ENDRA Life Sciences: Renergen’s ~$1.2B helium plan

Available on EDGAR Accepted by SEC EDGAR Learn about SEC filing dates
(Moderate)

Sentiment and the balance of points

Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

Form Type
425

Rhea-AI Filing Summary

ENDRA Life Sciences Inc. is identified as a party to proposed merger-related transactions involving ASP Isotopes, its wholly owned subsidiaries Renergen and Noble Africa (Renergen’s holding company), and ENDRA. In a webinar, Renergen COO Nick Mitchell said stable liquid helium production was reached in October after a cold-box repair, and storage tanks were being cooled ahead of customer deliveries. Renergen has produced LNG since September 2022 and supplied its first liquid-helium batch in 2025.

Renergen’s Phase 2 capital estimate is around $1.2 billion, with a projected scale about 13 times the Phase 1 pilot and approximately 890 MCF per day of helium output. Mitchell said $750 million of debt had been put together for the project, with the balance to come from equity. He reported around 400 billion cubic feet of natural gas and six billion cubic feet of helium at a 2P reserve level, proven on 15% of acreage. He said a Phase 2 investment decision was anticipated in the first half of next year, with earliest production at the end of 2030 and full production probably in 2031.

Filing Explained

Renergen is reviewing whether to stage Phase 2, which could bring some elements online sooner, but no change is decided; it says it will update shareholders after the work goes to the board and the board decides.

2P natural gas reserves around 400 billion cubic feet Renergen’s Virginia Gas Project, as described by Nick Mitchell.
2P helium reserves around six billion cubic feet Renergen’s Virginia Gas Project, as described by Nick Mitchell.
Acreage with proven reserves 15% Share of Renergen’s acreage Mitchell said was proven.
Phase 2 scale increase approximately 13 times Compared with the Phase 1 pilot project.
Phase 2 helium output approximately 890 MCF per day Projected production at Phase 2.
Phase 2 capital estimate around $1.2 billion Renergen project estimate described by Mitchell.
Phase 2 debt $750 million Mitchell said this debt had been put together for the project.
Earliest Phase 2 production end of 2030 Mitchell’s estimate; he said full production would probably be in 2031.
2P level technical
"a 2P level of around 400 billion cubic feet of natural gas"
nameplate capacity technical
"reaching our nameplate production capacity"
Nameplate capacity is the maximum output a power plant, factory, or piece of equipment can produce under ideal conditions, as specified by the manufacturer. Investors care because it sets the upper limit on potential revenue and growth—actual earnings depend on how often and efficiently that capacity is used, similar to a car’s top speed versus how fast you actually drive in daily traffic.
final investment decision technical
"take an FID, which is anticipated in the first half of next year"
A final investment decision is the point at which a person or organization chooses to move forward with a particular project or purchase after reviewing all the necessary information and options. It is like deciding to buy a house after considering all the costs, benefits, and alternatives. This decision is important because it determines whether and when the investment will be made, impacting future financial plans and outcomes.
cold box technical
"found a leak in the helium cold box"
A cold box is a specialized container used to keep certain products or materials at low temperatures during storage or transportation. It functions like a high-tech cooler, helping to preserve items that are sensitive to heat, such as medicines, food, or chemicals. For investors, understanding cold boxes can be important when evaluating companies involved in logistics, pharmaceuticals, or industries where temperature control is critical.

FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

What did the NDRA communication say about Renergen’s helium production?

Renergen COO Nick Mitchell said the company reached stable liquid helium production in October after repairing a cold box; storage tanks were being cooled while the company prepared deliveries to local and international customers.

What are Renergen’s Phase 2 output and cost estimates in the NDRA communication?

Mitchell described a Phase 2 capital estimate of around $1.2 billion and projected approximately 890 MCF per day of helium, about 13 times the Phase 1 pilot project’s scale.

When could Renergen’s Phase 2 produce helium, according to the NDRA communication?

Mitchell said the investment decision was anticipated in the first half of next year, with earliest production at the end of 2030 and full production probably in 2031.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

 

Filed by ASP Isotopes Inc.

Pursuant to Rule 425 under the Securities Act of 1933, as amended

and deemed filed pursuant to Rule 14a-12

under the Securities Exchange Act of 1934, as amended

Subject Company: ENDRA Life Sciences Inc.

(Commission File No. 001-37969)

 

The following sets forth excerpts of the transcript from a November 20, 2026 webinar presentation by Nick Mitchell, Chief Operating Officer of Renergen Ltd. (“Renergen”), hosted by  gasworld.com Ltd., relating to the proposed merger and related transactions (the “Proposed Transactions”) involving Renergen, a wholly owned subsidiary of ASP Isotopes (“Asp Isotopes”), Noble Africa LLC, a wholly owned subsidiary of ASP Isotopes and holding company for Renergen (“Noble Africa”), and ENDRA Life Sciences Inc. (“ENDRA”).

