.1
Management’s Discussion and Analysis of Operations and Financial Condition for the Three Months Ended March 31, 2026
99.2
Condensed Consolidated Interim Financial Statements as at and for the Three Months Ended March 31, 2026
 
 
 



allied-goldxlogoxonxwhite2.jpg


MANAGEMENT’S DISCUSSION AND ANALYSIS OF OPERATIONS AND FINANCIAL CONDITION

FOR THE THREE MONTHS ENDED MARCH 31, 2026





















TABLE OF CONTENTS

1HIGHLIGHTS AND RELEVANT UPDATES
4
2CORE BUSINESS, STRATEGY AND OUTLOOK
11
3REVIEW OF FINANCIAL RESULTS
11
4REVIEW OF OPERATIONS AND MINE PERFORMANCE
15
5CONSTRUCTION, DEVELOPMENT AND OTHER CORPORATE INITIATIVES
22
6MINERAL RESERVE AND MINERAL RESOURCE ESTIMATES
25
7FINANCIAL CONDITION AND LIQUIDITY
29
8ECONOMIC TRENDS, BUSINESS RISKS AND UNCERTAINTIES
32
9CONTINGENCIES
34
10CRITICAL ACCOUNTING POLICIES AND ESTIMATES
34
11NON-GAAP FINANCIAL PERFORMANCE MEASURES
36
12CAUTIONARY STATEMENTS AND INTERNAL CONTROLS OVER FINANCIAL REPORTING
41




ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
MANAGEMENT’S DISCUSSION AND ANALYSIS OF OPERATIONS & FINANCIAL CONDITION

This Management’s Discussion and Analysis of Operations and Financial Condition (“MD&A”), authorized for issuance by the Board of Directors of the Company on May 14, 2026, should be read in conjunction with Allied Gold Corporation’s (“Allied” or the “Company”) condensed consolidated interim financial statements for the three months ended March 31, 2026 (“Condensed Consolidated Interim Financial Statements”) and the most recently issued annual consolidated financial statements for the year ended December 31, 2025 (“Consolidated Financial Statements”). All figures are in United States Dollars (“US Dollars”) unless otherwise specified. The Condensed Consolidated Interim Financial Statements have been prepared in accordance with IAS 34 “Interim Financial Reporting”, as issued by the International Accounting Standards Board (“IASB”).

The Company has included certain non-GAAP financial performance measures, which the Company believes, that together with measures determined in accordance with IFRS, provide investors with an improved ability to evaluate the underlying performance of the Company. Non-GAAP financial performance measures do not have any standardized meaning prescribed under IFRS, and therefore they may not be comparable to similar non-GAAP financial performance measures employed by other companies. The data is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. The non-GAAP financial performance measures included in this MD&A, include:

Cash costs per gold ounce sold (“cash costs”), for which the most directly comparable IFRS measure is cost of sales;
All-in sustaining costs (“AISC”) per gold ounce sold, for which the most directly comparable IFRS measure is cost of sales;
Gross profit excluding Depreciation, Depletion and Amortization (“DDA”);
Sustaining, and non-sustaining (expansionary and exploration) capital expenditures;
Adjusted Net Earnings (Loss), for which the most directly comparable IFRS measure is Net Earnings (Loss); and
Earnings before Interest, Taxes, DDA ("EBITDA") and Adjusted EBITDA, for which the most directly comparable IFRS measure is Net Earnings (Loss).

Reconciliations and descriptions associated with the above non-GAAP financial performance measures can be found in Section 11: Non-GAAP Financial Performance Measures in this MD&A. In addition, each non-GAAP financial performance measure in this MD&A has been annotated with a reference to endnote (1), which are provided on the final page of this MD&A.

Cautionary statements regarding forward-looking information, mineral reserves and mineral resources and statements on internal controls over financial reporting can be found in Section 12: Cautionary Statements and Internal Controls Over Financial Reporting in this MD&A.

Additional information relating to the Company, not incorporated as part of this MD&A, including the Annual Information Form of the Resulting Issuer (as defined herein), is available on SEDAR+ at www.sedarplus.com and EDGAR at www.sec.gov.


allied-goldxlogoxonxwhite2.jpg | 3

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
1.    HIGHLIGHTS AND RELEVANT UPDATES

Allied Gold Corporation (“Allied”, “Allied Gold” or the “Company”) is a Canadian-based emerging senior gold producer with a portfolio of three operating gold mines, a significant gold development project, and exploration properties throughout Africa, located in Mali, Côte d’Ivoire, and Ethiopia. Allied plans to continue building on this base through expansion and optimization initiatives at its existing operating assets, the development of new mines, and the advancement of its exploration projects.

Allied is positioned for substantial growth, with a path to increase sustainable production to approximately 800,000 ounces by 2029. This robust growth trajectory, expected to drive a compounded and disproportionate increase in cash flows and profitability, is underpinned by the Company's exploration success and proven track record of reserve replacement and resource growth, notably at both Sadiola and the Côte d'Ivoire mines. Additionally, the Company benefits from low-risk, phased expansion projects that can be implemented quickly, such as the Kurmuk Project in Ethiopia currently under construction, and the Sadiola expansion project.

Allied is committed to developing high-quality mining assets and delivering shareholder value and returns. This is achieved by investing in high-potential generational assets and implementing operational improvements to enhance productivity, reduce costs, and increase cash flows. The aggregate ownership of management and Board members in the Company demonstrates strong alignment with shareholders and a firm commitment to value creation.

The Company is listed on the Toronto Stock Exchange (“TSX”) and the New York Stock Exchange (“NYSE”) under the ticker symbol AAUC. In addition, its publicly traded convertible debentures are listed on the TSX, trading in U.S. dollars under the symbol AAUC.DB.U.

Operational, Earnings and Cash Flows Highlights:

For the three months ended March 31, 2026, unless otherwise noted

Quarterly consolidated production of 96,016 gold ounces, in line with plan and representing a 14% increase over prior year comparative production, as follows:

For three months ended March 31, 2026
For three months ended March 31, 2025
Sadiola44,104 45,232 
Bonikro29,011 19,671 
Agbaou22,901 19,137 
Consolidated96,016 84,040 

Sales of 99,878 gold ounces, slightly higher than production due to the timing of shipments of production and sale of end of year inventory.

Total cost of sales(4), cash costs(1) and AISC(1) in the first quarter were $2,235, $2,048, and $2,264, respectively, per ounce sold on a consolidated basis for the first quarter, and were in line with plan. The estimated gold price impact on first quarter AISC(1) as a result of higher royalties due to average gold prices of approximately $4,775 versus initial cost guidance at $4,250 amounts to approximately $80 per ounce.
allied-goldxlogoxonxwhite2.jpg | 4

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
Operating highlights by mine for the quarter as follows:

For three months ended
March 31, 2026
Production Gold OuncesSales Gold OuncesCost of Sales Per Gold Ounce Sold
Cash Cost(1) Per Gold Ounce Sold
AISC(1) Per Gold Ounce Sold
Sadiola Gold Mine44,104 45,995 $2,647 $2,538 $2,642 
Bonikro Gold Mine29,011 31,265 $1,691 $1,418 $1,628 
Agbaou Gold Mine22,901 22,618 $2,147 $1,922 $2,376 
Total96,016 99,878 $2,235 $2,048 $2,264 

For the first quarter, Bonikro was a standout performer. As previously guided, elevated stripping and waste removal costs during the past two years were planned investments to access higher-quality ore, and results now confirm that these actions are delivering value. The program has repositioned the asset on both production and cost metrics, outperforming in the quarter relative to plan.

A similar trajectory is being established at Agbaou, which delivered production and cost performance in line with plan. Optimization initiatives and operational enhancements are in progress, with Bonikro serving as the benchmark. Agbaou is expected to follow as these measures are implemented and scaled, targeting reduced costs in the next quarters.

At Sadiola, with quarterly production tracking in line with guidance and near-term increases in throughput and feed grade planned for the next quarters, costs for the balance of the year are expected to decline, consistent with the anticipated transition from mining and feeding predominantly oxide ores to a blend dominated by higher-grade fresh mineralization. As part of the quarterly production plan, various blending strategies were progressively deployed to support the implementation of new operational practices, automation improvements, and enhanced process controls aimed at consolidating CIL circuit performance with increased fresh ore feed. This required increased ore rehandling and related expenditures during the quarter, compared to previous periods, which is expected to materially decrease going forward. Furthermore, the output of the Stage 1 crushing plant is expected to increase in the next quarter, allowing Sadiola to minimize reliance on contract crushing and rehandling, thereby reducing operating costs. As noted above, with the progressive implementation of these initiatives and other operational improvements paired with increased feed grades and throughput, a corresponding reduction of unit costs is expected over subsequent quarters. Importantly, Sadiola remains on track to deliver in excess of 200,000 ounces of production.

As at March 31, 2026, the Company had cash and cash equivalents of $424.2 million. The Company has immediately available credit of $50.0 million (inclusive of a $10.0 million accordion) under its revolving credit facility, which remains undrawn.

Net cash generated from operating activities for the quarter was $57.3 million. Operating cash flows before income tax paid and movements in working capital were a strong inflow of $162.7 million. Current period cash was positively impacted by strong gold sales and record high realized gold prices. Working capital impact for the first quarter is related to normal course movements in inventory (including stockpiles), timing of accounts payable, and payment of year-end accruals. As previously disclosed, certain positive impacts to working‑capital movements in the fourth quarter of 2025 were released in the first quarter of 2026, reflecting the settlement of various payables, accruals and other balance sheet items.

Net Loss Attributable to the Shareholders to the Company (“Attributable Net Loss”) for the three months ended March 31, 2026 was $58.3 million or $(0.47) per share. Management believes that certain adjustments for items that may not be reflective of current and on-going operations are appropriate, and better reflect the underlying economic results. Adjustments include unrealized gains and losses on financial instruments and foreign exchange, along with share-based compensation largely impacted by share price movements and certain tax adjustments. After these adjustments, the Company reports Adjusted Net Earnings(1) of $48.6 million or $0.39 per share. Details of the adjustments can be found in the Summary of Financial Results discussion below.

EBITDA(1) and Adjusted EBITDA(1) for the for the three months ended March 31, 2026 were $77.7 million and $173.3 million respectively. EBITDA(1) was impacted by unrealized mark-to-market losses on the Company's convertible debentures. The debentures will either be settled in cash at their face value at maturity, or converted at the pre-determined conversion ratio. The unrealized mark-to-market losses, which reflect fluctuations in the trading value of the publicly listed debentures, did not and will not result in cash outflows upon settlement above face value. Further, EBITDA(1) was impacted by remeasurements of contingent consideration. For consistency of showing underlying economic results, these losses are removed from the
allied-goldxlogoxonxwhite2.jpg | 5

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
calculation of Adjusted EBITDA(1). The Company's strong Adjusted EBITDA(1) demonstrates its strong cash-flow generating ability and continued operational efficiency.

At Kurmuk, the project continues to track well against plan, both in terms of physical completion and spend, while achieving key milestones and progress during the first quarter of 2026.

The project execution is progressing well, with the key focus during the quarter being on the logistics for the remaining equipment and materials to the site, the continued advancement of steel and mechanical erection activities, as well as the ramp-up of the electrical, control and instrumentation (“EC&I”) contractor, including the installation of medium-voltage cable, electrical-racking and lighting placement. Mining activities continue to advance toward building at least three months' worth of ore stockpiles to support the start of operations in mid-2026. The Ethiopian Electrical Power Company is advancing the power line construction, which is expected to be completed before commissioning. Pre-commissioning activities are planned to begin during the second quarter, with the first gold expected in mid-2026.
Along with the advancement of the project and as previously disclosed, the Company completed a review of the capacity of the processing plant in consideration of the ore inventory and the exploration progress at Dish Mountain, Ashashire and Tsenge. Allied made a strategic decision to maximize the operational flexibility for Kurmuk since the start of operations, and is now targeting an average processing capacity of up to 6.4 Mt/y. This increased flexibility has been incorporated into the project execution plan, with subsequent optimizations to the leaching circuit expected to be deployed in the future years to increase fresh ore recoveries. The enhancements and optimizations are expected to make Kurmuk a stronger, de-risked operation upon commencement of production, providing upside and operational flexibility, aligning with the Company’s long-term strategy of maximizing value at each of the Company's assets.

Over the last several years, the Company has been advancing a strategy of optimization and expansion at the Sadiola Gold Mine. Initial efforts focused on stabilizing the operation, primarily related to the existing processing capacity of mostly oxide ores, followed by a phased expansion to allow the processing of fresh ore and increased throughput. The objective is to increase production and cash flows in both the short and long term.

On December 21, 2025, the Company announced that it began processing ore through the new fresh-ore comminution circuit installed as part of the Phase 1 expansion, marking a significant milestone in the transformational growth strategy for this long-life asset. The Phase 1 expansion is the first step in the Company’s strategy to increase production, reduce costs, and materially increase cash flows through a progressive expansion approach. The Phase 1 mill ramped up in the first quarter of 2026, alongside the completion of ancillary systems and power-supply upgrades. Further optimizations to the processing circuit, including instrumentation and automation upgrades, are advancing this year. Together, these initiatives are expected to improve operating performance, enhance overall processing rates, and reduce operating costs.

The Company has been advancing studies to define the best strategy for the next phase of the mine's expansion. The initial conclusion of these studies was that adding a pre-leach thickener to the circuit allows the plant to process over 90% of the fresh ore in the feed, increasing operational flexibility and potentially increasing production. Given that a pre-leach thickener is required regardless of the selected expansion scenario, the Company decided to begin engineering and design work in late 2025 in order to improve the operational flexibility and the capacity to treat fresh ore. Project execution activities began in the first quarter, with the aim of fully commissioning this addition to the circuit in the first quarter of 2027.

Furthermore, Allied concluded in the fourth quarter of 2025 that the best execution strategy for expansion at Sadiola is to progressively optimize, develop, and expand the current processing plant and ancillary infrastructure, rather than to build a new processing plant to treat fresh ore. This organic growth strategy allows for more efficient deployment of capital and management of execution risks, and it enables the same ultimate throughput of over 9 Mt/y of ore processed as defined in the previous studies, but with interim, organic steps at 7 Mt/y and 8 Mt/y. This strategy also enables the recovery improvement project and the energy program to be implemented progressively as throughput capacity expands, thereby improving capital efficiency and returns. For 2026, the Company will advance the engineering to a feasibility study level, as well as detailed engineering of the early works required for the 7 Mt/y step. In addition to this, Allied will continue advancing studies to increase recoveries for fresh ore, including test work and engineering for the Albion process, as well as new tailings dam construction, solar farm earthworks and mobilization, and further upgrades to the plant instrumentation and control systems.

As previously disclosed, along with the advancement of the growth strategy for Sadiola, the Company is advancing its energy program for the asset and is undertaking a staged and scalable approach, initially having installed additional state-of-the-art diesel generators and control systems, followed by the implementation of a hybrid power solution, with the deployment of
allied-goldxlogoxonxwhite2.jpg | 6

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
more efficient medium-speed thermal units, and a photovoltaic plant with battery energy storage systems (“BESS”) sufficient to meet the power requirements of the Phase 1 expansion at reduced costs. The systems will then be scaled up to satisfy the energy needs of the next phase expansion, providing Sadiola with a flexible power solution capable of meeting its ultimate power needs, while being self-reliant, efficient and cost-effective. Please refer to the Sadiola Energy Program section for further details.

In relation to the exploration program at Côte d’Ivoire, first quarter activities reflect a continuation of the programs initiated in prior periods, with the objective of translating drilling and technical work into tangible mine life extensions and improvements to mine plans. The results to date provide a solid foundation, and the expectation is to provide an update for CDI by mid-year and for Sadiola and Kurmuk in the second half of 2026.

At Agbaou, ongoing infill drilling, both within and below a $2,000 pit shell, has demonstrated the continuity of the mineralized lenses with infill drilling focused on converting Inferred Mineral Resources to Indicated Mineral Resources as a necessary step to defining new reserves . Current results support the case for extending mine life beyond what is currently defined, with ongoing work aimed to complete de-risking and validating this potential. In parallel, the underground opportunity is gaining traction. Early-stage evaluation and drilling are focused on defining the scale and down-plunge continuity of mineralization, with the objective of establishing a complementary production profile to the open pit.

At Bonikro, exploration efforts remain active, with increased emphasis on the Oumé and Hiré districts. These areas represents a strategic priority, with ongoing work aimed at identifying additional targets to support growing a pipeline of future development opportunities to support long-term growth.

As of December 31, 2025, Proven and Probable Mineral Reserves were reported at 11.2 million ounces of gold, contained within 247.1 million tonnes at a grade of 1.41 g/t. This represents a net year-over-year increase, reflecting the addition of new Mineral Reserves, replacing depletion from 2025 production, and updates to economic and design assumptions. Total Measured and Indicated Mineral Resources stood at 15.3 million ounces of gold, contained within 336.7 million tonnes at a grade of 1.41 g/t. The modest decrease from 2024 is primarily attributable to the recategorization of some Indicated Mineral Resources to Inferred Mineral Resources. Inferred Mineral Resources, at year-end totalled 2.1 million ounces contained within 54.2 million tonnes at a grade of 1.20 g/t.


Financing and Corporate Development Highlights:

Transaction with Zijin Gold

The Company is advancing the transaction with Zijin Gold International Company Limited ("Zijin Gold") after entering into a definitive agreement (the "Arrangement Agreement" or the "Agreement") as previously disclosed. Zijin Gold, a public company listed on the Hong Kong Stock Exchange, agreed to acquire all of the issued and outstanding shares of Allied Gold at a price of C$44 per share (the “Offer Price”) in cash, pursuant to the terms of a court-approved plan of arrangement under the Business Corporations Act (Ontario) (the "Arrangement"). The Company's Board of Directors determined that the Arrangement immediately achieved fair value realization while mitigating business risks, particularly in highly volatile markets, and Zijin Gold had demonstrated a strong track record of long-term asset stewardship and consequently, there was a suspension of the other strategic opportunities. The transaction value of the Arrangement is approximately C$5.5 billion, realizing a significant, certain and immediate value for Allied Gold shareholders. Further details on the benefits of the Arrangement can be found in the Company's previous public disclosure filed on SEDAR+.

As previously disclosed, all requisite shareholder and court approvals have been obtained.

The Company and Zijin Gold are in continuous dialogue, planning for an orderly transition on completion of the Arrangement. Both companies continue to engage diligently and cooperatively with regulatory bodies pursuant to previously filed applications for regulatory approvals necessary to complete the Arrangement with the objective of closing in a timely manner within the timeframe set out in the Arrangement Agreement. The Arrangement Agreement provides for an outside date for closing of May 29, 2026, subject to extension by the parties if by that date any regulatory approvals or other conditions precedent are still in progress. Both companies continue to demonstrate a strong commitment to complete the transaction in accordance with the Arrangement Agreement.


allied-goldxlogoxonxwhite2.jpg | 7

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
Sustainability, Health and Safety Highlights:

Sustainability:

The Company's sustainability framework includes principles and expectations which are to be implemented to build a common understanding and approach to sustainability performance. The frameworks has the objective of enhancing the integration of sustainability within the Company’s strategy, operational processes, and culture.

During the first quarter of 2026, the Company continued supporting the development of its "We think safety, we act safely” culture, and finalized the development of the 2026 annual plan.

Health and Safety:

All rates are calculated on a 1,000,000 exposure-hour basis.

The Company’s Total Recordable Injury Rate (“TRIR”) for the three months ended March 31, 2026 was 1.80, compared to 1.21 for the 12 months ended December 31, 2025.

In terms of Lost Time Injuries (“LTI”), the Company reported three LTI for the three months ended March 31, 2026, which results in a Company Lost Time Injury rate (“LTIR”) for the three months ended March 31, 2026 of 0.45, compared to a LTIR of 0.29 for the 12 months ended December 31, 2025.

Environment and Social:

The Company did not report any significant Environmental Incidents for the three months ended March 31, 2026.

The Company did not report any significant Social Incidents for the three months ended March 31, 2026.

Summary of Operational Results

For three months ended March 31,
2026
2025
Gold ounces
Production96,016 84,040 
Sales(8)
99,878 131,520 
Per Gold Ounce Sold
Total Cost of Sales(4)
$2,235 $1,838 
Cash Costs(1)
$2,048 $1,656 
AISC(1)
$2,264 $1,811 
Average revenue per ounce for at-market sales*4,775 2,839 
Average market price per ounce$4,873 $2,860 
*Average revenue per ounce sold differs from average revenue per ounce for at-market sales predominantly due to hedge settlements and sales made under streams. For the first quarter, the impact of hedge settlements was $646/ounce (first quarter of 2025 - $18/ounce) and the impact of stream, in-kind dividends and IFRS 15 adjustments was $193/per ounce (first quarter of 2025 - $15/ounce).

Gold production of 96,016 ounces during the three months ended March 31, 2026, compared to 84,040 ounces during the comparative prior period. The increase was predominantly driven by production growth at Bonikro and Agbaou in the first quarter of 2026, resulting from the benefits of stripping work executed in prior quarters, as anticipated.

Total cost of sales(4) of $2,235 for the three months ended March 31, 2026 compared to $1,838 during the comparative prior period. Cash costs(1) on a per gold ounce sold basis of $2,048 for the three months ended March 31, 2026, compared to $1,656 during the comparative prior period. AISC(1) for the current quarter of $2,264 compared to the comparative period AISC(1) of $1,811 per gold ounce. For the quarter, unit costs per ounce sold on a consolidated basis for the first quarter, and were in line with plan. The estimated gold price impact
allied-goldxlogoxonxwhite2.jpg | 8

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
on first quarter AISC(1) as a result of higher royalties due to average gold prices of approximately $4,775 versus initial cost guidance at $4,250 amounts to approximately $80 per ounce.

Gold sales(8) of 99,878 ounces for three months ended March 31, 2026 compared to 131,520 ounces sold in the comparative period quarter. The variance in sales ounces is associated with the comparative prior year period, which was positively impacted by Korali-Sud gold production for the fourth quarter of 2024 being sold early in 2025, as previously disclosed.

Summary of Financial Results:

(In thousands of US Dollars, except for shares and per share amounts) (Unaudited)
For three months ended March 31,
2026
2025
Revenue$394,110 $346,407 
Cost of sales, excluding depreciation, depletion and amortization ("DDA")(203,259)(207,792)
Gross profit excluding DDA(1)
$190,851 $138,615 
DDA(19,923)(18,957)
Gross profit
$170,928 $119,658 
General and administrative expenses$(69,158)$(18,852)
Exploration and evaluation expenses(3,618)(3,527)
Loss on revaluation of financial instruments
(37,839)(14,116)
Other (losses) income
(2,527)1,128 
Net earnings before finance costs and income tax
$57,786 $84,291 
Finance income (costs)(5,798)(5,310)
Net earnings before income tax
51,988 78,981 
Current income tax expense
$(64,835)$(27,700)
Deferred income tax expense
(31,617)(11,344)
Net (loss) earnings for the period
$(44,464)$39,937 
(Loss) earnings attributable to:
Shareholders of the Company$(58,326)$15,124 
Non-controlling interests13,862 24,813 
Net (loss) earnings for the period
$(44,464)$39,937 
Net (loss) earnings per share attributable to shareholders of the Company
Basic$(0.47)$0.14 
Diluted$(0.47)$0.13 

Attributable Net Loss for the three months ended March 31, 2026 was $58.3 million, compared to an Attributable Net Earnings $15.1 million in the comparative prior year period. After the adjustments noted below, the Company reports an Adjusted Net Earnings(1) of $48.6 million for the current period, compared to Adjusted Net Earnings(1) of $45.1 million in the comparative prior year period.

EBITDA(1) and Adjusted EBITDA(1) for the for the three months ended March 31, 2026 were $77.7 million and $173.3 million respectively, compared to $103.2 million and $133.8 million in the comparative prior year period. EBITDA(1) was impacted by unrealized mark-to-market losses on the Company's convertible debentures. The debentures will either be settled in cash at their face value at maturity, or converted at the pre-determined conversion ratio. The unrealized mark-to-market losses, which reflect fluctuations in the trading value of the publicly listed debentures, did not and will not result in cash outflows upon settlement above face value. Further, EBITDA(1) was impacted by remeasurements of contingent consideration. For consistency of showing underlying economic results, these losses are removed from the calculation of Adjusted EBITDA(1). The Company's strong Adjusted EBITDA(1) demonstrates its strong cash-flow generating ability and continued operational efficiency.

allied-goldxlogoxonxwhite2.jpg | 9

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
Further details on Adjusted Net Earnings(1) can be found in the table that follows, while details on EBITDA(1) and Adjusted EBITDA(1) can be found in Section 11: Non-GAAP Financial Performance Measures.

