Cheniere Partners (NYSE: CQP) inks $4.69B EPC for Sabine Pass Phase 1

Filing Impact
(High)
Filing Sentiment
(Neutral)
Form Type
8-K

Rhea-AI Filing Summary

Cheniere Energy Partners, L.P. has entered into a lump-sum, turnkey EPC contract with Bechtel Energy, Inc. for Phase 1 of the Sabine Pass Expansion Project, under which its subsidiary SPLV will pay approximately $4.69 billion for Train 7 and a boil-off gas re-liquefaction unit at the Sabine Pass LNG terminal in Louisiana.

The contract covers engineering, procurement, construction, commissioning and start-up, and Bechtel has received a limited notice to proceed. Phase 1 is expected to provide over 6 mtpa of LNG production capacity and is supported by long-term commercial agreements, with a final investment decision targeted by early 2027, subject to regulatory approvals and financing. The filing also notes updated services agreements anticipating additional trains and a press release announcing the EPC contract and LNTP.

Positive

  • None.

Negative

  • None.

Insights

$4.69B EPC contract advances Cheniere Partners’ Sabine Pass expansion.

Cheniere Partners committed to an EPC contract with Bechtel for Phase 1 of the Sabine Pass Expansion, covering Train 7 and a boil-off gas re-liquefaction unit. The lump-sum price is about $4.69 billion, with Bechtel under a parent guarantee and subject to liquidated damages for delay and underperformance.

Phase 1 is expected to add over 6 mtpa of LNG capacity and is described as commercially underpinned by long-term agreements with creditworthy counterparties. A positive final investment decision is still pending and depends on regulatory approvals and financing, including FERC and DOE export authorizations that remain under review.

Execution risk is managed in part through change-order mechanics, performance and delay liquidated damages, and specified termination rights for both parties. The company signals an expectation to reach FID by early 2027, while emphasizing typical forward-looking statement cautions around market conditions, financing and regulatory outcomes.

Item 1.01 Entry into a Material Definitive Agreement Business
The company signed a significant contract such as a merger agreement, credit facility, or major partnership.
Item 7.01 Regulation FD Disclosure Disclosure
Material non-public information disclosed under Regulation Fair Disclosure, often investor presentations or guidance.
Item 9.01 Financial Statements and Exhibits Exhibits
Financial statements, pro forma financial information, and exhibit attachments filed with this report.
EPC Contract Price $4.69 billion Lump-sum turnkey agreement for Sabine Pass Train 7 and BOGR
Phase 1 Capacity over 6 mtpa LNG Expected total production for Phase 1 including debottlenecking
Expansion Project Capacity up to ~20 mtpa LNG Planned peak capacity for SPL Expansion Project across up to three trains
Existing Sabine Pass Capacity over 30 mtpa LNG Current production capacity at Sabine Pass LNG terminal
Full Notice to Proceed Deadline May 21, 2028 Either party may terminate EPC if full NTP not issued by this date
FID Target early 2027 Expected timing for final investment decision on Phase 1
Lump Sum Turnkey Agreement financial
"entered into a Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction..."
limited notice to proceed financial
"has issued the first limited notice to proceed on May 22, 2026."
A limited notice to proceed is a short, partial green light from a client that lets a contractor begin specific early work—such as site preparation, ordering long‑lead materials, or hiring crews—before the full contract is signed. For investors it signals that a project is moving from planning toward execution, which can accelerate revenue timing but also exposes the company to early costs and schedule risk if the full contract terms change; think of it as starting the foundation before the final building permit paperwork is complete.
performance liquidated damages financial
"Bechtel is required to pay the applicable performance liquidated damages."
delay liquidated damages financial
"Bechtel is required to pay SPLV delay liquidated damages at the applicable daily rate..."
final investment decision financial
"a positive final investment decision (“FID”) on Phase 1 is subject to, among other things..."
A final investment decision is the point at which a person or organization chooses to move forward with a particular project or purchase after reviewing all the necessary information and options. It is like deciding to buy a house after considering all the costs, benefits, and alternatives. This decision is important because it determines whether and when the investment will be made, impacting future financial plans and outcomes.
force majeure financial
"or is stopped due to a force majeure event for a specified period..."
Force majeure is a legal concept that refers to unexpected events beyond anyone’s control, such as natural disasters, war, or severe disruptions, that prevent a party from fulfilling their obligations. It matters to investors because it can delay or cancel agreements, affecting the timing and certainty of financial transactions and obligations. Essentially, it acts as a shield for parties facing unforeseen, uncontrollable problems.
0001383650false00013836502026-05-222026-05-22


UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
WASHINGTON, D.C. 20549
FORM 8-K
CURRENT REPORT

Pursuant to Section 13 or 15(d) of the Securities Exchange Act of 1934
Date of Report (Date of earliest event reported): May 22, 2026
    
CHENIERE ENERGY PARTNERS, L.P.
(Exact name of registrant as specified in its charter)
Delaware001-3336620-5913059
(State or other jurisdiction of incorporation)(Commission File Number)(I.R.S. Employer Identification No.)
845 Texas Avenue, Suite 1250
Houston, Texas 77002
(Address of principal executive offices) (Zip Code)
(713375-5000
(Registrant’s telephone number, including area code)
Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions:
    Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)
    Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)
    Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))
    Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))
    Securities registered pursuant to Section 12(b) of the Act:
Title of each classTrading SymbolName of each exchange on which registered
Common Units Representing Limited Partner InterestsCQPNYSE
    Indicate by check mark whether the registrant is an emerging growth company as defined in Rule 405 of the Securities Act of 1933 (§230.405 of this chapter) or Rule 12b-2 of the Securities Exchange Act of 1934 (§240.12b-2 of this chapter).
    Emerging growth company
    If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act.



Item 1.01    Entry into a Material Definitive Agreement.

EPC Contract

Sabine Pass Liquefaction Stage V, LLC (“SPLV”), an indirect wholly owned subsidiary of Cheniere Energy Partners, L.P. (the “Partnership”), has entered into a Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage V Liquefaction Project dated May 22, 2026 (the “EPC Contract”) with Bechtel Energy, Inc. (“Bechtel”), and has issued the first limited notice to proceed on May 22, 2026.

Parent Guarantee. Bechtel Global Energy, Inc. guarantees Bechtel’s obligations under the EPC Contract.

Scope of Work. The EPC Contract includes engineering, procurement, construction, pre-commissioning, commissioning, start-up and testing of Phase 1 of the Stage V natural gas liquefaction facility at the Sabine Pass liquefied natural gas terminal (the “Liquefaction Facility”) in Cameron Parish, Louisiana, which consists of one liquefaction train built with ConocoPhillips technology (“Train 7”), with an LNG production capacity substantially similar to the six existing trains at the Liquefaction Facility, and one boil-off gas re-liquefaction unit (“BOGR”) with approximately 1 million tonnes per annum of production capacity, along with other related equipment and infrastructure.

Contract Price. The EPC Contract provides that SPLV will pay Bechtel approximately $4.69 billion pursuant to the terms and payment schedule specified in the EPC Contract (the “Contract Price”).

Bechtel Change Orders. The Contract Price is subject to adjustment by change order as specified in the EPC Contract, including in the event of the following: (i) a delay in SPLV issuing limited notices to proceed by the dates specified in the EPC Contract or SPLV not issuing a full notice to proceed on or before the date specified in the EPC Contract, (ii) certain acts or omissions of SPLV, (iii) force majeure, (iv) SPLV’s request for an increase in coverage under the letter of credit to cover increases in the Contract Price as a result of change orders, (v) a change in law, (vi) suspension of work ordered by SPLV, (vii) changes to duties and tariffs as specified in the EPC Contract, (viii) subsurface soil conditions materially different from those described in the geotechnical studies, (ix) acceleration of work by SPLV, (x) physical damage caused by a third party not under Bechtel’s control, and (xi) other specified reasons in the EPC Contract.

Performance Liquidated Damages. If Train 7 or BOGR have not achieved the performance guarantee within a specified period after the guaranteed substantial completion date, then Bechtel is required to pay the applicable performance liquidated damages.