 

[…]

 

Rob Cockerill

 

Good morning, good afternoon, good evening and welcome to gasworld webinars with me, Rob Cockerill.

 

Thomas Dee

 

And me, Thomas Dee. The global helium market has always run on a narrow margin of supply security, and over recent years and months, we've seen just how narrow this margin is. With four named helium shortages, and ongoing geopolitical tensions and war threatening a fifth, that risk is far more than a theoretical concern.

 

Rob Cockerill

 

But looking to plug that gap is a new generation of helium explorers working across North America, East Africa and beyond to bring new, diverse sources of supply online. Some are years away from production while others are on their way to commercial scale. But just what is the current health of that industry? Where do the challenges lie and what does it take to turn a promising resource into a reliable source of supply?

 

Thomas Dee

 

Well, that's just what we'll look to explore over the course of this webinar, alongside our panel of industry experts. Over the course of the next hour or so, we're going to hear from Nick Mitchell of Renergen, Nick Tulloch of Mendel Helium, Malcolm Adams of Helium Evolution, and Tom Elliott of Hotspur Helium.

 

Rob Cockerill

 

And near the end of this webinar, once we have heard from all of today's speakers, we'll be putting your questions to our experts. So if you do have a question throughout this webinar, please do submit it as soon as possible and we'll do our best to get it answered.

 

Thomas Dee

 

Yes, please do. Let's now get this webinar underway and hear from our first speaker of the day, Nick Mitchell, Chief Operating Officer at Renergen, where he oversees operations, commercial strategy, and executive communications.

 

Rob Cockerill

 

He has spent more than a decade in South Africa's oil, gas and helium industry. Working with the team, he took the Virginia Gas Project from a stranded gas asset to the country's first producing LNG and liquid helium operation, which holds South Africa's only onshore petroleum production right. Nick also chairs the Onshore Petroleum Association of South Africa, where he works with government and industry to develop the country's onshore sector.

 

 
1

 

 

Thomas Dee

 

Nick, welcome to the webinar. Thanks for joining us today. To start things off, for anyone new to Renergen, please tell us about the company and the Virginia Gas Project that you're involved in. Where is it? Where are you producing? And where do things stand today?

 

Nick Mitchell

 

Great. And firstly, thank you, Thomas. Thank you, Rob, for having me on the call. And you know, great to be here with the rest of the panelists and thank you to the to the viewers for dialing in and watching  this episode. So for those that aren't aware of Renergen and what we do, we are located in South Africa. We have the first and only onshore petroleum production right. it spans about 187,000 hectares and it's located in the center of the of the country in a province known as the Free State Province. 187,000 hectares would equate to approximately 460,000 acres for those that use that nomenclature. and essentially when we bought the asset, this was back in 2013, we bought a call it conceptual field that had a production right and but no business plan and no idea on how to commercialize it. it had single digit proven gas reserve at that stage and what we needed to do is really understand and develop the opportunity so we've spent the last 13 years doing exactly that we've learnt a lot of lessons some hard ones but we haven't yet, well, we haven't just built a project. We've actually had to build a brand new sector in an environment that is not familiar with hydrocarbon exploration and is not used to producing deep cryogenic facilities, specifically around liquid helium type of processes. So, you know, aside from Just think is just simply developing the project. It's been developing the supply and the oil field services side that support us. It's been developing the supply chains for all the equipment and technology that would go into this project in order to see it break through the pilot stage and actually see us turn into a sustainable and reliable supplier. So where we stand right now. is we've been producing LNG since September of 2022. We service several customers in the call it industrial manufacturing space, as well as a more recent customer that is moved into the food manufacturing space. Our helium turned on a little later. We supplied our first batch of liquid helium to test the to test the product and test the quality.

 

We supplied that back in 2025, and since then we took a strategic decision to turn off the helium liquefier. That decision was to then focus on the exploration side of the business, really developing and drilling the exploration wells that would then see us ramp up to nameplate capacity. We announced approximately two months ago that we've turned on the helium system. We've been producing helium stably and we're in the process of now cooling down our large storage tanks and preparing for deliveries to our customers, both locally and abroad.

 

Rob Cockerill

 

Fantastic, thanks Nick. A great introduction to get us underway here today. In October you reached stable liquid helium production. What did it take for you to get to that stage?

