NMG Provides Q3 2026 Update and Highlights
First Full Quarter of Construction Execution at the Matawinie Mine
Highlights
| ● | Construction
at the Matawinie Mine has been advancing as planned and remains within the overall budget,
with activities in the third quarter ranging from civil works to structural concrete foundations,
infrastructure excavation and backfill, the continued advancement of detailed engineering
and procurement of key equipment and construction packages. |
| ● | NMG continues to advance the remaining steps toward financial close of the senior debt facilities for
the Matawinie Mine which is expected in the upcoming weeks. |
| ● | In October, the Company completed the first instalment of the required financial guarantee through the
placement of a surety bond following the approval of the mine’s Closure Plan in Q2 2026 and it obtained the mining lease for
the Matawinie Mine from Québec’s Ministry of Natural Resources and Forests. |
| ● | NMG is continuing the advancement of engineering and optimization activities and the ongoing work with
the various stakeholders in view of a targeted Final Investment Decision (FID) in the upcoming months for the 13ktpy Bécancour
Battery Material Plant. |
| ● | The Company appointed in October Mr. Lapo Pistelli, Director of Energy Transition Minerals Solutions at
Eni, to its Board of Directors. |
| ● | The Company announced the development, in collaboration with a research team from McGill University, of
a low-carbon-footprint anode material coating process which, together with its ongoing investments in R&D, reflects its commitment
to continuously improving its processes and products in order to deliver an ever-stronger value proposition to its present and future
customers. |
| ● | Operational discipline, with no major environmental incidents, a 12-month rolling Total Recordable Injury
Frequency Rate (TRIFR) of 0 for the Company’s employees and 5.78 for active contractors at the Matawinie Mine construction site
as of September 30, 2026. This represents a combined TRIFR of 1.47. |
MONTRÉAL, CANADA, November 12, 2026 -
Nouveau Monde Graphite Inc. (“NMG” or the “Company”) (NYSE : NMG, TSX : NOU)
provides a quarterly update on its financial and operational performance and strategic progress for the third quarter ended September
30, 2026. This period was defined by the continued advancement of the Company’s cornerstone projects: the Matawinie Mine and the
13ktpy Bécancour Battery Material Plant. Construction activities at the Matawinie Mine progressed as planned and within the overall
project budget, while required activities in support of a FID targeted in the upcoming months continued to advance for the 13ktpy Bécancour
Battery Material plant.
“The third quarter was about disciplined
execution and steady progress across key areas of our business,” said Eric Desaulniers, NMG Founder, President and Chief Executive
Officer. “At the Matawinie Mine, our teams continued to translate plans into infrastructure on the ground, while maintaining our
focus on schedule, cost control and responsible project delivery. In parallel, working closely with our partners, we continued to advance
the work required to support a targeted FID for our 13ktpy Bécancour Battery Material Plant in the upcoming months. Beyond project
development, we continued to strengthen the capabilities and relationships that will support NMG over the long term, from applied innovation
to our strengthening collaboration with Eni with the addition of one of their representatives to our Board. We remain focused on delivering
each step with rigour and building a strong foundation for the integrated graphite platform we are developing in Québec, Canada.”
Matawinie Mine (Phase 2)
| August 2026 |
November 2026 |
 |
 |
In the third quarter, construction activities
continued to progress as planned and remained within the overall budget, with C$67 million incurred in project expenditures as of September
30, 2026.
The Company reports close to 71,000 on-site
construction and engineering hours worked over the third quarter. Construction activities included:
| · | Concrete pours for building and mineral processing
equipment foundations; |
| · | Excavation and backfill of infrastructure at
the industrial platform; |
| · | Excavation of water control structures; |
| · | Backfill of material into the overburden and
organic stockpiles; |
| · | Ongoing permit/authorization applications for
the construction managed in line with the project execution schedule; |
| · | Continued advancement of detailed engineering
and procurement of key equipment and construction packages. |
Furthermore, NMG continues to advance the remaining
steps toward financial close of the senior debt facilities which is expected in the upcoming weeks.
In October, the Company obtained mining lease
no. 1057 for its Matawinie Mine from Québec’s Ministry of Natural Resources and Forests. The mining lease grants the Company
the right to mine the graphite deposit and marks a major regulatory milestone for the project. This milestone follows several years of
environmental, social and regulatory processes and reflects NMG’s commitment to developing the Matawinie Mine according to high
standards of environmental performance and sustainable development.