Delay Liquidated Damages. If substantial completion of Train 7 or BOGR occurs after the guaranteed substantial completion date, Bechtel is required to pay SPLV delay liquidated damages at the applicable daily rate as defined in the EPC Contract until substantial completion occurs.

Schedule Bonus. Bechtel will be entitled to receive specified bonuses for timely substantial completion.

Termination. If SPLV fails to issue the full notice to proceed on or before May 21, 2028, then either party may terminate the EPC Contract, and Bechtel will be paid termination costs as specified in the EPC Contract. In addition, the following termination rights exist under the EPC Contract:

SPLV has the right to terminate the EPC Contract at its convenience, if Bechtel is unable to pay its debts or an insolvency event occurs with respect to Bechtel or its guarantor, or



upon the occurrence of other customary events of default applicable to contractors under similar agreements of this type (subject to cure periods in certain circumstances);

Either party has the right to terminate the EPC Contract if the other party (i) breaches any of its representations or warranties and such failure has a material adverse effect upon the project or the non-breaching party’s ability to perform its obligations under the EPC Contract, or (ii) otherwise materially defaults on its obligations, though such termination right is subject to a cure period in certain circumstances; and

Bechtel has the right to terminate the EPC Contract if (i) SPLV fails to timely pay Bechtel amounts due under the EPC Contract (subject to certain cure periods), or (ii) all or a substantial portion of the work under the contract is suspended by SPLV for specified periods or is stopped due to a force majeure event for a specified period, subject to certain exceptions.

Limitation on Bechtel’s Liability. Bechtel’s liability under the EPC Contract is limited as specified in the EPC Contract, except that this limit does not apply to Bechtel’s title warranty, to certain indemnification obligations or to Bechtel’s obligation to complete all work required to ensure that Train 7 and BOGR are ready to receive natural gas and produce LNG, and this limit does not apply in the event of Bechtel’s fraud or abandonment of the work.

The description of the EPC Contract set forth above is not complete, and is subject to and qualified in its entirety by reference to the full text of the EPC Contract, a copy of which will be filed as an exhibit to the Partnership’s quarterly report on Form 10-Q for the quarter ended June 30, 2026.

Amendments to Services Agreements

Sabine Pass Liquefaction, LLC (“SPL”), an indirect wholly owned subsidiary of the Partnership, has entered into amendments to the below agreements in order to update the scope of the respective agreement in anticipation of the construction of additional liquefaction trains at the Liquefaction Facility:

Management Services Agreement, dated May 14, 2012, by and among SPL and Cheniere LNG Terminals, LLC, as amended on September 28, 2015.

Operation and Maintenance Agreement, dated May 14, 2012, by and among SPL, Cheniere Energy Investments, LLC and Cheniere LNG O&M Services, LLC, as amended on September 28, 2015.

The foregoing descriptions are not complete, and are subject to and qualified in their entirety by reference to the full text of the agreements, copies of which are filed as Exhibits 10.1 and 10.2 hereto and incorporated by reference herein.

Item 7.01     Regulation FD Disclosure.

On May 28, 2026, the Partnership issued a press release announcing the signing of the EPC Contract and the issuance of limited notice to proceed. A copy of the press release is attached as Exhibit 99.1 to this report and incorporated herein by reference.

The information contained in this Item 7.01 of this Current Report on Form 8-K is being furnished and shall not be deemed “filed” for purposes of Section 18 of the Securities Exchange Act of 1934, as amended (the “Exchange Act”), or otherwise subject to the liabilities of that Section, nor shall such



information be deemed incorporated by reference in any filing under the Securities Act of 1933, as amended or the Exchange Act, except as expressly set forth by specific reference in such filing.

Item 9.01     Financial Statements and Exhibits.