 

Nick Mitchell

 

Yeah, so stable liquid helium production. We did have a false start in the beginning, and I'll be upfront with the viewers. We had originally commissioned our system in 2023. We had announced and produced, but then we found a leak in the helium cold box, and that prevented us from actually entering, call it, stable operations at that point in time. So, we needed to repair the cold box. We did so locally in South Africa. Our team of engineers, along with some experts that support a chemical facility in one part of the country, teamed up. We repaired it over several months, returned it into operation, commissioned it and then produced our first liquid helium. Since then,

 

What I can tell you it does take is a reliable supply chain. It certainly takes technology that's developed and robust. There aren't many experts in this field around the world, as we all know on this call. There are very few liquid helium facilities around the world, approximately 15 to 16, and, you know, many of the people with the skill sets that developed those facilities are at an age now where they are leaving the industry. So it's also critical to ensure that you can get access to some of these support skills and ensure that you are plugged in to where these skills can be found to support you. Sitting in Africa simply exacerbates that problem, and you then really do need to be a lot more tenacious in order to bring that project online, in order to see that liquid doing what it well essentially cooling down to minus 269 degrees and being in a position to fill either dewars or large ISO containers. So I'm thankful to a very small team of dedicated resources that have worked around the clock on our side.

 

 
2

 

 

Nick Mitchell

 

It's their patience, it's their persistence, and it's their tenacity that have really pulled it through. And I would say the last thing to cap that off would be patient shareholders. We've been at this project since 2013, and in the public space since approximately 2015. And then more recently we sold our business to another listed group, which is the banner that I have on my background here, ASP Isotopes. And they've come in and supported us with the much-needed capital in order to see this project through and reach these milestones. Without them, that objective probably would not have been reached. So it's a combination of things; it's not one single silver bullet.

 

Thomas Dee

 

Fantastic. Thank you for that, Nick. If we turn our attention now to one of the challenges many in this industry face, and that's financing. It's something we've covered on our helium webinars previously. Capital constraints held up the Virginia project for a long time. So what should the various explorers on this panel and watching the webinar today learn from how Renergen navigated this to get from the discovery stage through to production?

 

Nick Mitchell

 

Yeah, so I think most entrepreneurs would have heard this: cash is king, and delays unfortunately cost more than capital overruns. I can deal with capital overruns every day of the week because they are controlled either through variations or amendments to a contract scope, but delays on a project timeline simply see a cost that you've embedded in the organization running month to month, and that ratchets up very quickly. So managing your project delays is absolutely critical. I would also suggest, you know, prove it at a small scale and then look to expand at an ambitious level. But you've got a lot of lessons to learn as you go through each one of these steps. And unfortunately, this is also a deep tech industry, as I would describe it. A lot of the problems that you face are iterative in nature and need to be solved. As you go through that process, the next problem will present itself. And when you're doing things for the first time in a brand new sector, in a territory that's never had these skills or operated in this technology field, you certainly do have a few more of those problems present themselves than you may have in more robust jurisdictions like the United States, Europe or the Middle East for that matter.

 

Rob Cockerill

 

Fantastic. Well, it's certainly been an interesting journey that Renergen has been on. We can see questions coming in too. Just one more for me for the moment, though, Nick. Looking ahead, phase two would scale Virginia up many times over. So what has to be in place before that goes ahead, and what can we expect in the future?

 

Nick Mitchell

 

Yeah, so phase two is our significant expansion. It would see an approximate thirteen-times increase from what we know as our phase one pilot project. That would produce approximately 890 MCF per day of helium and around 34,000 BTUs or gigajoules of LNG per day. So it's quite a robust project, with a capital estimate of around $1.2 billion. It is banked and backed by the United States government through the U.S. Development Finance Corporation, along with a commercial bank in South Africa. Together they have put together $750 million of debt for the project. The balance will be provided by way of equity, and our parent company has already made public announcements around that equity position and contribution. We're also involved in a reverse merger transaction, which will most likely be completed in the, call it, weeks and months to come, and off the back of that there would be a separate raising of equity as required.

 

What would need to be in place in order for us to start underpinning that project is essentially the completion of phase one, and that project is well underway now. We're anticipating reaching our nameplate production capacity towards the end of this year. The team is working very hard, late nights, early mornings, to get things done. We're confident that we'll achieve it, and with that milestone being met, we'll then be in a position to turn our attention to our phase two project. Alongside that, we are revalidating all the previous bid packages. We've obviously incorporated a few of the lessons learned from our phase one project into those processes. And we'll look at value engineering optimization over the next couple of months so that by the time we take an FID, which is anticipated in the first half of next year, we should be well on our way to a more robust, more mature development, along with the institutional memory, which is absolutely critical, of those employees that have learned the lessons, the hard lessons, over the last, call it, 13 years of development. And I think that has become one of our biggest pieces of institutional, call it, IP pieces, is that embedded, ingrained institutional memory that each one of our employees brings to the table.

