Denison Mines (NYSE: DNN) begins full-scale Phoenix ISR uranium build

(Neutral)
(Neutral)
Form Type
6-K

Rhea-AI Filing Summary

Denison Mines Corp. reports that work at its Phoenix In-Situ Recovery (ISR) uranium mine, part of the Wheeler River project in Saskatchewan, has moved from site preparation to full-scale construction, including the start of installation of the Phase 1 perimeter freeze wall.

Early works since March 2026 have completed substantial site clearing, schedule-sensitive civil works and construction management facilities. Temporary camp facilities have boosted accommodation capacity at Wheeler River to nearly 400 people. The company estimates that over 20% of overall site civil work is complete and civil subgrade work for the process plant and wellfield areas is near 100%, ahead of schedule-critical concrete pours expected to begin in August and around-the-clock activity with a second shift.

Wheeler River, described as the largest undeveloped uranium project in the eastern Athabasca Basin, is a joint venture between Denison (90%, operator) and JCU (10%), with Denison holding an effective 95% interest. The Phoenix ISR operation received provincial Environmental Assessment approval in July 2025 and federal Environmental Assessment approval plus a construction licence in February 2026, enabling full-scale construction to commence in July 2026.

Positive

  • Full-scale construction has begun at the Phoenix ISR uranium mine, marking a major development milestone for Denison’s flagship Wheeler River project following key environmental and construction approvals.

Negative

  • None.
On-site camp capacity nearly 400 people Accommodation capacity at the Wheeler River property after temporary camp installation
Site civil work completed +20% Estimated portion of overall site civil work completed during the early works program
Civil subgrade completion near 100% Civil subgrade work for the process plant and wellfield areas at Phoenix
Wheeler River joint venture interest Denison 90%; JCU 10% Ownership interests in the Wheeler River uranium project
Effective Wheeler River interest 95% Denison’s effective interest in its flagship Wheeler River Project
Athabasca Basin land position ~457,000 hectares Direct ownership interests in properties in the Athabasca Basin region
Phoenix EA provincial approval July 2025 Environmental Assessment approval by the Province of Saskatchewan
Phoenix construction licence February 2026 EA approval and construction licence grant by the Canadian Nuclear Safety Commission
In-Situ Recovery technical
"activities at the Phoenix In-Situ Recovery (“ISR”) uranium mine have transitioned"
In-situ recovery is a mining method that extracts a valuable material by dissolving it underground and pumping the solution to the surface instead of digging or blasting rock. For investors, it matters because this approach often lowers upfront construction costs, shortens development time and reduces visible land disturbance, but it also brings regulatory, environmental and groundwater risks that can affect project timelines, operating costs and valuation.
Environmental Assessment regulatory
"culminating in the July 2025 approval of the Project’s Environmental Assessment"
An environmental assessment is a process that evaluates how a project or activity might impact the natural surroundings, such as air, water, land, and wildlife. It helps identify potential environmental risks and ensures that any negative effects are managed or minimized. For investors, this assessment provides insight into the sustainability and long-term viability of projects, which can influence their financial decisions and risk management.
NI 43-101 Technical Report financial
"the technical report titled “NI 43-101 Technical Report on the Wheeler River Project"
A NI 43-101 technical report is a standardized, legally required study used in Canada that describes a mining project’s geology, exploration work, and estimates of how much mineral or ore might exist. Think of it as an independent inspector’s blueprint that explains the data, methods, and uncertainties behind those estimates so investors can judge how reliable the claims are and compare projects on a consistent basis.
toll milling agreement financial
"to process the ore from the Cigar Lake mine under a toll milling agreement"
A toll milling agreement is a contract where one company pays a processor to grind, mill or otherwise transform its raw materials into finished or semi‑finished products while the material owner keeps legal title and pays a fee for the service. For investors it matters because it lets a business avoid buying expensive production plants, affecting costs, margins, supply‑chain risk and operational flexibility—like renting a specialized workshop instead of owning it.
Pre-Feasibility Study technical
"a cost update to the 2018 Pre-Feasibility Study for conventional underground mining"
A pre-feasibility study is an initial assessment that evaluates whether a proposed project or investment idea is worth exploring further. It involves examining basic factors like costs, potential benefits, and possible challenges, similar to conducting a preliminary check before deciding to invest more time and resources. This helps investors determine if pursuing the project further is practical and likely to be successful.
construction licence regulatory
"approval of the Project’s EA and the grant of the construction licence"
A construction licence is an official government or municipal permit that authorizes a company to build, expand or alter a physical project, often with specific conditions, inspections and time limits. For investors it matters because the licence controls whether and when a project can proceed, affects costs and timelines, and creates legal risk—similar to needing a permit before starting a major renovation, without which the project can be delayed, fined or stopped.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google
Learn about SEC filing dates