(In thousands of US Dollars, except per share amounts)
For three months ended March 31,
2026
2025
Net (Loss) Earnings attributable to Shareholders of the Company
$(58,326)$15,124 
Net (Loss) Earnings attributable to Shareholders of the Company per Share
$(0.47)$0.14 
Loss on revaluation of financial instruments
37,839 14,116 
Depreciation of Korali share-based payment for permit 3,880 
Foreign exchange3,427 3,043 
Share-based compensation55,200 4,107 
Other2,620 10,949 
Tax adjustments7,839 (6,146)
Total increase to Attributable Net Earnings(2)
$106,925 $29,949 
Total increase to Attributable Net Earnings(2) per share
$0.85 $0.27 
Adjusted Net Earnings(1)
$48,599 $45,073 
Adjusted Net Earnings(1) per Share
$0.39 $0.41 

The current period was impacted by revaluations of financial instruments and the mark-to-market of the Company's publicly traded debt, foreign exchange, shared-based compensation, along with tax adjustments. Earnings for the prior year were impacted by similar matters.

The Company did not pay any dividends or have distributions to shareholders during the three months ended March 31, 2026 or 2025.

(In thousands of US Dollars)
For three months ended March 31,
2026
2025
Operating cash flows before income tax paid and working capital(6)
$162,714 $100,788 
Income tax paid$(10,468)$(7,904)
Operating cash flows before movements in working capital(6)
$152,246 $92,884 
Working capital movement(6)
(94,953)28,246 
Net cash generated from Operating activities
$57,293 $121,130 
Net cash used in Investing activities
(109,330)(103,870)
Net cash used in Financing activities
(256)(6,677)
Net (decrease) increase in cash and cash equivalents
$(52,293)$10,583 

Net cash generated from operating activities for the three months ended March 31, 2026 was $57.3 million. This compares to $121.1 million in the prior year comparative quarter. Current period cash was positively impacted by strong gold sales and record high realized gold prices. Prior year cash flows were positively impacted by the sale of Korali inventory in the first quarter of 2025 from 2024 which significantly increased sales quantities, while positively impacting working capital due to the sale. Working capital impact for the first quarter is related to normal course movements in inventory (including stockpiles), timing of accounts payable, and payment of year-end accruals. As previously disclosed, certain positive impacts to working‑capital movements in the fourth quarter of 2025 were released in the first quarter of 2026, reflecting the settlement of various payables, accruals and other balance sheet items.

Operating cash flows before income tax paid and movements in working capital for the three months ended March 31, 2026 increased significantly, at an inflow of $162.7 million compared with the prior year comparative quarter inflow of $100.8 million. This was due to higher realized gold prices. The impact of higher prices was partially offset by lower ounces sold in the current period in association with the sale of Korali inventory in the first quarter of 2025.

As at March 31, 2026, the Company had cash and cash equivalents of $424.2 million, compared with $479.8 million as at December 31, 2025.
allied-goldxlogoxonxwhite2.jpg | 10

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026

Summary of Capital Expenditures

For three months ended March 31,
20262025202620252026202520262025
(In thousands of US Dollars)
Sustaining(1)
Expansionary(1)
Exploration(1)
Total
Sadiola$714 $1,109 $7,895 $3,051 $185 $113 $8,794 $4,273 
Bonikro902 14,928  48 2,453 1,975 3,355 16,951 
Agbaou8,445 10,831  31 1,380 688 9,825 11,550 
Kurmuk and Ethiopia — 82,275 56,161 1,168 — 83,443 56,161 
Capitalized borrowings and Other 74 13,060 8,166  — 13,060 8,240 
Total$10,061 $26,942 $103,230 $67,457 $5,186 $2,776 $118,477 $97,175 
All expenditures associated with Ethiopia and Kurmuk for the period are classified as Expansionary in nature, including project costs and office costs but excluding capitalized borrowing costs under IFRS and VAT recoverable. Exploration activities in the current year have been disclosed separately. All IFRS capitalized borrowing costs are disclosed under Capitalized borrowings and Other.

2.    CORE BUSINESS, STRATEGY AND OUTLOOK

Allied Gold is a Canadian-based emerging senior gold producer with a portfolio of three operating gold mines, a significant gold development project, and exploration properties throughout Africa, located in Mali, Côte d’Ivoire, and Ethiopia. Allied plans to continue building on this base through expansion and optimization initiatives at its existing operating assets, the development of new mines, and the advancement of its exploration projects.

Allied’s principal mining properties comprise the Sadiola gold mine in the Kayes Region of West Mali (80% ownership), which includes the Korali-Sud open pit gold mine (65% ownership), the Bonikro (89.89% ownership) and Agbaou (85% ownership) gold mines in Côte d’Ivoire, and the Kurmuk gold development project in Ethiopia (100% ownership(7)).

Allied is positioned for substantial growth, with a path to increase sustainable production to approximately 800,000 ounces by 2029. This robust growth trajectory, expected to drive a compounded and disproportionate increase in cash flows and profitability, is underpinned by the Company's exploration success and proven track record of reserve replacement and resource growth, notably at both Sadiola and the Côte d'Ivoire mines. Additionally, the Company benefits from low-risk, phased expansion projects that can be implemented quickly, such as the Kurmuk Project in Ethiopia currently under construction, and the Sadiola expansion project.

The Company is listed on the Toronto Stock Exchange (“TSX”) and the New York Stock Exchange (“NYSE”) under the ticker symbol AAUC. In addition, its publicly traded convertible debentures are listed on the TSX, trading in U.S. dollars under the symbol AAUC.DB.U.


allied-goldxlogoxonxwhite2.jpg | 11

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
3.    REVIEW OF FINANCIAL RESULTS

For the three months ended March 31, 2026

Revenue

Revenue of $394.1 million for the three months ended March 31, 2026, compared to $346.4 million in the comparative prior year period. The significant change in revenue was driven by an increase in average revenue per ounce of 40% as a result of higher gold prices versus the comparative period, partially offset by a decrease in sales quantities of 31,642 ounces, or 24%. The variance in sales ounces is associated with the comparative prior year period, which was positively impacted by Korali-Sud gold production for the fourth quarter of 2024 being sold early in 2025, as previously disclosed.

The average realized gold price during the period, net of the impact of sales under the streaming arrangements and the settlement of gold collars, was $1,122/ounce higher, at $3,936/ounce compared to $2,814/ounce in the comparative prior period quarter.

Cost of sales, excluding DDA

Cost of sales, excluding DDA, of $203.3 million for the three months ended March 31, 2026, compared to $207.8 million in 2025. The decrease in Cost of Sales, excluding DDA was predominantly impacted by the anticipated and guided costs of production for the current year in relation to those from the prior year. Further, and importantly, current period costs were impacted by the increase in royalties associated with significantly higher gold prices. The prior year comparative quarter was also further impacted by the aforementioned delay in sale of Korali-Sud gold sold during the first quarter of 2025, which impacted the comparative cost of sales.

DDA

Total DDA(4) of $19.9 million for the three months ended March 31, 2026, was higher than the $19.0 million in the comparative prior year quarter. The increase is mostly attributable to the increase in deferred stripping capitalized during 2025 and their amortization in the first quarter of 2026, particularly at Bonikro and Agbaou. This has been partially offset by the change in ounces sold. Further, in connection with the definitive protocol agreement signed with the Government of Mali during the third quarter of 2024, the Company’s Korali-Sud mine and related assets were transferred to a new entity, Korali S.A., incorporated on January 8, 2025, and 35% of the ownership interests in the new entity were issued to the Government of Mali. The issuance of subsidiary shares is considered a share-based payment in exchange for the issuance of a definitive exploitation permit for large-scale mining and processing of ore mined at Korali at the Sadiola Plant, which is valued with reference to the fair value of the subsidiary shares granted. $6.0 million of the cost capitalized to the Korali mine was depreciated during the quarter ended March 31, 2025. The Company’s assets subject to DDA include a substantial amount of mining interests and PP&E, that are based on purchase price accounting and fair values from the mine acquisitions.

General and administrative expenses

Administrative expenses include costs related to the overall management of the business that are not part of direct mine operating costs.

For the three months ended March 31, 2026, administrative expenses excluding share-based expenses were $14.0 million, compared to $14.7 million in the comparative prior year quarter.

Share-based expense is impacted by volatility and share price performance, resulting in a mark-to-market and amortization of outstanding units, and are paid or issued based on future vesting and performance. As the Company’s stock gained over 36% in the first quarter alone, stock-based compensation for the first quarter increased accordingly, along with the normal course issuance of units during the year.

As costs further decrease, and production increases, the per ounce cost of general and administrative expenses will decrease more than
commensurately. The Company is establishing an administrative construct that supports growth from 375,000 ounces, to the near-term production plan of 600,000 ounces. Ultimately this will support a production platform of over one million ounces, targeting five to seven mines, without the requirement for additional significant overhead support, and costs decreasing meaningfully on a per ounce basis. Further, certain expenditures were incurred in different comparative prior year periods, resulting in expenditure volatility between quarters.

allied-goldxlogoxonxwhite2.jpg | 12

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
Exploration expenses

Exploration expenses relate to exploration campaigns carried out at each site, described in detail within this MD&A.

Loss on revaluation of financial instruments

The result for the three months ended March 31, 2026 relates to the following items, with the most significant components of the current period result being related to the convertible debt valuation and deferred consideration.

The revaluation of the convertible debenture and its associated unrealized mark-to-market impact, due to an increase in the observable market price of the debenture. The debentures will be either settled in cash at their face value or converted based on the predetermined conversion ratio. The unrealized mark-to-market losses, which reflect fluctuations in the trading value of the publicly listed debentures, did not and will not result in cash outflows upon settlement above face value.
The revaluation of the contingent consideration to Agbaou, predominantly associated with higher consensus market prices.
Then, to a smaller extent and not individually significant:
A portion of sales from the Bonikro Mine are subject to an offtake sales agreement. Pricing for this gold is based on a Quotational Period of six days and a loss is recorded in earnings as incurred, and
the revaluation of contingent consideration on the expected Net Smelter Return “NSR” royalty obligation that was part of the acquisition of the Agbaou Mine. The contingent consideration is revalued on each balance sheet date to include the latest life of mine production estimates and expected future gold prices.

Other (loss) income

Other loss for the three months ended March 31, 2026 was $2.5 million, compared to a gain of $1.1 million in the comparative prior year quarter.

Other losses for the current period and prior period are not significant and have no individually significant components.

Finance costs

Finance costs of $5.8 million for the three months ended March 31, 2026 were comparable to the finance costs of $5.3 million in the prior year comparative quarter. The costs comprise three major categories, as follows:

Interest on Borrowings. Interest expense was $2.3 million, compared to $2.3 million in the comparative prior year quarter. Interest is related to the convertible debentures issued on September 7, 2023. Details on the Company’s borrowings can be found in the Financial Condition and Liquidity section of this MD&A.
During the period, the Company capitalized interest of $13.1 million, associated with the construction of the Kurmuk project compared to $7.0 million in the comparative prior period.
Other Non-Cash Finance Cost was $13.1 million compared to $6.9 million in the comparative prior quarter. These non-cash charges relate to accretion of asset retirement obligation liabilities, accretion of deferred consideration, and the calculated interest charge on the stream agreements (refer to the Condensed Consolidated Interim Financial Statements for further details).
Current period costs included a loss of $3.4 million in foreign currency ($3.0 million loss in the prior year comparative period).

Income tax expense

Income tax expense was $96.5 million for the three months ended March 31, 2026 and reflects a current income tax expense of $64.8 million and a deferred income tax expense of $31.6 million. This compares to a total tax expense in the prior year comparative quarter of $39.0 million, with current income tax expense of $27.7 million and a deferred income tax expense of $11.3 million. The increase in income tax is related to the increase in revenue and the non-recognition of deferred tax assets.

The effective tax rate is subject to a number of factors including the source of income between different countries, different tax rates in the various jurisdictions, the recognition of deferred tax assets when applicable, foreign currency exchange movements, changes in tax laws and the impact of specific transactions and assessments. The high effective tax rate is the result of the tax impact of costs incurred in non-taxable jurisdictions which include general and administrative expenses, borrowing costs, hedging market-to-market and other non-operational expenses, while the underlying operations recorded income before tax. The effective tax rate on operations was approximately 42%, which is more in line with statutory rates.
allied-goldxlogoxonxwhite2.jpg | 13

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026

The Company operates in the following tax jurisdictions: Côte d’Ivoire, where the statutory tax rate is 25%; Mali, where the statutory tax rate is 30%; Ethiopia where the statutory tax rate is 25%; and Canada, where the combined federal and provincial statutory tax rate is 26.5%. The Company does not anticipate the statutory tax rates to change in the jurisdictions it operates in for the foreseeable future; therefore, there should be no impact on the calculation of the current or deferred tax expense in the period.

New taxation developments - OECD Pillar Two Model Rules

In June 2024, the Government of Canada enacted the Global Minimum Tax Act (“GMTA”) that was developed within the framework of the Organization for Economic Co-operation and Development (OECD)’s Pillar Two Model rules. The GMTA includes the introduction of a 15% global minimum tax that applies to large multinational enterprise groups with global consolidated revenues over €750 million for two out of the past four years. However, this legislation does not currently apply to the Company as 2025 was the first year that revenue exceeded €750 million. The effective tax rates in the jurisdictions in which the Company operate are above 15% and the Company does not expect a potential exposure to the global minimum tax when the rules apply to us in the future.


QUARTERLY FINANCIAL INFORMATION

(In thousands of US Dollars)Q1 2026Q4 2025Q3 2025Q2 2025Q1 2025Q4 2024Q3 2024Q2 2024
Revenue$394,110 $427,820 $305,618 $251,979 $346,407 $170,846 $188,855 $195,614 
(Loss) earnings attributable to shareholders
(58,326)(23,644)(17,917)(25,410)15,124 (10,280)(107,965)8,298 
(Loss) earnings per share attributable to shareholders of the Company
Basic(0.47)(0.19)(0.15)(0.22)0.14 (0.10)(1.28)0.10 
Diluted (0.47)(0.19)(0.15)(0.22)0.13 (0.10)(1.28)0.09 
allied-goldxlogoxonxwhite2.jpg | 14

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
4.    REVIEW OF OPERATIONS AND MINE PERFORMANCE

Sadiola (80% interest), Mali

Sadiola comprises the Sadiola (80% interest) open pit gold mine, located in the Kayes region of Mali, as well as the Korali-Sud open pit gold mine (65% interest), 15 kilometres south of the processing plant at Sadiola. The remaining ownership in Sadiola is retained by the Government of Mali.

Sadiola Key Performance Information
(100% Basis)
For three months ended March 31,
2026
2025
Operating
Ore mined (M tonnes)1.94 1.98 
Waste mined (M tonnes)7.28 6.06 
Ore processed (M tonnes)1.28 1.17 
Gold
Production (Ounces)44,104 45,232 
Sales(8) (Ounces)
45,995 92,033 
Feed grade (g/t)1.36 1.36 
Recovery rate (%)81.4 %89.3 %
Total cost of sales per ounce sold(4)
$2,647 $1,941 
Cash costs per ounce sold(1)
$2,538 $1,755 
AISC per ounce sold(1)
$2,642 $1,799 
Financial (In thousands of US Dollars)
Revenue$189,700 $234,445 
Cost of sales (excluding DDA)(116,954)(152,416)
Gross profit excluding DDA(1)
$72,746 $82,029 
DDA(4,797)(10,375)
Gross Profit$67,949 $71,654 
Capital Expenditures (In thousands of US Dollars)
Sustaining(1)
$714 $1,109 
Expansionary(1)
7,895 3,051 
Exploration(1)
185 113 

For the three months ended March 31, 2026, Sadiola produced 44,104 ounces of gold, compared to the 45,232 ounces produced in the comparative prior year quarter and aligned with the production plan. Production is expected to increase sequentially in the next quarter as result of increased grades and throughput. Sadiola remains on track to deliver in excess of 200,000 ounces of production.

Production in the first quarter of 2026 reflects the feed of transitional ore and oxide material from the Sadiola main pit and Sekekoto, supplemented by other oxide opportunities identified in late 2025. In parallel, the Phase 1 plant ramp-up progressed throughout the quarter, supported by the installation of new mill liners, instrumentation upgrades, improved process control, and other optimization initiatives.

With the continued ramp-up of mining capacity, ongoing processing optimization initiatives, and the flexibility to treat increased volumes of fresh ore, the operation is entering a phase of greater consistency and efficiency. These improvements are expected to translate into stronger throughput, improved feed grades and enhanced margin performance through the remainder of 2026.

Total cost of sales(4) and AISC(1) for the quarter of $2,647 and $2,642, respectively, per ounce sold on a consolidated basis for the first quarter, and were in line with plan. The estimated gold price impact on first quarter AISC(1) as a result of higher royalties due to average gold prices of approximately $4,775 versus initial cost guidance at $4,250 amounts to approximately $80 per ounce. For the quarter, with
allied-goldxlogoxonxwhite2.jpg | 15

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
quarterly production tracking in line with guidance and near-term increases in throughput and feed grade planned for the next quarters, costs for the balance of the year are expected to decline, consistent with the anticipated transition from mining and feeding predominantly oxide ores to a blend dominated by higher-grade fresh mineralization. As part of the quarterly production plan, various blending strategies were progressively deployed to support the implementation of new operational practices, automation improvements, and enhanced process controls aimed at consolidating CIL circuit performance with increased fresh ore feed. This required increased ore rehandling and related expenditures during the quarter, compared to previous periods, which is expected to materially decrease going forward. Furthermore, the output of the Stage 1 crushing plant is expected to increase in the next quarter, allowing Sadiola to minimize reliance on contract crushing and rehandling, thereby reducing operating costs. As noted above, with the progressive implementation of these initiatives and other operational improvements paired with increased feed grades and throughput, a corresponding reduction of unit costs is expected over subsequent quarters.

Gold sales for the current quarter were slightly higher than production, with small differences attributable to the timing of shipments. Sales in the prior year comparative quarter significantly exceeded production due to the sale of Korali inventory produced in the fourth quarter of 2024.

As disclosed in the Company's press release dated April 28, 2026, in light of recent events in Mali involving the conflicts between government and insurgent groups, the Company continues to monitor the situation and take precautions to ensure the safety and wellbeing of persons employed by the Company in the country.

Sadiola Expansion Project

Over the last several years, the Company has been advancing a strategy of optimization and expansion at the Sadiola Gold Mine. Initial efforts focused on stabilizing the operation, primarily related to the existing processing capacity of mostly oxide ores, followed by a phased expansion to allow the processing of fresh ore and increased throughput. The objective is to increase production and cash flows in both the short and long term.

On December 21, 2025, the Company announced that it began processing ore through the new fresh-ore comminution circuit installed as part of the Phase 1 expansion, marking a significant milestone in the transformational growth strategy for this long-life asset. The Phase 1 expansion is the first step in the Company’s strategy to increase production, reduce costs, and materially increase cash flows through a progressive expansion approach. The Phase 1 mill ramped up in the first quarter of 2026, alongside the completion of ancillary systems and power-supply upgrades. Further optimizations to the processing circuit, including instrumentation and automation upgrades, are advancing this year. Together, these initiatives are expected to improve operating performance, enhance overall processing rates, and reduce operating costs.

The Company has been advancing studies to define the best strategy for the next phase of the mine's expansion. The initial conclusion of these studies was that adding a pre-leach thickener to the circuit allows the plant to process over 90% of the fresh ore in the feed, increasing operational flexibility and potentially increasing production. Given that a pre-leach thickener is required regardless of the selected expansion scenario, the Company decided to begin engineering and design work in late 2025 in order to improve the operational flexibility and the capacity to treat fresh ore. Project execution activities began in the first quarter, with the aim of fully commissioning this addition to the circuit in the first quarter of 2027.

Allied concluded in the fourth quarter of 2025 that the best execution strategy for expansion at Sadiola is to progressively optimize, develop, and expand the current processing plant and ancillary infrastructure, rather than to build a new processing plant to treat fresh ore. This organic growth strategy allows for more efficient deployment of capital and management of execution risks, and it enables the same ultimate throughput of over 9 Mt/y of ore processed as defined in the previous studies, but with interim, organic steps at 7 Mt/y and 8 Mt/y. This strategy also enables the recovery improvement project and the energy program to be implemented progressively as throughput capacity expands, thereby improving capital efficiency and returns. For 2026, the Company will advance the engineering to a feasibility study level, as well as detailed engineering of the early works required for the 7 Mt/y step. In addition to this, Allied will continue advancing studies to increase recoveries for fresh ore, including test work and engineering for the Albion process, as well as new tailings dam construction, solar farm earthworks and mobilization, and further upgrades to the plant instrumentation and control systems.

The total capital expenditures for the 7 Mt/y step of the processing plant are estimated at approximately $200 million, including engineering and construction of a permanent two-stage crushing plant and a grinding mill in the second line of the Sadiola plant, which are planned to be developed between late 2026 and late 2028. The subsequent 8 Mt/y and 9 Mt/y per year steps consist of adding a permanent tertiary crushing circuit and wet plant upgrades, respectively, and could be executed sequentially or concurrently, along with related expansions to power generation and ancillary facilities.
allied-goldxlogoxonxwhite2.jpg | 16

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026

At the 7 Mt/y throughput, the plant configuration will include the existing Stage 1 three-stage crushing circuit operating in parallel with a new two-stage crushing circuit. Downstream, the comminution circuit will comprise two parallel milling circuits (Stage 1 and a new mill already owned by the Company), producing a final grind of P80 75 μm. The remainder of the flowsheet will include a pre-leach thickener, pre-oxidation, cyanidation, and carbon adsorption, utilizing the existing facilities and remaining consistent with the general processing path defined for Sadiola in the previous technical work.

Sadiola Energy Program

Along with the advancement of the growth strategy for Sadiola, the Company is advancing its energy program for the asset and is undertaking a staged and scalable approach, having initially installed additional diesel generators and control systems to support the start of operations of the first phase expansion, followed by the implementation of a hybrid power solution, with the deployment of medium-speed thermal units and a photovoltaic plant with battery energy storage systems (“BESS”) sufficient to meet the power requirements of the Phase 1 expansion at reduced costs and providing the base for a scalable system capable of satisfying the energy needs of the next phase expansion, thereby providing Sadiola with a flexible power solution capable of meeting its ultimate power needs and reducing its emissions, while being self-reliant, efficient and cost-effective.

The introduction of the initial photovoltaic plant and BESS is projected to reduce energy costs by up to 20 percent compared to current costs. The introduction of additional photovoltaic and BESS capacity, as well as medium-speed thermal generators, is projected to further reduce energy costs by up to 45 percent, representing a reduction in All-In Sustaining Costs ("AISC"), once the power program is fully implemented, estimated to range from an initial amount of $150 per ounce of gold to as much as $200 per ounce of gold with incremental interim reductions as each of the components of the power program are implemented. The projected operating costs are comparable to the average costs expected for grid-supplied power with diesel backup, adjusted for grid availability in Mali. Considering the schedule of implementation for the different stages of the plan noted above, which is driven by engineering and procurement timelines of the various components, cost improvements are expected to be modest in 2026 and then gradually increase with the deployment of solar and BESS in 2027, and then increase meaningfully with the subsequent introduction of medium-speed thermal generation.

These investments will secure power for the ongoing needs and future growth at Sadiola, while progressively lowering costs, fuel consumption and carbon intensity of operations. In addition, the hybrid power generation solution will ensure a robust, independent and uninterrupted power supply for operations, while preserving the option to connect to Mali's public grid system in the future. These enhancements reinforce Allied's commitment to disciplined capital allocation, operational excellence, and ESG-driven value creation for shareholders and stakeholders. With improved and more efficient, cost-effective energy availability, Allied remains on track to deliver the Sadiola expansion on schedule and within budget, while advancing its broader growth pipeline across Africa.