 

 
3

 

 

Thomas Dee

 

Fantastic. Well, thank you for that, Nick, and I'm sure that will return to you during our audience Q&A shortly. I can see plenty coming in, but if you do have any more questions for Nick or any of today's speakers, then please do send them in.

 

Rob Cockerill

 

Yes, please do. So Renergen has shown what it takes to bring a large helium project into production, but our next guest is taking a very different route by building production one well at a time.

 

Thomas Dee

 

Yes, we're delighted to now welcome Nick Tulloch of Mendel Helium to the webinar. Nick began his career as a solicitor and holds a master's in law from Oxford. He then spent more than twenty years advising companies on the UK capital markets at firms including Kazonvey and Kencos.

 

Rob Cockerill

 

In 2019, he joined Highlands Natural Resources as finance director and later became CEO. He led its move from oil and gas into CBD and it became the first CBD company quoted on the London Stock Exchange. He went on to found Voyager Life and he also chairs ECR Minerals, Axis Ventures and Physiomics.

 

Thomas Dee

 

Nick, thank you for joining us today. First off, please tell us all about Mendel Helium and everything that you're doing in Kansas.

 

Rob Cockerill

 

Brilliant, thanks Nick. That's a great introduction to the company and what you're doing. I'd like to get into that different route that I referenced a moment ago. So at Mendel Helium, you're very much building one well at a time. You've just given us some of those projects, activities, and updates as well. What does that kind of step-by-step approach give you, and where are the shortfalls with that?

 

Thomas Dee

 

Thank you for that, Nick. To those watching, just a quick note: if you have joined us late and you would like to catch up on what you've missed so far, this session will be available on demand once we conclude. But back to you now, Nick, and talking of different approaches, like Rob said, your current position is slightly different to what you're used to. You spent two decades advising companies on raising money, and now you're very much on the other side of the table. So what do investors actually need to see from a helium company before they'll back it?

 

Okay.

 

[…]

 

Rob Cockerill

 

Thanks, Nick. And just finally for now, the US has of course recently designated helium a critical material, just days after our helium summit in Houston, in fact. What does that change for a small US producer?

 

[…]

 

 
4

 

 

Thomas Dee

 

Fantastic. Well, thank you once again, Nick.

 

[…]

 

Rob Cockerill

 

And back to today's conversation now and back to today's panel, as it is time for our audience Q&A. There isn't much time left to get your questions sent in, so please do submit them as soon as possible. First up, we're going to run through these in as much chronological order as we can. That means we're going all the way back to Nick from Renergen. Karsten asks, how large is Renergen? Tell us a bit about your market cap and your headcount.

 

Nick Mitchell

 

Yeah, so right now we have approximately 85 full-time employees in the business. That's across our upstream, midstream, and downstream activities. As I mentioned in the beginning, we're vertically integrated, and we've had to build the entire supply chain in order to move all the molecules out. So we focus on the exploration, we focus on the midstream processing, and then we actually deliver and connect our gas or LNG into the client's footprint within those locations in South Africa. And then on the helium side, we have even acquired or leased our own fleet of ISOs. In terms of the extent of our project right now, we have proven reserves sitting at, call it, a 2P level of around 400 billion cubic feet of natural gas and around six billion cubic feet of helium. But that's only proven on fifteen percent of our acreage, so fifteen percent of the four hundred and sixty thousand acres that I mentioned previously. We're very focused on exploration and further development around the field.

 

What I would guide is to watch the space in due course as those exploration programs finish. We do anticipate increasing the size of the resource underground as we naturally extend beyond the 15% proven boundary at this stage.

 

Rob Cockerill

 

Brilliant. Thank you, Nick. And we'll stay with you just for a moment. There are often no easy questions on these helium webinars, and we've got one here for you. People are watching this space. Gerrit says here ASP Isotopes' share price is under pressure. That's their observation. And he asks, is a first commercial helium sale still on schedule, which may allay any concerns in the marketplace?

 

Nick Mitchell

 

Yeah, so obviously I'm not in a position to provide any market guidance on share price and activity. I'm a big believer in guiding the team to keep their heads down. We deliver the business, and the share price should take care of itself over time. We're on track for all of our estimates at this stage, and I am pleasantly comfortable with where we sit from a project progress perspective. We have had our delays; we have had our challenges. As the executive leading that team, I take those on the chin myself. I'm accountable for them. There are reasons. I won't go into the reasons or explain them because it will come across as excuses. But we are in very close proximity to achieving those requirements, and technically I don't see any obstacles that are going to block us.

 

Rob Cockerill

 

Well, no journey is ever smooth, is it? And you've shared with us a lot of the candid updates from that journey. So thank you very much, Nick.