(d) Exhibits

Exhibit No.Description
10.1
Second Amendment to Management Services Agreement, dated May 22, 2026, by and among SPL and Cheniere LNG Terminals, LLC (incorporated by reference to Exhibit 10.1 to SPL's Current Report on Form 8-K (SEC File No. 333-192373), filed on May 28, 2026).
10.2
Second Amendment to Operation and Maintenance Agreement, dated May 22, 2026, by and among SPL, Cheniere Energy Investments, LLC and Cheniere LNG O&M Services, LLC (incorporated by reference to Exhibit 10.2 to SPL's Current Report on Form 8-K (SEC File No. 333-192373), filed on May 28, 2026).
99.1*
Press Release, dated May 28, 2026.
104Cover Page Interactive Data File (embedded within the Inline XBRL document)
* Furnished herewith.





SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned hereunto duly authorized.

CHENIERE ENERGY PARTNERS, L.P.
By:CHENIERE ENERGY PARTNERS GP, LLC,
Its general partner
Date:
May 28, 2026By:/s/ Zach Davis
Name:Zach Davis
Title:Executive Vice President and
Chief Financial Officer






Exhibit 99.1

CHENIERE ENERGY PARTNERS, L.P. NEWS RELEASE

Cheniere Partners Signs EPC Contract with Bechtel for the First Phase of the Sabine Pass Expansion Project and Issues Limited Notice to Proceed

HOUSTON--(BUSINESS WIRE)-- Cheniere Energy Partners, L.P. (“Cheniere Partners” or the “Company”) (NYSE: CQP) announced today that its subsidiary, Sabine Pass Liquefaction Stage V, LLC (“SPLV”), has entered into a lump sum, turnkey, engineering, procurement and construction (“EPC”) contract with Bechtel Energy, Inc. (“Bechtel”) for the first phase of the SPL Expansion Project (“Phase 1”). In addition, SPLV has released Bechtel to commence early engineering and procurement for Phase 1 under a limited notice to proceed (“LNTP”).

The SPL Expansion Project is being developed for up to three large-scale liquefaction trains with an expected total peak production capacity of up to approximately 20 million tonnes per annum (“mtpa”) of liquefied natural gas (“LNG”), inclusive of estimated debottlenecking opportunities and supporting infrastructure. The SPL Expansion Project is being executed in a phased approach. The EPC agreement with Bechtel for Phase 1 includes a single train, Train 7, a boil-off gas re-liquefaction unit, along with supporting infrastructure and tie-ins to the existing Sabine Pass LNG Terminal. Inclusive of estimated debottlenecking, Phase 1 has an expected total production capacity of over 6 mtpa of LNG. Phase 1 is commercially underpinned by long-term agreements with creditworthy counterparties, and a positive final investment decision (“FID”) on Phase 1 is subject to, among other things, receipt of necessary regulatory approvals and an acceptable financing arrangement.
The Federal Energy Regulatory Commission (FERC) application for authorization to site, construct and operate the SPL Expansion Project, as well as the Department of Energy (DOE) application authorizing the export of LNG to non-free trade agreement (non-FTA) countries, remain pending. Cheniere Partners expects to reach FID on Phase 1 by early 2027.
“We are pleased to once again partner with Bechtel on the first phase of the SPL Expansion Project, and we look forward to building upon the unmatched track record for execution excellence the Cheniere and Bechtel relationship has established while successfully building our leading LNG platform. The EPC contract and the issuance of LNTP mark important steps toward FID, which we expect to occur by early next year. We are excited to have the project underway and are laser-focused on the remaining steps required to reach FID,” said Jack Fusco, Cheniere’s Chairman, President and Chief Executive Officer. “The SPL Expansion Project commences as LNG market dynamics highlight the criticality of secure supply in the global energy system. We look forward to bringing this much-needed LNG capacity to the market and providing our customers with reliable and flexible LNG from Train 7.”

About Cheniere Partners
Cheniere Partners owns the Sabine Pass LNG terminal located in Cameron Parish, Louisiana, which has natural gas liquefaction facilities with a total production capacity of over 30 mtpa of LNG in operation. The Sabine Pass LNG terminal also has operational regasification facilities that include five LNG storage tanks, vaporizers, and three marine berths. Cheniere Partners also owns the Creole Trail Pipeline, which interconnects the Sabine Pass LNG terminal with a number of large interstate and intrastate pipelines.