Sadiola Exploration

Since acquiring the Sadiola Project in 2021, Allied has identified over 15 million tonnes of economic oxide mineralization within the near-mine footprint, significantly enhancing the oxide resource base critical for the existing and planned processing infrastructure. Ongoing exploration activities at Sadiola Main, Tambali, Sekekoto West, FE3/4, FE2 Trend and TK1 support Allied's strategy to leverage the existing resources, known mineralization trends and infrastructure to maximize production and cash flows in the short to medium term.

During the first quarter of 2026, exploratory and resource drilling programs were conducted on the Sadiola license with a total of 138 holes drilled comprising 19,174 metres utilizing five exploration core and RC drill rigs. Resource and exploratory drilling programs continued and were expanded at Tambali and along the FE2 Trend during the first quarter. A sterilization drill program over a proposed solar field and waste pile site to the east of the FE2.5 oxide deposit did not indicate any significant mineralization.

While no exploratory drilling was carried out over at the Sekekoto West Deposit in the quarter, and the results from fresh rock core drilling are still pending, further drilling will likely be carried out at this target after the ongoing IP survey is completed. The IP survey is designed to trace the Sekekoto West host geology to the north and to provide enough data to create a 3D resistivity image of the S12 deposit which will be used to assist resource modelling of this highly prospective karsted zone.

At Tambali North, a program was designed to follow-up on historic oxide gold mineralization and test a model that suggests that the Tambali Deposit mineralization continued to the north into the Sadiola Main pit. This program initially comprised six short drill lines spaced 200 metres apart. Results to date have been positive and the Company will advance infill drilling at a 100-metre line spacing at Tambali North. As of the end of the first quarter of 2026, 83 holes, comprising 9,375 metres, had been completed with drilling continuing past the end of the quarter.
allied-goldxlogoxonxwhite2.jpg | 17

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026

Drilling continued at Sadiola Main during the quarter with 10 drill holes, totalling 7,975 metres. These holes are designed to test the southern strike extensions of the deposit and to test below previous drilling to begin to support an expansion of the reserve pit at depth and to evaluate Sadiola's underground potential. Additional holes are being planned with a goal to demonstrate depth extensions to the northern end of the Sadiola Main Zone and the northeast-trending cross-structures while gathering additional geological data to define bedding-parallel mineralization across the entire deposit area.

Drilling was completed at the north end of the FE2 Trend with 16 infill holes totalling 1,566 metres completed at FE2N and 24 RC holes totalling 2,552 metres completed at FE1 (located at the north end of the FE2 Trend). Next steps will be determined after a review of all of the results from these two target areas. Drilling tested a 2.3-kilometre limestone/clastic sediment contact with wide-spaced drill fences that is open to the north with a goal to exhibit short-term potential for shallow oxide gold resources.

Induced polarization geophysical surveys commenced over the S12 deposit area as part of a survey to test the Sekekoto West mineralized trend. S12 is a high-grade mineralized zone that has been subject to karsting, and one goal of the IP survey is to model the karsting and associated karst geological facies to support 3D modelling of this high-grade zone. IP surveys are predominantly used to outline potential zones of increased sulphides or quartz veins, both know to be related to gold mineralization.

Sterilization drilling was completed over a planned solar field site and at a proposed waste dump immediately east of the FE2.5 oxide deposit. This work, which comprised 37 holes totalling 3,632 metres, did not intersect any significant mineralized zones.

For the remainder of 2026, Sadiola will see continued efforts with four to five drills dedicated to continue testing for, and extending, the gold mineralized structures at Sadiola Main, Tambali North, FE2 Trend, Sekekoto Trend, FE3/FE4, TK1, Mandakoto and Kouloukan. The exploration is focused on both oxide and shallow fresh mineralization with a preference for oxide gold mineralization in the near term. Oxide ore is favoured in the short term as it provides the plant with relatively inexpensive, high-quality ounces. The horizontal and down-dip/down-plunge limits of these systems are still open and as such, expectations of new discoveries and additions to the mineral inventory are high.
Sadiola Mineral Reserves and Mineral Resources

Please refer to Section 6: Mineral Reserve and Mineral Resource Estimates for further details.

allied-goldxlogoxonxwhite2.jpg | 18

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
Bonikro (89.89% interest), Côte d’Ivoire

The Bonikro gold mine is an open pit gold mine located in the Oumé region of Côte d’Ivoire (“Bonikro” or “Bonikro Mine”). The remaining ownership is split between the Government of Côte d’Ivoire (10%) and a local minority shareholder (0.11%).

Bonikro is contiguous to Agbaou, and together they comprise the CDI Complex, with the two processing plants located only 20 km from each other.

Bonikro comprises two separate mining licences (the Bonikro Licence and Hiré Licence), although integrated as a single operation.

Bonikro Key Performance Information
(100% Basis)
For three months ended March 31,
2026
2025
Operating
Ore mined (M tonnes)0.91 0.44 
Waste mined (M tonnes)1.92 5.23 
Ore processed (M tonnes)0.61 0.63 
Gold
Production (Ounces)29,011 19,671 
Sales (Ounces)31,265 20,924 
Feed grade (g/t)1.63 1.07 
Recovery rate (%)93.4 %92.8 %
Total cost of sales per ounce sold(4)
$1,691 $1,721 
Cash costs per ounce sold(1)
$1,418 $1,390 
AISC per ounce sold(1)
$1,628 $1,582 
Financial (In thousands of US Dollars)
Revenue$113,548 $60,224 
Cost of sales (excluding DDA)(44,992)(29,218)
Gross profit excluding DDA(1)
$68,556 $31,006 
DDA(7,873)(6,799)
Gross Profit$60,683 $24,207 
Capital Expenditures (In thousands of US Dollars)
Sustaining(1)
$902 $14,928 
Expansionary(1)
 48 
Exploration(1)
2,453 1,975 

Bonikro produced 29,011 ounces of gold during the three months ended March 31, 2026, compared with 19,671 ounces in the first quarter of the previous year, due to mine sequencing and a standout performance in relation to the production plan. As previously guided, elevated stripping and waste removal costs during the past two years were planned investments to access higher-quality ore, and results now confirm that these actions are delivering value. The program has repositioned the asset on both production and cost metrics, outperforming in the quarter relative to plan.

For the first quarter, ore mined and total material mined were higher than plan, with higher grades obtained due to slight optimizations to the mining sequence. For the second quarter, mining performance is expected to remain stable, with minimal waste-stripping requirements for the current Stage 5. Process optimization initiatives continue with a focus on improving gravity circuit efficiency and slurry control.

Refinements to the mine design, supported by new geotechnical data, have enabled the inclusion of Stage 6 as Mineral Reserves at Bonikro, adding approximately 101,000 ounces of gold. Combined with additional Mineral Reserves at Hire, particularly at Akissi So, this will provide greater production flexibility at Bonikro while Oumé is being developed.
allied-goldxlogoxonxwhite2.jpg | 19

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
For costs, AISC(1) for the first quarter were in line with plan and include capitalized stripping at PB5 incurred during 2024 and 2025, which is being amortized in 2026 and 2027. This represents approximately $135 per ounce of gold sold in the cost structure.

During the quarter gold sales were higher than production, due to the timing of production and shipments related to fourth quarter of 2025 inventory.

Hiré Exploration

In the first quarter of 2026, drilling at Hiré focused on testing for oxides along the eastern extension of the Chapelle orebody and two more holes into the west end of the Akissi So Deposit. In total 32 holes comprising 3,315 metres were drilled with the bulk of the holes completed with an RC drill.

Drone magnetic surveying commenced in the first quarter with a plan to cover the northern part of the property package including the area north and east of the Bonikro Mine to the northernmost extents of the property. In total, 4,743.2 linear kilometres of 25 and 50 metre spaced drone magnetic lines were completed over the Oumé and Hire areas to April 4, 2026 comprising 61% of the planned surveying. This survey is designed to better define the structural zones that are associated with the gold zones to improve targeting success. As well, a secondary goal of the magnetic survey is to identify additional Bonikro Mine-type porphyritic felsic intrusions, which have been demonstrated to host significant gold zones.

Bonikro West Exploration

Infill soil sampling commenced over an area of historic gold-in-soil enrichment immediately west of the Bonikro Mine in 2026 with a goal of defining a drillable target. To the end of the first quarter of 2026, 991 of 1,232 planned samples were collected.

Oumé Exploration

Following the successful Oumé exploration program, which resulted in the declaration of initial Proven and Probable Mineral Reserves containing approximately 585,000 ounces of gold, Allied expanded its exploration efforts to test for extensions to the Oumé gold system. In the first quarter of 2026, exploration resumed over the projected eastern extent of the Oumé mineralized system, with 86 holes totalling 2,679 metres completed. Wide-spaced drill fences were designed to follow-up Au-in-soil anomalies, historic drill results, prospecting sample results and geological mapping. Approximately 233 scout holes are planned in this first pass program with additional holes pending results. Additional holes planned to test the southwestern extent of the mineralized system are scheduled for later in the second and third quarters of 2026.

Bonikro Mineral Reserve and Mineral Resource

Please refer to Section 6: Mineral Reserve and Mineral Resource Estimates for further details.


allied-goldxlogoxonxwhite2.jpg | 20

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
Agbaou (85% interest), Côte d’Ivoire

Agbaou is an open pit gold mine, located in the Oumé region of Côte d’Ivoire. The remaining ownership is split between the Government of Côte d’Ivoire (10%) and the SODEMI development agency (5%).

Agbaou is contiguous to Bonikro, and together they comprise the CDI Complex, with the two processing plants located only 20 km from each other. The combined milling capacity and existing infrastructure including water supply dams, tailings storage facilities, access and site roads, power supply and accommodation facilities provides optionality and significant synergies for the future.

Agbaou Key Performance Information
(100% Basis)
For three months ended March 31,
2026
2025
Operating
Ore mined (M tonnes)1.17 0.63 
Waste mined (M tonnes)7.70 8.77 
Ore processed (M tonnes)0.70 0.57 
Gold
Production (Ounces)22,901 19,137 
Sales (Ounces)22,618 18,563 
Feed grade (g/t)1.07 1.08 
Recovery rate (%)94.8 %95.3 %
Total cost of sales per ounce sold(4)
$2,147 $1,505 
Cash costs per ounce sold(1)
$1,922 $1,466 
AISC per ounce sold(1)
$2,376 $2,125 
Financial (In thousands of US Dollars)
Revenue$90,862 $51,738 
Cost of sales (excluding DDA)(41,313)(26,158)
Gross profit excluding DDA(1)
$49,549 $25,580 
DDA(7,253)(1,783)
Gross Profit$42,296 $23,797 
Capital Expenditures (In thousands of US Dollars)
Sustaining(1)
$8,445 $10,831 
Expansionary(1)
 31 
Exploration(1)
1,380 688 

Agbaou produced 22,901 ounces of gold during the three months ended March 31, 2026, compared to 19,137 ounces in the corresponding quarter of the previous year.

Agbaou AISC(1) for the first quarter were in line with plan. Optimization initiatives and operational enhancements are in progress, with Bonikro serving as the benchmark. Agbaou is expected to follow as these measures are implemented and scaled, targeting reduced costs in the next quarters.

Production in the first quarter focused primarily on ore from sources in the North extension area. Waste stripping in WP8 is underway with target access to higher-grade ore in the second quarter.

The Company has now completed the implementation of a centralized management model for both mines in CDI, streamlining processes, optimizing resources, enhancing service delivery for sustainable growth, and targeting lower AISC(1). The benefits of the centralized contractor model and the Hub-and-Spoke structure implemented are starting to materialize, enabling improved agility in managing shared resources and coordinating recovery efforts across sites. These enablers will be further embedded in the coming months as the Company transitions to full implementation.
allied-goldxlogoxonxwhite2.jpg | 21

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026

In addition to operational factors, the waste removal performed in 2025 allows for less reliance on short-term mineral resource conversion to support production levels in 2026, creating a bridge to focus additional exploration spending at Agbaou on more transformational targets aimed to add ounces and with an objective to increase mine life at Agbaou by four to six years, with the completion of the first stage exploration program in 2026.

Gold sales during the quarter were in line with production, with minor variances related to the timing of shipments.

Agbaou Exploration

At Agbaou, Allied is actively pursuing opportunities to extend the mine life by increasing Mineral Reserves through sustained drilling and other exploration efforts. In the first quarter of 2026, Allied completed 45 holes totalling 9,014 metres with up to five drills operating. These holes tested the down-dip extensions of known gold-bearing ore bodies and new gold zones. This sustained effort, which commenced in July 2025, comprises a minimum of 162 holes totalling 33,400 metres with a goal of adding to mine life. This work program is approximately 84% completed and scheduled to finish early in the second quarter of 2026. Modelling and resource estimation, in advance of updated Mineral Reserves, are in progress at the WP7 Agbaou Pit, which was the largest of the mineralized areas being subject to infill drilling with a goal to convert Inferred Mineral Resources to Indicated Mineral Resources. An updated mineral resource estimate will be completed after all assays have been received and interpreted, likely near mid-year 2026.

Soil sampling was completed over the Agbaou West target in the first quarter of 2026 with 849 samples collected out of a total of 1,232 planned samples. Anomalous gold-in-soil values noted in 4 areas, will be followed up in the second quarter of 2026 with infill sampling with a goal to develop coherent Au-in-soil anomalies that can be followed up with a scout.

Looking forward in 2026, continued testing of the known zones to depth will continue along with testing for oxide gold zones along strike of known deposits and new targets outside of the compensation boundaries.

Agbaou Mineral Reserve and Mineral Resource

Please refer to Section 6: Mineral Reserve and Mineral Resource Estimates for further details.


allied-goldxlogoxonxwhite2.jpg | 22

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
5.    CONSTRUCTION, DEVELOPMENT AND OTHER CORPORATE INITIATIVES

For details on the Sadiola Expansion Project, please refer to the Sadiola section of Section 4 of this MD&A.

Notable progress relating to some of the Company’s development and advanced stage exploration include, but are not limited to the following:

Kurmuk Project (100% Interest)(7), Ethiopia

Kurmuk Project Summary

The Kurmuk Project is a transformational development mine in the Benishangul-Gumuz region of Ethiopia. The Company holds an effective 100% ownership stake in the project; however, the Government of Ethiopia is entitled to a 7% equity participation in Kurmuk once the mine enters commercial production and certain governmental commitments such as public road upgrades and the finalized installation of a power line and substations. The power supply construction agreement is in development and is expected to be completed and energized ahead of first gold. An existing development agreement, signed with the Government of Ethiopia, spans an initial 20-year period and is renewable thereafter. The current project design encompasses the Dish Mountain and Ashashire deposits, with numerous exploration targets across the Kurmuk Project’s expansive 1,450 km² exploration territory.

Key project details are as follow:

First gold pour is expected mid-2026.
Currently defined 2.7 million ounces in Proven and Probable Mineral Reserves.
Kurmuk is expected to deliver between 100,000 and 150,000 gold ounces for the partial year of production in 2026, an average production level of approximately 290,000 gold ounces per annum over the first four years and 240,000 gold ounces per annum over a 10-year mine life at industry-leading AISC(1) below $950 per ounce, based solely on Mineral Reserves. This represents a significant improvement over the original project, which was projected to average 200,000 ounces annually at similar capital costs, with further upside potential supporting an initial strategic target mine life of 15-years.
A mining plan utilizing conventional open pit mining techniques with internationally recognized mining contractors and a robust process design using proven technologies.
A 2023 study proposed an increase in plant throughput from 4.4 Mt/y in the 2022 Definitive Feasibility Study to 6.0 Mt/y, representing a 38% increase. By utilizing existing major equipment and contractor mining, the proposed expanded project could be developed within the same capital requirements range as initially planned. The Company is now strategically targeting 6.4 Mt/y as further described below.

The project implementation team features strong African project delivery capabilities. Operational readiness remains a strategic focus, supported by active planning and phased preparation. Minopex, a specialized operational readiness company based in South Africa, was selected to assist the operational team with the commissioning, ramp-up, and stabilization of operations in the early months of the project, to enhance organizational depth and provide training and development for the local workforce.

Kurmuk Quarterly Progress

The project continues to track well against plan, both in terms of physical completion and spend, while achieving key milestones and progress during the first quarter of 2026.

The project execution is progressing well, with the key focus during the quarter being on the logistics for the remaining equipment and materials to the site, the continued advancement of steel and mechanical erection activities, as well as the ramp-up of the electrical, control and instrumentation (“EC&I”) contractor, including the installation of medium-voltage cable, electrical-racking and lighting placement. Mining activities continue to advance toward building at least three months' worth of ore stockpiles to support the start of operations in mid-2026. The Ethiopian Electrical Power Company is advancing the power line construction, which is expected to be completed before commissioning. Pre-commissioning activities are planned to begin during the second quarter, with the first gold expected in mid-2026.

The key focus beyond the first quarter, and for the remainder of the project to first gold in mid-2026 is on construction completion and operational readiness. All remaining mechanical and electrical equipment is expected on site during the second quarter, and the earthworks and civil contractor is expected to commence demobilization. Construction handovers are due to commence in the second quarter, with pre-commissioning activities commencing thereafter in the quarter. The tailings storage facility and haul road are due for
allied-goldxlogoxonxwhite2.jpg | 23

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
completion towards the end of the second quarter. Mining activities are expected to continue to ramp up in line with the production schedule, supporting the build-up of run-of-mine stockpiles and ensuring operational readiness for plant commissioning. The crushing circuit remains on track for early completion, which is critical to ensuring sufficient ore availability to support the targeted mid-year first gold milestone. Focus will be placed on achieving mechanical completion, testing, and handover of the crushing facilities to enable timely integration into the overall commissioning sequence.

Beyond the first gold expected for mid-year and a partial production year in 2026, the Company expects Kurmuk to produce an average of 290,000 ounces per year for the first four years and 240,000 ounces per year on average for the mine’s life, with AISC(1) below $950 per ounce.

Along with the advancement of the project and as previously disclosed, the Company completed a review of the capacity of the processing plant in consideration of the ore inventory and the exploration progress at Dish Mountain, Ashashire and Tsenge. Allied made a strategic decision to maximize the operational flexibility for Kurmuk since the start of operations, and is now targeting an average processing capacity of up to 6.4 Mt/y. This increased flexibility has been incorporated into the project execution plan, with subsequent optimizations to the leaching circuit expected to be deployed in the future years to increase fresh ore recoveries. The enhancements and optimizations are expected to make Kurmuk a stronger, de-risked operation upon commencement of production, providing upside and operational flexibility, aligning with the Company’s long-term strategy of maximizing value at each of the Company's assets.

Kurmuk Project Exploration

On November 27, 2025, Allied presented results of the exploration programs carried out over the Kurmuk Property during the period from mid 2024 to the middle of November 2025. The Company’s five-year exploration goal for Kurmuk is to reach 5 million ounces of Mineral Resources, representing a sequential target of over 1.5 million ounces of new Mineral Resources in addition to the current inventory. The objective is to add at least 0.5 million ounces of new Mineral Resources within 10 km of the mill to sustain or exceed the initial gold production of approximately 290,000 ounces per annum. The exploration plan considers expanding on the existing Mineral Resources near both the Ashashire and Dish Mountain deposits, advancing exploration at Tsenge utilizing a combination of geophysical surveys, trenching, and drilling, with a focus on higher-grades, and advancing exploration at three other prospects in the property. At both Dish Mountain and Ashashire, drilling continues to intersect lateral and vertical extensions of the deposits, with the limits of the mineralized system remaining open. At Tsenge, near-term exploration is focused on defining the extent of higher-grade zones and updating the mineralization models with a medium-term exploration goal of evaluating the entire 9-kilometre strike length of the gold-in-soil anomalies at Tsenge. A significant amount of highly successful trenching continues to be carried out at Tsenge, confirming the bedrock expression of the mineralized lenses that are coincident and proximal to the gold-in-soil anomalies aligned along this 9 km long trend. A second-pass drill program completed over the Urchin Prospect, located adjacent to the Ashashire haul road, yielded positive results that will require follow-up drilling.

During the first quarter of 2026, drilling was focused on resource extension drilling on the strike and depth extensions of Dish Mountain Resource, exploratory drilling and channel sampling continued at the Tsenge Prospect, the continuation of a new round of resource extension drilling at Ashashire, more follow-up drilling over the Urchin Prospect, and continued ROM and waste pad sterilization drilling. A total of 29 holes for 6,700 metres was drilled by five exploration drill rigs in the first quarter. Reprioritization of additional extensional drilling at Dish Mountain will be carried out in the second quarter of 2026.

Kurmuk Power Purchase Agreement ("PPA")

On August 19, 2024, the Company announced that its subsidiary, Kurmuk Gold Mine PLC, which owns the Kurmuk Project, entered into a definitive PPA with Ethiopian Electric Power to secure a reliable, competitive, and sustainable energy supply for Kurmuk throughout the life of the mine. This is an important milestone in the project's development, as a steady supply of hydroelectric power ensures that Kurmuk remains one of the lowest AISC(1) projects in the world. Ethiopia is a low-cost power producer, generating power almost entirely through hydroelectric sources, making it one of the most durable and cleanest power supplies globally.

Key Terms of the Agreement:

Term: The Power Purchase Agreement will be in effect for a period of twenty years and may be extended by mutual agreement.
Energy Charge: The agreement secures a flat energy charge of $0.04 per kWh, applicable from the supply commencement date and remaining fixed for the entire term, providing cost certainty for the project.
Renewable Energy Source: The project will benefit from Ethiopia's predominantly renewable energy sources, aligning with the Company's commitment to sustainable mining practices.
allied-goldxlogoxonxwhite2.jpg | 24

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
Transmission Line Construction: Electrical grid power will be supplied to the operation via a 75-kilometre, 132 kV power line, which is expected to be completed and energized ahead of first production in mid-2026, with substations at Asosa—a major city near the project—and at the project site. The government will provide the grid connection, which will increase their equity stake in Kurmuk Gold Mine PLC from 5% to 7%, as defined in the Kurmuk Development Agreement. On-site power will be distributed via a network of 11 kV power lines.

Securing the terms of the PPA marks a key milestone in advancing the Kurmuk Gold Project, cementing its path to becoming a low-cost producing mine for the Company. This agreement not only ensures the project's financial viability by locking in low energy costs but also reinforces Allied's strategic focus on leveraging sustainable energy solutions, positioning Kurmuk as a model for responsible mining in the region.

Currently the development of the installation works is trending towards being complete when the project requires full load for ramp up and performance testing. Progress updates are received weekly and aligned with the overall construction schedule. The progress will be monitored against challenging fuel constraints and global logistical concerns of late.

Kurmuk Mineral Reserve and Mineral Resource

Please refer to Section 6: Mineral Reserve and Mineral Resource Estimates for further details.

Transaction with Zijin Gold

The Company is advancing the transaction with Zijin Gold International Company Limited ("Zijin Gold") after entering into a definitive agreement (the "Arrangement Agreement" or the "Agreement") as previously disclosed. Zijin Gold, a public company listed on the Hong Kong Stock Exchange, agreed to acquire all of the issued and outstanding shares of Allied Gold at a price of C$44 per share (the “Offer Price”) in cash, pursuant to the terms of a court-approved plan of arrangement under the Business Corporations Act (Ontario) (the "Arrangement"). The Company's Board of Directors determined that the Arrangement immediately achieved fair value realization while mitigating business risks, particularly in highly volatile markets, and Zijin Gold had demonstrated a strong track record of long-term asset stewardship and consequently, there was a suspension of the other strategic opportunities. The transaction value of the Arrangement is approximately C$5.5 billion, realizing a significant, certain and immediate value for Allied Gold shareholders. Further details on the benefits of the Arrangement can be found in the Company's previous public disclosure filed on SEDAR+.

As previously disclosed, all requisite shareholder and court approvals have been obtained.

The Company and Zijin Gold are in continuous dialogue, planning for an orderly transition on completion of the Arrangement. Both companies continue to engage diligently and cooperatively with regulatory bodies pursuant to previously filed applications for regulatory approvals necessary to complete the Arrangement with the objective of closing in a timely manner within the timeframe set out in the Arrangement Agreement. The Arrangement Agreement provides for an outside date for closing of May 29, 2026, subject to extension by the parties if by that date any regulatory approvals or other conditions precedent are still in progress. Both companies continue to demonstrate a strong commitment to complete the transaction in accordance with the Arrangement Agreement.


allied-goldxlogoxonxwhite2.jpg | 25

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
6.    MINERAL RESERVE AND MINERAL RESOURCE ESTIMATES

Please refer to Section 12: Cautionary Statements and Internal Controls Over Financial Reporting – Notes on Mineral Reserves and Mineral Resources for further details.