 

 
5

 

 

Thomas Dee

 

Yes, thank you, Nick. We now have a question here from Anna. Anna says that Nick mentioned there are fifteen to sixteen liquid helium facilities in the world, and she'd like to know what percent of helium molecules currently in use in the world are produced by these facilities. Now, here at Gasworld, we believe this number to be north of ninety-five percent. Of course, we have a few caveats for recycled helium and helium that's sat inside MRI machines. But maybe

 

Tom, I'll come to you on this one. Is this a figure that you would broadly agree with?

 

[…]

 

Thomas Dee

 

Thanks for that, Tom. And what you've mentioned actually leads nicely into another question that we've had in from David. This is a question for the whole panel, so it'd be great to get everyone's thoughts on this. David asks, between Saskatchewan, South Africa and Kansas, how long is it estimated before full production from these facilities? And how could that have an impact, not only if the loss of production from Ras Laffan and the conflict in the Middle East persist, but also with this growing need for helium supply? Tom, I'll come back to you first, and then we'll go around the board.

 

[…]

 

Thomas Dee

 

Thank you for that, Nick. And just the last words with our second Nick.

 

Thomas Dee

 

I think you might be on mute there.

 

Nick Mitchell

 

Yes, thank you. Our first phase plant, which at nameplate capacity will produce approximately two ISOs a month, is coming up to achieving that target shortly. We're in the process of introducing all the additional wells into that facility. The pipeline construction is largely complete, the additional booster compressor stations are done, and the process plant is already built and waiting for that feed gas to be ramped up and dialed in. That brings the first phase into operation, so it's really imminent. Our second phase, which is the much bigger expansion, will produce approximately, you know, 890 MCF a day, call it 5% of global demand, and we anticipate similar timelines to what Malcolm had indicated. It's a new process, it's new wells, it's a new gas gathering pipeline and a process plant. So approximately a three-and-a-half to four-year build from the time we take the investment decision. And we're aiming to hit that investment decision next year, and that will be followed shortly by a financial close with the lenders on that facility. So we think

 

probably earliest production at the back end of 2030, and the full production year probably going into 2031.

 

Thomas Dee

 

Great, thanks to all of you for that and hopefully that answers David's question.

 

Rob Cockerill

 

Yeah, thanks very much. I would like to come back to Nick with Renergen, if we may, for a second. We've got a question from Michael, who asks, does Renergen get its power from Eskom? I'm not quite sure why he's asking that, but I do know from our new exploration panel in Houston, I was surprised to hear about some of the power and grid challenges that can face some new explorers. I wonder if there are any challenges you face, Nick.

 

 
6

 

 

Nick Mitchell

 

Yeah, so that question's probably directly linked to the fact that South Africa has been plagued with rolling blackouts since approximately twenty [inaudible]. That has been curtailed over the last twelve to fourteen months, and the utility has got a handle on it. We are supplied by the state utility, Eskom, but our line has not been load shed during that period of time. The reason for that is we're tied into one of the central substations that support the grid, and in the technical setup and design, if that substation goes offline, the country faces a complete blackout. So the utility is very well versed in managing and shedding load, and we haven't seen the country facing levels of blackouts, or call it load shedding, that have threatened a national blackout. So yes, while we are supplied by Eskom, it hasn't been a perceived risk for our phase one project. That said, for phase two, we are planning to be self-sufficient, and part of our waste stream of processed gas will be a methane-rich CO2 stream.

 

And we do plan to self-power both phase one and phase two from that methane stream.

 

Rob Cockerill

 

Fantastic. Thank you, Nick. I'm not sure anyone's not suffering grid or power problems in 26, 27.

 

Thomas Dee

 

Yeah, absolutely. I know we're running slightly over here, but there are just two more audience questions to get through, and this one's for you, Nick, of Mendel. Craig asks, in Fort Dodge, can you tell us a bit about the other components of the gas that you're getting?

 

[…]

 

Thomas Dee

 

Great, thank you for that.

 

Rob Cockerill

 

Yes, thank you very much. I'll come back again to Nick at Renergen; I knew you'd be getting lots of questions here. We've got Michael, who had the last question for you: just a great plan, thank you for sharing. You told us earlier about phase two and how it could really take an ambitious step forward for the project. John Leiper would like to ask, are there plans for you to perhaps phase or stagger phase two of the project?

 

Is that a possibility?

 

Nick Mitchell

 

Yeah, it's an excellent question. So obviously Renergen, as I mentioned, was acquired recently by a new parent company called ASP Isotopes. As part of that process, the board has strategically asked us to look at how we would manage the execution philosophy in order to manage risk, reduce risk, and possibly look at bringing elements of the project online sooner to support earlier revenues. So there's a whole host of work that we are currently running in parallel around value engineering optimization and schedule management in order to address these questions. I don't have the final answers yet. Once we as a team have rounded those out and made decisions, we'll obviously present to the board, and once the board takes a decision,

 

we will obviously communicate to shareholders. But rest assured, the ASPI board and the Renergen board are all looking at these matters very closely. We've brought in a lot of experts and a lot of specialists to support us, and we will make the right decisions so that we're effective for shareholders.