FAQ

What did Denison Mines (DNN) announce about the Phoenix ISR uranium project?

Denison announced that activities at the Phoenix ISR uranium mine have shifted from site preparation to full-scale construction, including starting installation of the Phase 1 perimeter freeze wall after completing critical civil works and support infrastructure.

How advanced is construction work at Denison’s Phoenix project (DNN)?

Denison estimates that over 20% of overall site civil work is complete, with civil subgrade work for the process plant and wellfield areas near 100%, positioning the project for schedule-critical concrete pours and accelerated construction through a second work shift.

What ownership interest does Denison Mines (DNN) hold in the Wheeler River project?

Wheeler River is a joint venture between Denison and JCU, with Denison holding 90% and acting as operator, and JCU holding 10%. Denison describes its effective interest in the flagship Wheeler River Project as 95%.

Which regulatory approvals has Denison (DNN) secured for the Phoenix ISR mine?

The Phoenix ISR operation obtained Environmental Assessment approval from Saskatchewan in July 2025 and received Environmental Assessment approval and a construction licence from the Canadian Nuclear Safety Commission in February 2026, enabling the start of full-scale construction in July 2026.

What workforce capacity does Denison’s Wheeler River camp now support?

After installing and commissioning temporary construction camp facilities, Denison states that accommodation capacity at the Wheeler River property has been increased to nearly 400 people, allowing a ramp-up of the on-site workforce and the introduction of a second construction shift.

Where are Denison Mines’ (DNN) other key uranium interests located?

Denison focuses on the Athabasca Basin in northern Saskatchewan, holding a 22.5% interest in the McClean Lake Joint Venture, 25.17% in the Midwest Joint Venture, and 70.55% in the THT and Huskie deposits, plus properties covering about 457,000 hectares.

What risks and uncertainties does Denison (DNN) highlight for Phoenix and Wheeler River?

Denison notes that technical study results and cost forecasts may change and that work could be affected by access to equipment, staffing, contractors, capital funding, joint venture and regulatory approvals, with outcomes potentially differing materially from current expectations.
 

 
UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
 
 
FORM 6-K
 

REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO RULE 13a-16 OR 15d-16
UNDER THE SECURITIES EXCHANGE ACT OF 1934
 
Date: July 28, 2026
 
Commission File Number: 001-33414
 
 
Denison Mines Corp. 
 (Name of registrant)
 
 
 
1100-40 University Avenue
Toronto Ontario
 M5J 1T1 Canada
 
 (Address of principal executive offices)
 

 Indicate by check mark whether the registrant files or will file annual reports under cover Form 20-F or Form 40-F.
 
Form 20-F  ☐            Form    40-F   ☒
 
Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(1):  ☐
Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(7):  ☐
 

 
 
 
 
SIGNATURES
 
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.
 
 
 
 
 
 
 
 
 
 
 
 
 
DENISON MINES CORP.
 
 
 
 
 
 
 
/s/ Amanda Willett
Date July 28, 2026
 
 
 
Amanda Willett
 
 
 
 
Vice President Legal and Corporate Secretary
 
 
 
 
 
FORM 6-K EXHIBIT INDEX
 
Exhibit Number
  
Description

 
99.1
 
Press release dated July 28, 2026

 


 




 
 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Exhibit 99.1 
 
 
Denison Mines Corp.
1100 – 40 University Ave
Toronto, ON M5J 1T1
www.denisonmines.com

PRESS RELEASE 
 
Denison Announces Completion of Site Preparation Activities
and Commencement of Full-Scale Construction at Phoenix ISR Uranium Mine
 
Toronto, ON – July 28, 2026. Denison Mines Corp. (“Denison” or the “Company”) (TSX: DML, NYSE American: DNN) is pleased to announce that activities at the Phoenix In-Situ Recovery (“ISR”) uranium mine (“Phoenix” or the “Project”) have transitioned from site preparations to full-scale construction, including initiation of the perimeter freeze wall installation for Phase 1 of the mine.
 