2025 Year-End Mineral Reserves and Mineral Resources Summary

Allied’s near-term guidance and longer-term outlook are underpinned by its Mineral Reserves and Mineral Resources, which support the reliability and sustainability of the Company’s production platform while providing flexibility to enhance near-term production and cash flows from high-yield, near-mine opportunities. During the year, Allied completed a comprehensive review of all its resource models and mining design parameters, incorporating new exploration and production information, standardized geological modelling processes and mining design assumptions, particularly with respect to mining selectivity and dilution. These adjustments were intended to strengthen ore control practices and improve short-term operational predictability. Allied remains confident that ongoing exploration efforts will continue to grow mineral inventories, with the objective of delivering additional growth during 2026. This has been demonstrated with the declaration of Mineral Reserves at Oumé for the first time in 2025, significantly increasing the LOM at Bonikro, along with the inclusion of Stage 6.

As of December 31, 2025, Proven and Probable Mineral Reserves were reported at 11.2 million ounces of gold, contained within 247.1 million tonnes at a grade of 1.41 g/t. This represents a net year-over-year increase, reflecting the addition of new Mineral Reserves, replacing depletion from 2025 production, and updates to economic and design assumptions. Total Measured and Indicated Mineral Resources stood at 15.3 million ounces of gold, contained within 336.7 million tonnes at a grade of 1.41 g/t. The modest decrease from 2024 is primarily attributable to the recategorization of some Indicated Mineral Resources to Inferred Mineral Resources. Inferred Mineral Resources, at year-end totalled 2.1 million ounces contained within 54.2 million tonnes at a grade of 1.20 g/t, increasing from 1.4 million ounces from the prior year, reflecting the Company’s progress on increasing its mineral inventories.

Further details on a mine-by-mine basis can be found in the Review of Operations section of this MD&A, along with the Construction section for Kurmuk.

The Company’s 2025 year-end statement is provided below.

Mineral Reserves (Proven and Probable)

The following table sets forth the Mineral Reserve estimates for the Company’s mineral properties at December 31, 2025.

Proven Mineral ReservesProbable Mineral ReservesTotal Mineral Reserves
Tonnes (kt)
Grade (g/t)
Content (k ounces)
Tonnes (kt)
Grade (g/t)
Content (k ounces)
Tonnes (kt)
Grade (g/t)
Content (k ounces)
Sadiola Mine37,164 1.17 1,400 104,664 1.61 5,411 141,827 1.49 6,811 
Korali-Sud Mine1,658 0.68 36 1,275 1.56 64 2,933 1.06 100 
Kurmuk Project7,893 1.28 324 56,057 1.32 2,382 63,950 1.32 2,706 
Bonikro Mine6,601 0.87 185 26,217 1.32 1,111 32,819 1.23 1,296 
Agbaou Mine1,798 1.07 62 3,810 1.53 188 5,608 1.39 250 
Total Mineral Reserves55,114 1.13 2,007 192,023 1.48 9,156 247,137 1.41 11,164 
Note: Rounding of numbers may lead to discrepancies when summing columns or rows.


allied-goldxlogoxonxwhite2.jpg | 26

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
Mineral Resources (Measured, Indicated, Inferred)

The following table set forth the Measured and Indicated Mineral Resource estimates (inclusive of Mineral Reserves) and for the Company’s mineral properties at December 31, 2025.

Measured Mineral ResourcesIndicated Mineral ResourcesTotal Measured and Indicated
Tonnes (kt)
Grade (g/t)
Content (k ounces)
Tonnes (kt)
Grade (g/t)
Content (k ounces)
Tonnes (kt)
Grade (g/t)
Content (k ounces)
Sadiola Mine49,326 1.06 1,686 158,434 1.55 7,872 207,760 1.43 9,557 
Korali-Sud Mine2,117 0.68 46 5,863 1.11 209 7,980 1.00 256 
Kurmuk Project7,748 1.45 361 64,969 1.44 3,002 72,717 1.44 3,363 
Bonikro Mine8,339 1.14 306 32,316 1.38 1,436 40,654 1.33 1,742 
Agbaou Mine3,064 1.25 123 4,537 1.73 252 7,601 1.53 374 
Total Mineral Resources (M&I)70,595 1.11 2,522 266,118 1.49 12,771 336,713 1.41 15,292 
Note: Rounding of numbers may lead to discrepancies when summing columns or rows.

The following table set forth the Inferred Mineral Resource estimates and for the Company’s mineral properties at December 31, 2025.

Inferred Mineral Resources
Tonnes (kt)
Grade (g/t)
Content (k ounces)
Sadiola Mine45,547 1.13 1,656 
Korali-Sud Mine1,209 1.66 65 
Kurmuk Project4,988 1.35 217 
Bonikro Mine1,659 1.65 88 
Agbaou Mine781 2.62 66 
Total Mineral Resources (Inferred)54,183 1.20 2,091 
Note: Rounding of numbers may lead to discrepancies when summing columns or rows.

allied-goldxlogoxonxwhite2.jpg | 27

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
Mineral Reserve and Mineral Resource Reporting Notes

1.Metal Price, Cut-off Grade, Metallurgical Recovery:
 Mineral ReservesMineral Resources
Sadiola (80%)
Price assumption: $2,000/ounce gold
Open pit cut-off grades range from 0.26 to 0.69 g/t gold
Price assumption: $2,300/ounce gold
Open pit cut-off grades range from 0.23 g/t to 0.58 g/t gold
Korali-Sud (65%)
Price assumption: $2,000/ounce gold
Open pit cut-off grades range from 0.34 to 0.76 g/t gold
Price assumption: $2,300/ounce gold
Open pit cut-off grades range from 0.30 g/t to 0.66 g/t gold
   
Kurmuk (100%)(7)
Price assumption: $1,700/ounce gold. Selected pit shells using values of US$1,530/oz (revenue factor 0.90) for Dish Mountain and US$1,300/oz (revenue factor 0.76) for Ashashire.
Open pit cut-off grades range from 0.36 to 0.49 g/t gold
Price assumption: $2,300/ounce gold
Open pit cut-off grades range from 0.37 g/t to 0.49 g/t gold
   
Bonikro (89.89%)
Price assumption: $2,000/ounce gold
Open pit cut-off grades range from 0.46 to 0.57 g/t gold.

Price assumption: $2,300/ounce gold
Open pit cut-off grades range from 0.38 g/t to 0.60 g/t gold
Oume (100%)
Price assumption: $2,300/ounce gold
Open pit cut-off grades range from 0.54 to 0.71 g/t gold.

Price assumption: $2,400/ounce gold
Open pit cut-off grades range from 0.54 g/t to 0.69 g/t gold
Hire (89.89%)
Price assumption: $2,000/ounce gold
Open pit cut-off grades range from 0.59 to 0.69 g/t gold.

Price assumption: $2,300/ounce gold
Open pit cut-off grades range from 0.38 g/t to 0.60 g/t gold
   
Agbaou (85%)
 
Price assumption: $2,000/ounce gold
Open pit cut-off grades range from 0.43 to 0.55 g/t gold
Price assumption: $2,300/ounce gold
Open pit cut-off grades range from 0.37 g/t to 0.48 g/t gold
   
2. Mineral Reserve and Mineral Resource estimates are shown on a 100% basis. Designated government entities and national minority shareholders hold the following interests in each of the mines: 20% of Sadiola, 35% of Korali-Sud, 10.1% of Bonikro and 15% of Agbaou. The Government of Ethiopia is entitled to a 7% equity participation in Kurmuk. Only a portion of the government interests are carried.
3. All Mineral Reserves and Mineral Resources have been estimated in accordance with the standards of the Canadian Institute of Mining, Metallurgy and Petroleum and NI 43-101.
4. The Measured and Indicated Mineral Resource estimates are inclusive of those Mineral Resource estimates modified to produce the Mineral Reserve estimates.
5. Mineral Resources which are not Mineral Reserves do not have demonstrated economic viability.
6. Mineral Reserves and Mineral Resources are reported as of December 31, 2025.
7. For the Qualified Person responsible for the Mineral Reserve and Mineral Resource estimates, see Section 12: Cautionary Statements and Internal Controls Over Financial Reporting of this MD&A.

allied-goldxlogoxonxwhite2.jpg | 28

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
7.    FINANCIAL CONDITION AND LIQUIDITY

(In thousands of US Dollars)
As at March 31, 2026
As at December 31, 2025
Current Assets (including Cash and Cash Equivalents)$748,404 $763,709 
Non-Current Assets1,496,353 1,359,970 
Total Assets$2,244,757 $2,123,679 
Current Liabilities1,156,083 988,564 
Non-Current Liabilities643,115 630,436 
Total Liabilities$1,799,198 $1,619,000 
Equity attributable to Shareholders of the Company
334,627 407,609 
Non-controlling interest110,932 97,070 
Total Equity$445,559 $504,679 
Net Working Capital(3)
$(193,121)$(70,543)

Total assets were $2,244.8 million as at March 31, 2026, compared to total assets of $2,123.7 million as at December 31, 2025. The Company’s asset base is primarily non-current assets such as property plant and equipment, mining interests and exploration and evaluation assets. This reflects the capital-intensive nature of the mining business and previous growth through acquisitions. Other significant assets include cash and cash equivalents, inventories, prepayments and other receivables (comprising value-added taxes in the jurisdictions in which the Company operates). Notable changes from the prior year are related to capital expenditures at Kurmuk, general increases to property, plant and equipment due to ongoing operations, and general changes to working capital.

Total liabilities as at March 31, 2026, were $1,799.2 million compared to $1,619.0 million as at December 31, 2025. The increase is predominantly attributable to unrealized mark-to-markets on the Company's gold collars and convertible debentures, and general timing on accounts payable and accrued liabilities, offset by payments under the claim settlement. Other significant liabilities include: provision of closure & reclamation, deferred and contingent consideration, trade and other payables, and income taxes (payable and deferred).

Cash and Working Capital

Cash and cash equivalents were $424.2 million as at March 31, 2026, compared to $479.8 million as at December 31, 2025. Cash balances were positively impacted by significant operating cash flows. This was offset by capital expenditures at Kurmuk and Sadiola Phase 1, general increases to property, plant and equipment due to ongoing operations, and general changes to working capital. The Company has sufficient cash on hand, and liquidity to fully manage its business. The Company believes that it is able to meet its obligations as they come due with funds from cash flows from operating activities.

Net working capital(3) was a deficit of $193.1 million at March 31, 2026, compared to negative $70.5 million at December 31, 2025. Working capital in the current period is affected by the short-term liabilities associated with the gold collars, which become payable when, on settlement, gold price average for the period exceed the collar’s upper limit. While settlements result in a cash outlay, such outlays are triggered by revenue cash generating events, with the proceeds of the sale at prices exceeding that limit providing the necessary funds for settlement. Further, working capital is impacted by the current component of deferred revenue which is settled by the delivery of gold under the respective agreements and does not result in a direct outlay of cash and cash equivalents.

Total Borrowings

The total borrowings, including the convertible debentures of the Company at March 31, 2026 were $214.6 million compared to $154.3 million as at December 31, 2025.

Current borrowings are associated with the convertible debentures, net of transaction costs, and movements from the prior period are fully associated with the mark-to-market of the instrument.

allied-goldxlogoxonxwhite2.jpg | 29

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
LIQUIDITY

The Company plans to meet its spending commitments, which include continued spending on business development activities, exploration and project development (notably the Sadiola Expansion Project and the Kurmuk Project), with funds on hand and cash flows from operating activities and, as described below, with the execution on number of non-dilutive stream and prepaid transactions.

Lastly, the Company has immediately available credit of $50.0 million (inclusive of a $10.0 million accordion) under its revolving credit facility, which remains undrawn.

The Company’s near-term financial obligations include capital commitments and other financing commitments of $118.5 million, interest payments of $9.4 million and deferred and contingent consideration of $30.3 million, along with accounts payable and accrued liabilities.


SOURCES AND USES OF CASH

The following table summarizes cash inflows and outflows:

(In thousands of US Dollars)
For three months ended March 31,
2026
2025
Operating cash flows before income tax paid and working capital(6)
$162,714 $100,788 
Income tax paid(10,468)(7,904)
Operating cash flows before movements in working capital(6)
$152,246 $92,884 
Working capital movement(6)
(94,953)28,246 
Net cash generated from operating activities
$57,293 $121,130 
Net cash used in investing activities
(109,330)(103,870)
Net cash used in financing activities
(256)(6,677)
Net (decrease) increase in cash and cash equivalents
$(52,293)$10,583 

Operating Activities

Net cash generated from operating activities for the three months ended March 31, 2026 was $57.3 million. This compares to $121.1 million in the prior year comparative quarter. Current period cash was positively impacted by strong gold sales and record high realized gold prices. Working capital impact for the first quarter is related to normal course movements in inventory (including stockpiles), timing of accounts payable, and payment of year-end accruals. As previously disclosed, certain positive impacts to working‑capital movements in the fourth quarter of 2025 were released in the first quarter of 2026, reflecting the settlement of various payables, accruals and other balance sheet items. Prior year cash flows were positively impacted by the sale of Korali inventory in the first quarter of 2025 from 2024 which significantly increased sales quantities, while positively impacting working capital due to the sale.

Operating cash flows before income tax paid and movements in working capital for the three months ended March 31, 2026 increased significantly, at an inflow of $162.7 million compared with the prior year comparative quarter inflow of $100.8 million, due to higher realized gold prices. The impact of higher prices was partially offset by lower ounces sold in the current period in association with the sale of Korali inventory in the first quarter of 2025.

Working capital movement(6) for the three months ended March 31, 2026 impacted cash flows by $95.0 million, compared to $28.2 million in the prior year comparative quarter. Working capital impact for the first quarter is related to normal course movements in inventory (including stockpiles), timing of accounts payable, and payment of year-end accruals. As previously disclosed, certain positive impacts to working‑capital movements in the fourth quarter of 2025 were released in the first quarter of 2026, reflecting the settlement of various payables, accruals and other balance sheet items. Prior year comparative working capital was positively impacted by the sale of Korali inventory that had been built up in the prior year.


allied-goldxlogoxonxwhite2.jpg | 30

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
Investing Activities

For the three months ended March 31, 2026, net cash used in investing activities was $109.3 million compared to $103.9 million in the prior year comparative quarter. Investing outflows in the current period comprised primarily additions to PP&E and exploration and evaluation assets, which importantly included Kurmuk construction-related activities, owner costs and capitalized borrowings.

Financing Activities

In the three months ended March 31, 2026, net cash used in financing activities was $0.3 million compared to outflows of $6.7 million in the comparative prior year quarter. Current quarter cash outflows from financing activities are immaterial, while prior comparative period financing cash flows are related to dividends paid to non-controlling interests.

CAPITAL RESOURCES

The capital of the Company consists of items included in shareholders’ equity and borrowings, net of cash and cash equivalents, as follows:

(In thousands of US Dollars)
As at March 31, 2026
As at December 31, 2025
Total Equity
$445,559 $504,679 
Current and Non-Current Borrowings
214,558 154,312 
$660,117 $658,991 
Less: Cash and cash equivalents(424,200)(479,777)

$235,917 $179,214 

To maintain or adjust its capital structure, the Company may, upon approval from its Board of Directors, issue shares, pay dividends, or undertake other activities as deemed appropriate under the specific circumstances.

The Company manages its discretionary spending to align with cash availability and future cash flow forecasts. Amounts above may be higher or lower than expected depending on cash flows generated during the year.



allied-goldxlogoxonxwhite2.jpg | 31

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
CONTRACTUAL OBLIGATIONS AND COMMITMENTS

In the normal course of business, the Company enters into contracts that give rise to commitments for future minimum payments. The following table summarizes the remaining contractual maturities of the Company’s financial liabilities and operating and capital commitments at March 31, 2026, shown on an undiscounted basis:

(In millions of US dollars)Within 1 yearYears 2 and 3Years 4 and 5After 5 yearsTotal
 Debt
Repayment of principal$— $107.3 $— $— $107.3 
Interest9.4 13.5 — — 22.9 
Accounts payable and accrued liabilities409.8 — — — 409.8 
Derivative financial liability174.3 — — — 174.3 
Reclamation and closure costs— — 13.9 224.7 238.6 
Deferred and contingent consideration30.3 38.6 24.9 — 93.8 
Capital and other financial commitments118.5 15.7 5.5 4.2 143.9 
Total contractual obligations and commitments$742.3 $175.1 $44.3 $228.9 $1,190.6 

OUTSTANDING SHARE DATA

The Company is authorized to issue an unlimited number of common shares at no par value. The following table summarizes the Company’s common shares and securities convertible into common shares as at the following dates:

(In millions of units)
As at May 13, 2026
As at March 31, 2026
As at December 31, 2025
Common Shares issued and outstanding125.9 125.9 124.7 
Stock options(5)
2.4 2.4 2.4 
Restricted share units(5)
2.2 2.2 3.3 
Convertible debentures(5)
6.2 6.2 6.2 
Total Shares and Convertible Securities Issued and Outstanding(5)
136.7 136.7 136.6 


allied-goldxlogoxonxwhite2.jpg | 32

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
8.    ECONOMIC TRENDS, BUSINESS RISKS AND UNCERTAINTIES

Exploration, development and mining of precious metals involve numerous risks as a result of the inherent nature of the business, global economic trends, and the influences of local social, political, environmental and economic conditions in the various geographical areas of operation. As such, the Company is subject to several financial and operational risks that could have a significant impact on its profitability and levels of operating cash flows.

Below is a summary of the principal financial risks and related uncertainties facing the Company. Readers are also encouraged to read and consider the risk factors and related uncertainties as described in the Annual Information Form of the Resulting Issuer, which is available on SEDAR+ at www.sedarplus.com. Such risk factors could materially affect the future operating results of the Company and could cause actual events to differ materially from those described in forward-looking statements.

METAL PRICE RISK

The Company’s profitability and long-term viability depend, in large part, upon the market price of metals that may be produced from the
Company’s properties, primarily gold. Market price fluctuations of these precious metals could adversely affect profitability of operations and lead to impairments of mineral properties. Metal prices fluctuate widely and are affected by numerous factors beyond the Company’s control including but not limited to supply and demand, consumption patterns, macroeconomic factors (interest, exchange, inflation), banking and political conditions, nature and climate condition risks, and mining specific factors.

chart-2166b4cb839746fb821a.jpg

During the three months ended March 31, 2026, spot gold prices as (as measured by the LBMA PM Gold Price) averaged $4,873 per ounce, compared to $2,860 per ounce during the comparative prior year quarter. During the period, the highest price was $5,405 per ounce and the lowest price was $4,353 per ounce.

Gold reached a new all‑time high in the first quarter of 2026, surpassing $5,000 per ounce in January before retreating sharply toward the end of the period. Early‑quarter strength was driven by elevated geopolitical and macroeconomic uncertainty. However, gold came under pressure in March as conflict escalated in the Middle East and both the U.S. dollar and oil prices rose significantly. Investor sentiment weakened, leading to broad liquidation of gold positions and an overall decline in global ETF holdings. Central banks remained net buyers of gold in 2026, with Poland and Uzbekistan leading official‑sector purchases.

In the near term, gold prices are expected to remain sensitive to geopolitical developments and broader macroeconomic conditions. Over the longer horizon, persistent global economic and geopolitical uncertainty, combined with sustained investor and central bank demand, should continue to provide support for gold.


allied-goldxlogoxonxwhite2.jpg | 33

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
CURRENCY RISK

Currency fluctuations may affect the Company’s assets and liabilities and the costs that the Company incurs at its operations. Gold is sold throughout the world based principally on a US Dollar price, but a significant portion of the Company’s operating and capital expenses are incurred in West African CFA franc (XOF). XOF is pegged to the Euro at a fixed rate of 655.957 per Euro. This effectively means the Company primary currency exposure is to the Euro.

All else being equal, a higher USD/EUR exchange rate will result in lower costs to the Company when measured in its reporting currency of USD.

chart-9a749de077e14c0a8eaa.jpg
During the three months ended March 31, 2026, the average USD/EUR exchange rate was 1.1706, the lowest was 1.1417, and the highest was 1.2041. The rate at the end of the period was 1.1553.

9.    CONTINGENCIES

The Company may be involved in disputes with other parties in the future that may result in litigation. If the Company is unable to resolve these disputes favourably, it may have a material adverse impact on the Company's financial condition, cash flows and results of operations.


allied-goldxlogoxonxwhite2.jpg | 34

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
10.    CRITICAL ACCOUNTING POLICIES AND ESTIMATES

BASIS OF PREPARATION

The Company’s Condensed Consolidated Financial Statements have been prepared in accordance with International Accounting Standard 34 “Interim Financial Reporting” (IAS 34). Other than as noted, the accounting policies applied by the Company in these Condensed Consolidated Financial Statements are the same as those set out in the Allied Gold audited financial statements for the year ended December 31, 2025, except for those discussed below.

New accounting standards and amendments adopted

Classification and Measurement of Financial Instruments - Amendments to IFRS 9, Financial Instruments and IFRS 7, Financial Instruments: Disclosures

On May 30, 2024, the IASB issued narrow scope amendments to IFRS 9 “Financial Instruments” (“IFRS 9”) and IFRS 7. The amendments include the clarification of the date of initial recognition or derecognition of financial liabilities, including financial liabilities that are settled in cash using an electronic payment system. The amendments also introduce additional disclosure requirements to enhance transparency regarding investments in equity instruments designated at FVOCI and financial instruments with contingent features. The amendments were adopted on January 1, 2026, and did not have a significant impact on the Company’s financial statements.

Contracts Referencing Nature-Dependent Electricity - Amendments to IFRS 9, Financial Instruments and IFRS 7, Financial Instruments: Disclosures

On December 18, 2024, the IASB issued targeted amendments to IFRS 9 and IFRS 7 to help companies better report the financial effects of nature-dependent electricity contracts. The amendments clarify the factors an entity would consider when assessing whether a renewable electricity contract qualifies for the own-use exemption under IFRS 9, as well as hedge accounting requirements for when a renewable electricity contract is designated as the hedging instrument in a cash flow hedge of forecasted sales or purchases of electricity. The amendments were adopted on January 1, 2026. The Company does not currently have such contracts in effect and therefore the adoption of the amendment did not have a significant impact on the Company's financial statements.

New accounting standards and amendments to be adopted

IFRS 18, Presentation and Disclosures of Financial Statements.

In April 2024, the IASB issued IFRS 18, Presentation and Disclosures of Financial Statements (“IFRS 18”) with the aim of improving companies’ reporting of financial performance and giving investors a better basis for analyzing and comparing companies. IFRS 18 introduces three new sets of requirements:
Improved comparability in the statements of income which introduces three defined categories for income and expenses: operating, investing and financing. These changes would require all companies to use the same structure of the statements of income and provide new defined subtotals, including operating profit.
Enhanced transparency of management-defined performance measures which would require companies to disclose explanations of those company specific measures that are related to the income statement.
More useful grouping of information in the financial statements which provides enhanced guidance on how to organize information and whether to provide it in the primary financial statements or in the notes.

IFRS 18 is effective for annual reporting periods beginning on or after January 1, 2027. The Company is currently evaluating the impact of this new standard.

The condensed financial statements do not include all of the information required for a complete set of IFRS financial statements and should be read in conjunction with the audited consolidated financial statements for the year ended December 31, 2025. Selected explanatory notes are included to explain events and transactions that are significant to an understanding of the changes in the Company’s financial position and performance since the audited financial statements for the year ended December 31, 2025.

CRITICAL JUDGEMENTS AND ESTIMATES

In preparing the consolidated financial statements in accordance with IFRS, management is required to make estimates and assumptions that affect the reported amounts of assets, liabilities, revenue and expenses. Critical accounting estimates represent estimates that are
allied-goldxlogoxonxwhite2.jpg | 35

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
uncertain and for which changes in those estimates could materially impact the Company's consolidated financial statements. Actual future outcomes may differ from present estimates. Management reviews its estimates and assumptions on an ongoing basis using the most current information available.