 

[…]

 

Thomas Dee

 

Thank you for that, Nick. And I think we've cleared that all up there. So, David, hopefully that's answered your question. I'm going to come to each of you now with one final wrap-up question, because I realize we're running over by about half an hour already.

 

[…]

 

 
7

 

 

Thomas Dee

 

Thank you, Tom. And Nick of Renergen, what does 2027 hold, and what do we have to look forward to?

 

Nick Mitchell

 

Yeah, so I think from our perspective, our operation will move into a scenario of reliable and stable supply. We'll be looking to demonstrate that to our customers. We'll most likely be supplying into some medium- and long-term contracts, both locally and internationally. And, you know, there might be a little bit of spot market play for us, but we don't see ourselves building a sustainable business in a spot market, especially a spot market in the helium market. In the, call it, global context, I think what we all heard at the helium summit late last month is that even if all the conflicts were resolved today, and supply started and production resumed and we were back up at, call it, capacity, it's going to take a long time before those supply chains normalize.

 

So we will see a constrained environment for a significant period of time. I do think the market has also felt quite a significant amount of pain, and it's also indicated that those supply chains are very vulnerable, even if they are restored. So there's going to be a certain amount of requisite diversification required by those entities that are consuming helium, and their boards and their shareholders will insist on it. So I think it's an exciting time for new explorers and new developers. It does come with its own concerns and its own issues, but those can be managed. And yeah, it's a good time to be in the helium business. We're certainly excited, and we're looking forward to what the next few years bring.

 

Thomas Dee

 

Thank you, Nick. And finally, Nick of Mendel, final words from you.

 

[…]

 

Thomas Dee

 

Great, thank you for that, Nick, and thanks to all of you. But sadly, that is all we have time for today. Our thanks once again to Nick Mitchell of Renergen, Nick Tulloch of Mendel Helium, Malcolm Adams of Helium Evolution, and Tom Elliott of Hotspur Helium.

 

Rob Cockerill

 

We are approaching the end of the year, with just a handful of gasworld webinars to come. In just a few days' time, on November 25th, we'll be taking a look at carbon capture and utilisation, delving into the emerging carbon economy, the route from capture to usable CO2, how to make the economics work, and the next generation of those projects.

 

Thomas Dee

 

We will also have a number of special in-conversation webinars in the coming weeks, so do be sure to keep an eye on gasworld.tv and register for any that may pique your interest.

 

Rob Cockerill

 

And you can catch us in person in Budapest in just over a week's time for the Global Industrial Gas Conference, where helium will again be on the agenda as we discuss helium risk, finance and investment. You can, of course, also visit gasworld.com to stay up to date with all the latest news, views and insights into the industrial gases business, including various written recaps and story cuts of this very webinar.

 

 
8

 

 

Thomas Dee

 

My final thanks of the day, as always, go to you, the viewers in homes and offices around the world, for watching and participating. But until next time, it's goodbye from me.

 

Rob Cockerill

 

And goodbye from me.

 

***

 

Cautionary Statement Regarding Forward-Looking Statements

 

This communication contains “forward-looking statements” within the meaning of the safe harbor provisions of the Private Securities Litigation Reform Act of 1995. Forward-looking statements are neither historical facts nor assurances of future performance. Instead, they are based only on the current beliefs, expectations, and assumptions of the parties regarding the future of the parties’ businesses, future plans and strategies, projections, anticipated events and trends, the economy, and other future conditions. Forward-looking statements can be identified by words such as “anticipates,” “believes,” “could,” “estimates,” “expects,” “intends,” “may,” “might,” “plans,” “projects,” “will,” and words of a similar nature. Examples of forward-looking statements include, but are not limited to, statements relating to the expected production quantities of LNG and liquid helium; Renergen’s expected revenues; the Proposed Transactions; the expected structure, timing and the completion of the Proposed Transactions, including investment amounts from investors, timing of closing of the Proposed Transactions, expected proceeds, expectations regarding the use of proceeds, and impact on ownership structure, and the expected effects, perceived benefits or opportunities of the Proposed Transactions; the combined company’s listing on Nasdaq after the closing of the Proposed Transactions; the expected executive officers and directors of the combined company; each company’s and the combined company’s expected cash position at the closing of the Proposed Transactions and cash runway of the combined company following the Proposed Transactions; the future operations and pipeline, estimates of financial position, competitive landscape, addressable market and strategic and financial initiatives of the combined company; the nature, strategy and focus of the combined company; statements regarding the continuation of Renergen’s Virginia Gas Project and its funding timeline and other statements that are not historical fact. Because forward-looking statements relate to the future, they are subject to inherent uncertainties, risks, and changes in circumstances that are difficult to predict, many of which are outside our control. Actual results, financial condition, and events may differ materially from those indicated in the forward-looking statements based upon a number of factors. Forward-looking statements are not a guarantee of future performance or developments. You are strongly cautioned that reliance on any forward-looking statements involves known and unknown risks and uncertainties. Therefore, you should not rely on any of these forward-looking statements.