Since the commencement of site preparation and early works in March 2026, significant progress has been made by Denison and its construction partners to complete several critical site preparation activities – including substantial completion of site clearing activities, advancement of schedule-sensitive site civil works, and the establishment of construction management facilities. Preparation activities also involved the installation and commissioning of temporary construction camp facilities, which significantly increases the accommodation capacity of the Wheeler River property to nearly 400 people and allows a ramp-up in the on-site workforce.
 
Additionally, aggregate production required for various site civil purposes continues at a nearby quarry, and the concrete batch plant has been mobilized to site. Schedule-critical concrete-related activities for the substation and the main process plant foundations are currently expected to commence in August.
 
David Cates, President & CEO of Denison, commented, “Completing the site-preparation activities needed to ramp up our on-site workforce and achieve a full-scale rate of construction is an important initial milestone for the Phoenix project.
 
Site civil work has progressed well during the early works program, with +20% of overall site civil work estimated to be completed to date. Importantly, we have achieved near 100% completion of civil subgrade work for the process plant and wellfield areas, which is needed to facilitate the planned concrete pour for the plant and the initiation of the freeze wall installation program.
 
Construction activity is expected to accelerate through the remainder of the summer months with the commencement of a second shift, which means seasonally sensitive civil and other construction work can continue virtually 24-hours a day in support of the completion of our key first-year construction milestones – including concrete pours of the foundations for the process plant and main power transformer, installation of the freeze wall, as well as earth works for the airstrip and on-site power distribution.
 
Achieving these positive early results demonstrates the readiness and commitment of Denison and our construction partners as we advance this unique nation-building project to become Canada’s first new large-scale uranium mine since Cigar Lake.”
 
About Wheeler River
 
Wheeler River is the largest undeveloped uranium project in the infrastructure-rich eastern portion of the Athabasca Basin region, in northern Saskatchewan. Wheeler River is host to the high-grade Phoenix and Gryphon uranium deposits, discovered by Denison in 2008 and 2014, respectively, and is a joint venture between Denison (90% and operator) and JCU (Canada) Exploration Company Limited (“JCU”, 10%). In August 2023, Denison filed a technical report (the “Wheeler River Report”) summarizing the results of (i) Phoenix Feasibility Study; and (ii) a cost update to the 2018 Pre-Feasibility Study for conventional underground mining of the basement-hosted Gryphon uranium deposit. Based on the respective studies, both deposits have the potential to be competitive with the lowest cost uranium mining operations in the world. Permitting efforts for the planned Phoenix ISR operation commenced in 2019, culminating in the July 2025 approval of the Project’s Environmental Assessment (“EA”) by the Province of Saskatchewan and the February 2026 approval of the Project’s EA and the grant of the construction licence by the Canadian Nuclear Safety Commission. Full-scale construction commenced for Phoenix in July 2026. More information is available in the technical report titled “NI 43-101 Technical Report on the Wheeler River Project Athabasca Basin, Saskatchewan, Canada” dated August 8, 2023 with an effective date of June 23, 2023, and an update to estimated Phoenix initial capital costs described in Denison’s Annual Information Form dated March 30, 2026, copies of which are available on Denison’s website and under its profile on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.gov/edgar. 
 