The critical judgements and key sources of estimation uncertainty in the application of accounting policies during the year ended December 31, 2026 are disclosed in note 5 to the Consolidated Financial Statements - Critical Judgements and Estimation Uncertainties.


11.    NON-GAAP FINANCIAL PERFORMANCE MEASURES

The Company has included certain non-GAAP financial performance measures to supplement its Condensed Consolidated Interim Financial Statements, which are presented in accordance with IFRS, including the following:

Cash costs per gold ounce sold;
AISC per gold ounce sold;
Gross profit excluding DDA;
Sustaining, Expansionary and Exploration Capital Expenditures;
Adjusted Net Earnings (Loss) and Adjusted Net Earnings (Loss) per share; and
EBITDA and Adjusted EBITDA

The Company believes that these measures, together with measures determined in accordance with IFRS, provide investors with an improved ability to evaluate the underlying performance of the Company.

Non-GAAP financial performance measures, including cash costs(1), AISC(1), Gross profit excluding DDA(1), Sustaining(1), Expansionary(1) and Exploration Capital Expenditures(1), Adjusted Net Earnings (Loss)(1), Adjusted Net Earnings (Loss) per Share(1), EBITDA(1) and Adjusted EBITDA(1), do not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to similar measures employed by other companies. Non-GAAP financial performance measures intend to provide additional information, and should not be considered in isolation as a substitute for measures of performance prepared in accordance with IFRS and are not necessarily indicative of operating costs, operating earnings or cash flows presented under IFRS.

Management’s determination of the components of non-GAAP financial performance measures and other financial measures are evaluated on a periodic basis, influenced by new items and transactions, a review of investor uses and new regulations as applicable. Any changes to the measures are described and retrospectively applied, as applicable. Subtotals and per unit measures may not calculate based on amounts presented in the following tables due to rounding.

The measures of cash costs and AISC, along with revenue from sales, are considered to be key indicators of a Company’s ability to generate operating earnings and cash flows from its mining operations. This data is furnished to provide additional information and is a non-GAAP financial performance measure.

CASH COSTS PER GOLD OUNCE SOLD

Cash costs(1) include mine site operating costs such as mining, processing, administration, production taxes and royalties which are not based on sales or taxable income calculations. Cash costs exclude DDA, exploration costs, accretion and amortization of reclamation and remediation, and capital, development and exploration spend. Cash costs include only items directly related to each mine site, and do not include any cost associated with the general corporate overhead structure.

The Company discloses cash costs because it understands that certain investors use this information to determine the Company’s ability to generate earnings and cash flows for use in investing and other activities. The Company believes that conventional measures of performance prepared in accordance with IFRS do not fully illustrate the ability of its operating mines to generate cash flows. The most directly comparable IFRS measure is cost of sales. As aforementioned, this non-GAAP measure does not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to similar measures employed by other companies, should not be considered in isolation as a substitute for measures of performance prepared in accordance with IFRS, and is not necessarily indicative of operating costs, operating earnings or cash flows presented under IFRS.

Cash costs(1) are computed on a weighted average basis, with the aforementioned costs, net of by-product revenue credits from sales of silver, being the numerator in the calculation, divided by gold ounces sold.

allied-goldxlogoxonxwhite2.jpg | 36

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
AISC PER GOLD OUNCE SOLD

AISC(1) figures are calculated generally in accordance with a standard developed by the World Gold Council (“WGC”), a non-regulatory, market development organization for the gold industry. Adoption of the standard is voluntary, and the standard is an attempt to create uniformity and a standard amongst the industry and those that adopt it. Nonetheless, the cost measures presented herein may not be comparable to other similarly titled measures of other companies. The Company is not a member of the WGC at this time.

AISC(1) include cash costs(1) (as defined above), mine sustaining capital expenditures (including stripping), sustaining mine-site exploration and evaluation expensed and capitalized, and accretion and amortization of reclamation and remediation. AISC(1) exclude capital expenditures attributable to projects or mine expansions, exploration and evaluation costs attributable to growth projects, DDA, income tax payments, borrowing costs and dividend payments. AISC(1) include only items directly related to each mine site, and do not include any cost associated with the general corporate overhead structure. As a result, Total AISC(1) represent the weighted average of the three operating mines, and not a consolidated total for the Company. Consequently, this measure is not representative of all of the Company’s cash expenditures. Further, in relation to Bonikro, as the 2025 waste stripping benefits not only 2025 but also the following two years of production, the AISC per ounce sold figure accounts for the allocation of the stripping spend over the ounces it benefits through 2027.

Sustaining capital expenditures are expenditures that do not increase annual gold ounce production at a mine site and excludes all expenditures at the Company’s development projects as well as certain expenditures at the Company’s operating sites that are deemed expansionary in nature, such as the Sadiola Phased Expansion and the construction and development of Kurmuk. Exploration capital expenditures represent exploration spend that has met criteria for capitalization under IFRS.

The Company discloses AISC, as it believes that the measure provides useful information and assists investors in understanding total sustaining expenditures of producing and selling gold from current operations, and evaluating the Company’s operating performance and its ability to generate cash flow. The most directly comparable IFRS measure is cost of sales. As aforementioned, this non-GAAP measure does not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to similar measures employed by other companies, should not be considered in isolation as a substitute for measures of performance prepared in accordance with IFRS, and is not necessarily indicative of operating costs, operating earnings or cash flows presented under IFRS.

AISC are computed on a weighted average basis, with the aforementioned costs, net of by-product revenue credits from sales of silver, being the numerator in the calculation, divided by gold ounces sold.

The following tables provide detailed reconciliations from total costs of sales to cash costs(1) and AISC(1). Subtotals and per unit measures may not calculate based on amounts presented in the following tables due to rounding.
allied-goldxlogoxonxwhite2.jpg | 37

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
(In thousands of US Dollars, unless otherwise noted)
For three months ended March 31, 2026
For three months ended March 31, 2025
BonikroAgbaouSadiolaTotalBonikroAgbaouSadiolaTotal
Cost of Sales, excluding DDA$44,992 $41,313 $116,954 $203,259 $29,218 $26,158 $152,416 $207,792 
DDA7,873 7,253 4,797 19,923 6,799 1,783 10,375 18,957 
Cost of Sales$52,865 $48,566 $121,751 $223,182 $36,017 $27,941 $162,791 $226,749 
Cash Cost Adjustments
DDA$(7,873)$(7,253)$(4,797)$(19,923)$(6,799)$(1,783)$(10,375)$(18,957)
Cost of production of ounces delivered as dividend prepayment    — — 9,135 9,135 
Agbaou Contingent Consideration 2,326  2,326 — 1,120 — 1,120 
Silver by-Product credit(659)(159)(223)(1,041)(137)(71)(48)(256)
Total Cash Costs(1)
$44,333 $43,480 $116,731 $204,544 $29,081 $27,207 $161,503 $217,791 
AISC(1) Adjustments to Total Cash Costs(1) noted above
Reclamation & Remediation Accretion$161 $113 $504 $778 $137 $156 $419 $712 
Exploration Capital945 1,380 185 2,510 675 688 113 1,476 
Exploration Expenses  3,392 3,392 445 235 2,432 3,112 
Sustaining Capital Expenditures5,124 8,445 714 14,283 2,452 10,831 1,109 14,392 
IFRS 16 Lease Adjustments322 322  644 322 322 — 644 
Total AISC(1)
$50,885 $53,740 $121,526 $226,151 $33,112 $39,439 $165,576 $238,127 
Gold Ounces Sold31,265 22,618 45,995 99,878 20,924 18,563 92,033 131,520 
Gold Ounces Sold excluding ounces distributed as dividend-in-kind31,265 22,618 45,995 99,878 20,924 18,563 83,878 123,365 
Cost of Sales per Gold Ounce Sold$1,691 $2,147 $2,647 $2,235 $1,721 $1,505 $1,941 $1,838 
Cash Cost(1) per Gold Ounce Sold
$1,418 $1,922 $2,538 $2,048 $1,390 $1,466 $1,755 $1,656 
AISC(1) per Gold Ounce Sold
$1,628 $2,376 $2,642 $2,264 $1,582 $2,125 $1,799 $1,811 
GROSS PROFIT EXCLUDING DDA

The Company uses the financial measure “Gross Profit excluding DDA” to supplement information in its financial statements. The Company believes that in addition to conventional measures prepared in accordance with IFRS, the Company and certain investors and analysts use this information to evaluate the Company’s performance.

Gross profit excluding DDA is calculated as Gross Profit plus DDA.

The Company discloses Gross Profit excluding DDA(1) because it understands that certain investors use this information to determine the Company’s ability to generate earnings and cash flows. The Company believes that conventional measures of performance prepared in accordance with IFRS do not fully illustrate the ability of its operating mines to generate cash flows. The most directly comparable IFRS measure is Gross Profit. As aforementioned, this non-GAAP measure does not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to similar measures employed by other companies, should not be considered in isolation as a substitute for measures of performance prepared in accordance with IFRS, and is not necessarily indicative of operating costs, operating earnings or cash flows presented under IFRS.

allied-goldxlogoxonxwhite2.jpg | 38

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
The reconciliation of Gross Profit to Gross Profit Excluding DDA can be found in Section 1: Highlights and Relevant Updates of this MD&A, under the Summary of Financial Results and Section 4: Review of Operations and Mine Performance, for the relevant mines.

ADJUSTED NET EARNINGS (LOSS) AND ADJUSTED NET EARNINGS (LOSS) PER SHARE

The Company uses the financial measures “Adjusted Net Earnings (Loss)”(1) and the non-GAAP ratio “Adjusted Net Earnings (Loss) per share”(1) to supplement information in its financial statements. The Company believes that in addition to conventional measures prepared in accordance with IFRS, the Company and certain investors and analysts use this information to evaluate the Company’s performance.

Adjusted Net Earnings (Loss)(1) and Adjusted Net Earnings (Loss)(1) per share are calculated as Net Earnings (Loss) attributable to Shareholders of the Company, excluding non-recurring items, items not related to a particular period and/or not directly related to the core mining business such as the following, with notation of Gains (Losses) as they would show up on the financial statements.

Gains (losses) related to the reverse takeover transaction events and other items,
Gains (losses) on the revaluation of historical call and put options,
Unrealized Gains (losses) on financial instruments and embedded derivatives,
Write-offs (reversals) on mineral interest, exploration and evaluation and other assets,
Gains (losses) on sale of assets,
Unrealized foreign exchange gains (losses),
Share-based (expense) and other share-based compensation,
Unrealized foreign exchange gains (losses) related to revaluation of deferred income tax asset and liability on non-monetary items,
Deferred income tax recovery (expense) on the translation of foreign currency inter-corporate debt,
One-time tax adjustments to historical deferred income tax balances relating to changes in enacted tax rates,
Non-recurring provisions,
Any other non-recurring adjustments and the tax impact of any of these adjustments calculated at the statutory effective rate for the same jurisdiction as the adjustment.

Non-recurring adjustments from unusual events or circumstances are reviewed from time to time based on materiality and the nature of the event or circumstance.

Management uses these measures for internal valuation of the core mining performance for the period and to assist with planning and forecasting of future operations. Management believes that the presentation of Adjusted Net Earnings (Loss) and Adjusted Net Earnings (Loss) per share provide useful information to investors because they exclude non-recurring items, items not related to or not indicative of current or future periods' results and/or not directly related to the core mining business and are a better indication of the Company’s profitability from operations as evaluated by internal management and the board of directors. The items excluded from the computation of Adjusted Net Earnings (Loss)(1) and Adjusted Net Earnings (Loss)(1) per share, which are otherwise included in the determination of Net Earnings (Loss) and Net Earnings (Loss) per share prepared in accordance with IFRS, are items that the Company does not consider to be meaningful in evaluating the Company’s past financial performance or the future prospects and may hinder a comparison of its period-to-period profitability.

The most directly comparable IFRS measure is Net Earnings (Loss). As aforementioned, this non-GAAP measure does not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to similar measures employed by other companies, should not be considered in isolation as a substitute for measures of performance prepared in accordance with IFRS, and is not necessarily indicative of operating costs, operating earnings or cash flows presented under IFRS.

The reconciliation of Net (Loss) Earnings to attributable to Shareholders of the Company to Adjusted Net Earnings can be found in Section 1: Highlights and Relevant Updates of this MD&A, under the Summary of Financial Results.

EBITDA AND ADJUSTED EBITDA

The Company uses the financial measures “EBITDA” and "Adjusted EBITDA” to supplement information in its financial statements. The Company believes that in addition to conventional measures prepared in accordance with IFRS, the Company and certain investors and analysts use this information to evaluate the Company’s performance.

EBITDA(1) is calculated as Net Earnings (Loss), plus Finance Costs, DDA, Current income tax expense and Deferred income tax expense. Adjusted EBITDA calculated is further calculated as EBITDA(1), excluding non-recurring items, items not related to a particular period and/
allied-goldxlogoxonxwhite2.jpg | 39

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
or not directly related to the core mining business such as the following, with notation of Gains (Losses) as they would show up on the financial statements.
Gains (losses) on the revaluation of historical call and put options,
Unrealized Gains (losses) on financial instruments and embedded derivatives,
Write-offs (reversals) on mineral interest, exploration and evaluation and other assets,
Gains (losses) on sale of assets,
Unrealized foreign exchange gains (losses),
Share-based (expense) and other share-based compensation,
Unrealized foreign exchange gains (losses) related to revaluation of deferred income tax asset and liability on non-monetary items,
Non-recurring provisions,
Non-recurring adjustments from unusual events or circumstances are reviewed from time to time based on materiality and the nature of the event or circumstance.

Management uses these measures for internal valuation of the cash flow generation ability of the period and to assist with planning and forecasting of future operations. Management believes that the presentation of EBITDA(1) and Adjusted EBITDA(1) provide useful information to investors because they exclude non-recurring items, items not related to or not indicative of current or future periods' results and/or not directly related to the core mining business and are a better indication of the Company’s cash flow from operations as evaluated by internal management and the board of directors. The items excluded from the computation of Adjusted EBITDA(1), which are otherwise included in the determination of Net Earnings (Loss) prepared in accordance with IFRS, are items that the Company does not consider to be meaningful in evaluating the Company’s past financial performance or the future prospects and may hinder a comparison of its period-to-period performance comparisons.

The most directly comparable IFRS measure is Net Earnings (Loss). As aforementioned, this non-GAAP measure does not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to similar measures employed by other companies, should not be considered in isolation as a substitute for measures of performance prepared in accordance with IFRS, and is not necessarily indicative of operating costs, operating earnings or cash flows presented under IFRS.

(In thousands of US Dollars)
For three months ended March 31,
2026
2025
Net (Loss) Earnings
$(44,464)$39,937 
Finance costs, net$5,798 $5,310 
DDA19,923 18,957 
Current income tax expense64,835 27,700 
Deferred income tax expense31,617 11,344 
EBITDA(1)
$77,709 $103,248 

(In thousands of US Dollars)
For three months ended March 31,
2026
2025
EBITDA(1)
$77,709 $103,248 
Loss on revaluation of financial instruments37,839 14,116 
Share-based compensation55,200 4,107 
Other2,527 12,363 
Adjusted EBITDA(1)
$173,275 $133,834 



allied-goldxlogoxonxwhite2.jpg | 40

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026

12.    CAUTIONARY STATEMENTS AND INTERNAL CONTROLS OVER FINANCIAL REPORTING

This MD&A provides a discussion and analysis of the financial condition and results of operations to enable a reader to assess material changes in financial condition between March 31, 2026, and December 31, 2025, and results of operations for the three months ended March 31, 2026, and March 31, 2025.

This MD&A has been prepared as of May 14, 2026. This MD&A is intended to supplement and complement the Condensed Consolidated Interim Financial Statements prepared in accordance with IFRS. Readers are encouraged to review the Consolidated Financial Statements in conjunction with their review of this MD&A. Certain notes to the Consolidated Financial Statements are specifically referred to in this MD&A. All dollar amounts in the MD&A are in US Dollars, unless otherwise specified.

CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION

This MD&A contains “forward-looking information” including "future oriented financial information" under applicable Canadian securities legislation. Except for statements of historical fact relating to the Company, information contained herein constitutes forward-looking information, including, but not limited to, any information as to the Company’s strategy, objectives, plans or future financial or operating performance. Forward-looking statements are characterized by words such as “plan”, “expect”, “budget”, “target”, “project”, “intend”, “believe”, “anticipate”, “estimate” and other similar words or negative versions thereof, or statements that certain events or conditions “may”, “will”, “should”, “would” or “could” occur. In particular, forward looking information included in this MD&A includes, without limitation, statements with respect to:

the Company’s expectations in connection with the production and exploration, development and expansion plans at the Company’s projects discussed herein being met;
the Company’s plans to continue building on its base of significant gold production, development-stage properties, exploration properties and land positions in Mali, Côte d’Ivoire and Ethiopia through optimization initiatives at existing operating mines, development of new mines, the advancement of its exploration properties and, at times, by targeting other consolidation opportunities with a primary focus in Africa;
the Company’s expectations relating to the performance of its mineral properties;
the estimation of Mineral Reserves and Mineral Resources;
the timing and amount of estimated future production;
the estimation of the life of mine of the Company’s projects;
the timing and amount of estimated future capital and operating costs;
the costs and timing of exploration and development activities;
the Company’s expectation regarding the timing of feasibility or pre-feasibility studies, conceptual studies or environmental impact assessments;
the Company’s expectations with respect to the Arrangement (as defined herein), including the ability of the Company and Zijin Gold (as defined herein) to obtain all necessary regulatory approvals in connection with the Arrangement in a timely manner or at all, and to satisfy all other conditions precedent in the Arrangement Agreement (as defined herein);
the effect of government regulations (or changes thereto) with respect to restrictions on production, export controls, income taxes, expropriation of property, repatriation of profits, environmental legislation, land use, water use, land claims of local people, mine safety and receipt of necessary permits;
the Company’s community relations in the locations where it operates and the further development of the Company’s social responsibility programs;
the Company’s expectations regarding the payment of any future dividends; and
the Company’s plans to continue implementing and scaling the Energy Program (as defined herein), including expectations regarding energy needs and the performance of the Energy Program.

Forward-looking information is based on the opinions, assumptions and estimates of management considered reasonable at the date the statements are made, and is inherently subject to a variety of risks and uncertainties and other known and unknown factors that could cause actual events or results to differ materially from those projected in the forward-looking information. These factors include the Company’s dependence on products produced from its key mining assets; fluctuating price of gold; risks relating to the exploration, development and operation of mineral properties, including but not limited to adverse environmental and climatic conditions, unusual and unexpected geologic conditions and equipment failures; risks relating to operating in emerging markets, particularly Africa, including risk of government expropriation or nationalization of mining operations; health, safety and environmental risks and hazards to which the Company’s operations are subject; the Company’s ability to obtain all necessary regulatory approvals in connection with the Arrangement in a timely manner or at all; the ability of Zijin Gold to obtain all necessary shareholder and regulatory approvals in connection with the
allied-goldxlogoxonxwhite2.jpg | 41

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
Arrangement in a timely manner or at all; the ability of the Company and Zijin Gold to satisfy all conditions precedent to the completion of the Arrangement; the Company’s ability to maintain or increase present level of gold production; nature and climatic condition risks; counterparty, credit, liquidity and interest rate risks and access to financing; cost and availability of commodities; increases in costs of production, such as fuel, steel, power, labour and other consumables; risks associated with infectious diseases; uncertainty in the estimation of Mineral Reserves and Mineral Resources; the Company’s ability to replace and expand Mineral Resources and Mineral Reserves, as applicable, at its mines; factors that may affect the Company’s future production estimates, including but not limited to the quality of ore, production costs, infrastructure and availability of workforce and equipment; risks relating to partial ownerships and/or joint ventures at the Company’s operations; reliance on the Company’s existing infrastructure and supply chains at the Company’s operating mines; risks relating to the acquisition, holding and renewal of title to mining rights and permits, and changes to the mining legislative and regulatory regimes in the Company’s operating jurisdictions; limitations on insurance coverage; risks relating to illegal and artisanal mining; the Company’s compliance with anti-corruption laws; risks relating to the development, construction and start-up of new mines, including but not limited to the availability and performance of contractors and suppliers, the receipt of required governmental approvals and permits, and cost overruns; risks relating to acquisitions and divestitures; title disputes or claims; risks relating to the termination of mining rights; risks relating to security and human rights; risks associated with processing and metallurgical recoveries; risks related to enforcing legal rights in foreign jurisdictions; competition in the precious metals mining industry; risks related to the Company’s ability to service its debt obligations; fluctuating currency exchange rates (including the US Dollar, Euro, West African CFA Franc and Ethiopian Birr exchange rates); the values of assets and liabilities based on projected future conditions and potential impairment charges; risks related to shareholder activism; timing and possible outcome of pending and outstanding litigation and labour disputes; risks related to the Company’s investments and use of derivatives; taxation risks; scrutiny from non-governmental organizations; labour and employment relations; risks related to third-party contractor arrangements; repatriation of funds from foreign subsidiaries; community relations; risks related to relying on local advisors and consultants in foreign jurisdictions; the impact of global financial, economic and political conditions, global liquidity, interest rates, inflation and other factors on the Company’s results of operations and market price of common shares; risks associated with financial projections; force majeure events; the Company’s plans with respect to dividend payment; transactions that may result in dilution to common shares; future sales of common shares by existing shareholders; the Company’s dependence on key management personnel and executives; possible conflicts of interest of directors and officers of the Company; the reliability of the Company’s disclosure and internal controls; compliance with international ESG disclosure standards and best practices; vulnerability of information systems including cyber attacks; the expected performance of the Energy Program not being realized; as well as those risk factors discussed or referred to herein.

Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking information, there may be other factors that could cause actions, events or results to not be as anticipated, estimated or intended. There can be no assurance that forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. The Company undertakes no obligation to update forward-looking information if circumstances or management’s estimates, assumptions or opinions should change, except as required by applicable law. The reader is cautioned not to place undue reliance on forward-looking information. The forward-looking information contained herein is presented for the purpose of assisting investors in understanding the Company’s expected financial and operational performance and results as at and for the periods ended on the dates presented in the Company’s plans and objectives and may not be appropriate for other purposes.

NOTES ON MINERAL RESERVES AND MINERAL RESOURCES

Mineral Resources are stated effective as at December 31, 2025 are estimated in accordance with the 2014 Canadian Institute of Mining, Metallurgy and Petroleum Definition Standards for Mineral Resources and Mineral Reserves (“CIM Standards”) and National Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101”). Where Mineral Resources are stated alongside Mineral Reserves, those Mineral Resources are inclusive of, and not in addition to, the stated Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

Mineral Reserves are stated effective as at December 31, 2025 and estimated in accordance with CIM Standards and NI 43-101. The Mineral Reserves:

are inclusive of the Mineral Resources which were converted in line with the material classifications based on the level of confidence within the Mineral Resource estimate;
reflect that portion of the Mineral Resources which can be economically extracted by open pit methods;
consider the modifying factors and other parameters, including but not limited to the mining, metallurgical, social, environmental, statutory and financial aspects of the project;
include an allowance for mining dilution and ore loss.

allied-goldxlogoxonxwhite2.jpg | 42

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
Mineral Reserve and Mineral Resource estimates are shown on a 100% basis. Designated government entities and national minority shareholders hold the following interests in each of the mines: 20% of Sadiola, 35% of Korali-Sud, 10.1% of Bonikro and 15% of Agbaou. Only a portion of the government interests are carried. The Government of Ethiopia is entitled to a 7% equity participation in Kurmuk once the mine enters into commercial production and certain governmental commitments such as public road upgrades and installation of a power line are complete.