 

 
9

 

 

There are many important factors that could cause actual results and financial condition to differ materially from those indicated in the forward-looking statements, including, but not limited to: the outcomes of various strategies and projects undertaken by Renergen; the potential impact of laws or government regulations or policies in South Africa or elsewhere; Renergen’s future capital requirements and sources and uses of cash; Renergen’s ability to obtain funding for its operations and future growth, including debt funding for Phase 2 of the Virginia Gas Project; Renergen’s reliance on the efforts of third parties; Renergen’s ability to complete Phase 1 and 2 of the Virginia Gas Project; the financial terms of any current and future commercial arrangements; Renergen’s ability to complete certain transactions and realize anticipated benefits from acquisitions and contracts; Renergen’s ability to comply with the terms of the loan and credit facilities of Renergen’s subsidiary Tetra4; the ability of Renergen and its subsidiaries to retain and hire key personnel; the volatility of LNG and liquid helium prices; Renergen’s success in discovering, estimating and developing natural gas and helium reserves; actions of competitors or regulators; limitations in the availability of, and costs of, supplies, materials, contractors and services that may delay the drilling or completion of wells or make such wells more expensive; the amount and timing of future development costs; uncertainties inherent in estimating quantities of natural gas and helium reserves and projecting future rates of production and timing of development activities; risks relating to the lack of capital available on acceptable terms to finance the Renergen’s continued growth; the competitive nature of Renergen’s industry; the risk that the conditions to the closing or consummation of the Proposed Transactions are not satisfied, including the failure to timely obtain approval of the Proposed Transactions from ENDRA stockholders, if at all; the risk that the proposed financings are not completed in a timely manner, if at all; uncertainties as to the timing of the consummation of the Proposed Transactions and the ability of each of ENDRA and Noble Africa to consummate the Proposed Transactions; risks related to ENDRA’s continued listing on Nasdaq until closing of the Proposed Transactions and the combined company’s ability to remain listed following the closing of the Proposed Transactions; the ability to obtain debt financing on terms that are favorable, or at all; the risk that Renergen does not receive funding from the U.S. DFC or Standard Bank SA or that such funding is delayed; risks related to ENDRA’s ability to correctly estimate its respective operating expenses and its respective expenses associated with the Proposed Transactions, as applicable, pending the closing of the Proposed Transactions, as well as uncertainties regarding the impact any delay in the closing would have on the anticipated cash resources of ENDRA, and other events and unanticipated spending and costs that could reduce ENDRA’s cash resources; risks related to the failure or delay in obtaining required approvals from any governmental or quasi-governmental entity necessary to consummate the Proposed Transactions; the occurrence of any event, change or other circumstance or condition that could give rise to the termination of the merger agreement; the effect of the announcement or pendency of the Proposed Transactions on ENDRA’s or Renergen’s business relationships, operating results and business generally; costs related to the Proposed Transactions; risks related to the market price of ENDRA’s common stock relative to the value suggested by the Proposed Transactions; the outcome of any legal proceedings that may be instituted against ENDRA, Noble Africa or any of their respective directors, managers, or officers related to the Proposed Transactions; costs of the Proposed Transactions and unexpected costs, charges or expenses resulting from the Proposed Transactions; changes in regulatory requirements and government incentives; risks associated with the possible failure to realize, or that it may take longer to realize than expected, certain anticipated benefits of the Proposed Transactions, including with respect to future financial and operating results, legislative, regulatory, political and economic developments, and those uncertainties and factors; and the risk of involvement in litigation, including securities class action litigation, that could divert the attention of the management of ENDRA or the combined company, harm the combined company’s business and may not be sufficient for insurance coverage to cover all costs and damages, and the other risks and uncertainties described in ENDRA’s filings with the U.S. Securities and Exchange Commission (the “SEC”), and under the heading “Risk Factors” in its most recent Annual Report on Form 10-K and Quarterly Reports on Form 10-Q, the factors disclosed in Part I, Item 1A. “Risk Factors” of ASP Isotopes’ Annual Report on Form 10-K for the fiscal year ended December 31, 2025 (as amended) and in ASP Isotopes’ subsequent reports filed with the SEC, each of which are available at www.sec.gov, and in other filings that ENDRA and ASP Isotopes have made and will make with the SEC in connection with the Proposed Transactions, including the Form S-4 and Proxy Statement described below under “Additional Information and Where to Find It”.