For additional information, please refer to the Cheniere Partners website at www.cheniere.com and Quarterly Report on Form 10-Q for the quarter ended March 31, 2026, filed with the Securities and Exchange Commission.

Forward-Looking Statements
This press release contains certain statements that may include “forward-looking statements.” All statements, other than statements of historical or present facts or conditions, included herein are “forward-looking statements.” Included among “forward-looking statements” are, among other things, (i) statements regarding Cheniere Partners’ financial and operational guidance, business strategy, plans and objectives, including the development, construction and operation of liquefaction facilities, (ii) statements regarding Cheniere Partners’ anticipated quarterly distributions and ability to make quarterly distributions at the base amount or any amount, (iii) statements regarding regulatory authorization and approval expectations, (iv) statements expressing beliefs and expectations regarding the development of Cheniere Partners’ LNG terminal and liquefaction business, (v) statements regarding the business operations and prospects of third-parties, (vi) statements regarding potential financing arrangements, (vii) statements regarding future discussions and entry into contracts, and (viii) statements relating to our goals,



commitments and strategies in relation to environmental matters. Although Cheniere Partners believes that the expectations reflected in these forward-looking statements are reasonable, they do involve assumptions, risks and uncertainties, and these expectations may prove to be incorrect. Cheniere Partners’ actual results could differ materially from those anticipated in these forward-looking statements as a result of a variety of factors, including those discussed in Cheniere Partners’ periodic reports that are filed with and available from the Securities and Exchange Commission. You should not place undue reliance on these forward-looking statements, which speak only as of the date of this press release. Other than as required under the securities laws, Cheniere Partners does not assume a duty to update these forward-looking statements.


Contacts

Cheniere Partners
Investors
Randy Bhatia713-375-5479
Frances Smith713-375-5753
Media Relations
Randy Bhatia713-375-5479
Bernardo Fallas713-375-5593

FAQ

What EPC contract did Cheniere Partners (CQP) sign for the Sabine Pass Expansion?

Cheniere Partners signed a lump-sum, turnkey EPC contract with Bechtel for Phase 1 of the Sabine Pass Expansion. The deal covers Train 7 and a boil-off gas re-liquefaction unit for about $4.69 billion, including engineering, procurement, construction and commissioning services.

How much LNG capacity will Phase 1 of Cheniere Partners’ Sabine Pass Expansion add?

Phase 1 of the Sabine Pass Expansion, centered on Train 7 and a boil-off gas re-liquefaction unit, has an expected total LNG production capacity of over 6 million tonnes per annum, inclusive of estimated debottlenecking opportunities and supporting infrastructure at the Sabine Pass terminal.

What is the total planned capacity of the SPL Expansion Project at Sabine Pass for CQP?

The SPL Expansion Project is being developed for up to three large-scale liquefaction trains with an expected total peak LNG production capacity of up to approximately 20 mtpa. This figure includes estimated debottlenecking and supporting infrastructure at the Sabine Pass LNG terminal in Louisiana.

When does Cheniere Partners expect to reach FID on Phase 1 of the SPL Expansion Project?

Cheniere Partners states it expects to reach a positive final investment decision on Phase 1 of the SPL Expansion Project by early 2027. That timing remains subject to obtaining necessary regulatory approvals and securing an acceptable financing arrangement for the expansion phase.

What regulatory approvals are pending for Cheniere Partners’ SPL Expansion Project at Sabine Pass?

The SPL Expansion Project still requires authorization from the Federal Energy Regulatory Commission to site, construct and operate the project. It also needs a Department of Energy authorization to export LNG to non-free trade agreement countries; both applications remain pending.

What protections and incentives are included in the Cheniere–Bechtel EPC contract?

The EPC contract includes performance and delay liquidated damages payable by Bechtel if Train 7 or the BOGR unit miss performance or completion targets. It also provides schedule bonus opportunities for timely completion, change-order mechanisms, liability caps with carve-outs, and specified termination rights for both parties.

Filing Exhibits & Attachments

4 documents