The Mineral Resource and Mineral Reserve estimates for each of the Company’s mineral properties have been approved by the qualified persons within the meaning of NI 43-101 as set forth below:

Mineral PropertyQualified Person of Mineral ReservesQualified Person of Mineral Resources
Sadiola MineEsteban Chacon, Ing. Chilean Mining CommissionAlejandro Garrone, MAusIMM (CP)
Korali-Sud MineEsteban Chacon, Ing. Chilean Mining CommissionAlejandro Garrone, MAusIMM (CP)
Kurmuk ProjectEsteban Chacon, Ing. Chilean Mining CommissionChelsey Protulipac, P.Geo
Bonikro MineEsteban Chacon, Ing. Chilean Mining CommissionChelsey Protulipac, P.Geo
Agbaou Mine Esteban Chacon, Ing. Chilean Mining CommissionChelsey Protulipac, P.Geo

Except as otherwise disclosed, all scientific and technical information contained in this MD&A has been reviewed and approved by Sébastien Bernier, P.Geo (Senior Vice President, Technical Services). Mr. Bernier is an employee of Allied and a "Qualified Person" as defined by Canadian Securities Administrators' National Instrument 43-101 - Standards of Disclosure for Mineral Projects (“NI 43-101”)

INTERNAL CONTROLS OVER FINANCIAL REPORTING

Management’s Report on Internal Controls Over Financial Reporting (“ICFR”)

Management is responsible for establishing and maintaining adequate internal controls over financial reporting (“ICFR”), as defined in Rules 13a-15(f) and 15d-15(f) under the Securities Exchange Act of 1934, as amended, (the "Exchange Act") and National Instrument 52-109 Certification of Disclosure in Issuers’ Interim Filings (“NI 52-109”). ICFR is designed to provide reasonable assurance regarding the reliability of financial reporting and preparation of consolidated financial statements for external purposes in accordance with IFRS. Any system of ICFR, no matter how well designed, has inherent limitations. Therefore, even those systems determined to be effective can provide only reasonable assurance with respect to financial statement preparation and presentation.

Beginning with the Company’s second annual report following its listing on the NYSE, for 2026 financial results, the Company will be required to provide a management report on ICFR and the Company's independent registered public accounting firm will be required to attest to the effectiveness of ICFR once the Company is subject to the auditor attestation requirements under Section 404(b) of the Sarbanes‑Oxley Act.

Under the supervision and with the participation of management, including the Chairman & Chief Executive Officer and Chief Financial Officer, the Company has designed ICFR based on the framework issued by the Committee of Sponsoring Organizations of the Treadway Commission in Internal Control – Integrated Framework (2013) and conducted an evaluation of the design and operating effectiveness of the Company's ICFR as of December 31, 2025 and March 31, 2026.

In connection with the preparation and audit of the consolidated financial statements as of and for the year ended December 31, 2025, the Company identified deficiencies in its ICFR which were deemed to aggregate to a material weakness. A “material weakness” is a deficiency, or a combination of deficiencies, in ICFR such that there is a reasonable possibility that a material misstatement of the Company’s annual or interim financial statements will not be prevented or detected on a timely basis.

The material weaknesses relate primarily to deficiencies in the Company’s information technology general controls ("ITGCs") predominantly related to legacy systems and deficiencies in the Company’s process-level IT application controls, including weaknesses in access management, segregation of duties, and control execution, which collectively create a reasonable possibility that the Company’s ICFR would not prevent or detect a material misstatement on a timely basis.

allied-goldxlogoxonxwhite2.jpg | 43

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
The Company has concluded that the material weaknesses resulted from limitations in its processes, systems, and resourcing, resulting in a pervasive potential impact to the consolidated financial statements. The control environment, systems architecture, documentation standards, and available resources require further redesign to meet the necessary formalized internal control, governance, and documentation requirements.

As remediation efforts are ongoing, the Company's Chairman & Chief Executive Officer and Chief Financial Officer concluded that, as of March 31, 2026 the Company has not yet remediated its material weaknesses. Consequently, it has been concluded that the Company did not maintain effective internal control over financial reporting.

Changes in ICFR

During the three months ended March 31, 2026, management continued remediation activities related to the previously identified material weaknesses. Other than in respect of the material weakness and related remediation, during the quarter ended March 31, 2026, no change occurred in the Company’s ICFR that has materially affected, or is reasonably likely to materially affect, the Company's ICFR.

Management’s Remediation Plan

The Company has developed and initiated a comprehensive remediation plan designed to strengthen the Company’s internal control environment and support sustainable public-company compliance, including:
Completing enhancements and redesign of ITGCs for certain legacy systems;
Continuing to perform ICFR and IT risk assessments and implementing additional control activities responsive to identified risks (including enhancements to IT general controls);
Implementing automated controls and system-based validations, where feasible, to reduce reliance on manual processes and strengthen control consistency;
Improving documentation and retention practices to ensure audit-ready support including clear supporting data sources, and evidence of timely review and approval in accordance with internal control and governance requirements;
Completing the formalization of policies and procedures across finance and IT functions to align with public company governance standards and NYSE listing requirements;
Continuing to engage a third-party advisor to support the SOX readiness efforts and to assist with control design, documentation, and testing in preparation for compliance with Section 404.

While management is making improvements to the Company’s control environment and business processes to support and scale with its growing operations, the remediation process is ongoing and the material weaknesses have not yet been fully remediated. The Company may not be able to fully remediate the material weaknesses until these steps have been completed and the internal controls have been operating effectively for a sufficient period of time.

This evaluation process, including testing the effectiveness of the remediation efforts, is expected to be substantially concluded prior to December 31, 2026, but may extend into 2027 as full remediation requires controls to operate effectively for a sufficient period of time.

Disclosure Controls and Procedures (“DCP”)

DCP have been designed to provide reasonable assurance that all relevant information required to be disclosed by the Company is gathered and communicated to senior management to allow timely decisions regarding required disclosure. Our Chairman & Chief Executive Officer and Chief Financial Officer, after evaluating the effectiveness of the Company's DCPs as of March 31, 2026, have concluded that, by implication of the aforementioned material weaknesses, the Company's DCPs were not effective in providing reasonable assurance that information required to be disclosed by the Company is (a) recorded, processed, summarized and reported within the time periods specified in the securities legislation, and (b) accumulated and communicated to management, including our Chairman & Chief Executive Officer and Chief Financial Officer, as appropriate, to allow timely decisions regarding required disclosure.

Control and Procedure Limitations

The Company’s management, including the Chairman & Chief Executive Officer and Chief Financial Officer, recognize that any ICFR and DCP, no matter how well designed or operated, have inherent limitations. Therefore, even those systems determined to be effective can provide only reasonable assurance that the objectives of the control system are achieved.
allied-goldxlogoxonxwhite2.jpg | 44

ALLIED GOLD
MANAGEMENT'S DISCUSSION AND ANALYSIS
For the three months ended March 31, 2026
ENDNOTES

(1)This is a non-GAAP financial performance measure. A cautionary note regarding non-GAAP financial performance measures, along with detailed reconciliations and descriptions, can be found in Section 11: Non-GAAP Financial Performance Measures.

(2)Adjustments to net earnings are those attributable to the Shareholders of the Company.

(3)Net working capital is defined as the excess of current assets over current liabilities. Current liabilities for the purpose of the net working capital calculation exclude the borrowings associated with the Convertible Debenture, which is classified as current as per IAS 1. Holders can convert at any time, but a conversion would not result in a cash outlay for the Company as it would be settled in shares.

(4)Historically, Cost of sales was presented inclusive of DDA. Cost of sales is the sum of mine production costs, royalties, and refining cost, while DDA refers to the sum of DDA of mining interests. Starting in the prior year, these figures appear on the face of the Consolidated Financial Statements. The metric “Total cost of sales per ounce sold” is defined as Cost of sales inclusive of DDA, divided by ounces sold.

(5)Each stock option is exercisable into one common share of the Company, upon vesting. Restricted share units once fully vested are redeemable into one common share of the Company.

(6)Working Capital movement refers to the sum of
a.(Increase) / decrease in trade and other receivables
b.(Increase) / decrease in inventories
c.Increase / (decrease) in trade and other payables

(7)The Government of Ethiopia is entitled to a 7% equity participation in Kurmuk once the mine enters commercial production and certain governmental commitments such as public road upgrades and installation of a power line are complete.

(8)Included in gold ounces sold for the three months ended March 31, 2025 are 8,155 ounces from Korali-Sud not included in revenue, as they were distributed to the Government of Mali as an advance dividend-in-kind at prevailing market prices.

(9)Cost of Sales per Gold Ounces Sold is determined based on ounces considered revenue not including those advanced as a dividend-in-kind, while Cash Costs(1) and AISC(1) are determined based on total sales of gold ounces, including the ounces advanced as a dividend-in-kind, along with the costs of production associated with those ounces.
allied-goldxlogoxonxwhite2.jpg | 45

allied-goldxlogoxonxwhiteb.jpg


UNAUDITED CONDENSED CONSOLIDATED INTERIM FINANCIAL STATEMENTS

FOR THE THREE MONTHS ENDED MARCH 31, 2026 AND 2025




TABLE OF CONTENTS

CONDENSED CONSOLIDATED INTERIM STATEMENTS OF FINANCIAL POSITION
3
CONDENSED CONSOLIDATED INTERIM STATEMENTS OF (LOSS) EARNINGS
4
CONDENSED CONSOLIDATED INTERIM STATEMENTS OF OTHER COMPREHENSIVE (LOSS) EARNINGS
5
CONDENSED CONSOLIDATED INTERIM STATEMENTS OF CHANGES IN EQUITY
6
CONDENSED CONSOLIDATED INTERIM STATEMENTS OF CASH FLOWS
7

NOTES TO THE CONDENSED CONSOLIDATED INTERIM FINANCIAL STATEMENTS
1NATURE OF OPERATIONS
8
2BASIS OF PREPARATION AND PRESENTATION
8
3OPERATING SEGMENTS
9
4REVENUE
11
5COST OF SALES
11
6GENERAL AND ADMINISTRATIVE
11
7OTHER LOSSES (GAINS)
12
8FINANCE COSTS
12
9EARNINGS (LOSS) PER SHARE
12
10NON-CONTROLLING INTERESTS13
11FINANCIAL INSTRUMENTS
14
12TRADE RECEIVABLES, PREPAYMENTS AND OTHER RECEIVABLES
16
13INVENTORIES
17
14MINERAL PROPERTY, PLANT AND EQUIPMENT
17
15TRADE AND OTHER PAYABLES
18
16DEFERRED REVENUE
19
17BORROWINGS
21
18LEASE OBLIGATIONS
21
19SHARE CAPITAL
22
20SHARE-BASED EXPENSE23
21DEFERRED AND CONTINGENT CONSIDERATION
26



ALLIED GOLD
CONDENSED CONSOLIDATED INTERIM STATEMENTS OF FINANCIAL POSITION

(In thousands of US dollars) (Unaudited)
Note
As at March 31, 2026
As at December 31, 2025
Assets
Current assets
Cash and cash equivalents $424,200 $479,777 
Trade receivables, prepayments, and other receivables12131,356 117,093 
Derivative financial asset1138,570 26,703 
Inventories13154,278 140,136 
Total current assets$748,404 $763,709 
Non-current assets
Mineral property, plant and equipment14$1,362,467 $1,240,630 
Trade receivables, prepayments and other receivables1237,652 28,798 
Deferred tax assets972 3,377 
Inventories1378,296 70,056 
Restricted cash16,966 17,109 
Total non-current assets$1,496,353 $1,359,970 
Total assets$2,244,757 $2,123,679 
 
Liabilities and Total Equity
Current liabilities
Trade and other payables15$409,828 $373,193 
Derivative financial liability11174,333 167,260 
Income tax payable230,326 177,122 
Provisions11,983 16,134 
Deferred and contingent consideration2130,321 30,117 
Borrowings17214,558 154,312 
Deferred revenue1676,880 67,427 
Lease obligations187,854 2,999 
Total current liabilities$1,156,083 $988,564 
Non-current liabilities
Provision for reclamation and closure costs188,402 187,623 
Deferred tax liability85,283 56,071 
Deferred and contingent consideration2145,832 44,906 
Deferred revenue16299,288 329,373 
Lease obligations1824,310 12,463 
Total non-current liabilities$643,115 $630,436 
Total liabilities$1,799,198 $1,619,000 
 
Equity
Share capital19$824,993 $813,355 
Retained earnings (deficit)
(339,132)(280,806)
Accumulated OCI(180,017)(155,854)
Share-based payments reserve2028,783 30,914 
Total equity attributable to shareholders of the Company$334,627 $407,609 
Non-controlling interests10110,932 97,070 
Total equity$445,559 $504,679 
Total liabilities and shareholders' equity$2,244,757 $2,123,679 

The accompanying notes are an integral part of the condensed consolidated interim financial statements.





"Peter Marrone""Richard Graff"
PETER MARRONERICHARD GRAFF
DirectorDirector











ALLIED GOLD
CONDENSED CONSOLIDATED INTERIM STATEMENTS OF (LOSS) EARNINGS


(In thousands of US Dollars except for shares and per share amounts) (Unaudited)
Note
For three months ended March 31,
2026
2025
Revenue4$394,110 $346,407 
Cost of sales, excluding depreciation, depletion and amortization ("DDA")5(203,259)(207,792)
DDA5(19,923)(18,957)
Gross profit
$170,928 $119,658 
General and administrative expenses6$(69,158)$(18,852)
Exploration and evaluation expenses(3,618)(3,527)
Loss on revaluation of financial instruments
11(37,839)(14,116)
Other (losses) income
7(2,527)1,128 
Net earnings before finance costs and income tax
$57,786 $84,291 
Finance costs8$(5,798)$(5,310)
Net earnings before income tax
$51,988 $78,981 
Current income tax expense
$(64,835)$(27,700)
Deferred income tax expense
(31,617)(11,344)
Net (loss) earnings for the period
$(44,464)$39,937 
 
(Loss) earnings attributable to:
Shareholders of the Company$(58,326)$15,124 
Non-controlling interests1013,862 24,813 
Net (loss) earnings for the period
$(44,464)$39,937 
 
(Loss) earnings per share attributable to shareholders of the Company
Basic$(0.47)$0.14 
Diluted$(0.47)$0.13 

The accompanying notes are an integral part of the condensed consolidated interim financial statements.









allied-goldxlogoxonxwhiteb.jpg | 4


ALLIED GOLD
CONDENSED CONSOLIDATED INTERIM STATEMENTS OF OTHER COMPREHENSIVE (LOSS) EARNINGS
(In thousands of US Dollars except for shares and per share amounts) (Unaudited)
Note
For three months ended March 31,
2026
2025
Net earnings (loss)$(44,464)$39,937 
Other comprehensive earnings (loss), net of taxes (nil)
Items that may be reclassified subsequently to net earnings:
Cash-flow hedges
- Effective portion of changes in fair value of cash flow hedges
11(100,291)(37,151)
- Reclassification of losses recorded in earnings93,217 2,200 
Sum(7,074)(34,951)
Items that will not be reclassified to net earnings:
Changes in the fair value of financial instruments at FVOCI(17,089)2,235 
Total other comprehensive loss$(24,163)$(32,716)
Total comprehensive (loss) earnings$(68,627)$7,221 
Attributable to:
Shareholders of the Company$(82,489)$(17,592)
Non-controlling interests13,862 24,813 
Total comprehensive (loss) earnings$(68,627)$7,221 


The accompanying notes are an integral part of the condensed consolidated interim financial statements.



allied-goldxlogoxonxwhiteb.jpg | 5


ALLIED GOLD
CONDENSED CONSOLIDATED INTERIM STATEMENTS OF CHANGES IN EQUITY

(In thousands of US Dollars) (Unaudited)
Share capitalShare-based payment reserveAccumulated OCIRetained earnings (deficit)Total attributable to Shareholders of the CompanyNon-controlling interestTotal equity
Balance at December 31, 2024
$587,119 $8,492 $(13,052)$(236,794)$345,765 $70,532 $416,297 
Share-based payments— 1,953 — — 1,953 — 1,953 
Recognition of non-controlling interest— — — 7,835 7,835 (2,312)5,523 
Distribution of dividend in kind to non-controlling interest— — — — — (23,896)(23,896)
Total (loss) earnings and comprehensive (loss) earnings
— — (32,716)15,124 (17,592)24,813 7,221 
Balance at March 31, 2025
$587,119 $10,445 $(45,768)$(213,835)$337,961 $69,137 $407,098 
Balance at December 31, 2025
$813,355 $30,914 $(155,854)$(280,806)$407,609 $97,070 $504,679 
Share-based payments— 9,507 — — 9,507 — 9,507 
Shares issued to settle RSUs11,638 (11,638)— —  —  
Total (loss) earnings and comprehensive (loss) earnings
— — (24,163)(58,326)(82,489)13,862 (68,627)
Balance at March 31, 2026
$824,993 $28,783 $(180,017)$(339,132)$334,627 $110,932 $445,559 

The accompanying notes are an integral part of the condensed consolidated interim financial statements.
allied-goldxlogoxonxwhiteb.jpg | 6


ALLIED GOLD
CONDENSED CONSOLIDATED INTERIM STATEMENTS OF CASH FLOWS

(In thousands of US Dollars) (Unaudited)
Note
For three months ended March 31,
2026
2025
Net inflow (outflow) of cash related to the following activities
Operating
Net (loss) earnings for the period
$(44,464)$39,937 
Income tax expense
96,452 39,044 
Adjustments for:
Share-based expense2055,200 4,107 
DDA20,022 19,110 
Loss on revaluation of financial instruments
33,572 14,116 
Other losses (gains)
72,527 (12,238)
Non-cash revenue from stream arrangements16(6,393)(8,598)
Finance costs85,798 5,310 
Operating cash flows before income tax paid, government settlements and movements in working capital$162,714 $100,788 
Income tax paid(10,468)(7,904)
Operating cash flows before movements in working capital$152,246 $92,884 
Increase in trade receivables, prepayments and other receivables
(23,735)(22,590)
(Increase) decrease in inventories
13(22,382)49,561 
(Decrease) increase in trade and other payables
(48,836)1,275 
Net cash generated from operating activities
$57,293 $121,130 
Investing activities
Additions of mineral property, plant and equipment(99,636)(97,088)
Borrowing costs capitalized11(4,694)(4,694)
Capitalized exploration and evaluation(5,000)(2,088)
Net cash used in investing activities
$(109,330)$(103,870)
Financing activities
Dividend paid to NCI10 (6,677)
Repayment of lease principal(541)— 
Other interest received or finance costs (paid)285 — 
Net cash used in financing activities
$(256)$(6,677)
Net (decrease) increase in cash and cash equivalents
$(52,293)$10,583 
Cash and cash equivalents at beginning of period
479,777 224,994 
Effect of foreign exchange rate changes(3,284)(3,327)
Cash and cash equivalents, end of the period
$424,200 $232,250 
The accompanying notes are an integral part of the condensed consolidated interim financial statements.
allied-goldxlogoxonxwhiteb.jpg | 7


ALLIED GOLD
NOTES TO THE CONDENSED CONSOLIDATED INTERIM FINANCIAL STATEMENTS

For the Three Months Ended March 31, 2026 and 2025
(Tabular amounts in thousands of US dollars, unless otherwise noted)
1.    NATURE OF OPERATIONS

Allied Gold Corporation (“Allied Gold” or “the Company”) was incorporated under the British Columbia Business Corporations Act but completed the endorsement process to continue as an Ontario Corporation on September 7, 2023. The Company is listed on the Toronto Stock Exchange (“TSX”) and the New York Stock Exchange (“NYSE”) under the ticker symbol AAUC. In addition, its publicly traded convertible debentures are listed on the TSX, trading in U.S. dollars under the symbol AAUC.DB.U. The registered office of the Company is located at Royal Bank Plaza, North Tower, 200 Bay Street, Suite 2200, Toronto, Ontario M5J 2J3.

The Company is an emerging gold producer, operator and majority owner (through its subsidiaries) of the following producing gold mines and gold development project:

the Sadiola Mine, located in Mali (the “Sadiola mine”, 80% interest), comprising two separate mining licences (the Sadiola Licence and the Korali-Sud Licence (previously referred to as Diba, 65% interest)) although integrated as a single operation;
the Bonikro Mine located in Côte d’Ivoire (the “Bonikro mine”, 89.89% interest). The Bonikro mine comprises two separate mining licences (the Bonikro Licence and Hiré Licence) although integrated as a single operation;
the Agbaou Mine, located in Côte d’Ivoire (the “Agbaou mine”, 85% interest); and
the Kurmuk Gold Project, located in Ethiopia (the “Kurmuk project”, 100% interest).

The Company is advancing the transaction with Zijin Gold International Company Limited ("Zijin Gold") after entering into a definitive agreement (the "Arrangement Agreement" or the "Agreement") as previously disclosed. Zijin Gold, a public company listed on the Hong Kong Stock Exchange, agreed to acquire all of the issued and outstanding shares of Allied Gold at a price of C$44 per share (the “Offer Price”) in cash, pursuant to the terms of a court-approved plan of arrangement under the Business Corporations Act (Ontario) (the "Arrangement").

As previously disclosed all requisite shareholder and court approvals have been obtained. The Company and Zijin Gold continue to engage with regulatory bodies pursuant to previously filed applications for regulatory approvals necessary to complete the Arrangement. The Arrangement Agreement provides for an outside date for closing of May 29, 2026, subject to extension by the parties if by that date any regulatory approvals or other conditions precedent are still in progress.

2.    BASIS OF PREPARATION AND PRESENTATION

The unaudited condensed consolidated interim financial statements have been prepared in accordance with IAS 34 “Interim Financial Reporting”, as issued by the International Accounting Standards Board (“IASB"). Accordingly, certain disclosures included in the Company’s annual consolidated financial statements prepared in accordance with IFRS Accounting Standards ("IFRS”) have been condensed or omitted. The accounting policies applied by the Company in these condensed consolidated interim financial statements are the same as those set out in the Company’s audited consolidated financial statements for the year ended December 31, 2025, except for those described below.

In preparing the unaudited condensed consolidated interim financial statements, management has made judgements, estimates and assumptions that affect the application of accounting policies and the reported amounts of assets and liabilities, revenue and expenses. Actual results may differ from these estimates. The critical judgements made by management in applying the Company’s accounting policies and the key sources of estimation uncertainty were the same as those applied and disclosed in the Company’s audited consolidated financial statements for the year ended December 31, 2025.

The unaudited condensed consolidated financial statements are presented in United States dollars ("US$", or “$”), which is the Company’s functional and presentation currency. The unaudited condensed consolidated financial statements were authorized for issuance by the Board of Directors of the Company, on May 14, 2026.

New accounting standards and amendments adopted

Classification and Measurement of Financial Instruments - Amendments to IFRS 9, Financial Instruments and IFRS 7, Financial Instruments: Disclosures

On May 30, 2024, the IASB issued narrow scope amendments to IFRS 9 “Financial Instruments” (“IFRS 9”) and IFRS 7. The amendments include the clarification of the date of initial recognition or derecognition of financial liabilities, including financial liabilities that are settled in cash using an electronic payment system. The amendments also introduce additional disclosure requirements to enhance
allied-goldxlogoxonxwhiteb.jpg | 8



transparency regarding investments in equity instruments designated at FVOCI and financial instruments with contingent features. The amendments were adopted on January 1, 2026, and did not have a significant impact on the Company’s financial statements.

Contracts Referencing Nature-Dependent Electricity - Amendments to IFRS 9, Financial Instruments and IFRS 7, Financial Instruments: Disclosures

On December 18, 2024, the IASB issued targeted amendments to IFRS 9 and IFRS 7 to help companies better report the financial effects of nature-dependent electricity contracts. The amendments clarify the factors an entity would consider when assessing whether a renewable electricity contract qualifies for the own-use exemption under IFRS 9, as well as hedge accounting requirements for when a renewable electricity contract is designated as the hedging instrument in a cash flow hedge of forecasted sales or purchases of electricity. The amendments were adopted on January 1, 2026. The Company does not currently have such contracts in effect and therefore the adoption of the amendment did not have a significant impact on the Company's financial statements.

New accounting standards and amendments to be adopted

IFRS 18, Presentation and Disclosures of Financial Statements.

In April 2024, the IASB issued IFRS 18, Presentation and Disclosures of Financial Statements (“IFRS 18”) with the aim of improving companies’ reporting of financial performance and giving investors a better basis for analyzing and comparing companies. IFRS 18 introduces three new sets of requirements:
Improved comparability in the statements of income which introduces three defined categories for income and expenses: operating, investing and financing. These changes would require all companies to use the same structure of the statements of income and provide new defined subtotals, including operating profit.
Enhanced transparency of management-defined performance measures which would require companies to disclose explanations of those company specific measures that are related to the income statement.
More useful grouping of information in the financial statements which provides enhanced guidance on how to organize information and whether to provide it in the primary financial statements or in the notes.