 

Any forward-looking statement made by the parties in this communication is based only on information currently available to the parties and speaks only as of the date on which it is made. The parties undertake no obligation to publicly update any forward-looking statement, whether as a result of new information, future developments or otherwise. No information in this communication should be interpreted as an indication of future success, revenues, results of operations, or stock price. All forward-looking statements herein are qualified by reference to the cautionary statements set forth herein and should not be relied upon.

 

Important Additional Information and Where to Find It

 

This communication relates to the Proposed Transactions involving ENDRA, ASP Isotopes, Renergen and Noble Africa and may be deemed to be solicitation material in respect of the Proposed Transactions. In connection with the Proposed Transactions, ENDRA has filed relevant materials with the SEC, including a registration statement on Form S-4 (the “Form S-4”) that contains a proxy statement (the “Proxy Statement”) and prospectus. This communication is not a substitute for the Form S-4, the Proxy Statement or for any other document that ENDRA may file with the SEC and/or send to its stockholders in connection with the Proposed Transactions.

 

INVESTORS AND STOCKHOLDERS OF ENDRA ARE URGED TO READ THE FORM S-4, THE PROXY STATEMENT AND ANY OTHER RELEVANT DOCUMENTS THAT MAY BE FILED WITH THE SEC, AS WELL AS ANY AMENDMENTS OR SUPPLEMENTS TO THESE DOCUMENTS, CAREFULLY AND IN THEIR ENTIRETY IF AND WHEN THEY BECOME AVAILABLE BECAUSE THEY WILL CONTAIN IMPORTANT INFORMATION ABOUT ENDRA, ASP ISOTOPES, RENERGEN, NOBLE AFRICA, THE PROPOSED TRANSACTIONS AND RELATED MATTERS.

 

 
10

 

 

Investors and stockholders will be able to obtain free copies of the Form S-4, the Proxy Statement and other documents filed by ENDRA and ASP Isotopes with the SEC (when they become available) through the website maintained by the SEC at www.sec.gov. ENDRA’s Internet website address is www.endrainc.com.

 

ENDRA’s Annual Report on Form 10-K, Quarterly Reports on Form 10-Q, Current Reports on Form 8-K, including exhibits, and amendments to those reports filed or furnished pursuant to Section 13(a) or 15(d) of the Exchange Act are available free of charge through the investor relations page of its Internet website as soon as reasonably practicable after it electronically files such material with, or furnishes such material to, the SEC.

 

Participants in the Solicitation

 

ENDRA, ASP Isotopes, Renergen, Noble Africa, and their respective directors and managers and certain of their executive officers and other members of management may be deemed to be participants in the solicitation of proxies from ENDRA’s stockholders in connection with the Proposed Transactions under the rules of the SEC.

 

Information about ENDRA’s directors and executive officers, including a description of their interests in ENDRA, is included in ENDRA’s most recent Annual Report on Form 10-K for the year ended December 31, 2025. Information about ASP Isotopes’ directors and executive officers, including a description of their interests in ASP Isotopes, is included in ASP Isotopes’ most recent Annual Report on Form 10-K for the year ended December 31, 2025. Additional information regarding the persons who may be deemed participants in the proxy solicitations, including the directors and executive officers of Renergen, and a description of their direct and indirect interests, by security holdings or otherwise, is also included in the Form S-4 and the Proxy Statement and may be included in other relevant materials filed with the SEC. These documents can be obtained free of charge from the sources indicated above.

 

No Offer or Solicitation

 

This communication is not intended to and does not constitute a solicitation of a proxy, consent or approval with respect to any securities or in respect of the Proposed Transactions or an offer to sell or the solicitation of an offer to subscribe for or buy or an invitation to purchase or subscribe for any securities pursuant to the Proposed Transactions or otherwise, nor shall there be any sale, issuance or transfer of securities in any jurisdiction in contravention of applicable law.

 

No offering of securities shall be made except by means of a prospectus meeting the requirements of Section 10 of the Securities Act of 1933, as amended, and otherwise in accordance with applicable law, or an exemption therefrom. Subject to certain exceptions to be approved by the relevant regulators or certain facts to be ascertained, the public offer will not be made directly or indirectly, in or into any jurisdiction where to do so would constitute a violation of the laws of such jurisdiction, or by use of the mails or by any means or instrumentality (including without limitation, facsimile transmission, telephone and the internet) of interstate or foreign commerce, or any facility of a national securities exchange, of any such jurisdiction.

 

 