In addition, following the approval of the Closure
Plan for the Matawinie Mine in the second quarter, the first instalment of the required financial guarantee was completed in October through
the placement of a surety bond.
Planned key construction activities in the fourth quarter include:
| · | Continued advancement of civil and concrete works,
with focus on maximizing concrete placement prior to the winter period; |
| · | Advancement of awards for construction and equipment
packages required in 2027; |
| · | Continued progress in detailed engineering to
support tender and construction needs. |
13ktpy Bécancour Battery Material Plant
In the third quarter, the Company continued to advance the required
technical, commercial and financing activities supporting a FID targeted in the upcoming months.
Key activities during this period included:
| · | The advancement into the detailed engineering
phase to refine and optimize the process design; |
| · | Ongoing due diligence activities with partners; |
| · | The continued advancement of optimization activities;
and |
| · | The ongoing collaboration with Panasonic Energy
to ensure the plant design meets their key requirements and expectations. |
In addition, Panasonic Energy has reiterated its
intent to support this project, which may entail an equity investment by Panasonic at the FID of the 13ktpy Bécancour Battery Material
Plant, in line with their initial investment in 2024.
Planned key activities in the fourth quarter include
further advancement of the above-mentioned activities as well as the continued optimization of capital structure and negotiations of major
contracts for the production equipment and for the construction.
In parallel, NMG also continues various workstreams
to develop Additional Battery Material Plants of active anode material and/or advanced graphite materials production that could be developed
on its existing 200,000 m² adjacent greenfield or other strategically positioned sites either in North America or in Europe.
Commercial Strategy and Value Creation
NMG has established a diversified commercial foundation
across key graphite markets through binding offtake agreements with Panasonic Energy for the lithium-ion battery market, Traxys for the
refractory market, and the Government of Canada for specialized graphite applications. These agreements, representing approximately 70%
of the Matawinie Mine production, provide commercial visibility across large-volume and specialized markets and validate the relevance
of NMG’s planned product portfolio. In addition, the Company continues to advance its commercialization strategy and is actively
engaged with other tier-1 potential customers interested in the remaining volume of NMG’s Phase 2 production for natural flake graphite,
active anode material, and/or specialized graphite materials for niche applications.
Building on this foundation, NMG’s strategy
is focused on maximizing the value generated from its planned graphite production through the development of additional value-added opportunities.
Potential avenues include additional active anode material capacity and the valorization of by-products and tailings. The execution of
these initiatives could enable NMG to capture additional value across its production base, diversify its sources of potential revenue
and progressively expand its earnings-generating capacity.
In the immediate near-term, NMG remains focused on the disciplined
and rigorous execution of the construction of the Matawinie Mine and on advancing the remaining activities in support of a targeted FID
for the 13ktpy Bécancour Battery Material Plant project, while continuing to work closely with its partners and stakeholders to
advance these priorities.
To consult NMG's Management
Discussion and Analysis for the nine-month period ended September 30, 2026, visit: [https://nmg.com/wp-content/uploads/2026/11/MDA-Q3-2026-ENG-VF.pdf]
About Nouveau Monde Graphite
Nouveau Monde Graphite is an integrated company
developing responsible mining and advanced processing operations to supply the global economy with carbon-neutral advanced graphite materials.
The Company is developing in Québec, Canada, a fully integrated ore-to-processed-graphite value chain to serve tomorrow’s
industries in energy, advanced technology, and manufacturing. With recognized ESG standards and structuring partnerships with major customers,
NMG is set to become a strategic supplier of advanced materials to leading specialized manufacturers while promoting sustainability,
innovation, and supply chain traceability. www.NMG.com.