IFRS 18 is effective for annual reporting periods beginning on or after January 1, 2027. The Company is currently evaluating the impact of this new standard.

3.    OPERATING SEGMENTS

The Company operates in Côte d’Ivoire (Bonikro mine and Agbaou mine), Mali (Sadiola and Korali-Sud mines), Ethiopia (Kurmuk project) and has its Corporate office in Canada.

The following table provides the Company’s results by operating segment in the way information is provided to and used by the Company’s chief operating decision maker, being the Company's senior executive group, to make decisions about the allocation of resources to the segments and assess their performance. The Company considers each of its operational mines to be a separate segment, with the exception of the Bonikro and Hiré mining licenses and the Sadiola and Korali-Sud mining licenses, which each form a single segment due to the interrelationships in the operations of the mines and operate as the Bonikro and Sadiola mines, respectively. Corporate legal entities are aggregated and presented together as part of the "other" segment on the basis of them sharing similar economic characteristics at March 31, 2026.

allied-goldxlogoxonxwhiteb.jpg | 9



Three months ended March 31, 2026
Sadiola mineBonikro mineAgbaou mineTotal
Country of OperationMaliCôte d’IvoireCôte d’Ivoire
Revenue$189,700 $113,548 $90,862 $394,110 
Cost of sales, excluding DDA(116,954)(44,992)(41,313)(203,259)
DDA(4,797)(7,873)(7,253)(19,923)
Gross profit
$67,949 $60,683 $42,296 $170,928 
Site exploration and evaluation expenses$(3,392)$ $ $(3,392)
Corporate Adjustments
General and administrative expenses$(69,158)
Exploration and evaluation expense overhead$(226)
Loss on revaluation of financial instruments$(37,839)
Other losses$(2,527)
Net earnings before finance costs and income tax$57,786 
Finance costs$(5,798)
Net earnings before income tax$51,988 
Three months ended March 31, 2025
Sadiola mineBonikro mineAgbaou mineTotal
Country of OperationMaliCôte d’IvoireCôte d’Ivoire
Revenue$234,445 $60,224 $51,738 $346,407 
Cost of sales, excluding DDA(152,416)(29,218)(26,158)(207,792)
DDA(10,375)(6,799)(1,783)(18,957)
Gross profit
$71,654 $24,207 $23,797 $119,658 
Site exploration and evaluation expenses$(2,432)$(445)$(235)$(3,112)
Corporate Adjustments
General and administrative expenses$(18,852)
Exploration and evaluation expense overhead$(415)
Gain on revaluation of financial instruments$(14,116)
Other income$1,128 
Net earnings before finance costs and income tax$84,291 
Finance costs$(5,310)
Net loss before income tax$78,981 


Balances at March 31, 2026
Sadiola mineBonikro mineAgbaou mineKurmuk projectCorporate and otherTotal
Country of OperationMaliCôte d’IvoireCôte d’IvoireEthiopia
Current assets$299,616 $94,682 $120,160 $15,063 $218,883 $748,404 
Non-current assets(1)
351,110 218,223 71,483 823,326 32,211 1,496,353 
Total assets$650,726 $312,905 $191,643 $838,389 $251,094 $2,244,757 
 
Current liabilities$270,308 $119,574 $98,696 $79,687 $587,818 $1,156,083 
Non-current liabilities174,445 58,404 67,560 41,534 301,172 643,115 
Total liabilities$444,753 $177,978 $166,256 $121,221 $888,990 $1,799,198 
(1) Non-current assets are predominantly comprised of MPP&E
allied-goldxlogoxonxwhiteb.jpg | 10




Balances at December 31, 2025
Sadiola mineBonikro mineAgbaou mineKurmuk projectCorporate and otherTotal
Country of OperationMaliCôte d’IvoireCôte d’IvoireEthiopia
Current assets$295,796 $83,125 $104,782 $2,224 $277,782 $763,709 
Non-current assets(1)
322,691 226,925 70,371 707,685 32,298 1,359,970 
Total assets$618,487 $310,050 $175,153 $709,909 $310,080 $2,123,679 
  
Current liabilities$246,720 $105,528 $96,840 $68,224 $471,252 $988,564 
Non-current liabilities153,639 48,997 62,136 34,322 331,342 630,436 
Total liabilities$400,359 $154,525 $158,976 $102,546 $802,594 $1,619,000 
(1) Non-current assets are predominantly comprised of MPP&E

4.    REVENUE

For three months ended March 31,
2026
2025
Gold(1)
$393,070 $346,116 
Silver1,040 291 
Total sales revenue$394,110 $346,407 
(1) Approximately 77% of gold sales were to a single customer for the three months ended March 31, 2026 (89% for the three months ended March 31, 2025).

5.    COST OF SALES

For three months ended March 31,
2026
2025
Mine production costs$135,611 $159,694 
Royalties66,851 47,134 
Refining797 964 
Cost of sales, excluding DDA$203,259 $207,792 
DDA$19,923 $18,957 
Cost of sales$223,182 $226,749 
The amount of recoveries of inventories recognized in the period was $3.5 million ($3.8 million recovery for the three months ended March 31, 2025).

6.    GENERAL AND ADMINISTRATIVE

For three months ended March 31,

2026
2025
Salaries and related benefits(1)
$57,873 $11,346 
General and Administrative Expenses(2)
11,285 7,506 
Total general and administrative
$69,158 $18,852 
(1)Includes share-based compensation expense in the amount of $55.2 million for the three months ended March 31, 2026 ($4.1 million for the three months ended March 31, 2025).
(2) Includes professional and consulting fees, travel and lodging expenses, office and IT expenses, and depreciation for Corporate and other assets.

allied-goldxlogoxonxwhiteb.jpg | 11



7.    OTHER LOSSES (GAINS)

For three months ended March 31,

2026
2025
Corporate development and transaction related costs2,200 3,540 
Gain on distribution of dividend-in-kind (note 10)
 (14,491)
Other losses(1)
327 9,823 
Total other losses (gains)
$2,527 $(1,128)
(1) Comprises a variety of items that are individually insignificant.


8.    FINANCE COSTS

For three months ended March 31,
2026
2025
Interest expenses from financial liabilities
Borrowings (note 17)
$2,347 $2,315 
Accretion on deferred and contingent consideration (note 21)
1,206 1,024 
Other finance costs
Accretion of environmental obligations778 712 
Financing component of streaming arrangements (note 16)
10,762 5,412 
Other interest expense (income)338 (212)
Foreign exchange3,427 3,043 
Borrowing costs capitalized(1)
(13,060)(6,984)
Total finance costs$5,798 $5,310 
(1) Borrowing costs have been capitalized and allocated mostly to the development of Kurmuk, with an immaterial amount allocated to Sadiola Phase 1 expansion. The weighted average borrowing rate used for the capitalization was 10.1% for the period ended March 31, 2026 (2024 - 10.7%).


9.    EARNINGS (LOSS) PER SHARE

Basic (loss) earnings per share and the reconciliation of the number of shares used to calculate basic and diluted (loss) earnings per share are as follows:

For three months ended March 31,
2026
2025
Net (loss) earnings attributable to shareholders of the Company
$(58,326)$15,124 
  
Weighted average shares issued and outstanding post-consolidation(1)
125,343,326 109,629,216 
Weighted-average shares outstanding – basic125,343,326 109,629,216 
Effect of dilutive share-based payment arrangements 10,248,107 
Weighted-average shares outstanding – diluted125,343,326 119,877,323 
 
Basic (loss) earnings per share
$(0.47)$0.14 
Diluted (loss) earnings per share
$(0.47)$0.13 
(1)Share amounts have been adjusted to reflect the effect of the 3:1 share consolidation that took place on May 20, 2025, unless otherwise noted.

allied-goldxlogoxonxwhiteb.jpg | 12



For the three months ended March 31, 2026, 4,578,818 units related to share-based payment arrangements and 6,176,052 units related to the convertible debenture were not included in the calculation as their effect would be anti-dilutive (March 31, 2025 - 2,191,812 units related to share-based payment arrangements and 6,176,052 units related to the convertible debenture).


10.    NON-CONTROLLING INTERESTS

The movement in the non-controlling interests balance for the three months ended March 31, 2026 are as follows:

Balance at January 1, 2025
$70,532 
Recognition of minority shareholder(2,312)
Dividend in-kind paid to minority shareholder(23,896)
Dividend paid to minority shareholder(2,408)
Share of profit for the period
55,154 
Balance at December 31, 2025
$97,070 
Share of profit for the period
13,862 
Balance at March 31, 2026
$110,932 

Non-controlling interests represent the 10.11% ownership of the Bonikro mine and 15% of the Agbaou mine by the Government of Côte d'Ivoire and 20% of the Sadiola mine, owned by the Government of Mali. As of December 31, 2024, the Company's ownership of Korali-Sud was 100%; however, the Company's ownership was reduced to 65% on January 8, 2025 in association with the 2023 Mining Code. During the fourth quarter of 2024, a $37.2 million gross intercompany dividend was declared for distribution, from which $6.7 million was accrued as at December 31, 2024 and paid to the Government of Mali on January 30, 2025.

In connection with the definitive protocol agreement signed with the Government of Mali during the third quarter of 2024, the Company’s Korali-Sud mine and related assets were transferred to a new entity, Korali S.A., incorporated on January 8, 2025, and 35% of the ownership interests in the new entity were issued to the Government of Mali. The issuance of shares is considered a share-based payment in exchange for the issuance of a definitive exploitation permit for large-scale mining and processing of ore mined at Korali at the Sadiola Plant, which is valued with reference to the fair value of $5.5 million of the shares of Korali S.A. granted. In arriving at the fair value of the shares issued, the Company valued working capital assets and liabilities at cost and valued the inventory and fixed assets using a discounted cash flow model incorporating significant assumptions that included such factors as mineable mineralization including resources, future production levels, operating and capital costs, gold prices ranging from $2,551 to $2,598 per ounce, and a discount rate of 13.9%.

The NCI was recognized at the proportional share of the identifiable net assets of Korali S.A. of negative $2.3 million. The difference of $7.8 million between the value of the exploitation permit received capitalized to the cost of the Korali mine and the value of the NCI was recognized in retained earnings. Due to the life of the mine, the entire $5.5 million of the cost capitalized for this permit was recognized as depletion expense during 2025.

On January 8, 2025, the Government of Mali requested that 280 kg of gold be transferred to the state, which was treated as an advance against future dividends payable under the terms of the 2023 Mining Code. Control over the gold was transferred on February 18, 2025 and had a carrying value of $9.4 million. The fair value of the distribution was $23.9 million, which is equal to the value of the dividend paid in-kind, resulting in a gain on distribution of dividend-in-kind of $14.5 million, recognized under Other gains and losses (note 7).










allied-goldxlogoxonxwhiteb.jpg | 13



11.    FINANCIAL INSTRUMENTS

Financial assets at amortized cost

Current
As at March 31, 2026
As at December 31, 2025
Cash and cash equivalents$424,200 $479,777 
Restricted cash(1)
16,966 17,109 
Trade and other receivables21,244 17,482 
Total$462,410 $514,368 
(1) The Company has cash in separate restricted accounts to comply with environmental matters in Cote d’Ivoire.

Fair value of derivatives

Hedge derivatives

On December 19, 2024, the Company entered into zero-cost collars to hedge the price on gold production of 10,000 ounces per month, beginning April 2025 through to December 2026, for a total of 210,000 ounces, at an average put and call strike price of $2,200 per ounce and $3,125 per ounce, respectively. On May 6, 2025, the Company entered into additional zero-cost collars to hedge the price on gold production of 15,500 ounces per month beginning in June 2025 and ending in March 2026 at an average call and strike price of $3,048 and $4,000 per ounce. As of March 31, 2026, 90,000 ounces of gold collars remain unsettled. These hedges result in cash inflows or outflows only when the underlying LBMA gold price is below the collar floor, or above the collar ceiling, respectively, at the time of settlement. These contract are expected to settle over time by the end of 2026.

The aggregate fair value of the position as of March 31, 2026 was a $174.3 million liability (March 31, 2025 - $49.5 million liability), which is current. The fair value of zero-cost collar contracts was determined based on gold future forward prices.

The gold collar contracts are designated as cash flow hedging instruments, with the effective portion of changes in fair value recognized in other comprehensive income, net of tax. Any ineffective portion of a hedge relationship is recognized immediately in the condensed consolidated interim statement of (loss) earnings.

Non-hedge derivatives

On October 29, 2025, the Company purchased average rate gold call options with a strike price of $4,500 per ounce, for the period of November 2025 to December 2026, for a total of 217,500 ounces. The call options effectively mitigate the cash outflow on the hedge derivatives when gold exceeds $4,500. The total premium is $20.5 million, paid on a monthly deferred basis. The gold call options have not been designated as hedging instruments. As of March 31, 2026, 90,000 ounces of gold call options remain unsettled.

The aggregate fair value of the position as of March 31, 2026 was a $38.6 million current asset included in Derivative financial assets (December 31, 2025 - $26.7 million). The fair value of the gold call options was determined based on future forward prices.

Financial liabilities at amortized cost

As at March 31, 2026
As at December 31, 2025
Trade and other payables$409,828 $373,193 
Deferred consideration - Kurmuk21,250 21,250 
Deferred consideration - Korali-Sud1,000 1,000 
Lease liabilities32,164 15,462 
Total $464,242 $410,905 

allied-goldxlogoxonxwhiteb.jpg | 14



Financial liabilities at fair value through profit or loss

As at March 31, 2026
As at December 31, 2025
Borrowings$214,558 $154,312 
Contingent consideration - Sadiola36,497 35,291 
Contingent consideration - Agbaou17,406 17,482 
Total $268,461 $207,085 

Fair value measurement

All assets and liabilities for which fair value is measured or disclosed in the consolidated financial statements are categorized within the fair value hierarchy based on the lowest level input that is significant to the fair value measurement as a whole:

Level 1 – Unadjusted quoted prices in active markets for identical assets or liabilities;
Level 2 – Quoted prices in markets that are not active or inputs that are observable, either directly or indirectly, for substantially the full term of the asset or liability; and
Level 3 – Prices or valuation techniques that require inputs that are both significant to the fair value measurement and unobservable (supported by little or no market activity).

The fair value hierarchy gives the highest priority to Level 1 inputs and the lowest priority to Level 3 inputs.

Assets and liabilities measured at fair value on a recurring basis

For financial assets and liabilities for which fair value is measured or disclosed on a recurring basis, the Company assesses their classification at each reporting date and determines whether there have been any transfers between fair value hierarchy levels during the period.

During the quarter ended March 31, 2026 there were no transfers between categories.

The fair values of cash and cash equivalents, trade and other receivables, and trade and other payables approximate their carrying values due to their short-term nature.

As at March 31, 2026, the Company's financial assets and liabilities measured at fair value on a recurring basis using the fair value hierarchy were as follows:

Fair value
Carrying amountLevel 1Level 2Level 3
Financial assets:
Restricted cash16,966 16,966   
Derivative financial asset38,570  38,570  
Total financial assets55,536 16,966 38,570  
Financial liabilities
Derivative financial liability174,333  174,333  
Deferred consideration - Kurmuk (Note 21)21,250   21,250 
Deferred consideration - Korali-Sud (Note 21)1,000   1,000 
Borrowings (Note 17)214,558 214,558   
Contingent consideration - Sadiola (Note 21)36,497   36,497 
Contingent consideration - Agbaou (Note 21)17,406   17,406 
Total financial liabilities465,044 214,558 174,333 76,153 


allied-goldxlogoxonxwhiteb.jpg | 15



As at December 31, 2025, the Company's financial assets and liabilities measured at fair value on a recurring basis using the fair value hierarchy were as follows:

Fair value
Carrying amountLevel 1Level 2Level 3
Financial assets:
Restricted cash17,109 17,109   
Derivative financial asset26,703  26,703  
Total financial assets43,812 17,109 26,703  
Financial liabilities
Derivative financial liability167,260  167,260  
Deferred consideration - Kurmuk (Note 21)21,250   21,250 
Deferred consideration - Korali-Sud (Note 21)1,000   1,000 
Borrowings (Note 17)154,312 154,312   
Contingent consideration - Sadiola (Note 21)35,291   35,291 
Contingent consideration - Agbaou (Note 21)17,482   17,482 
Total financial liabilities396,595 154,312 167,260 75,023 


12.    TRADE RECEIVABLES, PREPAYMENTS AND OTHER RECEIVABLES

Current
As at March 31, 2026
As at December 31, 2025
Trade and other receivables$21,244 $17,482 
VAT receivable66,079 56,803 
Prepayments44,033 42,808 
Total current trade receivables, prepayments, and other receivables$131,356 $117,093 

Non-current
As at March 31, 2026
As at December 31, 2025
VAT receivable37,652 28,798 
Total non-current trade receivables, prepayments, and other receivables$37,652 $28,798 

The carrying value of trade and other receivables approximate their fair value.














allied-goldxlogoxonxwhiteb.jpg | 16



13.    INVENTORIES

Current
As at March 31, 2026
As at December 31, 2025
Doré bars(1)
$14,741 $17,612 
Ore stockpiles and gold in circuit98,148 75,872 
Material and supplies41,389 46,652 
Total current inventories$154,278 $140,136 

Non-current
As at March 31, 2026
As at December 31, 2025
Ore stockpiles$78,296 $70,056 
Total non-current inventories$78,296 $70,056 
(1) In the first quarter of 2025, the Company delivered 48,939 ounces of gold from Korali-Sud that were inventoried at the Sadiola mine. These ounces include, in association with the establishment of Korali S.A., an advance to the Government of Mali of future dividends from the entity, in the form of gold, equal to 8,154 ounces.

Inventories are held at lower of cost or net realizable value.

In the three months ended March 31, 2026 inventories recognized as an expense within cost of sales amounted to $153.6 million (March 31, 2025: $170.2 million).


14.    MINERAL PROPERTY, PLANT AND EQUIPMENT

Land, building, plant & equipment (2)
Operating mine mineral interestsDevelopment projects and Exploration & evaluationTotal
Cost
As at January 1, 2026
$483,120 $198,758 $815,126 $1,497,004 
Additions 35,234 — 106,525 141,759 
At March 31, 2026
$518,354 $198,758 $921,651 $1,638,763 
Accumulated depreciation and amortization and impairment
At January 1, 2026
$(190,541)$(65,833)$— $(256,374)
DDA(17,989)(1,933)— (19,922)
At March 31, 2026
(208,530)(67,766) (276,296)
Carrying amount, at March 31, 2026 (1)
$309,824 $130,992 $921,651 $1,362,467 
Amounts included above as at March 31, 2026
Exploration and evaluation assets$— $— $9,772 $9,772 
Assets under construction$— $— $911,880 $911,880 
(1) Includes $13.1 million in borrowing costs capitalized as at March 31, 2026, allocated mainly to Kurmuk project.
(2) Inclusive of right-of-use assets with a carrying value of $39.0 million as at March 31, 2026, and a depreciation expense of $3.8 million.

allied-goldxlogoxonxwhiteb.jpg | 17



Land, building, plant & equipment (2)
Operating mine mineral interestsDevelopment projects and Exploration & evaluationTotal
Cost
As at January 1, 2025
$364,922 $178,199 $437,155 $980,276 
Additions 26,119 — 436,696 462,815 
Transfers54,568 20,559 (75,127)— 
Environmental obligations, change of estimate37,511 — 16,402 53,913 
At December 31, 2025
$483,120 $198,758 $815,126 $1,497,004 
Accumulated depreciation and amortization and impairment
At January 1, 2025
$(137,439)$(47,192)$— $(184,631)
DDA(53,102)(18,641)— (71,743)
At December 31, 2025
(190,541)(65,833)— (256,374)
Carrying amount, December 31, 2025 (1)
$292,579 $132,925 $815,126 $1,240,630 
Amounts included above as at December 31, 2025
Exploration and evaluation assets$— $— $6,278 6,278 
Assets under construction$— $— $808,849 $808,849 
1) Includes $36.6 million in borrowing costs capitalized as of December 31, 2025, allocated mainly to Kurmuk project, and an immaterial balance to the Sadiola expansion project.
(2) Inclusive of right-of-use assets with a carrying value of $18.0 million as at December 31, 2025, and a depreciation expense of $11.1 million.

Operating mine mineral interests represents the fair value of acquired mines and is amortized on a unit of production basis.

The costs of exploration and evaluation assets are not subject to amortization until production has commenced.

15.    TRADE AND OTHER PAYABLES

As at March 31, 2026
As at December 31, 2025
Trade payables151,580 118,378 
Other payables and accrued expenses(1)(2)
171,563 164,850 
Royalties86,685 89,965 
Total trade and other payables
$409,828 $373,193 
(1) As of March 31, 2026, Other payables include $19.8 million of PSU liabilities and $5.5 million of DSU liabilities, discussed in note 20.

















allied-goldxlogoxonxwhiteb.jpg | 18



16.    DEFERRED REVENUE

Stream arrangements
Gold prepays and advance sales (2)
Total
At January 1, 2026$237,082 $159,718 $396,800 
Cash received2,761  2,761 
Amount recognized as revenue(9,154)(25,000)(34,154)
Accrued interest(1)
7,295 3,467 10,762 
As March 31, 2026
$237,984 $138,185 $376,169 
Current balance$5,616 $71,265 $76,881 
Non-current balance$232,368 $66,920 $299,288 

Stream arrangements
Gold prepays and advance sales (2)
Total
At January 1, 2025$105,418 $100,000 $205,418 
Cash received135,751 150,000 285,751 
Amount recognized as revenue(20,896)(100,000)(120,896)
Accrued interest(1)
16,809 9,718 26,527 
At December 31, 2025$237,082 $159,718 $396,800 
Current balance$7,621 $59,806 $67,427 
Non-current balance$229,461 $99,912 $329,373 
(1) As of March 31, 2026, $7.3 million (December 31, 2025 - $16.8 million) of accrued interest from stream arrangements has been capitalized, in accordance with IAS 23 - Borrowing Costs.
(2) As of March 31, 2026, comprises $125.0 million of gold prepays and advance sales. (December 31, 2025 - $150.0 million of gold prepays and advance sales).


allied-goldxlogoxonxwhiteb.jpg | 19



Stream Arrangements

On October 10, 2019 the Company entered into a streaming agreement, currently held by Royal Gold Inc. (“Royal Gold”). Under this agreement, the counterparty has the right to purchase certain quantities of gold at a fixed price of US$400/ounce. Royal Gold has the right to purchase 6% of the first 650,000 ounces of production at the Bonikro mine (39,000 ounces). Subsequently, they may purchase up to 3.5% of each lot between 650,000 ounces and 1,300,000 ounces of refined gold (a further 22,750 ounces and 61,750 ounces inclusive), up to 2% of each lot thereafter.

On August 7, 2024, the Company entered into a streaming transaction with Triple Flag International Ltd., a wholly-owned subsidiary of Triple Flag Precious Metals Corp. (collectively, “Triple Flag”). Under the terms of the agreement, the Company received a $53.0 million upfront cash payment on August 14, 2024 and will receive an ongoing payment equal to 10% of the spot gold price. Triple Flag will have the right to purchase 3% of the payable gold produced at each of the Agbaou and Bonikro mines, subject to a step-down to 2% after set delivery thresholds. Costs incurred in the transaction total $1.9 million.

On December 5, 2024, the Company entered into a streaming transaction with Wheaton Precious Metals International Ltd. ("WPMI"), a wholly-owned subsidiary of Wheaton Precious Metals Corp. Under the terms of the streaming agreement, the Company will receive an aggregate $175.0 million upfront cash payment to support the funding of the development of the Kurmuk project. WPMI will have the right to purchase 6.7% of payable gold from the Kurmuk mine. The gold stream rate will step down to 4.8% of payable gold after the delivery of 220,000 ounces of gold. WPMI will make ongoing payments of 15% of the spot gold price for each ounce delivered under the stream. The stream will cover the existing Kurmuk mining license and until 255,000 ounces of gold have been delivered to WPMI. On December 19, 2024, the Company met the conditions to withdraw the first of four planned payments of $43.8 million each. The three additional planned withdraws were completed on June 30, September 16, and December 15, 2025.

