This summary description about us and our business highlights selected information contained elsewhere in this prospectus or incorporated by reference in this prospectus. This summary does not contain all of the information you should consider before buying our securities. You should carefully read this entire prospectus and any applicable prospectus supplement, including each of the documents incorporated by reference herein or therein, before making an investment decision.
Overview
ioneer’s primary business is to develop a lithium-boron mine and processing facility, known as the Rhyolite Ridge Project, in Esmeralda County, Nevada, United States (the “Project”). The Project is located on public land administered by the Bureau of Land Management (the “BLM”) of the U.S. Department of Interior. ioneer currently holds a 100% interest in the Project. On June 2, 2025, we released revised Project economics to the completed definitive feasibility study (the “DFS”) announced April 30, 2020, which was followed by a second announcement of further material improvement in Project economics released in September 2025. In October 2025, we announced an additional material improvement in Project economics, as described in the Rhyolite Ridge Lithium-Boron Project S-K 1300 Technical Report Summary dated as of April 25, 2026 and filed as Exhibit 15.11 to the Transition Report. The updated Project economics reaffirmed the Project can operate at scale, over a long life and with the potential to be a low-cost and globally significant producer of both lithium and boron. Following the completion of all technical studies and all necessary permitting activities, we may undertake mining and processing activities to become a U.S. source of lithium and boron.
As of December 31, 2025, we had invested US$ 209.0 million in the Project.
On October 25, 2024, the Project received its federal permit from the BLM. The formal Record of Decision followed the issuance in September 2024 of the final Environmental Impact Statement by the BLM. This concluded the federal permitting process, which began in early 2020.
On January 20, 2025, we announced the closing of a US$ 996 million loan from the U.S. Department of Energy Loan Programs Office under the Advanced Technology Vehicles Manufacturing program to support the development of an on-site processing facility at the Project. The total amount of the loan, US$ 996 million, includes US$ 968 million in principal and US$ 28 million in capitalized interest with a term of 20 years. The loan amount represents a US$ 268 million increase in loan principal from the conditional loan commitment announced January 16, 2023. The loan will be at an interest rate fixed from the date of each advance for the term of the loan at applicable U.S. Treasury rates. Conditions precedent to first loan funding include, among other requirements, closing a strategic partnering agreement for the equity component of the build cost, securing necessary additional required funding and a project finance model bring down. ioneer is currently running a strategic partnering process with the assistance of Goldman Sachs to secure additional funding requirements for the Project.
Our ordinary shares are publicly traded on the Australian Securities Exchange under the symbol “INR”. Our ADSs, each representing 40 of our ordinary shares, are publicly traded on the Nasdaq Capital Market under the symbol “IONR”. The Bank of New York Mellon, acting as depositary, registers and delivers the ADSs.
Corporate Information
Our head office is located at 16.01, Level 16, 213 Miller Street, North Sydney, NSW 2060 Australia. Our registered office is located at 16.01, Level 16, 213 Miller Street, North Sydney, NSW 2060 Australia. The telephone number of our registered office is +61 (2) 9922-5800.
We also maintain a website at www.ioneer.com. The information contained on our website or available through our website is not incorporated by reference into and should not be considered a part of this prospectus, and the reference to our website in this prospectus is an inactive textual reference only.