 
 
 
About Denison 
 
Denison is a leading uranium exploration and development company with interests focused in the Athabasca Basin region of northern Saskatchewan, Canada. In addition to Denison’s effective 95% interest in its flagship Wheeler River Project, Denison's interests in Saskatchewan include a 22.5% ownership interest in the McClean Lake Joint Venture ("MLJV"), which includes uranium deposits (with mining at the McClean North deposit having commenced in 2025 using the MLJV's SABRE mining method) and the McClean Lake uranium mill (currently utilizing a portion of its licensed capacity to process the ore from the Cigar Lake mine under a toll milling agreement), plus a 25.17% interest in the Midwest Joint Venture Midwest Main and Midwest A deposits, and a 70.55% interest in the Tthe Heldeth Túé ("THT") and Huskie deposits on the Waterbury Lake Property. The Midwest Main, Midwest A, THT and Huskie deposits are located within 20 kilometres of the McClean Lake mill. Taken together, Denison has direct ownership interests in properties covering ~457,000 hectares in the Athabasca Basin region.
 
Additionally, through its 50% ownership of JCU (Canada) Exploration Company, Limited (“JCU”), Denison holds interests in various uranium project joint ventures in Canada, including the Millennium project (JCU, 30.099%), the Kiggavik project (JCU, 33.8118%) and Christie Lake (JCU, 34.4508%).
 
In 2024, Denison celebrated its 70th year in uranium mining, exploration, and development, which began in 1954 with Denison’s first acquisition of mining claims in the Elliot Lake region of northern Ontario. 
 
For more information, please contact 
 
David Cates                                                     (416) 979-1991 ext. 362
President and Chief Executive Officer
 
Geoff Smith                                                      (416) 979-1991 ext. 358
Vice President Corporate Development & Commercial
 
Follow Denison on Twitter                                 @DenisonMinesCo
 
 
CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING STATEMENTS
 
Certain information contained in this news release constitutes 'forward-looking information', within the meaning of the applicable United States and Canadian legislation, concerning the business, operations and financial performance and condition of Denison. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as 'potential', 'plans', 'expects', 'budget', 'scheduled', 'estimates', 'forecasts', 'intends', 'anticipates', or 'believes', or the negatives and/or variations of such words and phrases, or state that certain actions, events or results 'may', 'could', 'would', 'might' or 'will' 'be taken', 'occur' or 'be achieved'. In particular, this news release contains forward-looking information pertaining to Denison's current expectations, intentions and objectives with respect to Wheeler River and Phoenix, including the Company's outlook generally with respect to ISR mine development and operations, and milestones related thereto, for Phoenix.  
 
Forward looking statements are based on the opinions and estimates of management as of the date such statements are made, and they are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Denison to be materially different from those expressed or implied by such forward-looking statements. For example, the results and underlying assumptions and interpretations of its technical studies and cost forecasting may not be maintained after further testing, procurement, or operations, or be representative of actual conditions at the Project or within the applicable deposits. In addition, Denison may decide or otherwise be required to discontinue work if it is unable to maintain or otherwise secure the necessary resources (such as equipment, staffing, contractors, testing facilities, capital funding, joint venture approvals, regulatory approvals, etc.). Denison believes that the expectations reflected in this forward-looking information are reasonable but no assurance can be given that these expectations will prove to be accurate and results may differ materially from those anticipated in this forward-looking information. For a discussion in respect of risks and other factors that could influence forward-looking events, please refer to the factors discussed in Denison's Annual Information Form dated March 30, 2026 under the heading 'Risk Factors' or in subsequent quarterly financial reports. These factors are not, and should not be construed as being, exhaustive.
 
Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking information contained in this news release is expressly qualified by this cautionary statement. Any forward-looking information and the assumptions made with respect thereto speaks only as of the date of this news release. Denison does not undertake any obligation to publicly update or revise any forward-looking information after the date of this news release to conform such information to actual results or to changes in Denison's expectations except as otherwise required by applicable legislation. 
 
 
 
 
 
Figure 1. Phoenix ISR Mine, Site Preparation Progress as of April 30, 2026
 
 
 
Figure 2. Phoenix ISR Mine, Civil Works for Wellfield, Process Plant, and Substation Areas as of July 21, 2026
 
 
 
 
 
 
Figure 3. Temporary Construction Camp Facilities Installation Progress at the Phoenix Site as of July 6, 2026
 
 
 
Figure 4. Airstrip Site Preparation (Phoenix site in the distances) as of July 25, 2026
 
 