The stream arrangements have been accounted for as deferred revenue, as the upfront payments pertain to future production. As such, revenue is recognized as the services are performed for the counterparty, reducing the unearned deferred revenue balance. The streams contain an intrinsic financing component, which has been valued as part of the subsequent measurement of the deferred revenue stream. The Company estimated the financing component to be 24.99% for the Royal Gold stream, 9.98% for the Triple Flag stream, and 12.02% for the Wheaton stream.

As of March 31, 2026, accrued interest of $0.8 million, $0.9 million and $5.6 million has been calculated for the Royal Gold, Triple Flag and WPMI stream agreements, respectively. The amount of revenue recognized for the Royal Gold agreement is $3.4 million, out of which $1.1 million is on a cash basis (at $400 per ounce) while the remainder is non-cash (amortization of deferred revenue). For the Triple Flag agreement, the Company recognized revenue in the amount of $5.7 million, out of which $1.7 million is on a cash basis while the remainder is non-cash amortization of deferred revenue.

Gold prepays and advance sales

On December 19, 2024, the Company entered into a gold prepaid forward arrangement with select lenders, for a total advance of $75.0 million. Under the arrangement, the Company will deliver to the lenders an aggregate of 2,802 ounces of gold per month over a period of twelve months, starting in October 2026. The Company estimated the financing component for this arrangement to be 11.0%. As of March 31, 2026, accrued interest of $3.5 million has been calculated for this gold prepay forward arrangement.

On December 20, 2024 the Company entered into an advance sale agreement to deliver 9,613 ounces of gold at a price of $2,601 per ounce, for a total of $25.0 million. The advance sale was recognized as deferred revenue, and presented as current. Delivery of the gold was completed on January 21, 2025.

On September 25, 2025, the Company entered into an advance sale forward agreement with select lenders, for a total advance of $50.0 million. Under the arrangement, the Company will deliver an aggregate of 1,233 ounces of gold per month over a period of twelve months, starting in October 2026. The advance sale was recognized as deferred revenue and presented as non-current. The Company estimated the financing component for this arrangement to be 9.8%.

On December 24, 2025 the Company entered into an advance sale agreement to deliver 5,713 ounces of gold at a price of $4,376 per ounce, for a total of $25.0 million. The advance sale was recognized as deferred revenue, and presented as current. Delivery of the gold was completed on January 21, 2026.

The gold prepays and advance sales have been accounted for as deferred revenue, as the upfront payments pertain to future production. As such, revenue is recognized as the services are performed for the counterparty, reducing the unearned deferred revenue balance.
allied-goldxlogoxonxwhiteb.jpg | 20




17.    BORROWINGS

Convertible Debenture
Borrowings - January 1, 2025
$96,356 
Change in fair value of debt57,956 
Borrowings - December 31, 2025
$154,312 
Change in fair value of debt60,246 
Borrowings - March 31, 2026
$214,558 

Convertible Debentures

On August 30, 2023, the Company issued 107,279 convertible debentures at a price of $1,000 per unit. Each convertible debenture entitled the holder to receive one unsecured convertible debenture of AMC, which was subsequently exchanged for one unsecured convertible debenture of the Company on an economically equivalent basis on September 7, 2023. The convertible debentures bear interest at 8.75% annually, payable semi-annually on September 30 and March 31 of each year, and a maturity date of 5 years. The Company incurred $5.3 million in costs related to this transaction.

The debentures are convertible at the holder's option into the Company's shares at any time during their five-year tenure at a price of $17.37 per share (“Conversion Price”). The Company has the right to force the conversion of all of the principal amount of the convertible debentures into common shares at the Conversion Price at any time after three years from the date of issuance, provided that the current market price is not less than 115% of the Conversion Price. The convertible debentures also contain embedded derivatives, including the right for conversion and the right to repay the principal amount in common shares upon maturity.

Using readily observable inputs from the market, the fair value of the convertible debentures as at March 31, 2026, was determined to be $214.6 million, net of $nil interest payable. The total fair value loss of $60.3 million includes a $17.1 million loss from the change in credit risk conditions, recorded in OCI, and a $43.2 million loss from the change in option value and market conditions recorded in the condensed consolidated interim statement of (loss) earnings for the period ended March 31, 2025.

Credit Facility

On December 18, 2024, the Company executed a credit facility for $40.0 million, plus an additional $10.0 million accordion, for a total of $50 million and a three-year term. The Company expects to use the funds for financial flexibility and general business purposes. Interest rates are determined based on the leverage ratio, ranging between 350 basis points ("bps") and 450 bps Secured Overnight Financing Rate ("SOFR") Loan or between 250 bps and 350 bps Canadian Prime Loan or Base Rate Loan, with a standby fee of between 87.5 bps and 112.5 bps.

The facility is subject to customary covenants and is secured by assets of the Company and its material subsidiaries. It contains certain financial covenants that include (a) a minimum interest coverage ratio; (b) a maximum net leverage ratio; and (c) a minimum liquidity level. As at March 31, 2026, the Company is in compliance with the covenants.

No funds have been withdrawn from the facility.

18.    LEASE OBLIGATIONS

Current and non-current lease liabilities as at March 31, 2026 are presented below:

As at March 31, 2026
As at December 31, 2025
Current lease liabilities$7,854 $2,999 
Non-current lease liabilities24,310 12,463 
Total$32,164 $15,462 

allied-goldxlogoxonxwhiteb.jpg | 21



On November 3, 2023 the Company signed a lease agreement for its Toronto head office, which can be extended. The net present value of the lease obligation and the right-of-use asset was estimated at $2.7 million, using a 9.30% discount rate.

On May 16, 2024, the Company entered into a contract to lease twenty-one generators for the Bonikro and Agbaou mines over a three year term. The net present value of the lease obligation was estimated at $14.2 million, using an 8.07% discount rate. The generators were commissioned on June 11, 2024. The Company incurred additional costs of $14.9 million to bring the generators to use, resulting in the recognition of a right-of use asset of $28.4 million, with $14.9 million and $13.5 million allocated to Bonikro and Agbaou, respectively.

During the fourth quarter of 2024, the Company entered into contract mining agreements for Sadiola, Bonikro and Agbaou; while the contract mining agreement with Kurmuk was signed on March 1, 2025. As disclosed in Note 5 - Critical judgements and estimations uncertainties, in the Company’s audited consolidated financial statements for the year ended December 31, 2025, management has concluded that while the arrangements contain a lease, due to the variable nature of the payments, there was no lease amount to measure for the lease liability. The total variable cost incurred during 2026 related to those mining service agreements was $67.1 million ($45.1 million at March 31, 2025).

During the quarter ended March 31, 2026, the Company entered into lease arrangements resulting in right-of-use additions of $24.7 million and lease obligation additions of $18.2 million with a weighted average discount rate of 14.4% (for the quarter ended March 31, 2025, there were no additions).

During the quarter ended March 31, 2026, the Company recognized $0.5 million in interest expense, included in Finance costs arising from lease liabilities (for the quarter ended March 31, 2025, $0.1 million).

19.    SHARE CAPITAL

Number of Common Shares (2)
Share Capital
As at January 1, 2025109,629,215 $587,119 
Shares issued for RSUs vested739,988 $8,679 
Shares issued for payment of Kurmuk deferred consideration1,474,882 $21,250 
Shares issued in public offering (1)
12,893,136 $196,307 
As at December 31, 2025124,737,221 $813,355 
Shares issued for RSUs vested1,144,008 $11,638 
 As at March 31, 2026
125,881,229 $824,993 
(1)Net of transaction costs incurred of $10.1 million.
(2) Shares issued prior to May 20, 2025, have been retrospectively adjusted for the impact of the 3 to 1 share consolidation ratio.

The Company's authorized share capital includes an unlimited number of common shares with no par value.

On April 22, 2025, and May 1, 2025 the Company closed an underwriting agreement, and an over-allotment option, respectively, pursuant to which the underwriters agreed to purchase, on a bought deal basis, an aggregate of 17,250,000 common shares at a price of C$5.35 per share for aggregate gross proceeds of $66.8 million (C$92.3 million). The cost of this transaction was $2.8 million, therefore net proceeds were $64.0 million.

On October 20, 2025, the Company filed a prospectus supplement related to an overnight marketed equity offering. Pursuant to this offering, 7,143,200 common shares were issued at a price of C$27.35 per share for gross proceeds of approximately $139.6 million (CAD$195.3 million) and net proceeds of approximately $134.0 million (CAD$187.4 million).





allied-goldxlogoxonxwhiteb.jpg | 22



20.    SHARE-BASED EXPENSE

Share-based payment reserve

As at March 31, 2026
As at December 31, 2025
Opening balance$30,914 $8,492 
Charge for the period
9,507 30,727 
Share-based payments settled in the period
(11,638)(8,305)
Closing balance$28,783 $30,914 

Stock option units ("Stock options')Restricted share units ("RSU")Deferred share units ("DSU")Performance share units ("PSU")
Outstanding units, January 1, 2025199,998 1,174,874 39,817 — 
Granted2,154,500 2,891,940 138,186 3,427,156 
Settled— (749,346)— — 
Closing balance, December 31, 20252,354,498 3,317,468 178,003 3,427,156 
Granted— 50,860 — — 
Forfeited/expired— — — (446,970)
Settled— (1,144,008)— (304,658)
Closing balance, March 31, 2026
2,354,498 2,224,320 178,003 2,675,528 
The stock option, RSU, DSU, and PSU amounts have been adjusted to reflect the effect of the 3:1 share consolidation that took place on May 20, 2025, unless otherwise noted.

Stock Options

On September 7, 2023, the Company adopted a plan providing for the grant of stock options to directors, senior officers or employees of the Company to purchase common shares. Stock options are granted at the weighted average trading price for the 5 consecutive trading days immediately prior to the relevant date. Vesting and term conditions are determined at the discretion of the Board.

The Board authorized a maximum of 5% of the total number of shares outstanding be issuable under the plan. The number of securities issuable to insiders, at any time, under all Share Compensation Arrangements, shall not exceed 10% of the issued and outstanding securities and that the number of securities issued to insiders, within any one-year period, under all Share Compensation Arrangements, shall not exceed 10% of the issued and outstanding securities. In the event of a change of control, all vested stock options may be exercised and the holder shall receive the securities, property or cash that they would have been entitled to had they exercised the options immediately prior to the change of control, unless the directors of the Company determine a different basis for the exercise of options. In connection with the proposed acquisition of the Company (see Note 1), under the terms of the agreement, all outstanding options would vest, be exercised and a payment calculated based on the difference in the acquisition share price and strike price of the options would be paid to all option holders.

On September 8, 2023, the Company granted 199,998 stock options to certain directors, with a three-year, equal annual tranche vesting period and an expiration term of 7 years. Using a Black-Scholes valuation model, the options were valued at CAD$8.82 per option, using an exercise price of CAD$17.61 per share, volatility of 38%, 0% expected dividend yield, expected life of 7 years, and a 4% interest rate. As of March 31, 2026, the remaining contractual life of these options was 4.4 years and 133,332 of these options were exercisable (2025 - 133,332).

On December 16, 2025, 2,154,500 options were issued to directors and senior management personnel, with a three-year, equal annual tranche vesting period and an expiration term of 7 years. Using a Black-Scholes valuation model, the options were valued at CAD$18.94 per option, using an exercise price of CAD$31.11 per share, volatility of 59% determined based on the Company's share price history, 0%
allied-goldxlogoxonxwhiteb.jpg | 23



expected dividend yield, expected life of 7 years, and a 3% risk-free interest rate. As of March 31, 2026, the remaining contractual life of these options was 6.7 years and none of these options were exercisable.

For the period ended March 31, 2026, the Company recorded $4.4 million share-based expense for stock options (for the year ended March 31, 2025, $0.1 million).


Restricted Shares Units (“RSUs”)

On September 7, 2023, the Company adopted a plan providing for the payment of bonuses in the form of the acquisition of Shares or, at the option of the Company, cash by participants for the purpose of advancing the interests of the Company through the motivation, attraction and retention of eligible employees and eligible contractors. A maximum of 5,850,232 shares (17,550,697 pre 3:1 consolidation basis) are issuable under the Plan. Vesting and term conditions are determined at the discretion of the Board. In the event of a change of control, all RSUs outstanding shall immediately vest and be payable in cash on the date immediately prior to the change of control, regardless of the restricted period. The payment shall be in an amount equal to the market value of the shares underlying the RSU calculated as at the date that is two business days prior to the change of control.

DateRSUs grantedRSUs outstandingGrant priceVesting conditions and other matters
September 7, 20231,191,211 1,141,265 
$13.35
67,425 units vesting in equal tranches over three years and 1,123,786 units vesting on third anniversary.
November 9, 2023305,000 — 
$8.94 (CAD$12.33)
Vesting in equal tranches over three years. Accelerated. (1)
August 8, 202416,125 10,750 
$6.20 (CAD$8.50)
Vesting in equal tranches over three years.
January 21, 2025816,943 354,781 
$7.10 (CAD$10.17)
Vesting 50% on first anniversary, 25% tranches vesting each on second and third anniversaries.
April 13, 20252,075,000 666,664 
$12.01 (CAD$16.68)
Vesting in equal tranches on November 24, 2025, February 24, 2026 and May 26, 2026
February 25, 202650,860 50,860 $31.57 (CAD$43.17)
Vesting in equal tranches over three years.
Total4,455,139 2,224,320 
(1)On September 9, 2024, the Board approved the immediate vesting of these RSUs and corresponding shares issuance. Out of the total charge for the period noted above, the Company capitalized the total accelerated expense of this RSU grant to the Kurmuk project, for $2.7 million.

On February 25, 2026, the Company granted 50,860 RSUs at a price of $31.57 (CAD$43.17) to officers and directors. The units vest in three equal tranches on December 16 of 2026, 2027 and 2028.

During the quarter ended March 31, 2026, 86,269 RSUs with a value of $0.9 million were accelerated due to a retirement, resulting in the recognition of an accelerated expense of $0.3 million.

For the period ended March 31, 2026, the Company recorded $5.1 million share-based compensation expense and has 2,224,320 RSUs outstanding (period ended March 31, 2025 - $2.2 million).

Deferred Share Units ("DSUs")

To align interests between eligible directors and the shareholders of the Company, a DSU plan was adopted on September 7, 2023, providing eligible directors the ability to elect to be paid a portion of annual director compensation in DSUs. Eligible officers can elect to be paid their long term incentive compensation in DSUs. In the event of a change of control, all DSUs outstanding become payable once the holder ceases to be a director or officer of the Company.

allied-goldxlogoxonxwhiteb.jpg | 24



DateDSUs granted and outstandingGrant date price
April 16, 20246,768 
$8.70 (CAD$11.79)
May 21, 202411,011 
$6.72 (CAD$9.15)
August 15, 202410,805 
$6.84 (CAD$9.39)
November 14, 202411,232 
$6.60 (CAD$9.21)
April 2, 20259,812 
$10.37 (CAD$14.85)
May 14, 202514,277 
$11.66 (CAD$16.29)
August 13, 202513,964 
$11.92 (CAD$16.39)
November 12, 202510,134 
$16.48 (CAD$23.10)
December 16, 202590,000 
$22.59 (CAD$31.11)
Total178,003 

For the period ended March 31, 2026, the Company recorded $1.4 million share-based compensation expense from the DSUs granted in the year (2025 - $0.1 million). As of March 31, 2026, $5.5 million of DSU liabilities are included in other payables (refer to note 15).

Performance Share Units ("PSUs")

On September 7, 2023, the Company adopted a plan to provide additional rewards to senior management for services performed and to promote a greater alignment of interest between senior management and shareholders of the Company. The Plan is administered by the Board of Directors, through a Compensation Committee, which determines specific in regards to the value of the PSUs, the vesting period and the performance indicator on which the issuance is based. Under the terms of the plan, in the event of a change of control, all outstanding PSUs vest and become payable immediately on the date prior to the change of control, regardless of their stated performance periods.

On January 21, 2025, the Company issued 1,084,656 PSUs at a price of $7.11 (CAD$10.17), with a two-year vesting period ending on December 31, 2026, to eligible senior management, to be settled in cash in an amount based on the Company's common share price and a multiplier based on the relative value of the Company's common share price in relation to the S&P Global Gold index (the "index").

On December 16, 2025, the Company issued 2,342,500 PSUs at a price of $22.60 (CAD$31.11) to eligible senior management to be settled in cash in an amount based on the growth of the Company's common share price on maturity and a multiplier based on the growth of the Company's common share price in comparison with that of the share prices of the constituents of the S&P/TMX Global Gold Index. The PSUs vest on the earlier of December 14, 2028, a three year time frame, or, should the Company's shares trade on the TSX at a price 40% above the initial price for 4 months, maturity will be at the end of that four month period. Further, for approximately 75% of the units the maximum payable will be limited to a payment of 62.5% of the total payable amount otherwise, unless the share price increase is equal to or greater than 80% from the initial price. Based on management's judgement and statistical modelling, December 14, 2028 was determined to be the most probable maturity date as of the date of grant and is therefore used as the vesting date for accounting purposes.

On February 18, 2026, the Company accelerated 304,658 units granted on January 21, 2025, resulting in an accelerated expense of $10.4 million and the recognition of $24.1 million in Trade and other payables. Furthermore, the Company approved the conversion of 750,000 units of the December 16, 2025 grant subjected to the 62.5% payout limiter to 303,030 units without the 62.5% limiter, resulting in the net cancellation of 446,970 units.

As of March 31, 2026, the Company recognized $43.9 million expense from stock based compensation related to PSUs (2025 - $1.8 million). As of March 31, 2026, the fair value of PSUs outstanding of $19.8 million was included in other payables (refer to note 15).








allied-goldxlogoxonxwhiteb.jpg | 25




21.    DEFERRED AND CONTINGENT CONSIDERATION

As part of previously completed acquisitions of Agbaou and Sadiola mines, including Korali-Sud, and the remaining interest in Kurmuk, the Company has recorded deferred and contingent consideration payable to the various sellers in post-acquisition years as follows:

For three months ended March 31, 2026
Sadiola mine Agbaou mineKurmuk projectKorali-Sud projectTotal
Opening balance, January 1, 2026$35,291 $17,482 $21,250 $1,000 $75,023 
Accretion1,206 — — — 1,206 
Revaluation— 2,250 — — 2,250 
Balance Payable— (1,116)— — (1,116)
Payments— (1,210)— — (1,210)
Closing balance$36,497 $17,406 $21,250 $1,000 $76,153 
Current$— $8,071 $21,250 $1,000 $30,321 
Non-current36,497 9,335 — — 45,832 
Total deferred and contingent consideration$36,497 $17,406 $21,250 $1,000 $76,153 

For the year ended December 31, 2025Sadiola mine Agbaou mineKurmuk projectKorali-Sud projectTotal
Opening balance, January 1, 2025$31,698 $20,013 $38,267 $1,000 $90,978 
Accretion6,093 — 4,233 — 10,326 
Revaluation— 3,639 — — 3,639 
Balance Payable— (1,210)— — (1,210)
Payments(2,500)(4,960)(21,250)— (28,710)
Closing balance$35,291 $17,482 $21,250 $1,000 $75,023 
Current$— $7,867 $21,250 $1,000 $30,117 
Non-current35,291 9,615 — — 44,906 
Total deferred and contingent consideration$35,291 $17,482 $21,250 $1,000 $75,023 

Agbaou mine – Acquisition of Endeavour Resources Inc. on March 1, 2021

The contingent consideration recorded on the acquisition of Agbaou relates to a royalty on future production from the Agbaou mine applicable to ore that is mined in excess of 320,611 ounces. This threshold was met in late 2022, and consequently the Company continues to value to royalty payable based on future production and using a discounted cash flow approach.

The primary input to the valuation of the contingent consideration are the consensus forward gold price, from $4,799 per ounce to $4,036 per ounce, and the expected future production of the mine.

Sadiola mine – Acquisition of Société d’Exploitation des Mines d’Or de Sadiola S.A on December 30, 2020

Contingent consideration recorded on the acquisition of Sadiola includes a first tranche of $24.9 million ($12.45 million each to AngloGold Ashanti (“AGA”) and IAMGOLD Corporation (“IMG”)) upon the production of the first 250,000 ounces from the Sadiola Sulphides Project (“SSP”); and a further tranche of $24.9 million ($12.45 million each to AGA and IMG) upon the production of a further 250,000 ounces from the SSP. The contingent consideration was valued using the discounted cash flow approach.

allied-goldxlogoxonxwhiteb.jpg | 26



The primary input to the valuation of the contingent consideration is the expected timing of future production from of the mine.

Korali-Sud project – Acquisition of Korali-Sud on November 9, 2023

Deferred consideration recorded on the acquisition of Korali-Sud project includes a $1.0 million deferred consideration.

Kurmuk project – Acquisition of APM Ethiopia Ltd. on September 6, 2023

Deferred consideration recorded on the asset acquisition of Kurmuk includes a consideration consisting of one payment of $25.0 million and two payments of $21.25 million each. The form of these payments includes:

First payment: $25.0 million in cash due on the first anniversary after completion of the acquisition; or $12.5 million paid in cash within 60 days of first anniversary after completion and $12.5 million paid in shares. The first payment was completed in 2024;
Second payment: $21.25 million due on the second anniversary after completion of the acquisition; or at the election of the counterparty: $21.25 million in cash due on the third anniversary after completion of the acquisition; or $21.25 million in shares due on the second anniversary after completion of the acquisition. The second payment was completed in 2025;
Third payment: $21.25 million in cash due at the earlier of the Commercial Production Commencement Date (estimated to be no earlier than the 3rd anniversary); and the fourth anniversary after completion of the acquisition.

On September 9, 2024, the Company issued 5,917,063 shares to partially settle the first payment, in the amount of $12.5 million. The $12.5 million cash portion of the first payment was completed on November 7, 2024. On September 8, 2025, the Company issued 1,474,882 shares to settle the second payment, in the amount of $21.25 million.

The Company used their best estimate for the elected option for the deferred consideration, estimating the amount of the deferred consideration to be $21.3 million as of March 31, 2026, presented as current liability. The deferred consideration is valued using the amortized cost method.

allied-goldxlogoxonxwhiteb.jpg | 27

FAQ

How did Allied Gold (AAUC) perform operationally in Q1 2026?

Allied Gold produced 96,016 ounces of gold in Q1 2026, up from 84,040 ounces a year earlier. Growth came mainly from Bonikro and Agbaou, while Sadiola remained broadly on plan. Consolidated AISC averaged $2,264 per ounce, reflecting stronger prices and mine-specific cost dynamics.

What were Allied Gold’s key financial results for Q1 2026?

Allied Gold generated revenue of $394.1 million in Q1 2026, with Adjusted Net Earnings of $48.6 million and Adjusted EBITDA of $173.3 million. Reported net loss attributable to shareholders was $58.3 million, mainly due to non‑cash items like financial instrument revaluations and share‑based compensation.

What is the status of the Zijin Gold acquisition of Allied Gold (AAUC)?

Zijin Gold agreed to acquire all Allied Gold shares for C$44 in cash per share, valuing the deal at about C$5.5 billion. Shareholder and court approvals are complete, and both parties are working with regulators toward closing by the arrangement’s outside date of May 29, 2026, subject to allowed extensions.

How strong is Allied Gold’s liquidity and cash position after Q1 2026?

As of March 31, 2026, Allied Gold held $424.2 million in cash and cash equivalents and had an undrawn $50.0 million revolving credit facility. Net cash from operating activities was $57.3 million for Q1, supported by higher realized gold prices and solid mine performance.

What progress has Allied Gold made on the Kurmuk project in Ethiopia?

Kurmuk construction is progressing in line with plan, targeting first gold in mid‑2026. The project is designed for about 290,000 ounces per year over its first four years at AISC below $950/oz, with processing capacity now targeted at up to 6.4 Mt/y and a long-term mine life of around 10 years based on reserves.

What are Allied Gold’s current Mineral Reserves and Resources?

As of December 31, 2025, Allied Gold reported Proven and Probable Mineral Reserves of 11.2 million ounces of gold at an average grade of 1.41 g/t. Measured and Indicated Mineral Resources totaled 15.3 million ounces, and Inferred Mineral Resources were 2.1 million ounces, supporting its multi‑asset growth plan.