Cadeler (NYSE: CDLR) secures EUR 70–80 million Taiwan offshore wind deal
Rhea-AI Filing Summary
Cadeler A/S has signed a firm contract with Synera Renewable Energy for the transportation and installation of 35 Siemens Gamesa 14MW wind turbines at the Formosa 4 offshore wind farm in Taiwan. The work will be carried out by one of Cadeler’s next-generation M-class installation vessels.
Operations are scheduled to start in March 2028 and last about 150 days, with projected revenue for Cadeler of between EUR 70 and 80 million. Formosa 4 is located 18 to 20 kilometres off Miaoli County, will span 58 square kilometres, and is designed to deliver 495 MW of offshore wind capacity, supporting Taiwan’s green energy supply and Cadeler’s long-term strategy in the Asia-Pacific region.
Positive
- None.
Negative
- None.
Insights
Cadeler secures a sizeable Taiwan offshore wind installation contract.
Cadeler has locked in a firm transportation and installation contract with Synera Renewable Energy for 35 Siemens Gamesa 14MW turbines at the Formosa 4 project in Taiwan. The contract is expected to generate revenue between EUR 70 and 80 million, tied to about 150 days of work starting in March 2028.
This agreement converts part of a previously disclosed reservation into a binding commitment, giving more visibility on future vessel utilization in the Asia-Pacific region. The use of an M-class vessel underscores demand for next-generation installation capacity and supports Cadeler’s positioning in deeper-water, large-turbine projects.
Formosa 4 is planned to provide 495 MW of capacity, highlighting the scale of work in Taiwan’s offshore wind build-out. Subsequent developments could come from ongoing negotiations for a second offshore wind project referenced alongside this contract.
FAQ
What contract did Cadeler (CDLR) sign related to the Formosa 4 wind farm?
How much revenue is Cadeler (CDLR) expecting from the Formosa 4 contract?
When will Cadeler start work on the Formosa 4 offshore wind project?
What is the planned capacity of the Formosa 4 offshore wind farm in Taiwan?
Where is the Formosa 4 offshore wind farm located?
How does this contract support Cadeler’s (CDLR) Asia-Pacific strategy?