|
Contact
Media
Juliana Salaun
Director, communications and public relations
jsalaun@nmg.com |
Investors
Marc Jasmin
Director, Investor relations
+1-450-757-8905 #993
mjasmin@nmg.com |
Subscribe to our news feed: https://bit.ly/3UDrY3X
CAUTIONARY NOTE REGARDING FORWARD-LOOKING INFORMATION
This press release contains “forward-looking
information” and “forward-looking statements” within the meaning of applicable securities legislation (collectively,
“forward-looking statements”), including, but not limited to, statements relating to future financial or operating events
or future performance of the Company and reflect management’s expectations and assumptions regarding the Company’s growth,
results, performance and business prospects and opportunities. Such forward-looking statements reflect management’s current beliefs
and are based on information currently available to it. In some cases, forward-looking statements can be identified by words such as “aim”,
“anticipate”, “aspire”, “attempt”, “believe”, “budget”, “could”,
“estimate”, “expect”, “forecast”, “intend”, “may”, “mission”,
“plan”, “potential”, “predict”, “progress”, “outlook”, “schedule”,
“should”, “study”, “target”, “will”, “would” or the negative of these terms
or other similar expressions concerning matters that are not historical facts. In particular, statements regarding the Company’s
future results, the intended construction, commissioning and ramp-up of the Matawinie Mine, the completion and timing of the financial
close of the committed senior debt facilities for the Matawinie Mine, including the satisfaction of applicable conditions precedent, the
expected benefits associated with the mining lease for the Matawinie Mine and the Company’s ability to comply with the terms of
the lease, the implementation of the Matawinie Mine closure plan including the posting of financial guarantees associated therewith, the
completion and timing of a FID for the 13ktpy Bécancour Battery Material Plant, the ability to obtain sufficient financing for
the development of the 13ktpy Bécancour Battery Material Plant on favorable terms, the potential participation of strategic partners
or investors including Panasonic Energy in connection with the financing of the 13ktpy Bécancour Battery Material Plant, the intended
strategy and development of Additional Battery Material Plants, the Company’s commercialization strategy and ability to secure additional
customer commitments, the development and commercialization of the low-carbon-footprint anode material coating process and other technological
innovations, the Company’s development activities and product plans, market trends, the results of the 2026 Class 3 AACE Project
Cost Estimate for the 13ktpy Bécancour Battery Material Plant, the Company’s ability to develop and operate an integrated
graphite value chain and establish itself as a strategic supplier of advanced graphite materials and any information as to future plans
and outlook for the Company are or involve forward-looking statements.
Forward-looking statements are based on reasonable
assumptions that have been made by the Company as at the date of such statements and are subject to known and unknown risks, uncertainties,
and other factors that may cause the actual results, level of activity, performance, or achievements of the Company to be materially different
from those expressed or implied by such forward-looking statements. Forward-looking statements are further subject to risks and uncertainties
relating to the Company’s ability to achieve the financial close of the Matawinie Mine debt financing on a timely basis or at all,
satisfy conditions precedent under its financing arrangements, execute construction activities in accordance with planned schedules and
budgets, manage inflationary pressures and labor availability, comply with the mining lease and other permits and authorizations, maintain
the financial guarantees required under the Matawinie Mine closure plan, obtain an FID for the 13ktpy Bécancour Battery Material
Plant on the anticipated timeline or at all, secure sufficient financing, perform its obligations under existing commercial agreements,
maintain its commercial relationships and secure additional customer commitments, successfully develop, scale and commercialize new technologies
and advance the development of Additional Battery Material Plants.
Such risks, uncertainties and other factors
include, but are not limited to, the actual results of current development, engineering and planning activities, access to capital and
future prices of graphite, risks inherent in new mining operations, risks inherent in mineral exploration and development activities,
the speculative nature of mining development, changes in mineral production performance, the uncertainty of processing the Company’s
technology on a commercial basis, development and production timetables, competition and market risks, pricing pressures, other risks
of the mining industry, the fact that certain of the initiatives described in this press release are still in the early
stages and may not materialize, business continuity and crisis management, political instability and international conflicts and additionally,
such other factors discussed in the section entitled “Risk Factors” in the Company’s most recent annual information
form, which is available under the Company’s profile on SEDAR+ (www.sedarplus.ca) and on EDGAR (www.sec.gov).
Although the Company has attempted to identify
important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may
be other factors that may cause results not to be as anticipated, estimated, or intended. There can be no assurance that such statements
will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly,
readers should not place undue reliance on forward-looking statements and are cautioned that the list of risks, uncertainties, assumptions
and other factors are not exhaustive. The Company does not undertake to update or revise any forward-looking statements that are included
in this press release, whether as a result of new information, future events, or otherwise, except in accordance with applicable
securities laws. Additional information regarding the Company is available on SEDAR+ (www.sedarplus.ca), on EDGAR (www.sec.gov)
and on the Company’s website (www.NMG.com).